SlideShare a Scribd company logo
1 of 13
Download to read offline
A CRITIQUE
IMPOSSIBILITY & DOCTRINE
OF FRUSTRATION
as interpreted by the SC in Energy Watchdog v. CERC (Adani Case)
1Aditi Duggal | SLS Noida
ENERGY WATCHDOG v. CERC
2
 1.) Power Purchase Agreements :. Clause 12.3 defined force majeure to
include any event or circumstance or combination thereof which “wholly
or partly prevents” performance of obligations. Clause 12.7(a) stated that
the affected party will be immune if performance was “prevented,
hindered or delayed” due to a force majeure event. Clause 12.4(ii)
excluded applicability of force majeure to changes in cost of fuel for the
project or onerous performance of the agreement.
 2.) Rise in price of coal : An unforeseeable change in Indonesian
regulation aligned the coal prices to international prices which made
procurement unforeseeably exorbitant thereby hindering the performance
of obligations under PPAs.
 3.) Defense of frustration : It was argued that they should either be
discharged on account of frustration of the PPAs or restored to the same
economic position prior to force majeure and/or change in law. The matter
went to CERC and then to APTEL & was ultimately decided by the SC.
Aditi Duggal | SLS Noida
LEGISLATIVE INTENT
32 – Contingent contracts 56 – Impossibility of performance
The contract can be enforced on the
happening of the contingent event
which, on becoming impossible, renders
the contract void.
It is a rule of positive law embodying the
doctrine of frustration. In order for
frustration to apply, contract must fall
under section 32 or 56.
No present obligation; The obligation
arises on the occurrence of the
contingent event
Doctrine of frustration implies discharge
of contract due to supervening
impossibility or illegality of the act
The fulfilment of condition has the effect
of converting potential obligation into
actual obligation
Impossibility must be interpreted
“practically” & not “literally” i.e.
fundamental basis of contract should
be materially altered beyond the
contemplation of parties
Parties pre-contemplate the
contingency & accordingly draft the
contract in express or implied
contractual terms.
Parties do not contemplate beforehand
the impossibility or unlawfulness of the
act agreed to be done. It is not applicable
to self-induced frustration & express
contractual stipulation to that extent.
FORESEEABILITY MUST BE
PRESENT. OBJECTIVE INTENT OF
PARTIES
FORESEEABILITY MUST BE ABSENT.
SUBJECTIVE INTENT OF PARTIES
3Aditi Duggal | SLS Noida
SUPREME COURT ON FRUSTRATION &
INAPPLICABILITY OF FORCE MAJEURE
Factually
• Parties knowingly assumed the risk of fluctuation in price.
• Deliberate quoting of non-escalable tariff is not an absolute bar to the
plea of frustration; Alternative modes of performance are an important
factor
• The exclusion of Clause 12.4 applies to the case and consequently, S.
56 does not apply.
Legally
• Narrow construction and non-exhaustive nature of force majeure clauses
• Fundamental basis of contract is the test of impossibility
• Impossibility relates to practicality of performance
• Inadequacy of onerous method of performance & ground of rise in cost
• Multi-factorial approach including context of the contract, knowledge,
contemplations, risk, nature of supervening event, and parties’
contemplation of future performance
4Aditi Duggal | SLS Noida
FINDINGS
Insofar as force majeure is relatable to an express
or implied clause in a contract, it is governed by
Chapter III of the Contract Act, particularly S. 32.
Insofar as a force majeure event occurs dehors the
contract, it is dealt with by a rule of positive law
under Section 56 of the Indian Contract Act
“As has been held, in particular, in Satyabrata
Ghose case, when a contract contains a force
majeure clause which on construction by the
Court is held attracted to the facts of the case,
Section 56 can have no application.”
5Aditi Duggal | SLS Noida
SATYABRATA GHOSE
In the large majority of cases, however, the doctrine of frustration is not
applied on the ground of express or implied contractual terms. The relief
u/s 56 is given on the ground of subsequent impossibility when the
whole purpose or basis of a contract was frustrated by the intrusion or
occurrence of an unexpected event or change of circumstances which
was beyond the contemplation of parties at the time of conclusion of
contract.
It allows for discharge of obligations if an untoward event or change of
circumstance totally upsets the very foundation of the agreement
Section 56 lays down a rule of positive law and does not leave the
matter to be determined according to the intention of the parties
6Aditi Duggal | SLS Noida
FOOD FOR THOUGHT?!!
S. 56 & 32 mutually exclusive : There is no clarification on how
Section 56 operates as a default rule and how the applicability of S. 56
was eclipsed by the application of PPA clause on force majeure
If 56 inapplicable, no reason to go into common law of frustration :.
The judgement first dismisses the defense of S. 56 and later holds that it
is not applicable in the first place. Therefore, it tied the test of
impossibility under S. 32 to that of “fundamental basis” under S. 56
thereby impliedly linking them but expressly separating them at the
same time.
Restrictive interpretation of Satyabrata Ghose : Parties can choose to
override the protection of S. 56 vide the S. 32 route. Satyabrata Ghose
made it clear that S. 56 operates independent of the intent of the Parties.
Adani case validated that parties can, if they so intend, escape the
mandate of S. 56 by contractually resorting to S. 32.
7
Aditi Duggal | SLS Noida
Was applicability
of S. 32 through a
particular clause
legislatively
intended to be an
absolute escape
for the mandate
in S. 56?
Is there actually
no scope of an
overlap between
the two?
8Aditi Duggal | SLS Noida
BURNING QUESTIONS!!!
9
SECTION 56 APPLIES
Bypass the test of section 32 as the fundamental change would be
judged in light of possibility of performance.
Test of section - judge the possibility of the act (whether there is a
fundamental change which would make the performance impossible)
Governs the contract
Aditi Duggal | SLS Noida
10
SECTION 32 APPLIES
Even if the change makes the performance impossible it would not
be considered force majure.
The agreement of parties to consider a change as not fundamental to
the performance of contract would not entail the parties to argue in
future that the change is now fundamental to the performance of the
contract under the purview of Section 56.
Governs the clause
Aditi Duggal | SLS Noida
IS IT JUST??...
11
PRINCIPLE OF EQUALITY
• Party who agreed for a particular act not be considered
impossible should be made liable for performance
• Even if act is impossible the party should be made liable to pay
damages.
PRINCIPLE OF LEGITIMATE
EXPECTATIONS
• When the legitimate expectation of the party who agreed for the
change is violated, the act even violating the legitimate
expectation can be judged in light of Section 56.
Aditi Duggal | SLS Noida
CONCLUSION
Legal Position : Contract law acknowledges impossibility
under Section 56 however simultaneously allows parties to
agree for a particular impossibility not to be considered as a
reason of non-performance.
Ambiguity : Clearly, S. 56 encompasses a wider concept of
impossibility that should not be absolutely curtailed by the
application of S. 32. Satyabrata Ghose should have been,
therefore, read to imply that S. 56 does not apply in the
construction of the particular force majeure clause but it
should still remain available as an alternative basis for
avoidance of obligations in terms of the entire contract.
12Aditi Duggal | SLS Noida
THANK YOU!!
13Aditi Duggal | SLS Noida

