Running head: TECHLETIC: PROJECT NARRATIVE
	
	
	
	
Techletic: Project Narrative
Mitchell Ajimatanrareje, Tony Long, Angela Richmond, Michael Trummel, and Jessica Yan
George Fox University
TECHLETIC:	PROJECT	NARRATIVE		
Project Charter
The project charter describes in detail the objective(s) of our project. It acts as an
introduction to the project and illustrates its importance and value proposition. It is important
that the project charter explicitly details the nature of the project, a timeline, who will be
involved, and what the product of the project will be at its conclusion.
Techletic is a 2-day event proposal for Chehalem Parks and Recreation. Our event
proposal creates an obstacle course for children ages 6 – 12 to complete. The obstacle course will
consist of a combination of technological puzzles and physical tasks. The purpose of the event
will be to encourage children to develop a healthy balance between using their technological
devices and playing outside. Through the use of digital puzzles and physical objectives,
Techletic will help children participants develop an exciting connection between being active
and playing games. Recently, through the “Let’s Move” initiative of the First Lady Michelle
Obama, schools and other organizations are creating programs to inspire children to be more
active to fight childhood obesity.
Chehalem Parks and Rec will host the event, inviting children from all local cities of
McMinnville, Sherwood, Wilsonville and Salem. Elementary and Middle Schools will be
involved to maximize the potential of attendance by children and their families. During the
summer, Chehalem Parks and Rec hosts a variety of events for the community that families can
participate in. Techletic will take place the first week (Mon/Tues.) of August. The project will be
developed by five project coordinators and executed by Chehalem Parks and Rec. Partnerships
with local businesses will ease the financial burden on Chehalem Parks and Rec.
Critical to Quality Tree
The Critical to Quality Tree helps to obtain a focus on the main objective of our project and the
measurable to quantify those objectives. This deliverable highlights the reason we are striving to
accomplish the project and how it benefits the major players.
It is important for every member of the project team to understand the why and the who.
These two major points are imperative for the project team’s overall understanding. This
document will ensure that we are all on the same page and understand the motivation for the
project.
Our quality driver is to get the participants (kids) outside to play. Keeping kids active and
healthy is the important “Why” for what we are trying to accomplish. This can be measured by
TECHLETIC: PROJECT NARRATIVE
many standards and must show how they are quantified. The performance requirement for the
Techletic event for getting kids outside to play is to time the games and obstacle course to ensure
the events last longer than one hour. The next quality driver is to have a fun experience. The
performance requirement for this is to conduct a customer satisfaction survey after the event
concludes. This will highlight any issues or comments that can be used for future events and can
be assessed for the quality of the experience.
The next participant that will be affected by the event is Chehalem Parks and Rec. The
quality driver for a successful event is the safety of all who participate through the performance
requirement of a minimized number of injuries. The next quality driver for Chehalem Parks and
Rec. will be through financial gain of the event. The performance requirement for this driver is to
give back $6,000 upon completion of all expenses and the event concludes.
The final participant to be affected by the event are the sponsors. The quality driver for
the sponsors will be the perception that the community of participants (parents/children) have of
the sponsors who took part in the event and the quality of their contributions. The post-event
customer satisfaction survey will be the performance requirement for assessing the quality and
validity of the sponsors involved.
Work Breakdown Structure
The work breakdown structure is an overview of the tasks that need to be accomplished. In
our project, we have identified four elements in order to successfully execute the project. These
four elements are:
1. Planning: This section includes: develop the budget, secure the dates and locations of the
event, contact sponsors, search for volunteers, etc. This will help our team to get the big
picture of how the event will look and what we need to prepare for the event.
2. Preparation: This section includes: confirm volunteers, sponsors and vendors, advertising,
set up a trial course, check weather and etc. This allows us to make sure that we have
everything we need on site ready for the event.
3. Event Day: During the event, it is critical to ensure the event goes smoothly and ensure
the safety of the kids. The event day also includes tear-down of equipment and clean up
after the event.
TECHLETIC:	PROJECT	NARRATIVE		
4. Review: After the event, we will perform a post-event debrief and write an after-action
report, as well as send out surveys to our clients so that we can make improvements in
future events.
Responsibility Matrix
There are many tasks in the project that need to be accomplished in order and on time.
The responsibility matrix can help a team to identify who is responsible for what task and how
they will be supported. The responsibility matrix also tells the team members how their portion
of the project connects with the project as a whole.
There are four sections in our responsibility matrix, as mentioned in our work breakdown
structure. We assigned each team member to be responsible for different tasks and assigned
others as support required, to be notified, to be consulted or approval required to hold each other
accountable, and accomplish the tasks on time and with quality.
Project Network Diagram
The Project Network Diagram helps us see the critical chain of events and supporting
tasks that help guide us through the project requirements. We can see the entire project and how
each task is connected through the chain. As long as we can solidify our tasks and the order/date
of those tasks with relation to our respective end date, we can create an efficient and effective
Project Network Diagram.
Our Project Network Diagram includes every step of the process for the project and the
order in which they are required to be accomplished. Each step of the process incorporates the
dates in which they start, finish, and who is working on that part of the process. This is where all
project team members can easily see the critical chain.
Our critical chain consists of the following tasks: approach Chehalem, budget, evaluate
costs, confirm pricing, search for volunteers/coaches, contact volunteers/coaches, set-up trial
course and tech, contact trainers, confirm vendors, check weather, sign-up booth/liability
waivers/wristband distribution, storage of equipment, tear down of equipment, post-event
debrief, after action report, and customer satisfaction survey.
Project Schedule
The purpose of a project schedule is to help those involved in the project to understand
best start dates, and latest possible start dates in order to reach the end objective on time. This
graphical representation shows the best timeline of the project to reach a specified deadline.
TECHLETIC: PROJECT NARRATIVE
In order to determine the timeline of our schedule, it was most important to identify the tasks that
would take the most time, and identify which team members would be best for those tasks in a
manner that would not strain our resources. In addition, it was very important in the process of
planning our schedule to determine a date when this event would be best accessible to our target
age range.
The best possible schedule for our project would be 134 days, with the main two-day
event occurring during a Monday and Tuesday the first week of August. By scheduling the date
within the summer, more kids ages 6-12 will be available to attend the event. Another reason the
event would best in this timeline is that the weather will be warm. To achieve this possible end
date the project would need to start mid-February.
Project Budget
The purpose of the project budget is to help us understand how much money we will be
spending to complete the project from start to finish. The budgeting process will start with our
team creating a list of everything we will need for the project from start to completion. We will
then take this itemized budget to our partner (Chehalem Parks & Rec.) and go over it with them.
This process will involve a give and take the scenario to come up with the final budget. Budgets
are important to every project so that we can utilize every dollar we have available and stay on
track. Every aspect of our project down to the cent will need to be identified before completing
this.
As noted in the budget, the course materials will cost $5000, 5 ladders at $40 each per
day will cost $400, two 7X3 banners at $47.25 each will cost $94.50, 10 Ipad 4’s at $40 each for
the first day and $15 each the second day will cost $550, a Wix website for free,
marketing/advertising materials will cost $1000 (posters and handouts for schools), $250 for
liability insurance with up to a million dollars in liability, tickets and wristbands will cost $200,
and water for the participants will cost $50. In the case of extreme weather, we will need two
10X20 tents at $130 each, and 30 spray-fan-misters at $4 each. If it is raining or above 95
degrees, we will incur the corresponding costs from either option. Through this process, we will
need $7,544.50 and with the extra costs due to weather extremes, it could be as much as
$7804.50 (with rain) or $7664.50 (with extreme heat).
The budgeting process not only helps us figure out how much money we will need to
complete the project, but also how many hours it will take. In the budget, the amount of
TECHLETIC:	PROJECT	NARRATIVE		
volunteer and group hours needed for completion are outlined in detail. Our group will average 6
hours a week (5 people total) for 20 weeks which totals to 600 total hours, dry-run set-up day
will require 20 volunteers for 8 hours for a total of 160 hours, the 2-day Techletic event will
require 40 volunteers for 8 hours each for a total of 640 hours, building the website will take 15
total hours, the marketing/advertising materials and promotion will require a total of 60 hours
across the 20 weeks, and we will also need emergency response and police volunteers for a total
of 32 hours. Through this process, we will need 1507 total hours.
Risk Management Plan
The risk management plan will be imperative to the success of our project. This
document includes risk assessment of our entire plan. It identifies what risks are possible through
our process, the different impacts of each risk, and plans to combat these potential risks. By
identifying risks before they happen, it ensures that we will be able to act proactively instead of
reactively.
The risk management plan highlights seven key areas of the Techletic event that have the
most potential to create problems. The seven key areas are as follows: Lack of sponsor interest,
weather, lack of public interest (minimal number of participants), lack of volunteer participation,
Logistics/course set-up, competing for events, and children safety.
We see the highest amount of risk coming from lack of sponsor interest and lack of
public interest. We plan to combat the first issue by communicating early and often with the
potential sponsors, and by pitching the event in a way that shows its true value to them, the
participants, as well as the community. The second issue we will address by making a website
specifically for the event, reaching out to schools, and explaining the importance to the parents
as to why Techletic is such a special event for their child/children.
A3
A smattering of graphical information coupled with specific details of the project
representing the entire process of the project. The information provided in the A3 gives a
snapshot of the performance of the project. Specific graphical information that is presented in the
A3 for this project is as follows: Goal/Background for Project, Critical to Quality Tree, Project
Budget, and Responsibility Matrix.
TECHLETIC:	PROJECT	CHARTER	
	
