A VISION ON INTEGRATED INSPECTION PLANNING
    RISK BASED PROTOTYPING.

     STORK AMS         Reliability and Integrity.
     Nov. 10th 2009.
TODAYS AGENDA FOR THIS PRESENTATION.



# 1 Introduction on Risk Based Inspection planning
# 2 Generics on multi disciplinary inspection planning
# 3 Compliancy issues by RIMAP and T0260
# 4 The STORK AMS Approach
# 5 Support for specific interest groups
# 6 The way forward
# 7 How to join forces
# 8 Contact details
# 9 Queries; How can I…….?
#1: INTRODUCTION ON RISK BASED INSPECTION PLANNING.


Widely accepted points of reference for use of RBI are that it defines how to:
• Benefit of experiences elsewhere for your own situation
• Gather your own experience in a well defined manner
• Manage you asset cost efficient in a rationalised way
• Look ahead whilst learning from looking back
    – Make use of an integrated approach combining your specific knowledge with
      specialists knowledge (corrosion & materials engineers covering various
      deterioration mechanisms)
• Save on expenses for which there is no clear added value
    – Make use of legislative possibilities for interval extension where feasible
• Reveal compliance with legislation, stakeholders interests and available
  best practises such as PAS 55, RIMAP (EU) and T0260 (NL)
#1: INTRODUCTION ON RBI: COMMON ISSUES

BP’s “Lessons learned from the Texas City Refinery Explosion”) reveals that
usually various barriers fail in case of an incident.
RBI therefore focusses onto safeguarding the functionality of technical
assets, thereby preventing the risk on costly failures.
# 1: INTRODUCTION ON RBI; GENERICS

       RBI strategic concept.

 For this strategic concept three “key issues” combined:
 Have control on:
 • The way of use (Process).
 • The way design and construction have been realised (Plant)
 • The way inspections are performed and documented (People)
 In which peoples behavior impacts all aspects.
WHAT IS THE KEY ISSUE?




Managing risks is not about simply implementing an IT solution.
It’s about adapting your organisation to have risks assessed and act accordingly.
# 2: GENERICS ON MULTI DISCIPLINARY INSPECTION PLANNING.


Generic issues to make multi disciplinary inspection planning work:
• Use a uniform risk concept.
    – use the same principle for consequences of failure assessment
    – Use the same principle for probability of failure assessment
• Relate this uniform concept to specific legislative requirements in a
  transparent, ambiguous way.
• Make sure that risks assessed comply with the risk interpretation of
  the people involved in integrity management
    – Otherwise “RBI” and “current practise” will each go their own way
• Use widely accepted risk approached to safeguard compliance with
  common sense.
    – This implies use of IEC 61508 and RIMAP having a status as best
      practise in industry
# 2: GENERICS ON MULTI DISCIPLINARY INSPECTION PLANNING.


Generic in all disciplines about risk is:
• There is uncertainty about the trend in future behavior
• Consequences of failure relate to QHSE

The common framework that covers this is:
• Integrate a bandwidth for future behaviour (for instance 4 categories)
• Integrate various categories for consequence of failure (IEC 61508)
    Predictability   Variation Correction factor
    Very good        10%       0,9
    Good             25%       0,8
    Average          50%       0,67
    Poor / Bad       100%      0,5
# 3: COMPLIANCY ISSUES BY RIMAP AND T0260


• RIMAP being a European Initiative on Risk Based Inspection &
  Maintenance (RBIM) has defined a CEN Workshop Agreement
  being the CWA 15740 dated April 2008. This framework states
  amongst others that:
   – Compliance with local legislation should be safeguarded
   – Flexible in the sense of supporting qualitative to full probabilistic
     approaches
   – The approach used should be fully auditable
   – Costs optimisation should be demonstrated (so CoF should be
     determined in terms of costs as well)
• T0260 states that the methodology used should address the same
  issues as the default KINT/PMP method whilst the resulting intervals
  should not exceed the results of the default method.
# 3: COMPLIANCY ISSUES BY RIMAP AND T0260


How is this to be addressed?
• Simply by checking all these issues and demonstrating the
  compliance by available procedures.
• An example is shown below:




