6. SALCO Tasks & Milestone based on
DSI time schedule
Hardscape (%) Irrigation (%) Softscape (%) Area Handed Over by DSI Area handed over by SALCO
Area 1 65.50 (m2) 23.70 19.70 1-July-13 Jan-13
51.83 (Lm)
Area 2 1.66 9.00 11.33 15 juin-13 August-13
Area 3 7.62 13.50 10.23 July-13 Sep-13
Area 4 0.00 2.50 1.77 30 Juin-13 Sep-13
Area 5 0.00 0.00 0.00 30-Apr-13 ------
Area 6 0.00 1.75 1.27 15-July-13 15-August-13
Area 7 4.46 5.22 4.23 15-Juin-13 30-July-13
Area 8 4.66 21.93 23.10 15-Juin-13 15-October-13
Area 9 16.08 (m2) 22.40 28.34 15 Juin-13 July-13
Area 10
48.16 (Lm)
0.56 0.00 0.00 15-Juin-13 30-July-13
* All Starting date for SALCO scope are based on DSI and sub-contractors schedule (MEP, FCC , etc …)
* Interface pending issues between MEP & SBM are not yet finished and we still waiting for their response
* After installation of the Irrigation System, SALCO needs 35 to 45 days to make the final arrangement of the Controlling System