Techletic Project Charter
Project Title: Techletic
Project Leader: Angela Richmond
Team Members: Michael Trummel, Jessica Yan, Tony Long, Jim Bernard (Parks Coordinator),
Lynne Patrick (Recreation and Education Coordinator), & Sarah Craft (Recreation Specialist).
Business Case: Increased screen-time spent by children ages 6 – 12 has adverse affects on
childhood development and increased potential for childhood obesity.
Problem/Opportunity Statement: Children ages 6 – 12 need more activities especially during
the summer to be active and spend less time in front of a tablet/computer/phone.
Goal Statement: Create a 2-day event, the first week of August, combining physical tasks and
technology to encourage children to find a balance between playing outside and on their devices.
Project Scope: Team members will meet from 12:30 – 2:00PM every Monday. Team members
will be responsible for developing specific parts of project plan. Existing data on Chahalem
Parks and Rec events will be compiled and assessed for events specifically relating to children.
Stakeholders: Food Vendors, Coaches, Event Coordinators, Supervisors, Security, Field
Physicians, Set-up Staff, Tear-down Staff, Clean-up staff, Attendants, Volunteers, Sponsors &
Chehalem Parks & Rec.
TECHLETIC: PROJECT CRITICAL TO QUALITY TREE
WhoQualityDriverPerformanceRequirement
Participants
Chehalem
ParksandRec.
Sponsors
Exercise60minutes
FunExperience
FinancialGain
SafeEvent
Communityperception
Gamesandobstaclecourseduration
Post-eventsurvey
$6,000donation
Minimizednumberofinjuries
Post-eventsurvey
TECHLETIC: PROJECT RISK WORK BREAK DOWN STRUCTURE
	
1.0Planning2.0Preparation3.0EventDays4.0Review
1.1ApproachChehalem2.1ConfirmPricing
3.1Emergencyteamson
station
4.1Post-eventdebrief
1.2Budget2.2ConfirmSponsors3.2Securityonstation4.2After-actionreport
1.3EvaluateCost
2.3Contactcoaches,volunteers,
andnotifysecurity/medicalteams
3.3Coordinatevendors4.3Customersatisfactionsurvey
1.4SecureDates2.4Setuptrialcourseandtech3.4Setupevents
1.5SecureLocation2.5Coachtraining
3.5Sign-upbooth,liability
walvers,wrist-band
distrobution
1.6Contactsponsors,contractors,
developers,DJ
2.6Buildwebsite3.6Storageofequipment
1.7Obstaclecoursespeciakist2.7Advertising3.7Tear-downofequipment
1.8SearchforVolunteers/coaches
2.10Sendinvitationstoschools,
etc.
2.11Confirmparticipants
2.12Confirmvendors
2.13Checkweather
TECHLETIC: PROJECT RESPONSIBILITY MATRIX
WBS Elements
ProjectLeader
Corresponant
CreativeTechnical
PartnerRelations
AthleticConsultant
WBS Elements
Angela Jessica Mitchell Micheal Tony
1.1 Approach Chehalem R N N N N
1.2 Budget N R N N N
1.3 Evaluate Cost N R N N N
1.4 Secure Dates A R A A A
1.5 Secure Location A R A A A
1.6
Contact sponsors,
contractors, developers, DJ
N R R N N
1.7 Obstacle course specialist R
1.8 Search for Volunteers/coaches R
2.1 Confirm Pricing N R N N N
2.2 Confirm Sponsors N R N N N
2.3
Contact coaches, volunteers,
and notify security/medical
teams
N R
2.4 Set up trial course and tech N R
2.5 Coach training R
2.6 Build website R
2.7 Advertising S S S R S
2.8 Send invitations to schools, etc. R
2.9 Confirm participants R
2.10 Confirm vendors S R
2.11 Check weather R
3.1 Emergency teams on station R S
3.2 Security on station R
3.3 Coordinate vendors R
3.4 Set up events R S S S S
3.5
Sign-up booth, liability
walvers, wrist-band
distrobution
R
3.6 Storage of equipment S R S S S
3.7 Tear-down of equipment S S R S S
4.1 Post-event debrief S S S R S
4.2 After-action report S S S S R
4.3 Customer satisfaction survey N N N R N
Key: S: Support, N: Must be notified, C:Must be consulted, A:Approval Required
Planning
Event Days
Review
WBS Elements
Preparation
TECHLETIC: PROJECT NETWORK DIAGRAM
	