More Related Content

What's hot

AGREEMENT EXPRESSLY DECLARED AS VOID
AGREEMENT EXPRESSLY DECLARED AS VOIDAGREEMENT EXPRESSLY DECLARED AS VOID
AGREEMENT EXPRESSLY DECLARED AS VOIDKhushiGoyal20
 
Indian contract act 1872
Indian contract act 1872Indian contract act 1872
Indian contract act 1872rajesh25
 
Contract & agreement
Contract & agreementContract & agreement
Contract & agreementAnkitkumar2943
 
Contract act ch 1 legal aspect of business law
Contract act ch 1  legal aspect of business law Contract act ch 1  legal aspect of business law
Contract act ch 1 legal aspect of business law Karan Kukreja
 
Legal Aspects Of Business Unit - 1 PPTs
Legal Aspects Of Business Unit - 1 PPTsLegal Aspects Of Business Unit - 1 PPTs
Legal Aspects Of Business Unit - 1 PPTsMohan Raj
 
Mortgage vaibhav goyal
Mortgage vaibhav goyalMortgage vaibhav goyal
Mortgage vaibhav goyalVaibhav Goyal
 
Contract act----by sumit mukherjee
Contract act----by sumit  mukherjeeContract act----by sumit  mukherjee
Contract act----by sumit mukherjeesumit mukherjee
 
indian contract and negotiable instrument
indian contract and negotiable instrumentindian contract and negotiable instrument
indian contract and negotiable instrumentsaurabh sen sky
 
Contract and agreement
Contract and agreement Contract and agreement
Contract and agreement AWAN BROTHERS
 
Force Majeure & Commecial Impracticability
Force Majeure & Commecial ImpracticabilityForce Majeure & Commecial Impracticability
Force Majeure & Commecial ImpracticabilityChristopher Tompkins
 