•   The risc based time interval correction factor extends within 5% when using the default 0,65
    correction factor per category. Case: IIPP Free Inspection Management Tool versus T0260.
# 4: THE STORK AMS APPROACH


Our approach is as follows:
• Being an independant service supplier, we offer integrity
  management services as well as implementation of specific tools.
  We can do this being a IBM Tivoli AAA rated software supplier as
  well as a recognised integrity supplier that has a track record on
  integrated service contracts (IICorr; GLT; AJS).
• We do this by defining your requirements, mirroring this against the
  available options, thereby defining the best fit.
• Based on the best fit, we help you to implement the selected
  solution. (Ref.: centre of innovation)
• We can therefore assist you with any package that you own, no
  matter what you own or want to own.
• This is because our goal is to meet your integrity requirements; it’s
  NOT about pushing a single solution.
# 5: SUPPORT FOR SPECIFIC INTEREST GROUPS


What we see in practise is as follows:
• Large companies use state of the art CMMS systems like SAP,
  Maximo etc. and a mutiplicity of specific applications; this leads to
  an urgency for an integrated solution.
    – For these companies we offer a customer specific selection process, in
      which we determine which integrated package suits best with their
      needs. Of course we assist implementing one ot fhese solutions as well.
• Small companies use lite CMMS versions while lacking in many
  cases a specific solution for inspection management
    – For these companies, that quite commonly lack the specific expertise
      and budget for investment in specific integrity management, we offer
      dedicated services in integrity management. Their information
      requirements can be delt with by various solutions, one of which is a
      free of charge inspection management tool that we can offer.
# 6: THE WAY FORWARD


Our way forward is as follows:
• Integrate current approaches into one module
    – Experiences dating back to 1995 have been integrated in the module
•   Integrate user’s best practise requirements into this module
•   Define a Integrated Inspection Planning Prototype (IIPP) using this
    module (IIPP available as per Nov. 2009)
•   Mirror selected integrated packages against this IIP Prototype
•   Assist companies with adopting one of the selected packages in their
    business environment

We do this on the basis of our status as an independent service supplier.
For this purpose, our IIPP module which is available as per today is
supplied free of charge so that it may serve its goal for development
purposes.
# 7: HOW TO JOIN FORCES


We have various initiatives going on in order to leverage your asset
management to a higher level:

All companies:     you can use of freeware inspection management solution
                   that covers the next aspects:
    –   Inspection reporting
    –   Risk Based Inspection planning (when to inspect)
    –   Inspection plan (which preparatory measures are required)
    –   LTARP / EOL (Long Term Asset Replacement Program / End Of Life
        assessment

•   Smaller businesses in NL (MKB):
     – Make use of the maintenance excellence program as defined for the MKB.
•   Large businesses:
     – Make use of one of our supported integrated solutions that comply with
       SAP, Maximo or any other CMMS system.

In case of interest send a mail to geerthenk.wijnants@stork.com
# 8: CONTACT DETAILS


As internet can show you every day, what you experience today has
already been experienced elsewhere.

Therefore we offer you access to our best expertise through the next
access hubs:

• www.storkams.com
• www.centreofexcellence.com
# 9: QUERIES: HOW CAN I……?

In case of queries don’t hesitate to
discuss your issue with us:
You can call us or send an Email to
the next adresses:

GeertHenk.Wijnants@Stork.com
Dial: +31-6-1335 7246

ams@stork.com
Dial: +31-30-669 1864

Internet: www.stork.com/ams
www.centreofexcellence.com

More Related Content

Similar to A Vision On Integrated Inspection Planning Prototyping

Role of the virtual ciso
Role of the virtual cisoRole of the virtual ciso
Role of the virtual cisoMichael Ball
 
Independent verification & validation presented by Maneat v02
Independent verification & validation presented by Maneat v02Independent verification & validation presented by Maneat v02
Independent verification & validation presented by Maneat v02Dr. Pierpaolo Mangeruga
 
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical IntegrityWebinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical IntegrityStork
 
Sdec10 lean package implementation
Sdec10 lean package implementationSdec10 lean package implementation
Sdec10 lean package implementationTerry Bunio
 
John Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practice
John Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practiceJohn Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practice
John Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practiceitSMF UK
 
Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...
Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...
Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...Julie Rampello
 
Webinar | Asset Management Health Check
Webinar | Asset Management Health CheckWebinar | Asset Management Health Check
Webinar | Asset Management Health CheckStork
 
Gain business insight with Continuous Controls Monitoring
Gain business insight with Continuous Controls MonitoringGain business insight with Continuous Controls Monitoring
Gain business insight with Continuous Controls MonitoringEmma Kelly
 
Julie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentationJulie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentationProjetech
 
Sabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdfSabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdfBrion Carroll (II)
 
The Demystification of successful cybersecurity initiatives.
The Demystification of successful cybersecurity initiatives.The Demystification of successful cybersecurity initiatives.
The Demystification of successful cybersecurity initiatives.FitCEO, Inc. (FCI)
 
TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15
TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15
TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15FitCEO, Inc. (FCI)
 
Digital Strategy and Transformation
Digital Strategy and TransformationDigital Strategy and Transformation
Digital Strategy and TransformationGustavoVelandia3
 
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1ptulachan
 
Steps to iso 27001 implementation
Steps to iso 27001 implementationSteps to iso 27001 implementation
Steps to iso 27001 implementationRalf Braga
 
UAT for a Major US Banking Conglomerate
UAT for a Major US Banking ConglomerateUAT for a Major US Banking Conglomerate
UAT for a Major US Banking ConglomerateThinksoft Global
 
More practical insights on the 20 critical controls
More practical insights on the 20 critical controlsMore practical insights on the 20 critical controls
More practical insights on the 20 critical controlsEnclaveSecurity
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceYalcin Gerek
 

Similar to A Vision On Integrated Inspection Planning Prototyping (20)

Role of the virtual ciso
Role of the virtual cisoRole of the virtual ciso
Role of the virtual ciso
 
Independent verification & validation presented by Maneat v02
Independent verification & validation presented by Maneat v02Independent verification & validation presented by Maneat v02
Independent verification & validation presented by Maneat v02
 
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical IntegrityWebinar | GE & Stork | APM Best Practices - Mechanical Integrity
Webinar | GE & Stork | APM Best Practices - Mechanical Integrity
 
Sdec10 lean package implementation
Sdec10 lean package implementationSdec10 lean package implementation
Sdec10 lean package implementation
 
John Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practice
John Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practiceJohn Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practice
John Mcdermott - Gold sponsor session: Hybrid - IT needs hybrid good practice
 
Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...
Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...
Maximo KPI Maintenance & Asset Reliability Support Workshop IMC 2013 presenta...
 
Webinar | Asset Management Health Check
Webinar | Asset Management Health CheckWebinar | Asset Management Health Check
Webinar | Asset Management Health Check
 
Gain business insight with Continuous Controls Monitoring
Gain business insight with Continuous Controls MonitoringGain business insight with Continuous Controls Monitoring
Gain business insight with Continuous Controls Monitoring
 
Julie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentationJulie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentation
 
Session 5
Session 5Session 5
Session 5
 
Sabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdfSabrion_Consulting_Overview CPG Retail Apparel.pdf
Sabrion_Consulting_Overview CPG Retail Apparel.pdf
 
The Demystification of successful cybersecurity initiatives.
The Demystification of successful cybersecurity initiatives.The Demystification of successful cybersecurity initiatives.
The Demystification of successful cybersecurity initiatives.
 
TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15
TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15
TheDemystification_of_SuccessfulCyberSecurity_VIMRO_LB_VH_MHF_10_11_15
 
Digital Strategy and Transformation
Digital Strategy and TransformationDigital Strategy and Transformation
Digital Strategy and Transformation
 
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
 
Steps to iso 27001 implementation
Steps to iso 27001 implementationSteps to iso 27001 implementation
Steps to iso 27001 implementation
 
GRC in Australia slides
GRC in Australia slidesGRC in Australia slides
GRC in Australia slides
 
UAT for a Major US Banking Conglomerate
UAT for a Major US Banking ConglomerateUAT for a Major US Banking Conglomerate
UAT for a Major US Banking Conglomerate
 
More practical insights on the 20 critical controls
More practical insights on the 20 critical controlsMore practical insights on the 20 critical controls
More practical insights on the 20 critical controls
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information Governance
 

