SlideShare a Scribd company logo
1 of 37
Section 2aSelection Method Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers
Quality- and Cost-Based Selection Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers
Quality- and Cost-Based Selection Para 2.2 QCBS is based on the quality of the technical proposal and the cost of the services to be provided. Since under QCBS the cost of the proposed services is a factor in the selection, this method is appropriate when,  the scope of work can be precisely defined,  the TOR are well specified and clear, and  ADB or the borrower and the consultants can estimate with reasonable precision the personnel time as well as the other inputs required of the consultants.
Quality-and Cost-Based Selection Procedure for Loans and Delegated TAs  Selection Method
Quality-and Cost-Based Selection Para 2.3 The QCBS procedure for loan and delegated TA consultants, when the borrower is responsible, is outlined below and summarized in Appendix 1. Normally, the borrower will be required to make three submissions (prior reviews) for ADB approval:  a draft RFP including the shortlist,  a technical proposal evaluation report, and  overall evaluation and ranking report.  However, borrowers with proven capacity are required to make only two submissions:  a draft RFP including the shortlist, and an overall evaluation and ranking report.
Quality-and Cost-Based Selection Procedure Preparation of the Terms of Reference  Cost Estimates (Budget for the Assignment)  Advertising  Preparation of Long List of Consultants  Preparation of Shortlist of Consultants  Preparation and Issuance of the Request for Proposals (RFPs)  Receipt of Proposals
Quality-and Cost-Based Selection Procedure Evaluation of Technical Proposal  Public Opening of Financial Proposals  Evaluation of Financial Proposal  Ranking of Proposals  Negotiations  Publication of the Award of Contract  Debriefing
Preparation of the Terms of Reference  Para 2.4 Before the process of recruitment of a consulting firm starts, the objective and scope of the proposed work, and the functions and duties to be assigned to the consultants should be clearly and adequately defined in the TOR.
Cost Estimates (Budget for the Assignment)  Para 2.5 Well-developed cost estimates are essential to ensure realistic budgetary resources are provided.  The cost estimates for loan projects shall be prepared by the borrower based on assessment of the resources needed to carry out the assignment:  expert time,  logistical support, and  physical inputs (for example, vehicles, laboratory equipment).
Cost Estimates (Budget for the Assignment)  Para 2.5 Costs shall be divided into two broad categories:  remuneration (according to the type of contract used) and  out-of-pocket expenses.  The cost of expert time shall be estimated on a realistic basis for international and national personnel.
Advertising  Para 2.6 ADB normally lists all loan projects requiring consulting services on ADB’s website before shortlisting.  To attract EOls from consulting firms, the borrower, may also advertise in an appropriate national journal, newspaper, or website.
Preparation of Long List of Consultants  Para 2.7 The borrower shall prepare a long list of technically qualified firms based on EOIs submitted.
Preparation of Shortlist of Consultants  Para 2.8 The borrower is responsible for preparation of the shortlist.  The borrower shall give first consideration to those firms expressing interest that possess the relevant qualifications.  Shortlists shall comprise six firms with a wide geographic spread, with no more than two firms from any one country and at least one firm from a developing country, unless qualified firms from developing countries are not identified.  ADB may agree to shortlists comprising a smaller number of firms in special circumstances, for example, when only a few qualified firms have expressed interest in the specific assignment or when the size of the contract does not justify wider competition.
Preparation of Shortlist of Consultants  Para 2.8 For the purpose of establishing the shortlist, the nationality of a firm is that of the country in which it is registered or incorporated and, in the case of a joint venture, the nationality of the firm appointed to represent the joint venture. Once ADB has issued a “no objection” to a shortlist, the borrower shall not add or delete names.
Preparation of Shortlist of Consultants  Para 2.9  The shortlist may comprise entirely national consultants (firms registered or incorporated in the country), if the assignment is below any ceiling (or ceilings) established in the procurement plan approved by ADB,sufficient qualified firms are available to enable a shortlist of firms with competitive costs to be drawn up, and when competition, including foreign consultants, is prima facie not justified or foreign consultants have not expressed interest.  These same amounts will be used in ADB lending operations supporting sector wide approaches (SWAps)(in which government and/or donor funds are pooled) as the threshold below which shortlists will be composed entirely of national firms selected under procedures agreed with ADB. However, if foreign firms express interest, they shall be considered.
Preparation and Issuance of the Request for Proposals (RFPs) Para 2.10  Borrowers shall use the standard RFP. The RFP includes:  letter of invitation;  instructions to consultants, including a data sheet and evaluation criteria;  technical proposal standard forms;  financial proposal standard forms;  TOR;  standard form of contract; and  list of ADB member countries.
Preparation and Issuance of the Request for Proposals (RFPs) Para 2.11  The borrower shall send RFPs to consultants on the shortlist. The borrower may use an electronic system to distribute the RFP, provided that ADB is satisfied with the adequacy of such system.  If the RFP is distributed electronically, the electronic system shall be secure to avoid modifications to the RFP and shall not restrict the access of shortlisted consultants to the RFP.