Void agreement and void contract
Void agreement and void contractVoid agreement and void contract
Void agreement and void contractsadir
 

What's hot (17)

AGREEMENT EXPRESSLY DECLARED AS VOID
AGREEMENT EXPRESSLY DECLARED AS VOIDAGREEMENT EXPRESSLY DECLARED AS VOID
AGREEMENT EXPRESSLY DECLARED AS VOID
 
discharge
 discharge discharge
discharge
 
VOID AGREEMENT
VOID AGREEMENTVOID AGREEMENT
VOID AGREEMENT
 
Indian contract act 1872
Indian contract act 1872Indian contract act 1872
Indian contract act 1872
 
Contract & agreement
Contract & agreementContract & agreement
Contract & agreement
 
Contract act ch 1 legal aspect of business law
Contract act ch 1  legal aspect of business law Contract act ch 1  legal aspect of business law
Contract act ch 1 legal aspect of business law
 
Assignment 1
Assignment 1Assignment 1
Assignment 1
 
Legal Aspects Of Business Unit - 1 PPTs
Legal Aspects Of Business Unit - 1 PPTsLegal Aspects Of Business Unit - 1 PPTs
Legal Aspects Of Business Unit - 1 PPTs
 
Ica 5
Ica 5Ica 5
Ica 5
 
Mortgage vaibhav goyal
Mortgage vaibhav goyalMortgage vaibhav goyal
Mortgage vaibhav goyal
 
Contract act----by sumit mukherjee
Contract act----by sumit  mukherjeeContract act----by sumit  mukherjee
Contract act----by sumit mukherjee
 
indian contract and negotiable instrument
indian contract and negotiable instrumentindian contract and negotiable instrument
indian contract and negotiable instrument
 
Contract and agreement
Contract and agreement Contract and agreement
Contract and agreement
 
Business
BusinessBusiness
Business
 
Force Majeure & Commecial Impracticability
Force Majeure & Commecial ImpracticabilityForce Majeure & Commecial Impracticability
Force Majeure & Commecial Impracticability
 
Void agreement and void contract
Void agreement and void contractVoid agreement and void contract
Void agreement and void contract
 
Force Majeure
Force Majeure Force Majeure
Force Majeure
 

Similar to Presentation aditi duggal

Validity of contingent contracts under ica
Validity of contingent contracts under icaValidity of contingent contracts under ica
Validity of contingent contracts under icaRatul7
 
Termination of contract
Termination of contractTermination of contract
Termination of contractNcell
 
Article force majeure in covid rcllp
Article force majeure in covid rcllpArticle force majeure in covid rcllp
Article force majeure in covid rcllpChetan Konaraddi
 
Non-complete Clauses , Stamp duties , Rectification deed , Consultancy Agree...
Non-complete Clauses ,  Stamp duties , Rectification deed , Consultancy Agree...Non-complete Clauses ,  Stamp duties , Rectification deed , Consultancy Agree...
Non-complete Clauses , Stamp duties , Rectification deed , Consultancy Agree...VALLIAMMAI PALANIAPPAN
 
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...Hitendra Hiremath
 
Void and illegal agreements distinguished
Void and illegal agreements distinguishedVoid and illegal agreements distinguished
Void and illegal agreements distinguishedPrateek Mishra
 
White paper on Force Majeure
White paper on Force MajeureWhite paper on Force Majeure
White paper on Force MajeurePratieksha Singh
 
Legal aspect of business
Legal aspect of businessLegal aspect of business
Legal aspect of businessZubair Ahmad
 
Impact of Force Majeure clause in commercial contracts
Impact of Force Majeure clause in commercial contractsImpact of Force Majeure clause in commercial contracts
Impact of Force Majeure clause in commercial contractsPooja Jain
 
Force majeure clause and COVID-19
Force majeure clause and COVID-19Force majeure clause and COVID-19
Force majeure clause and COVID-19Giridhar Sai
 
Lecture 8 Exclusion and Limiting Clauses - Notes
Lecture 8   Exclusion and Limiting Clauses - NotesLecture 8   Exclusion and Limiting Clauses - Notes
Lecture 8 Exclusion and Limiting Clauses - NotesRamona Vansluytman
 
Critical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptx
Critical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptxCritical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptx
Critical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptxtaxguruedu
 
Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...
Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...
Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...Antara Rabha
 
Contrast between misrepresentation under indian law and uae law
Contrast between misrepresentation under indian law and uae lawContrast between misrepresentation under indian law and uae law
Contrast between misrepresentation under indian law and uae lawShaun Menon
 