Approach Chehalem
Start: Mon 2/29/16 ID: 1
Finish: Thu 3/17/16 Dur: 14 days
Res: Anglea
Budget
Start: Fri 3/18/16 ID: 2
Finish: Mon 3/28/16Dur: 7 days
Res: Jessica
Evaluate cost
Start: Tue 3/29/16 ID: 3
Finish: Mon 4/11/16Dur: 10 days
Res: Jessica
Confirm pricing
Start: Tue 4/12/16 ID: 4
Finish: Thu 4/14/16 Dur: 3 days
Res: Jessica
Secure location
Start: Fri 4/15/16 ID: 6
Finish: Mon 4/25/16Dur: 7 days
Res: Jessica
Search for volunteers/coaches
Start: Tue 4/26/16 ID: 9
Finish: Mon 6/6/16 Dur: 30 days
Res: Tony
Contact coaches, volnteers, and notify security/medical teams
Start: Tue 6/7/16 ID: 11
Finish: Fri 6/24/16 Dur: 14 days
Res: Tony
Set up trial course and tech
Start: Mon 6/27/16 ID: 12
Finish: Tue 7/5/16 Dur: 7 days
Res: Tony
Coach trainers
Start: Wed 7/6/16 ID: 13
Finish: Fri 7/8/16 Dur: 3 days
Res: Tony
Build website
Start: Wed 7/6/16 ID: 14
Finish: Thu 7/14/16 Dur: 7 days
Res: Mitchell
Secure dates
Start: Fri 4/15/16 ID: 5
Finish: Tue 4/19/16 Dur: 3 days
Res: Jessica
Contact sponsors, contractors, developers, DJ, and Vedors
Start: Tue 4/26/16 ID: 7
Finish: Mon 6/6/16 Dur: 30 days
Res: Jessica, Mitchell
Obstacle course specialist
Start: Tue 4/26/16 ID: 8
Finish: Fri 5/13/16 Dur: 14 days
Res: Mitchell
Confirm vendors
Start: Mon 7/11/16 ID: 18
Finish: Thu 7/28/16 Dur: 14 days
Res: Mitchell
Coordinate vedors
Start: Fri 7/29/16 ID: 22
Finish: Mon 8/1/16 Dur: 2 days
Res: Mitchell
Check weather
Start: Fri 7/29/16 ID: 19
Finish: Fri 7/29/16 Dur: 1 day
Res: Angela
Confirm sponsors
Start: Tue 6/7/16 ID: 10
Finish: Fri 6/24/16 Dur: 14 days
Res: Jessica
Emergency teams on station
Start: Wed 8/3/16 ID: 20
Finish: Thu 8/4/16 Dur: 2 days
Res: Angela
Security on station
Start: Mon 8/1/16 ID: 21
Finish: Tue 8/2/16 Dur: 2 days
Res: Michael
Set up event
Start: Mon 8/1/16 ID: 23
Finish: Tue 8/2/16 Dur: 2 days
Res: Angela, Jessica, Michael, Mitchell, Tony
Sign-up booth, liability waivers, wrist-band distrobution
Start: Mon 8/1/16 ID: 24
Finish: Tue 8/2/16 Dur: 2 days
Res: Angela
Storage of equipment
Start: Wed 8/3/16 ID: 25
Finish: Wed 8/3/16 Dur: 1 day
Res: Angela, Jessica, Michael, Mitchell, Tony
Tear-down of equipment
Start: Thu 8/4/16 ID: 26
Finish: Fri 8/5/16 Dur: 2 days
Res: Angela, Jessica, Michael, Mitchell, Tony Customer satisfaction survey
Start: Mon 8/8/16 ID: 29
Finish: Mon 8/8/16 Dur: 1 day
Res: Michael
After-action report
Start: Mon 8/8/16 ID: 28
Finish: Mon 8/8/16 Dur: 1 day
Res: Angela, Jessica, Michael, Mitchell, Tony
Post-even debrief
Start: Mon 8/8/16 ID: 27
Finish: Mon 8/8/16 Dur: 1 day
Res: Angela, Jessica, Michael, Mitchell, Tony
Advertising
Start: Fri 7/15/16 ID: 15
Finish: Thu 7/21/16 Dur: 5 days
Res: Michael
Send invitations to schools, etc.
Start: Fri 7/15/16 ID: 16
Finish: Thu 7/28/16 Dur: 10 days
Res: Mitchell
Confirm participants
Start: Fri 7/29/16 ID: 17
Finish: Tue 8/2/16 Dur: 3 days
Res: Michael
Page 1
TECHLETIC: PROJECT SCHEDULE
IDTask
Mode
TaskNameDuration
1ApproachChehalem14days
2Budget7days
3Evaluatecost10days
4Confirmpricing3days
5Securedates3days
6Securelocation7days
7Contactsponsors,
contractors,developers,
DJ,andVedors
30days
8Obstaclecourse
specialist
14days
9Searchfor
volunteers/coaches
30days
10Confirmsponsors14days
11Contactcoaches,
volnteers,andnotify
security/medicalteams
14days
12Setuptrialcourseand
tech
7days
13Coachtrainers3days
14Buildwebsite7days
15Advertising5days
16Sendinvitationsto
schools,etc.
10days
17Confirmparticipants3days
18Confirmvendors14days
19Checkweather1day
20Emergencyteamson
station
2days
21Securityonstation2days
22Coordinatevedors2days
23Setupevent2days
24Sign-upbooth,liability
waivers,wrist-band
distrobution
2days
25Storageofequipment1day
26Tear-downofequipment2days
27Post-evendebrief1day
28After-actionreport1day
29Customersatisfaction
survey
1day
Anglea
Jessica
Jessica
Jessica
Jessica
Jessica
Jessica,Mitchell
Mitchell
Tony
Jessica
Tony
Tony
Tony
Mitchell
Michael
Mitchell
Michael
Mitchell
Angela
Angela
Michael
Mitchell
Angela,Jessica,Michael,Mitchell,Tony
Angela
Angela,Jessica,Michael,Mitchell,Tony
Angela,Jessica,Michael,Mitchell,Tony
Angela,Jessica,Michael,Mitchell,Tony
Angela,Jessica,Michael,Mitchell,Tony
Michael
21286132027310172418152229512192631017243171421284111825
Feb'16Mar'16Apr'16May'16Jun'16Jul'16Aug'16Sep'16
Task
Split
Milestone
Summary
ProjectSummary
InactiveTask
InactiveMilestone
InactiveSummary
ManualTask
Duration-only
ManualSummaryRollup
ManualSummary
Start-only
Finish-only
ExternalTasks
ExternalMilestone
Deadline
Critical
CriticalSplit
Progress
ManualProgress
Page1
Project:Athlet-tech
Date:Mon3/28/16
TECHLETIC: PROJECT CRITICAL TO QUALITY TREE
ResourceTimeAllottedDollarAmount/DescriptionTotalAllottedCost
Volunteers
GroupVolunteerTimeAverageof6hoursaweekfor20weeks$0120hoursperperson=600
Dry-RunSetupDayVolunteerOneDay:20volunteersfor8hours$08hoursperperson=160
2-DayEventVolunteersTwoDays:40Volunteersfor8hourseachday$016hoursperperson=640
Expenses
CourseMaterials:ropes,obstacles,andsand(Set-up&tear-downhoursincludedinvolunteertime)$5,000$3,000
Laddersforset-upN/A5laddersat$40$200aday=$400
BannersN/A7X3bannerat$47.252banners=$94.50
Ipad4RentalN/A$40forfirstdayand$15for2nddayperIpad10Ipads=$400+$150=$550
Website15hoursforwebsitebuildFreeonWix15hoursand$0
Marketing&AdvertisingMaterials3hoursaweekfor20weeks$1,00060hoursand$1000
LiabilitiesInsuranceN/AMilliondollarsinliabilityforevent$250$250
TicketandWristbandsN/A(Assumingwereachourgoalof150-200peopleaday$200)$200
WaterN/A$50$50
MedicalandSecurity
EmergencyResponseTeam8hourseachday$02days=16hours
Police8hourseachday$02days=16hours
PossibleExtraCosts
Tentsincaseofrain210X20Tentsat$130WeekendRental=$260
Spraybottlefanmistersincaseofhottemps30at$4each$120
TotalTimeandMoney=1507hoursand$5544.50
(Totalwithtents=$5804.50)
(Totalwithspraybottles=$5664.50)
VENDOR/CHEHALEMPARK&REC.
$2772.50willbeputupbyChehalemand$2772.50by
vendors/sponsors
$6000willbedonatedbacktoChehalem
TECHLETIC: PROJECT RISK ASSESSMENT
 