Receipt of Proposals  Para 2.12  Firms shall be required to submit technical and financial proposals in separate sealed envelopes at the same time.  Any proposal received after the closing time for submission of proposals will be returned unopened, and no amendments to the technical or financial proposals will be accepted after the deadline.
Evaluation of Technical Proposal  Para 2.13  The evaluation shall be based on the evaluation criteria defined in the instructions to consultants.  After the technical quality is evaluated, firms whose technical proposals did not meet the minimum qualifying score of 750 points out of a possible 1,000 points, or were considered non-responsive to the invitation requirements, will be advised and their financial proposals will be returned unopened.  Firms that have secured the minimum qualifying technical score will be advised of the location, date, and time for opening of financial proposals.
Public Opening of Financial Proposals  Para 2.14  The borrower shall then inform the firms whose technical proposals scored 750 points or more of the time and place where the borrower will publicly open their financial proposals.  The name of the firms, the technical quality scores, and the proposed prices shall be announced, and recorded when the financial proposals are opened.
Evaluation of Financial Proposal  Para 2.15  The borrower shall then review the congruency of the technical and financial proposals, make adjustments as appropriate, and correct arithmetical or computational errors.
Ranking of Proposals  Para 2.16  The total score shall be obtained by weighting and adding the technical and financial scores; this will determine the overall ranking of the consultants’ proposals. The weight for the “cost” shall be chosen, taking into account the complexity of the assignment and the relative importance of quality.  Except as provided for in the case of other selection methods, the weight for cost shall normally be 20%.
Negotiations  Para 2.17  The borrower shall then negotiate a contract with the first ranked firm. Negotiations will include discussions of the TOR, the methodology, personnel schedule, the borrower’s counterpart facilities and the quantities of cost items in the firm’s financial proposal. However, these discussions will not substantially alter the TOR attached to the invitation.  The selected firm should not be allowed to substitute experts, unless both parties agree that undue delay in the selection process makes such substitution unavoidable or that such changes are critical to meet the objectives of the assignment.
Negotiations  Para 2.17  Proposed unit rates for remuneration shall not be altered and other expenses shall not be negotiated since unit rate cost has been a factor in the selection process.  Successful negotiations conclude with signing of the contract. Financial negotiations shall include clarification of the consultant’s tax liability in the borrower’s country (if any) and how this tax liability has been or would be reflected in the contract.  If the borrower and the firm cannot reach agreement, the borrower may terminate the negotiations with ADB’s prior agreement and start negotiations with the next ranked firm until an agreement is reached. The borrower shall send a copy of the signed contract to ADB for its records.
Publication of the Award of Contract  Para 2.18  After the award of contract, the borrower shall provide ADB with the following information which ADB shall publish on ADB’s website: the names of all consultants who submitted proposals,  the technical points assigned to each consultant,  the offered prices of each consultant,  the overall ranking of the consultants, and  the name of the winning consultant and the contract sum.
Debriefing  Para 2.19  In the publication of award of contract the borrower shall specify that if any consultant who submitted a proposal wishes to ascertain the reasons why its proposal was not selected, such consultant should request an explanation from the borrower.  The borrower shall promptly provide an explanation as to why its proposal was not selected.
Rejection of All Proposals and Reinvitation  Para 2.20  The borrower will be justified in rejecting all proposals only if all proposals are non-responsive because they present major deficiencies in complying with the TOR or if they involve costs substantially higher than the original estimate. In the latter case, the feasibility of increasing the budget, or scaling down the scope of the services with the firm should be investigated in consultation with ADB.
Rejection of All Proposals and Reinvitation  Para 2.20 Before all proposals are rejected and new proposals are invited, the borrower shall notify ADB, indicating the reasons for rejection of all proposals, and shall obtain ADB’s “no objection” before proceeding with the rejection and the new process.  The new process may include revising the RFP (including the shortlist) and the budget. These revisions shall be agreed upon with ADB.
Confidentiality  Para 2.21  Information relating to evaluation of proposals and recommendations concerning awards shall not be disclosed to the consultants who submitted the proposals or to other persons not officially concerned with the process until the publication of the award of contract, except as provided in paras 2.14 and 2.16 above.
Quality- and Cost-Based Selection Procedures for Technical Assistance  Selection Method
Quality- and Cost-Based Selection Procedures for Technical Assistance  Para 2.22  The procedure for TA is similar to that for loan and delegated TA consultants and is summarized in Appendix 1.
Appendix 1 Summary of Quality- and Cost-Based Selection (QCBS)and Quality-Based Selection (QBS) Procedures  Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers
Table A1: QCBS Procedure
Table A1: QCBS Procedure
Table A2: QBS Procedure
Table A2: QBS Procedure
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers - Selection Method Part#1