Discharge of Contract
Discharge of ContractDischarge of Contract
Discharge of ContractAmitGuleria13
 
Specific Relief Act Sections & Case Laws PPT.pptx
Specific Relief Act Sections & Case Laws PPT.pptxSpecific Relief Act Sections & Case Laws PPT.pptx
Specific Relief Act Sections & Case Laws PPT.pptxsrikarna235
 
Discharge of Contract
Discharge of Contract Discharge of Contract
Discharge of Contract Jaspreet Kaur
 
13533 execution of contracts and legal remedies available for breach of contr...
13533 execution of contracts and legal remedies available for breach of contr...13533 execution of contracts and legal remedies available for breach of contr...
13533 execution of contracts and legal remedies available for breach of contr...annu90
 

Similar to Presentation aditi duggal (20)

Validity of contingent contracts under ica
Validity of contingent contracts under icaValidity of contingent contracts under ica
Validity of contingent contracts under ica
 
Termination of contract
Termination of contractTermination of contract
Termination of contract
 
Business laws
Business lawsBusiness laws
Business laws
 
Article force majeure in covid rcllp
Article force majeure in covid rcllpArticle force majeure in covid rcllp
Article force majeure in covid rcllp
 
Non-complete Clauses , Stamp duties , Rectification deed , Consultancy Agree...
Non-complete Clauses ,  Stamp duties , Rectification deed , Consultancy Agree...Non-complete Clauses ,  Stamp duties , Rectification deed , Consultancy Agree...
Non-complete Clauses , Stamp duties , Rectification deed , Consultancy Agree...
 
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
 
Void and illegal agreements distinguished
Void and illegal agreements distinguishedVoid and illegal agreements distinguished
Void and illegal agreements distinguished
 
White paper on Force Majeure
White paper on Force MajeureWhite paper on Force Majeure
White paper on Force Majeure
 
Legal aspect of business
Legal aspect of businessLegal aspect of business
Legal aspect of business
 
Impact of Force Majeure clause in commercial contracts
Impact of Force Majeure clause in commercial contractsImpact of Force Majeure clause in commercial contracts
Impact of Force Majeure clause in commercial contracts
 
Force majeure clause and COVID-19
Force majeure clause and COVID-19Force majeure clause and COVID-19
Force majeure clause and COVID-19
 
Lecture 8 Exclusion and Limiting Clauses - Notes
Lecture 8   Exclusion and Limiting Clauses - NotesLecture 8   Exclusion and Limiting Clauses - Notes
Lecture 8 Exclusion and Limiting Clauses - Notes
 
6096247 (1).ppt
6096247 (1).ppt6096247 (1).ppt
6096247 (1).ppt
 
Critical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptx
Critical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptxCritical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptx
Critical Appraisal of Section 124 & 125 of Indian Contract Act, 1872.pptx
 
Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...
Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...
Void agreements, Performance Discharge, Breach of legal contract, Quasi Contr...
 
Contrast between misrepresentation under indian law and uae law
Contrast between misrepresentation under indian law and uae lawContrast between misrepresentation under indian law and uae law
Contrast between misrepresentation under indian law and uae law
 
Discharge of Contract
Discharge of ContractDischarge of Contract
Discharge of Contract
 
Specific Relief Act Sections & Case Laws PPT.pptx
Specific Relief Act Sections & Case Laws PPT.pptxSpecific Relief Act Sections & Case Laws PPT.pptx
Specific Relief Act Sections & Case Laws PPT.pptx
 
Discharge of Contract
Discharge of Contract Discharge of Contract
Discharge of Contract
 
13533 execution of contracts and legal remedies available for breach of contr...
13533 execution of contracts and legal remedies available for breach of contr...13533 execution of contracts and legal remedies available for breach of contr...
13533 execution of contracts and legal remedies available for breach of contr...
 

Recently uploaded

一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理Airst S
 
Call Girls in Nizamabad 9332606886 High Profile Call Girls You Can Get The...
Call Girls in Nizamabad   9332606886  High Profile Call Girls You Can Get The...Call Girls in Nizamabad   9332606886  High Profile Call Girls You Can Get The...
Call Girls in Nizamabad 9332606886 High Profile Call Girls You Can Get The...Sareena Khatun
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理bd2c5966a56d
 
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理F La
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理e9733fc35af6
 
judicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxjudicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxIshikaChauhan30
 
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理ss
 
posts-harmful-to-secular-structure-of-the-country-539103-1.pdf
posts-harmful-to-secular-structure-of-the-country-539103-1.pdfposts-harmful-to-secular-structure-of-the-country-539103-1.pdf
posts-harmful-to-secular-structure-of-the-country-539103-1.pdfbhavenpr
 
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证trryfxkn
 
一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理e9733fc35af6
 
Understanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective BargainingUnderstanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective Bargainingbartzlawgroup1
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxelysemiller87
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYJulian Scutts
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategyJong Hyuk Choi
 
Career As Legal Reporters for Law Students
Career As Legal Reporters for Law StudentsCareer As Legal Reporters for Law Students
Career As Legal Reporters for Law StudentsNilendra Kumar
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理F La
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理Airst S
 
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理ss
 

Recently uploaded (20)

一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
Call Girls in Nizamabad 9332606886 High Profile Call Girls You Can Get The...
Call Girls in Nizamabad   9332606886  High Profile Call Girls You Can Get The...Call Girls in Nizamabad   9332606886  High Profile Call Girls You Can Get The...
Call Girls in Nizamabad 9332606886 High Profile Call Girls You Can Get The...
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
Chambers Global Practice Guide - Canada M&A
Chambers Global Practice Guide - Canada M&AChambers Global Practice Guide - Canada M&A
Chambers Global Practice Guide - Canada M&A
 
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
一比一原版(TheAuckland毕业证书)新西兰奥克兰大学毕业证如何办理
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
 
judicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxjudicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptx
 
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
 
posts-harmful-to-secular-structure-of-the-country-539103-1.pdf
posts-harmful-to-secular-structure-of-the-country-539103-1.pdfposts-harmful-to-secular-structure-of-the-country-539103-1.pdf
posts-harmful-to-secular-structure-of-the-country-539103-1.pdf
 
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
 
一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理
 
Understanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective BargainingUnderstanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective Bargaining
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 
Career As Legal Reporters for Law Students
Career As Legal Reporters for Law StudentsCareer As Legal Reporters for Law Students
Career As Legal Reporters for Law Students
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
 