Potential Failure Mode Effect of Failure Cause of Failure Detection of Failure Solution and/or Control of Failure Risk Failure 
Lack of sponsor Interest Not enough capital to fund the event, not 
enough vendors for food and drink 
1)Not enough effort made into 
acquiring them,  
2)Not enough excess money for 
corporate­­ poor economic 
environment 
By solidifying sponsors early on 
and creating a date where they all 
must be confirmed 
1)Communication with sponsors early and often in 
the process, 2)Offer the best sales pitch as to why 
this event is important for them to be involved 
with­­value proposition 
Moderate 
Weather Low volunteer and participant turnout, 
possible poor experience 
Mother Nature­­Hot weather (Event is 
in August) or possible rain 
Weather forecast starting a week 
before the event 
1)The event will be held in August to ensure the 
best outcome.  
2)We will bring tents in case of rain if the forecast 
suggests.  
3)Adversely, if the forecast suggests higher than 
95, bring fan misters 
Moderately Low 
Lack of Public Interest (Minimal 
Number of Participants) 
1)Inability to meet sponsor needs for 
business (They will be selling food and 
drinks)  
2)Lack of proceeds to benefit Chehalem 
Parks & Rec 
1)Not enough advertising/marketing in 
the community  
2)Ineffective advertising/marketing 
  
Being on top of ticket sales and 
website traffic 
1)Creation of website just for the event  
2) Reaching out to schools in the area  
3) Push the benefit of the event to adults 
Moderate 
Lack of Volunteer Participation 1)Disorganized and chaotic 2)Children 
getting hurt because of lack of supervision 
3)Frustrated parents 4)Participant 
satisfaction drops significantly 
1)Not enough reaching out in 
community­­poor recruitment strategy 
2)Ineffective pitch to volunteers as to 
how the event will benefit the 
community  
3)Volunteers are sick 
Constant communication between 
our team and volunteers to keep an 
active and updated roster 
Extensive and detailed planning before 
event­­­directions to the event site, update 
volunteer roster, constant communication 
Low 
Logistics: Course Set­up 1)No event without the course set­up  
2)Hurt children if not properly set­up 
1)Not enough volunteers  
2)Poor leadership and lack of direction  
3)Lack of proper training  
4)Lack of all the pieces showing up on 
time 
1)Unstable structures 2)Safety 
inspection failure 
3)Communication with set­up team 
prior to event  
1) Dry run event to get the kinks out  
2) Safety Inspection the day before event 
3)Communication with set­up team prior to event 
Moderately Low 
Competing Events Inability to attract a large enough crowd to 
satisfy charitable and sponsor/vendor 
needs 
1)Limited monitoring and response to 
other events 
 2)Lack of coordination with other 
events  
3)Summer camps, sports  
Planning and coordination of local 
events well before we choose a 
date  
1)Communicate with Chehalem Parks and Rec 
about other events during time period 
2)Communicate with local schools and what events 
kids participate in  
Low 
Children Safety 1)Children getting hurt  
2)Parent lawsuits  
1)No medical staff  
2) Unstable structures  
3)Not enough volunteer staff 
Preparation  Partner with medical teams and police department 
to help with the event 
Moderately Low 
 
 
 
TECHLETIC: PROJECT A3

More Related Content

Viewers also liked

Cuento teatrín porque lloras
Cuento teatrín porque llorasCuento teatrín porque lloras
Cuento teatrín porque lloraskatyaroxanameza
 
Dramatización
DramatizaciónDramatización
Dramatizaciónmezakaren
 
ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)
ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)
ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)HarunyahyaUrdu
 
Poetica y narrativa del espacio
Poetica y narrativa del espacio  Poetica y narrativa del espacio
Poetica y narrativa del espacio planarqubvbolivar
 
The environmental considerations and barriers involved with developing wind e...
The environmental considerations and barriers involved with developing wind e...The environmental considerations and barriers involved with developing wind e...
The environmental considerations and barriers involved with developing wind e...MacDarragh Fitzpatrick
 
D1T1 overview of the theoretical foundations for ecological niche models
D1T1 overview of the theoretical foundations for ecological niche modelsD1T1 overview of the theoretical foundations for ecological niche models
D1T1 overview of the theoretical foundations for ecological niche modelsTown Peterson
 

Viewers also liked (7)

Cuento teatrín porque lloras
Cuento teatrín porque llorasCuento teatrín porque lloras
Cuento teatrín porque lloras
 
Dramatización
DramatizaciónDramatización
Dramatización
 
ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)
ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)
ایک انسان کے معجزات. انسانی معجزات. Urdū (اُردُو)
 
Poetica y narrativa del espacio
Poetica y narrativa del espacio  Poetica y narrativa del espacio
Poetica y narrativa del espacio
 
The environmental considerations and barriers involved with developing wind e...
The environmental considerations and barriers involved with developing wind e...The environmental considerations and barriers involved with developing wind e...
The environmental considerations and barriers involved with developing wind e...
 