More Related Content

What's hot

Consultant contract for small assignments – time based
Consultant contract for small assignments – time basedConsultant contract for small assignments – time based
Consultant contract for small assignments – time based
Joy Irman
 
Consultant contract for small assignments – lump sum payments
Consultant contract for small assignments – lump sum paymentsConsultant contract for small assignments – lump sum payments
Consultant contract for small assignments – lump sum payments
Joy Irman
 
Wb procurement icb c1
Wb procurement icb c1Wb procurement icb c1
Wb procurement icb c1
Joy Irman
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
abenyeung1
 
Wb consultant 4b
Wb consultant 4bWb consultant 4b
Wb consultant 4b
Joy Irman
 
Wb procurement icb a
Wb procurement icb aWb procurement icb a
Wb procurement icb a
Joy Irman
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
Joy Irman
 

What's hot (20)

Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...
 
Consultant contract for small assignments – time based
Consultant contract for small assignments – time basedConsultant contract for small assignments – time based
Consultant contract for small assignments – time based
 
Consultant contract for small assignments – lump sum payments
Consultant contract for small assignments – lump sum paymentsConsultant contract for small assignments – lump sum payments
Consultant contract for small assignments – lump sum payments
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost Submission
 
Contract Drafting Competition 2019
Contract Drafting Competition 2019Contract Drafting Competition 2019
Contract Drafting Competition 2019
 
Wb procurement icb c1
Wb procurement icb c1Wb procurement icb c1
Wb procurement icb c1
 
Whole Life Cycle Cost
Whole Life Cycle CostWhole Life Cycle Cost
Whole Life Cycle Cost
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
 
GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016
GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016
GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
 
GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016
GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016
GUSII MWALIMU SACCO TENDER DOCUMENTS 2015_2016
 
Wb consultant 4b
Wb consultant 4bWb consultant 4b
Wb consultant 4b
 
Engagement of Consultant for Advising and Managing the Process of Disinvestme...
Engagement of Consultant for Advising and Managing the Process of Disinvestme...Engagement of Consultant for Advising and Managing the Process of Disinvestme...
Engagement of Consultant for Advising and Managing the Process of Disinvestme...
 