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
 

Presentation aditi duggal

  • 1. A CRITIQUE IMPOSSIBILITY & DOCTRINE OF FRUSTRATION as interpreted by the SC in Energy Watchdog v. CERC (Adani Case) 1Aditi Duggal | SLS Noida
  • 2. ENERGY WATCHDOG v. CERC 2  1.) Power Purchase Agreements :. Clause 12.3 defined force majeure to include any event or circumstance or combination thereof which “wholly or partly prevents” performance of obligations. Clause 12.7(a) stated that the affected party will be immune if performance was “prevented, hindered or delayed” due to a force majeure event. Clause 12.4(ii) excluded applicability of force majeure to changes in cost of fuel for the project or onerous performance of the agreement.  2.) Rise in price of coal : An unforeseeable change in Indonesian regulation aligned the coal prices to international prices which made procurement unforeseeably exorbitant thereby hindering the performance of obligations under PPAs.  3.) Defense of frustration : It was argued that they should either be discharged on account of frustration of the PPAs or restored to the same economic position prior to force majeure and/or change in law. The matter went to CERC and then to APTEL & was ultimately decided by the SC. Aditi Duggal | SLS Noida
  • 3. LEGISLATIVE INTENT 32 – Contingent contracts 56 – Impossibility of performance The contract can be enforced on the happening of the contingent event which, on becoming impossible, renders the contract void. It is a rule of positive law embodying the doctrine of frustration. In order for frustration to apply, contract must fall under section 32 or 56. No present obligation; The obligation arises on the occurrence of the contingent event Doctrine of frustration implies discharge of contract due to supervening impossibility or illegality of the act The fulfilment of condition has the effect of converting potential obligation into actual obligation Impossibility must be interpreted “practically” & not “literally” i.e. fundamental basis of contract should be materially altered beyond the contemplation of parties Parties pre-contemplate the contingency & accordingly draft the contract in express or implied contractual terms. Parties do not contemplate beforehand the impossibility or unlawfulness of the act agreed to be done. It is not applicable to self-induced frustration & express contractual stipulation to that extent. FORESEEABILITY MUST BE PRESENT. OBJECTIVE INTENT OF PARTIES FORESEEABILITY MUST BE ABSENT. SUBJECTIVE INTENT OF PARTIES 3Aditi Duggal | SLS Noida
  • 4. SUPREME COURT ON FRUSTRATION & INAPPLICABILITY OF FORCE MAJEURE Factually • Parties knowingly assumed the risk of fluctuation in price. • Deliberate quoting of non-escalable tariff is not an absolute bar to the plea of frustration; Alternative modes of performance are an important factor • The exclusion of Clause 12.4 applies to the case and consequently, S. 56 does not apply. Legally • Narrow construction and non-exhaustive nature of force majeure clauses • Fundamental basis of contract is the test of impossibility • Impossibility relates to practicality of performance • Inadequacy of onerous method of performance & ground of rise in cost • Multi-factorial approach including context of the contract, knowledge, contemplations, risk, nature of supervening event, and parties’ contemplation of future performance 4Aditi Duggal | SLS Noida
  • 5. FINDINGS Insofar as force majeure is relatable to an express or implied clause in a contract, it is governed by Chapter III of the Contract Act, particularly S. 32. Insofar as a force majeure event occurs dehors the contract, it is dealt with by a rule of positive law under Section 56 of the Indian Contract Act “As has been held, in particular, in Satyabrata Ghose case, when a contract contains a force majeure clause which on construction by the Court is held attracted to the facts of the case, Section 56 can have no application.” 5Aditi Duggal | SLS Noida
  • 6. SATYABRATA GHOSE In the large majority of cases, however, the doctrine of frustration is not applied on the ground of express or implied contractual terms. The relief u/s 56 is given on the ground of subsequent impossibility when the whole purpose or basis of a contract was frustrated by the intrusion or occurrence of an unexpected event or change of circumstances which was beyond the contemplation of parties at the time of conclusion of contract. It allows for discharge of obligations if an untoward event or change of circumstance totally upsets the very foundation of the agreement Section 56 lays down a rule of positive law and does not leave the matter to be determined according to the intention of the parties 6Aditi Duggal | SLS Noida
  • 7. FOOD FOR THOUGHT?!! S. 56 & 32 mutually exclusive : There is no clarification on how Section 56 operates as a default rule and how the applicability of S. 56 was eclipsed by the application of PPA clause on force majeure If 56 inapplicable, no reason to go into common law of frustration :. The judgement first dismisses the defense of S. 56 and later holds that it is not applicable in the first place. Therefore, it tied the test of impossibility under S. 32 to that of “fundamental basis” under S. 56 thereby impliedly linking them but expressly separating them at the same time. Restrictive interpretation of Satyabrata Ghose : Parties can choose to override the protection of S. 56 vide the S. 32 route. Satyabrata Ghose made it clear that S. 56 operates independent of the intent of the Parties. Adani case validated that parties can, if they so intend, escape the mandate of S. 56 by contractually resorting to S. 32. 7 Aditi Duggal | SLS Noida
  • 8. Was applicability of S. 32 through a particular clause legislatively intended to be an absolute escape for the mandate in S. 56? Is there actually no scope of an overlap between the two? 8Aditi Duggal | SLS Noida BURNING QUESTIONS!!!
  • 9. 9 SECTION 56 APPLIES Bypass the test of section 32 as the fundamental change would be judged in light of possibility of performance. Test of section - judge the possibility of the act (whether there is a fundamental change which would make the performance impossible) Governs the contract Aditi Duggal | SLS Noida
  • 10. 10 SECTION 32 APPLIES Even if the change makes the performance impossible it would not be considered force majure. The agreement of parties to consider a change as not fundamental to the performance of contract would not entail the parties to argue in future that the change is now fundamental to the performance of the contract under the purview of Section 56. Governs the clause Aditi Duggal | SLS Noida
  • 11. IS IT JUST??... 11 PRINCIPLE OF EQUALITY • Party who agreed for a particular act not be considered impossible should be made liable for performance • Even if act is impossible the party should be made liable to pay damages. PRINCIPLE OF LEGITIMATE EXPECTATIONS • When the legitimate expectation of the party who agreed for the change is violated, the act even violating the legitimate expectation can be judged in light of Section 56. Aditi Duggal | SLS Noida
  • 12. CONCLUSION Legal Position : Contract law acknowledges impossibility under Section 56 however simultaneously allows parties to agree for a particular impossibility not to be considered as a reason of non-performance. Ambiguity : Clearly, S. 56 encompasses a wider concept of impossibility that should not be absolutely curtailed by the application of S. 32. Satyabrata Ghose should have been, therefore, read to imply that S. 56 does not apply in the construction of the particular force majeure clause but it should still remain available as an alternative basis for avoidance of obligations in terms of the entire contract. 12Aditi Duggal | SLS Noida