D1T1 overview of the theoretical foundations for ecological niche models
D1T1 overview of the theoretical foundations for ecological niche modelsD1T1 overview of the theoretical foundations for ecological niche models
D1T1 overview of the theoretical foundations for ecological niche models
 
Mini dal mill
Mini dal millMini dal mill
Mini dal mill
 

Similar to Techletic Final

Project Management Final Project
Project Management Final ProjectProject Management Final Project
Project Management Final ProjectBrea Silva
 
Running Head Compensation and Benefit Package Planning1.docx
Running Head Compensation and Benefit Package Planning1.docxRunning Head Compensation and Benefit Package Planning1.docx
Running Head Compensation and Benefit Package Planning1.docxtodd271
 
1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docx1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docxkarisariddell
 
I need this assignment done using this paper that follows it.Pro.docx
I need this assignment done using this paper that follows it.Pro.docxI need this assignment done using this paper that follows it.Pro.docx
I need this assignment done using this paper that follows it.Pro.docxevontdcichon
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morekimchibhendalbhai070
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpcmmaao
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmppmicmmaao
 
Project Charter template (contains Scope Section) project nameExe.docx
Project Charter template (contains Scope Section)  project nameExe.docxProject Charter template (contains Scope Section)  project nameExe.docx
Project Charter template (contains Scope Section) project nameExe.docxstilliegeorgiana
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
SolutionStream Case Study 2021.pdf
SolutionStream Case Study 2021.pdfSolutionStream Case Study 2021.pdf
SolutionStream Case Study 2021.pdfStoriesOnBoard
 
Near east university
Near east universityNear east university
Near east universityDerrickDusabe
 
For the week 7 Final Project you will create a presentation (CO8)
For the week 7 Final Project you will create a presentation (CO8) For the week 7 Final Project you will create a presentation (CO8)
For the week 7 Final Project you will create a presentation (CO8) ShainaBoling829
 
For word document Part 1 Project Budget (Cost Management)1. .docx
For word document Part 1 Project Budget (Cost Management)1. .docxFor word document Part 1 Project Budget (Cost Management)1. .docx
For word document Part 1 Project Budget (Cost Management)1. .docxericbrooks84875
 
FINALS-INFO-MGT.-LESSON-1.pptx
FINALS-INFO-MGT.-LESSON-1.pptxFINALS-INFO-MGT.-LESSON-1.pptx
FINALS-INFO-MGT.-LESSON-1.pptxshiedakayn1
 

Similar to Techletic Final (20)

Project Management Final Project
Project Management Final ProjectProject Management Final Project
Project Management Final Project
 
Running Head Compensation and Benefit Package Planning1.docx
Running Head Compensation and Benefit Package Planning1.docxRunning Head Compensation and Benefit Package Planning1.docx
Running Head Compensation and Benefit Package Planning1.docx
 
1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docx1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docx
 
I need this assignment done using this paper that follows it.Pro.docx
I need this assignment done using this paper that follows it.Pro.docxI need this assignment done using this paper that follows it.Pro.docx
I need this assignment done using this paper that follows it.Pro.docx
 
computer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for morecomputer science.docx. Mohit Class 12 follow for more
computer science.docx. Mohit Class 12 follow for more
 
Project management
Project managementProject management
Project management
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmp
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmp
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmp
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmp
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmp
 
Cmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmpCmmaao cba-pmi-pmp
Cmmaao cba-pmi-pmp
 
Project Charter template (contains Scope Section) project nameExe.docx
Project Charter template (contains Scope Section)  project nameExe.docxProject Charter template (contains Scope Section)  project nameExe.docx
Project Charter template (contains Scope Section) project nameExe.docx
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
SolutionStream Case Study 2021.pdf
SolutionStream Case Study 2021.pdfSolutionStream Case Study 2021.pdf
SolutionStream Case Study 2021.pdf
 
Near east university
Near east universityNear east university
Near east university
 
JIT Project
JIT ProjectJIT Project
JIT Project
 
For the week 7 Final Project you will create a presentation (CO8)
For the week 7 Final Project you will create a presentation (CO8) For the week 7 Final Project you will create a presentation (CO8)
For the week 7 Final Project you will create a presentation (CO8)
 
For word document Part 1 Project Budget (Cost Management)1. .docx
For word document Part 1 Project Budget (Cost Management)1. .docxFor word document Part 1 Project Budget (Cost Management)1. .docx
For word document Part 1 Project Budget (Cost Management)1. .docx
 
FINALS-INFO-MGT.-LESSON-1.pptx
FINALS-INFO-MGT.-LESSON-1.pptxFINALS-INFO-MGT.-LESSON-1.pptx
FINALS-INFO-MGT.-LESSON-1.pptx
 

Techletic Final

  • 1. Running head: TECHLETIC: PROJECT NARRATIVE Techletic: Project Narrative Mitchell Ajimatanrareje, Tony Long, Angela Richmond, Michael Trummel, and Jessica Yan George Fox University
  • 2. TECHLETIC: PROJECT NARRATIVE Project Charter The project charter describes in detail the objective(s) of our project. It acts as an introduction to the project and illustrates its importance and value proposition. It is important that the project charter explicitly details the nature of the project, a timeline, who will be involved, and what the product of the project will be at its conclusion. Techletic is a 2-day event proposal for Chehalem Parks and Recreation. Our event proposal creates an obstacle course for children ages 6 – 12 to complete. The obstacle course will consist of a combination of technological puzzles and physical tasks. The purpose of the event will be to encourage children to develop a healthy balance between using their technological devices and playing outside. Through the use of digital puzzles and physical objectives, Techletic will help children participants develop an exciting connection between being active and playing games. Recently, through the “Let’s Move” initiative of the First Lady Michelle Obama, schools and other organizations are creating programs to inspire children to be more active to fight childhood obesity. Chehalem Parks and Rec will host the event, inviting children from all local cities of McMinnville, Sherwood, Wilsonville and Salem. Elementary and Middle Schools will be involved to maximize the potential of attendance by children and their families. During the summer, Chehalem Parks and Rec hosts a variety of events for the community that families can participate in. Techletic will take place the first week (Mon/Tues.) of August. The project will be developed by five project coordinators and executed by Chehalem Parks and Rec. Partnerships with local businesses will ease the financial burden on Chehalem Parks and Rec. Critical to Quality Tree The Critical to Quality Tree helps to obtain a focus on the main objective of our project and the measurable to quantify those objectives. This deliverable highlights the reason we are striving to accomplish the project and how it benefits the major players. It is important for every member of the project team to understand the why and the who. These two major points are imperative for the project team’s overall understanding. This document will ensure that we are all on the same page and understand the motivation for the project. Our quality driver is to get the participants (kids) outside to play. Keeping kids active and healthy is the important “Why” for what we are trying to accomplish. This can be measured by
  • 3. TECHLETIC: PROJECT NARRATIVE many standards and must show how they are quantified. The performance requirement for the Techletic event for getting kids outside to play is to time the games and obstacle course to ensure the events last longer than one hour. The next quality driver is to have a fun experience. The performance requirement for this is to conduct a customer satisfaction survey after the event concludes. This will highlight any issues or comments that can be used for future events and can be assessed for the quality of the experience. The next participant that will be affected by the event is Chehalem Parks and Rec. The quality driver for a successful event is the safety of all who participate through the performance requirement of a minimized number of injuries. The next quality driver for Chehalem Parks and Rec. will be through financial gain of the event. The performance requirement for this driver is to give back $6,000 upon completion of all expenses and the event concludes. The final participant to be affected by the event are the sponsors. The quality driver for the sponsors will be the perception that the community of participants (parents/children) have of the sponsors who took part in the event and the quality of their contributions. The post-event customer satisfaction survey will be the performance requirement for assessing the quality and validity of the sponsors involved. Work Breakdown Structure The work breakdown structure is an overview of the tasks that need to be accomplished. In our project, we have identified four elements in order to successfully execute the project. These four elements are: 1. Planning: This section includes: develop the budget, secure the dates and locations of the event, contact sponsors, search for volunteers, etc. This will help our team to get the big picture of how the event will look and what we need to prepare for the event. 2. Preparation: This section includes: confirm volunteers, sponsors and vendors, advertising, set up a trial course, check weather and etc. This allows us to make sure that we have everything we need on site ready for the event. 3. Event Day: During the event, it is critical to ensure the event goes smoothly and ensure the safety of the kids. The event day also includes tear-down of equipment and clean up after the event.
  • 4. TECHLETIC: PROJECT NARRATIVE 4. Review: After the event, we will perform a post-event debrief and write an after-action report, as well as send out surveys to our clients so that we can make improvements in future events. Responsibility Matrix There are many tasks in the project that need to be accomplished in order and on time. The responsibility matrix can help a team to identify who is responsible for what task and how they will be supported. The responsibility matrix also tells the team members how their portion of the project connects with the project as a whole. There are four sections in our responsibility matrix, as mentioned in our work breakdown structure. We assigned each team member to be responsible for different tasks and assigned others as support required, to be notified, to be consulted or approval required to hold each other accountable, and accomplish the tasks on time and with quality. Project Network Diagram The Project Network Diagram helps us see the critical chain of events and supporting tasks that help guide us through the project requirements. We can see the entire project and how each task is connected through the chain. As long as we can solidify our tasks and the order/date of those tasks with relation to our respective end date, we can create an efficient and effective Project Network Diagram. Our Project Network Diagram includes every step of the process for the project and the order in which they are required to be accomplished. Each step of the process incorporates the dates in which they start, finish, and who is working on that part of the process. This is where all project team members can easily see the critical chain. Our critical chain consists of the following tasks: approach Chehalem, budget, evaluate costs, confirm pricing, search for volunteers/coaches, contact volunteers/coaches, set-up trial course and tech, contact trainers, confirm vendors, check weather, sign-up booth/liability waivers/wristband distribution, storage of equipment, tear down of equipment, post-event debrief, after action report, and customer satisfaction survey. Project Schedule The purpose of a project schedule is to help those involved in the project to understand best start dates, and latest possible start dates in order to reach the end objective on time. This graphical representation shows the best timeline of the project to reach a specified deadline.