A Vision On Integrated Inspection Planning Prototyping

  • 1. A VISION ON INTEGRATED INSPECTION PLANNING RISK BASED PROTOTYPING. STORK AMS Reliability and Integrity. Nov. 10th 2009.
  • 2. TODAYS AGENDA FOR THIS PRESENTATION. # 1 Introduction on Risk Based Inspection planning # 2 Generics on multi disciplinary inspection planning # 3 Compliancy issues by RIMAP and T0260 # 4 The STORK AMS Approach # 5 Support for specific interest groups # 6 The way forward # 7 How to join forces # 8 Contact details # 9 Queries; How can I…….?
  • 3. #1: INTRODUCTION ON RISK BASED INSPECTION PLANNING. Widely accepted points of reference for use of RBI are that it defines how to: • Benefit of experiences elsewhere for your own situation • Gather your own experience in a well defined manner • Manage you asset cost efficient in a rationalised way • Look ahead whilst learning from looking back – Make use of an integrated approach combining your specific knowledge with specialists knowledge (corrosion & materials engineers covering various deterioration mechanisms) • Save on expenses for which there is no clear added value – Make use of legislative possibilities for interval extension where feasible • Reveal compliance with legislation, stakeholders interests and available best practises such as PAS 55, RIMAP (EU) and T0260 (NL)
  • 4. #1: INTRODUCTION ON RBI: COMMON ISSUES BP’s “Lessons learned from the Texas City Refinery Explosion”) reveals that usually various barriers fail in case of an incident. RBI therefore focusses onto safeguarding the functionality of technical assets, thereby preventing the risk on costly failures.
  • 5. # 1: INTRODUCTION ON RBI; GENERICS RBI strategic concept. For this strategic concept three “key issues” combined: Have control on: • The way of use (Process). • The way design and construction have been realised (Plant) • The way inspections are performed and documented (People) In which peoples behavior impacts all aspects.
  • 6. WHAT IS THE KEY ISSUE? Managing risks is not about simply implementing an IT solution. It’s about adapting your organisation to have risks assessed and act accordingly.
  • 7. # 2: GENERICS ON MULTI DISCIPLINARY INSPECTION PLANNING. Generic issues to make multi disciplinary inspection planning work: • Use a uniform risk concept. – use the same principle for consequences of failure assessment – Use the same principle for probability of failure assessment • Relate this uniform concept to specific legislative requirements in a transparent, ambiguous way. • Make sure that risks assessed comply with the risk interpretation of the people involved in integrity management – Otherwise “RBI” and “current practise” will each go their own way • Use widely accepted risk approached to safeguard compliance with common sense. – This implies use of IEC 61508 and RIMAP having a status as best practise in industry
  • 8. # 2: GENERICS ON MULTI DISCIPLINARY INSPECTION PLANNING. Generic in all disciplines about risk is: • There is uncertainty about the trend in future behavior • Consequences of failure relate to QHSE The common framework that covers this is: • Integrate a bandwidth for future behaviour (for instance 4 categories) • Integrate various categories for consequence of failure (IEC 61508) Predictability Variation Correction factor Very good 10% 0,9 Good 25% 0,8 Average 50% 0,67 Poor / Bad 100% 0,5
  • 9. # 3: COMPLIANCY ISSUES BY RIMAP AND T0260 • RIMAP being a European Initiative on Risk Based Inspection & Maintenance (RBIM) has defined a CEN Workshop Agreement being the CWA 15740 dated April 2008. This framework states amongst others that: – Compliance with local legislation should be safeguarded – Flexible in the sense of supporting qualitative to full probabilistic approaches – The approach used should be fully auditable – Costs optimisation should be demonstrated (so CoF should be determined in terms of costs as well) • T0260 states that the methodology used should address the same issues as the default KINT/PMP method whilst the resulting intervals should not exceed the results of the default method.
  • 10. # 3: COMPLIANCY ISSUES BY RIMAP AND T0260 How is this to be addressed? • Simply by checking all these issues and demonstrating the compliance by available procedures. • An example is shown below: • The risc based time interval correction factor extends within 5% when using the default 0,65 correction factor per category. Case: IIPP Free Inspection Management Tool versus T0260.