154092688 rfp32sites
154092688 rfp32sites154092688 rfp32sites
154092688 rfp32sites
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Wb procurement icb a
Wb procurement icb aWb procurement icb a
Wb procurement icb a
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Portfolio manager
Portfolio managerPortfolio manager
Portfolio manager
 
Ballou High School Contractor Awareness Event Presentation
Ballou High School Contractor Awareness Event PresentationBallou High School Contractor Awareness Event Presentation
Ballou High School Contractor Awareness Event Presentation
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
 

Viewers also liked

Recruitment And Selection Hiring The Right Person
Recruitment And Selection Hiring The Right PersonRecruitment And Selection Hiring The Right Person
Recruitment And Selection Hiring The Right Person
MariaVyalkova
 
Consultant's technical & financial proposal
Consultant's technical & financial proposalConsultant's technical & financial proposal
Consultant's technical & financial proposal
Mohamed Ahmed
 
Consumer research dove
Consumer research doveConsumer research dove
Consumer research dove
talreja13
 
Introduction : Employee testing and selection
Introduction : Employee testing and selectionIntroduction : Employee testing and selection
Introduction : Employee testing and selection
Micha Paramitha
 
Recruitment, Selection Process Methods And Steps,
Recruitment, Selection Process Methods And Steps,Recruitment, Selection Process Methods And Steps,
Recruitment, Selection Process Methods And Steps,
rajeevgupta
 

Viewers also liked (11)

Recruitment and selection method
Recruitment and  selection methodRecruitment and  selection method
Recruitment and selection method
 
Recruitment And Selection Hiring The Right Person
Recruitment And Selection Hiring The Right PersonRecruitment And Selection Hiring The Right Person
Recruitment And Selection Hiring The Right Person
 
Consulting proposals
Consulting proposalsConsulting proposals
Consulting proposals
 
Recruitment process, goals, sources, constraints, selection methods and diffe...
Recruitment process, goals, sources, constraints, selection methods and diffe...Recruitment process, goals, sources, constraints, selection methods and diffe...
Recruitment process, goals, sources, constraints, selection methods and diffe...
 
TRAINING AND SELECTION
TRAINING AND SELECTIONTRAINING AND SELECTION
TRAINING AND SELECTION
 
Consultant's technical & financial proposal
Consultant's technical & financial proposalConsultant's technical & financial proposal
Consultant's technical & financial proposal
 
HUMAN RESOURCE
HUMAN RESOURCEHUMAN RESOURCE
HUMAN RESOURCE
 
Consumer research dove
Consumer research doveConsumer research dove
Consumer research dove
 
Introduction : Employee testing and selection
Introduction : Employee testing and selectionIntroduction : Employee testing and selection
Introduction : Employee testing and selection
 
Feasibility study(technical aspect)
Feasibility study(technical aspect)Feasibility study(technical aspect)
Feasibility study(technical aspect)
 
Recruitment, Selection Process Methods And Steps,
Recruitment, Selection Process Methods And Steps,Recruitment, Selection Process Methods And Steps,
Recruitment, Selection Process Methods And Steps,
 

Similar to Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers - Selection Method Part#1

Wb consultant 2a
Wb consultant 2aWb consultant 2a
Wb consultant 2a
Joy Irman
 
Srfp consultants 26 negotiations
Srfp consultants 26   negotiationsSrfp consultants 26   negotiations
Srfp consultants 26 negotiations
Joy Irman
 
Wb consultant 2c
Wb consultant 2cWb consultant 2c
Wb consultant 2c
Joy Irman
 
Hitachi RFP for Janitorial FINAL
Hitachi RFP for Janitorial  FINALHitachi RFP for Janitorial  FINAL
Hitachi RFP for Janitorial FINAL
Bruce Elledge
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
Joy Irman
 
Adb procurement guidelines icb-a
Adb procurement guidelines   icb-aAdb procurement guidelines   icb-a
Adb procurement guidelines icb-a
Joy Irman
 
Wb procurement icb b1
Wb procurement icb b1Wb procurement icb b1
Wb procurement icb b1
Joy Irman
 

Similar to Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers - Selection Method Part#1 (20)

Wb consultant 2a
Wb consultant 2aWb consultant 2a
Wb consultant 2a
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Presentation_Advisory & Intragroup service.pptx
Presentation_Advisory & Intragroup service.pptxPresentation_Advisory & Intragroup service.pptx
Presentation_Advisory & Intragroup service.pptx
 
Final standard tender doc
Final standard tender docFinal standard tender doc
Final standard tender doc
 
Srfp consultants 26 negotiations
Srfp consultants 26   negotiationsSrfp consultants 26   negotiations
Srfp consultants 26 negotiations
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
Document samples
Document samplesDocument samples
Document samples
 
BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptx
 
Wb consultant 2c
Wb consultant 2cWb consultant 2c
Wb consultant 2c
 
Eoi indoor & outdoor venue branding
Eoi indoor & outdoor venue brandingEoi indoor & outdoor venue branding
Eoi indoor & outdoor venue branding
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptx
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Hitachi RFP for Janitorial FINAL
Hitachi RFP for Janitorial  FINALHitachi RFP for Janitorial  FINAL
Hitachi RFP for Janitorial FINAL
 
2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
 
Adb procurement guidelines icb-a
Adb procurement guidelines   icb-aAdb procurement guidelines   icb-a
Adb procurement guidelines icb-a
 
Wb procurement icb b1
Wb procurement icb b1Wb procurement icb b1
Wb procurement icb b1
 

More from Joy Irman

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Joy Irman
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Joy Irman
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
Joy Irman
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
Joy Irman
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
Joy Irman
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
Joy Irman
 

More from Joy Irman (20)

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development Bank
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA Loans
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkungan
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronik
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaan
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barang
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasa
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen
 

Recently uploaded

!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
laloo_007
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 

Recently uploaded (20)

!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial Wings
 

Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers - Selection Method Part#1

  • 1. Section 2aSelection Method Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers
  • 2. Quality- and Cost-Based Selection Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers
  • 3. Quality- and Cost-Based Selection Para 2.2 QCBS is based on the quality of the technical proposal and the cost of the services to be provided. Since under QCBS the cost of the proposed services is a factor in the selection, this method is appropriate when, the scope of work can be precisely defined, the TOR are well specified and clear, and ADB or the borrower and the consultants can estimate with reasonable precision the personnel time as well as the other inputs required of the consultants.
  • 4. Quality-and Cost-Based Selection Procedure for Loans and Delegated TAs Selection Method
  • 5. Quality-and Cost-Based Selection Para 2.3 The QCBS procedure for loan and delegated TA consultants, when the borrower is responsible, is outlined below and summarized in Appendix 1. Normally, the borrower will be required to make three submissions (prior reviews) for ADB approval: a draft RFP including the shortlist, a technical proposal evaluation report, and overall evaluation and ranking report. However, borrowers with proven capacity are required to make only two submissions: a draft RFP including the shortlist, and an overall evaluation and ranking report.
  • 6. Quality-and Cost-Based Selection Procedure Preparation of the Terms of Reference Cost Estimates (Budget for the Assignment) Advertising Preparation of Long List of Consultants Preparation of Shortlist of Consultants Preparation and Issuance of the Request for Proposals (RFPs) Receipt of Proposals
  • 7. Quality-and Cost-Based Selection Procedure Evaluation of Technical Proposal Public Opening of Financial Proposals Evaluation of Financial Proposal Ranking of Proposals Negotiations Publication of the Award of Contract Debriefing
  • 8. Preparation of the Terms of Reference Para 2.4 Before the process of recruitment of a consulting firm starts, the objective and scope of the proposed work, and the functions and duties to be assigned to the consultants should be clearly and adequately defined in the TOR.
  • 9. Cost Estimates (Budget for the Assignment) Para 2.5 Well-developed cost estimates are essential to ensure realistic budgetary resources are provided. The cost estimates for loan projects shall be prepared by the borrower based on assessment of the resources needed to carry out the assignment: expert time, logistical support, and physical inputs (for example, vehicles, laboratory equipment).
  • 10. Cost Estimates (Budget for the Assignment) Para 2.5 Costs shall be divided into two broad categories: remuneration (according to the type of contract used) and out-of-pocket expenses. The cost of expert time shall be estimated on a realistic basis for international and national personnel.
  • 11. Advertising Para 2.6 ADB normally lists all loan projects requiring consulting services on ADB’s website before shortlisting. To attract EOls from consulting firms, the borrower, may also advertise in an appropriate national journal, newspaper, or website.
  • 12. Preparation of Long List of Consultants Para 2.7 The borrower shall prepare a long list of technically qualified firms based on EOIs submitted.
  • 13. Preparation of Shortlist of Consultants Para 2.8 The borrower is responsible for preparation of the shortlist. The borrower shall give first consideration to those firms expressing interest that possess the relevant qualifications. Shortlists shall comprise six firms with a wide geographic spread, with no more than two firms from any one country and at least one firm from a developing country, unless qualified firms from developing countries are not identified. ADB may agree to shortlists comprising a smaller number of firms in special circumstances, for example, when only a few qualified firms have expressed interest in the specific assignment or when the size of the contract does not justify wider competition.
  • 14. Preparation of Shortlist of Consultants Para 2.8 For the purpose of establishing the shortlist, the nationality of a firm is that of the country in which it is registered or incorporated and, in the case of a joint venture, the nationality of the firm appointed to represent the joint venture. Once ADB has issued a “no objection” to a shortlist, the borrower shall not add or delete names.
  • 15. Preparation of Shortlist of Consultants Para 2.9 The shortlist may comprise entirely national consultants (firms registered or incorporated in the country), if the assignment is below any ceiling (or ceilings) established in the procurement plan approved by ADB,sufficient qualified firms are available to enable a shortlist of firms with competitive costs to be drawn up, and when competition, including foreign consultants, is prima facie not justified or foreign consultants have not expressed interest. These same amounts will be used in ADB lending operations supporting sector wide approaches (SWAps)(in which government and/or donor funds are pooled) as the threshold below which shortlists will be composed entirely of national firms selected under procedures agreed with ADB. However, if foreign firms express interest, they shall be considered.
  • 16. Preparation and Issuance of the Request for Proposals (RFPs) Para 2.10 Borrowers shall use the standard RFP. The RFP includes: letter of invitation; instructions to consultants, including a data sheet and evaluation criteria; technical proposal standard forms; financial proposal standard forms; TOR; standard form of contract; and list of ADB member countries.
  • 17. Preparation and Issuance of the Request for Proposals (RFPs) Para 2.11 The borrower shall send RFPs to consultants on the shortlist. The borrower may use an electronic system to distribute the RFP, provided that ADB is satisfied with the adequacy of such system. If the RFP is distributed electronically, the electronic system shall be secure to avoid modifications to the RFP and shall not restrict the access of shortlisted consultants to the RFP.
  • 18. Receipt of Proposals Para 2.12 Firms shall be required to submit technical and financial proposals in separate sealed envelopes at the same time. Any proposal received after the closing time for submission of proposals will be returned unopened, and no amendments to the technical or financial proposals will be accepted after the deadline.
  • 19. Evaluation of Technical Proposal Para 2.13 The evaluation shall be based on the evaluation criteria defined in the instructions to consultants. After the technical quality is evaluated, firms whose technical proposals did not meet the minimum qualifying score of 750 points out of a possible 1,000 points, or were considered non-responsive to the invitation requirements, will be advised and their financial proposals will be returned unopened. Firms that have secured the minimum qualifying technical score will be advised of the location, date, and time for opening of financial proposals.
  • 20. Public Opening of Financial Proposals Para 2.14 The borrower shall then inform the firms whose technical proposals scored 750 points or more of the time and place where the borrower will publicly open their financial proposals. The name of the firms, the technical quality scores, and the proposed prices shall be announced, and recorded when the financial proposals are opened.
  • 21. Evaluation of Financial Proposal Para 2.15 The borrower shall then review the congruency of the technical and financial proposals, make adjustments as appropriate, and correct arithmetical or computational errors.
  • 22. Ranking of Proposals Para 2.16 The total score shall be obtained by weighting and adding the technical and financial scores; this will determine the overall ranking of the consultants’ proposals. The weight for the “cost” shall be chosen, taking into account the complexity of the assignment and the relative importance of quality. Except as provided for in the case of other selection methods, the weight for cost shall normally be 20%.
  • 23. Negotiations Para 2.17 The borrower shall then negotiate a contract with the first ranked firm. Negotiations will include discussions of the TOR, the methodology, personnel schedule, the borrower’s counterpart facilities and the quantities of cost items in the firm’s financial proposal. However, these discussions will not substantially alter the TOR attached to the invitation. The selected firm should not be allowed to substitute experts, unless both parties agree that undue delay in the selection process makes such substitution unavoidable or that such changes are critical to meet the objectives of the assignment.
  • 24. Negotiations Para 2.17 Proposed unit rates for remuneration shall not be altered and other expenses shall not be negotiated since unit rate cost has been a factor in the selection process. Successful negotiations conclude with signing of the contract. Financial negotiations shall include clarification of the consultant’s tax liability in the borrower’s country (if any) and how this tax liability has been or would be reflected in the contract. If the borrower and the firm cannot reach agreement, the borrower may terminate the negotiations with ADB’s prior agreement and start negotiations with the next ranked firm until an agreement is reached. The borrower shall send a copy of the signed contract to ADB for its records.
  • 25. Publication of the Award of Contract Para 2.18 After the award of contract, the borrower shall provide ADB with the following information which ADB shall publish on ADB’s website: the names of all consultants who submitted proposals, the technical points assigned to each consultant, the offered prices of each consultant, the overall ranking of the consultants, and the name of the winning consultant and the contract sum.
  • 26. Debriefing Para 2.19 In the publication of award of contract the borrower shall specify that if any consultant who submitted a proposal wishes to ascertain the reasons why its proposal was not selected, such consultant should request an explanation from the borrower. The borrower shall promptly provide an explanation as to why its proposal was not selected.
  • 27. Rejection of All Proposals and Reinvitation Para 2.20 The borrower will be justified in rejecting all proposals only if all proposals are non-responsive because they present major deficiencies in complying with the TOR or if they involve costs substantially higher than the original estimate. In the latter case, the feasibility of increasing the budget, or scaling down the scope of the services with the firm should be investigated in consultation with ADB.
  • 28. Rejection of All Proposals and Reinvitation Para 2.20 Before all proposals are rejected and new proposals are invited, the borrower shall notify ADB, indicating the reasons for rejection of all proposals, and shall obtain ADB’s “no objection” before proceeding with the rejection and the new process. The new process may include revising the RFP (including the shortlist) and the budget. These revisions shall be agreed upon with ADB.
  • 29. Confidentiality Para 2.21 Information relating to evaluation of proposals and recommendations concerning awards shall not be disclosed to the consultants who submitted the proposals or to other persons not officially concerned with the process until the publication of the award of contract, except as provided in paras 2.14 and 2.16 above.
  • 30. Quality- and Cost-Based Selection Procedures for Technical Assistance Selection Method
  • 31. Quality- and Cost-Based Selection Procedures for Technical Assistance Para 2.22 The procedure for TA is similar to that for loan and delegated TA consultants and is summarized in Appendix 1.
  • 32. Appendix 1 Summary of Quality- and Cost-Based Selection (QCBS)and Quality-Based Selection (QBS) Procedures Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers
  • 33. Table A1: QCBS Procedure
  • 34. Table A1: QCBS Procedure
  • 35. Table A2: QBS Procedure
  • 36. Table A2: QBS Procedure