  • 5. TECHLETIC: PROJECT NARRATIVE In order to determine the timeline of our schedule, it was most important to identify the tasks that would take the most time, and identify which team members would be best for those tasks in a manner that would not strain our resources. In addition, it was very important in the process of planning our schedule to determine a date when this event would be best accessible to our target age range. The best possible schedule for our project would be 134 days, with the main two-day event occurring during a Monday and Tuesday the first week of August. By scheduling the date within the summer, more kids ages 6-12 will be available to attend the event. Another reason the event would best in this timeline is that the weather will be warm. To achieve this possible end date the project would need to start mid-February. Project Budget The purpose of the project budget is to help us understand how much money we will be spending to complete the project from start to finish. The budgeting process will start with our team creating a list of everything we will need for the project from start to completion. We will then take this itemized budget to our partner (Chehalem Parks & Rec.) and go over it with them. This process will involve a give and take the scenario to come up with the final budget. Budgets are important to every project so that we can utilize every dollar we have available and stay on track. Every aspect of our project down to the cent will need to be identified before completing this. As noted in the budget, the course materials will cost $5000, 5 ladders at $40 each per day will cost $400, two 7X3 banners at $47.25 each will cost $94.50, 10 Ipad 4’s at $40 each for the first day and $15 each the second day will cost $550, a Wix website for free, marketing/advertising materials will cost $1000 (posters and handouts for schools), $250 for liability insurance with up to a million dollars in liability, tickets and wristbands will cost $200, and water for the participants will cost $50. In the case of extreme weather, we will need two 10X20 tents at $130 each, and 30 spray-fan-misters at $4 each. If it is raining or above 95 degrees, we will incur the corresponding costs from either option. Through this process, we will need $7,544.50 and with the extra costs due to weather extremes, it could be as much as $7804.50 (with rain) or $7664.50 (with extreme heat). The budgeting process not only helps us figure out how much money we will need to complete the project, but also how many hours it will take. In the budget, the amount of
  • 6. TECHLETIC: PROJECT NARRATIVE volunteer and group hours needed for completion are outlined in detail. Our group will average 6 hours a week (5 people total) for 20 weeks which totals to 600 total hours, dry-run set-up day will require 20 volunteers for 8 hours for a total of 160 hours, the 2-day Techletic event will require 40 volunteers for 8 hours each for a total of 640 hours, building the website will take 15 total hours, the marketing/advertising materials and promotion will require a total of 60 hours across the 20 weeks, and we will also need emergency response and police volunteers for a total of 32 hours. Through this process, we will need 1507 total hours. Risk Management Plan The risk management plan will be imperative to the success of our project. This document includes risk assessment of our entire plan. It identifies what risks are possible through our process, the different impacts of each risk, and plans to combat these potential risks. By identifying risks before they happen, it ensures that we will be able to act proactively instead of reactively. The risk management plan highlights seven key areas of the Techletic event that have the most potential to create problems. The seven key areas are as follows: Lack of sponsor interest, weather, lack of public interest (minimal number of participants), lack of volunteer participation, Logistics/course set-up, competing for events, and children safety. We see the highest amount of risk coming from lack of sponsor interest and lack of public interest. We plan to combat the first issue by communicating early and often with the potential sponsors, and by pitching the event in a way that shows its true value to them, the participants, as well as the community. The second issue we will address by making a website specifically for the event, reaching out to schools, and explaining the importance to the parents as to why Techletic is such a special event for their child/children. A3 A smattering of graphical information coupled with specific details of the project representing the entire process of the project. The information provided in the A3 gives a snapshot of the performance of the project. Specific graphical information that is presented in the A3 for this project is as follows: Goal/Background for Project, Critical to Quality Tree, Project Budget, and Responsibility Matrix.
  • 7. TECHLETIC: PROJECT CHARTER Techletic Project Charter Project Title: Techletic Project Leader: Angela Richmond Team Members: Michael Trummel, Jessica Yan, Tony Long, Jim Bernard (Parks Coordinator), Lynne Patrick (Recreation and Education Coordinator), & Sarah Craft (Recreation Specialist). Business Case: Increased screen-time spent by children ages 6 – 12 has adverse affects on childhood development and increased potential for childhood obesity. Problem/Opportunity Statement: Children ages 6 – 12 need more activities especially during the summer to be active and spend less time in front of a tablet/computer/phone. Goal Statement: Create a 2-day event, the first week of August, combining physical tasks and technology to encourage children to find a balance between playing outside and on their devices. Project Scope: Team members will meet from 12:30 – 2:00PM every Monday. Team members will be responsible for developing specific parts of project plan. Existing data on Chahalem Parks and Rec events will be compiled and assessed for events specifically relating to children. Stakeholders: Food Vendors, Coaches, Event Coordinators, Supervisors, Security, Field Physicians, Set-up Staff, Tear-down Staff, Clean-up staff, Attendants, Volunteers, Sponsors & Chehalem Parks & Rec.
  • 8. TECHLETIC: PROJECT CRITICAL TO QUALITY TREE WhoQualityDriverPerformanceRequirement Participants Chehalem ParksandRec. Sponsors Exercise60minutes FunExperience FinancialGain SafeEvent Communityperception Gamesandobstaclecourseduration Post-eventsurvey $6,000donation Minimizednumberofinjuries Post-eventsurvey
  • 9. TECHLETIC: PROJECT RISK WORK BREAK DOWN STRUCTURE 1.0Planning2.0Preparation3.0EventDays4.0Review 1.1ApproachChehalem2.1ConfirmPricing 3.1Emergencyteamson station 4.1Post-eventdebrief 1.2Budget2.2ConfirmSponsors3.2Securityonstation4.2After-actionreport 1.3EvaluateCost 2.3Contactcoaches,volunteers, andnotifysecurity/medicalteams 3.3Coordinatevendors4.3Customersatisfactionsurvey 1.4SecureDates2.4Setuptrialcourseandtech3.4Setupevents 1.5SecureLocation2.5Coachtraining 3.5Sign-upbooth,liability walvers,wrist-band distrobution 1.6Contactsponsors,contractors, developers,DJ 2.6Buildwebsite3.6Storageofequipment 1.7Obstaclecoursespeciakist2.7Advertising3.7Tear-downofequipment 1.8SearchforVolunteers/coaches 2.10Sendinvitationstoschools, etc. 2.11Confirmparticipants 2.12Confirmvendors 2.13Checkweather
  • 10. TECHLETIC: PROJECT RESPONSIBILITY MATRIX WBS Elements ProjectLeader Corresponant CreativeTechnical PartnerRelations AthleticConsultant WBS Elements Angela Jessica Mitchell Micheal Tony 1.1 Approach Chehalem R N N N N 1.2 Budget N R N N N 1.3 Evaluate Cost N R N N N 1.4 Secure Dates A R A A A 1.5 Secure Location A R A A A 1.6 Contact sponsors, contractors, developers, DJ N R R N N 1.7 Obstacle course specialist R 1.8 Search for Volunteers/coaches R 2.1 Confirm Pricing N R N N N 2.2 Confirm Sponsors N R N N N 2.3 Contact coaches, volunteers, and notify security/medical teams N R 2.4 Set up trial course and tech N R 2.5 Coach training R 2.6 Build website R 2.7 Advertising S S S R S 2.8 Send invitations to schools, etc. R 2.9 Confirm participants R 2.10 Confirm vendors S R 2.11 Check weather R 3.1 Emergency teams on station R S 3.2 Security on station R 3.3 Coordinate vendors R 3.4 Set up events R S S S S 3.5 Sign-up booth, liability walvers, wrist-band distrobution R 3.6 Storage of equipment S R S S S 3.7 Tear-down of equipment S S R S S 4.1 Post-event debrief S S S R S 4.2 After-action report S S S S R 4.3 Customer satisfaction survey N N N R N Key: S: Support, N: Must be notified, C:Must be consulted, A:Approval Required Planning Event Days Review WBS Elements Preparation
  • 11. TECHLETIC: PROJECT NETWORK DIAGRAM Approach Chehalem Start: Mon 2/29/16 ID: 1 Finish: Thu 3/17/16 Dur: 14 days Res: Anglea Budget Start: Fri 3/18/16 ID: 2 Finish: Mon 3/28/16Dur: 7 days Res: Jessica Evaluate cost Start: Tue 3/29/16 ID: 3 Finish: Mon 4/11/16Dur: 10 days Res: Jessica Confirm pricing Start: Tue 4/12/16 ID: 4 Finish: Thu 4/14/16 Dur: 3 days Res: Jessica Secure location Start: Fri 4/15/16 ID: 6 Finish: Mon 4/25/16Dur: 7 days Res: Jessica Search for volunteers/coaches Start: Tue 4/26/16 ID: 9 Finish: Mon 6/6/16 Dur: 30 days Res: Tony Contact coaches, volnteers, and notify security/medical teams Start: Tue 6/7/16 ID: 11 Finish: Fri 6/24/16 Dur: 14 days Res: Tony Set up trial course and tech Start: Mon 6/27/16 ID: 12 Finish: Tue 7/5/16 Dur: 7 days Res: Tony Coach trainers Start: Wed 7/6/16 ID: 13 Finish: Fri 7/8/16 Dur: 3 days Res: Tony Build website Start: Wed 7/6/16 ID: 14 Finish: Thu 7/14/16 Dur: 7 days Res: Mitchell Secure dates Start: Fri 4/15/16 ID: 5 Finish: Tue 4/19/16 Dur: 3 days Res: Jessica Contact sponsors, contractors, developers, DJ, and Vedors Start: Tue 4/26/16 ID: 7 Finish: Mon 6/6/16 Dur: 30 days Res: Jessica, Mitchell Obstacle course specialist Start: Tue 4/26/16 ID: 8 Finish: Fri 5/13/16 Dur: 14 days Res: Mitchell Confirm vendors Start: Mon 7/11/16 ID: 18 Finish: Thu 7/28/16 Dur: 14 days Res: Mitchell Coordinate vedors Start: Fri 7/29/16 ID: 22 Finish: Mon 8/1/16 Dur: 2 days Res: Mitchell Check weather Start: Fri 7/29/16 ID: 19 Finish: Fri 7/29/16 Dur: 1 day Res: Angela Confirm sponsors Start: Tue 6/7/16 ID: 10 Finish: Fri 6/24/16 Dur: 14 days Res: Jessica Emergency teams on station Start: Wed 8/3/16 ID: 20 Finish: Thu 8/4/16 Dur: 2 days Res: Angela Security on station Start: Mon 8/1/16 ID: 21 Finish: Tue 8/2/16 Dur: 2 days Res: Michael Set up event Start: Mon 8/1/16 ID: 23 Finish: Tue 8/2/16 Dur: 2 days Res: Angela, Jessica, Michael, Mitchell, Tony Sign-up booth, liability waivers, wrist-band distrobution Start: Mon 8/1/16 ID: 24 Finish: Tue 8/2/16 Dur: 2 days Res: Angela Storage of equipment Start: Wed 8/3/16 ID: 25 Finish: Wed 8/3/16 Dur: 1 day Res: Angela, Jessica, Michael, Mitchell, Tony Tear-down of equipment Start: Thu 8/4/16 ID: 26 Finish: Fri 8/5/16 Dur: 2 days Res: Angela, Jessica, Michael, Mitchell, Tony Customer satisfaction survey Start: Mon 8/8/16 ID: 29 Finish: Mon 8/8/16 Dur: 1 day Res: Michael After-action report Start: Mon 8/8/16 ID: 28 Finish: Mon 8/8/16 Dur: 1 day Res: Angela, Jessica, Michael, Mitchell, Tony Post-even debrief Start: Mon 8/8/16 ID: 27 Finish: Mon 8/8/16 Dur: 1 day Res: Angela, Jessica, Michael, Mitchell, Tony Advertising Start: Fri 7/15/16 ID: 15 Finish: Thu 7/21/16 Dur: 5 days Res: Michael Send invitations to schools, etc. Start: Fri 7/15/16 ID: 16 Finish: Thu 7/28/16 Dur: 10 days Res: Mitchell Confirm participants Start: Fri 7/29/16 ID: 17 Finish: Tue 8/2/16 Dur: 3 days Res: Michael Page 1
  • 12. TECHLETIC: PROJECT SCHEDULE IDTask Mode TaskNameDuration 1ApproachChehalem14days 2Budget7days 3Evaluatecost10days 4Confirmpricing3days 5Securedates3days 6Securelocation7days 7Contactsponsors, contractors,developers, DJ,andVedors 30days 8Obstaclecourse specialist 14days 9Searchfor volunteers/coaches 30days 10Confirmsponsors14days 11Contactcoaches, volnteers,andnotify security/medicalteams 14days 12Setuptrialcourseand tech 7days 13Coachtrainers3days 14Buildwebsite7days 15Advertising5days 16Sendinvitationsto schools,etc. 10days 17Confirmparticipants3days 18Confirmvendors14days 19Checkweather1day 20Emergencyteamson station 2days 21Securityonstation2days 22Coordinatevedors2days 23Setupevent2days 24Sign-upbooth,liability waivers,wrist-band distrobution 2days 25Storageofequipment1day 26Tear-downofequipment2days 27Post-evendebrief1day 28After-actionreport1day 29Customersatisfaction survey 1day Anglea Jessica Jessica Jessica Jessica Jessica Jessica,Mitchell Mitchell Tony Jessica Tony Tony Tony Mitchell Michael Mitchell Michael Mitchell Angela Angela Michael Mitchell Angela,Jessica,Michael,Mitchell,Tony Angela Angela,Jessica,Michael,Mitchell,Tony Angela,Jessica,Michael,Mitchell,Tony Angela,Jessica,Michael,Mitchell,Tony Angela,Jessica,Michael,Mitchell,Tony Michael 21286132027310172418152229512192631017243171421284111825 Feb'16Mar'16Apr'16May'16Jun'16Jul'16Aug'16Sep'16 Task Split Milestone Summary ProjectSummary InactiveTask InactiveMilestone InactiveSummary ManualTask Duration-only ManualSummaryRollup ManualSummary Start-only Finish-only ExternalTasks ExternalMilestone Deadline Critical CriticalSplit Progress ManualProgress Page1 Project:Athlet-tech Date:Mon3/28/16
  • 13. TECHLETIC: PROJECT CRITICAL TO QUALITY TREE ResourceTimeAllottedDollarAmount/DescriptionTotalAllottedCost Volunteers GroupVolunteerTimeAverageof6hoursaweekfor20weeks$0120hoursperperson=600 Dry-RunSetupDayVolunteerOneDay:20volunteersfor8hours$08hoursperperson=160 2-DayEventVolunteersTwoDays:40Volunteersfor8hourseachday$016hoursperperson=640 Expenses CourseMaterials:ropes,obstacles,andsand(Set-up&tear-downhoursincludedinvolunteertime)$5,000$3,000 Laddersforset-upN/A5laddersat$40$200aday=$400 BannersN/A7X3bannerat$47.252banners=$94.50 Ipad4RentalN/A$40forfirstdayand$15for2nddayperIpad10Ipads=$400+$150=$550 Website15hoursforwebsitebuildFreeonWix15hoursand$0 Marketing&AdvertisingMaterials3hoursaweekfor20weeks$1,00060hoursand$1000 LiabilitiesInsuranceN/AMilliondollarsinliabilityforevent$250$250 TicketandWristbandsN/A(Assumingwereachourgoalof150-200peopleaday$200)$200 WaterN/A$50$50 MedicalandSecurity EmergencyResponseTeam8hourseachday$02days=16hours Police8hourseachday$02days=16hours PossibleExtraCosts Tentsincaseofrain210X20Tentsat$130WeekendRental=$260 Spraybottlefanmistersincaseofhottemps30at$4each$120 TotalTimeandMoney=1507hoursand$5544.50 (Totalwithtents=$5804.50) (Totalwithspraybottles=$5664.50) VENDOR/CHEHALEMPARK&REC. $2772.50willbeputupbyChehalemand$2772.50by vendors/sponsors $6000willbedonatedbacktoChehalem
  • 14. TECHLETIC: PROJECT RISK ASSESSMENT   Potential Failure Mode Effect of Failure Cause of Failure Detection of Failure Solution and/or Control of Failure Risk Failure  Lack of sponsor Interest Not enough capital to fund the event, not  enough vendors for food and drink  1)Not enough effort made into  acquiring them,   2)Not enough excess money for  corporate­­ poor economic  environment  By solidifying sponsors early on  and creating a date where they all  must be confirmed  1)Communication with sponsors early and often in  the process, 2)Offer the best sales pitch as to why  this event is important for them to be involved  with­­value proposition  Moderate  Weather Low volunteer and participant turnout,  possible poor experience  Mother Nature­­Hot weather (Event is  in August) or possible rain  Weather forecast starting a week  before the event  1)The event will be held in August to ensure the  best outcome.   2)We will bring tents in case of rain if the forecast  suggests.   3)Adversely, if the forecast suggests higher than  95, bring fan misters  Moderately Low  Lack of Public Interest (Minimal  Number of Participants)  1)Inability to meet sponsor needs for  business (They will be selling food and  drinks)   2)Lack of proceeds to benefit Chehalem  Parks & Rec  1)Not enough advertising/marketing in  the community   2)Ineffective advertising/marketing     Being on top of ticket sales and  website traffic  1)Creation of website just for the event   2) Reaching out to schools in the area   3) Push the benefit of the event to adults  Moderate  Lack of Volunteer Participation 1)Disorganized and chaotic 2)Children  getting hurt because of lack of supervision  3)Frustrated parents 4)Participant  satisfaction drops significantly  1)Not enough reaching out in  community­­poor recruitment strategy  2)Ineffective pitch to volunteers as to  how the event will benefit the  community   3)Volunteers are sick  Constant communication between  our team and volunteers to keep an  active and updated roster  Extensive and detailed planning before  event­­­directions to the event site, update  volunteer roster, constant communication  Low  Logistics: Course Set­up 1)No event without the course set­up   2)Hurt children if not properly set­up  1)Not enough volunteers   2)Poor leadership and lack of direction   3)Lack of proper training   4)Lack of all the pieces showing up on  time  1)Unstable structures 2)Safety  inspection failure  3)Communication with set­up team  prior to event   1) Dry run event to get the kinks out   2) Safety Inspection the day before event  3)Communication with set­up team prior to event  Moderately Low  Competing Events Inability to attract a large enough crowd to  satisfy charitable and sponsor/vendor  needs  1)Limited monitoring and response to  other events   2)Lack of coordination with other  events   3)Summer camps, sports   Planning and coordination of local  events well before we choose a  date   1)Communicate with Chehalem Parks and Rec  about other events during time period  2)Communicate with local schools and what events  kids participate in   Low  Children Safety 1)Children getting hurt   2)Parent lawsuits   1)No medical staff   2) Unstable structures   3)Not enough volunteer staff  Preparation  Partner with medical teams and police department  to help with the event  Moderately Low