  • 11. # 4: THE STORK AMS APPROACH Our approach is as follows: • Being an independant service supplier, we offer integrity management services as well as implementation of specific tools. We can do this being a IBM Tivoli AAA rated software supplier as well as a recognised integrity supplier that has a track record on integrated service contracts (IICorr; GLT; AJS). • We do this by defining your requirements, mirroring this against the available options, thereby defining the best fit. • Based on the best fit, we help you to implement the selected solution. (Ref.: centre of innovation) • We can therefore assist you with any package that you own, no matter what you own or want to own. • This is because our goal is to meet your integrity requirements; it’s NOT about pushing a single solution.
  • 12. # 5: SUPPORT FOR SPECIFIC INTEREST GROUPS What we see in practise is as follows: • Large companies use state of the art CMMS systems like SAP, Maximo etc. and a mutiplicity of specific applications; this leads to an urgency for an integrated solution. – For these companies we offer a customer specific selection process, in which we determine which integrated package suits best with their needs. Of course we assist implementing one ot fhese solutions as well. • Small companies use lite CMMS versions while lacking in many cases a specific solution for inspection management – For these companies, that quite commonly lack the specific expertise and budget for investment in specific integrity management, we offer dedicated services in integrity management. Their information requirements can be delt with by various solutions, one of which is a free of charge inspection management tool that we can offer.
  • 13. # 6: THE WAY FORWARD Our way forward is as follows: • Integrate current approaches into one module – Experiences dating back to 1995 have been integrated in the module • Integrate user’s best practise requirements into this module • Define a Integrated Inspection Planning Prototype (IIPP) using this module (IIPP available as per Nov. 2009) • Mirror selected integrated packages against this IIP Prototype • Assist companies with adopting one of the selected packages in their business environment We do this on the basis of our status as an independent service supplier. For this purpose, our IIPP module which is available as per today is supplied free of charge so that it may serve its goal for development purposes.
  • 14. # 7: HOW TO JOIN FORCES We have various initiatives going on in order to leverage your asset management to a higher level: All companies: you can use of freeware inspection management solution that covers the next aspects: – Inspection reporting – Risk Based Inspection planning (when to inspect) – Inspection plan (which preparatory measures are required) – LTARP / EOL (Long Term Asset Replacement Program / End Of Life assessment • Smaller businesses in NL (MKB): – Make use of the maintenance excellence program as defined for the MKB. • Large businesses: – Make use of one of our supported integrated solutions that comply with SAP, Maximo or any other CMMS system. In case of interest send a mail to geerthenk.wijnants@stork.com
  • 15. # 8: CONTACT DETAILS As internet can show you every day, what you experience today has already been experienced elsewhere. Therefore we offer you access to our best expertise through the next access hubs: • www.storkams.com • www.centreofexcellence.com
  • 16. # 9: QUERIES: HOW CAN I……? In case of queries don’t hesitate to discuss your issue with us: You can call us or send an Email to the next adresses: GeertHenk.Wijnants@Stork.com Dial: +31-6-1335 7246 ams@stork.com Dial: +31-30-669 1864 Internet: www.stork.com/ams www.centreofexcellence.com

Editor's Notes

  1. Explain the main focus of Risk Based Inspection
  2. The multi barrier approach shows that incidents commonly are the result of multiple barriers failing. The backside of this is that it also shows that single effective barrier can have effects in preventing the combination of causes leading to failures.
  3. Risk Based Inspection is not just a tool that can be used.It is the result of a management decision to safeguard the integrity of your plant in a rationalised manner using a systematic and well defined approach.
  4. The key issue is to adapt and align your organisation efficiently.So it is not just getting the right software package and wait for the results to come.It’s all about assessing, planning and acting accordingly.
  5. It’s all about defining a common framework of understanding so safeguarding there are no barriers for mutual understanding when going from one discipline to another.
  6. We invite you to come to us with your integrity related queries rather then invent the wheel yourself again.As the internet shows every day, what you experience today has already been experienced elsewhere some time ago. So that’s why we like to save you the costs of re-inventing the wheel by offering you the use of our best practises.Amongst others, the next adressed can be used to send your queries to: