SlideShare a Scribd company logo
1 of 16
How has financial crises
                        changed PPP market?

Filip Drapak
World Bank Institute
May 2009
quot;Infrastructure offers significant investment opportunities for long-term investors, even
in a time of global crisisquot;

                              Ngozi N. Okonjo-Iweala, Managing Director,
                              World Bank, December 2008




“Recent review of infrastructure projects for the last six months, 
including social
projects, statistics revealed that 50% were unaffected by the global financial crisis, 25%
had had substantial increases and 25% had been cancelled.”

                                  Tadesse Admassu, Development Bank of Southern
                                  Africa (DBSA) international division executive vice-
                                  president, April 2009



                                                                                             2
Key issues of PPP in financial crises




 PPP economics have changed

 Lack of funding on both equity and debt side

 Lack of interest of investors and operators



     “The monoline wrapped bond market, which has been the financial structure of
     choice for large PFI projects over the past 10 years, is now effectively closed to new
     transactions. This has increased reliance on the banking market.

     The combination of capital adequacy requirements, reduced liquidity and higher
     funding costs has increased the strain on the project finance banking model. While
     the banks’ views of the PFI risk profile have not changed materially, funding
     availability is limited and credit margins have moved up.”


                                               Andy Rose, Executive Director, PUK

                                                                                              3
PPP economics have changed


 Economic cycle has to be taken in to the account

                           “Equity price bubble busts every 13 years on average, last for
                           2 ½ years and are associated with GDP losses of 4 percent of
                           GDP. Housing price busts are less frequent, but lasted nearly
                           twice as long and were associated with output losses that
                           were less twice as large…”

                           World Economic Outlook




    Risk management and mitigation implication

    (a) Country risk
    (b) On project risk
    (c) Refinancing risk



                                                                                            4
PPP economics have changed

 Implications for the VfM

             (a) Projects less likely to achieve VfM

                       - Increased cost of equity
                       - Increased role of equity and proportion of equity financing
                       - Increased cost of debt (offset by lower interest rates?)

             (b) Fiscal space implications to VfM


             (c) Some governments more rigorous on VfM and can be more keen on
litigation

                              Ernst & Young’s P3 team in the UK infrastructure reports that the average
                              margin for availability payment-based P3s, increased from 82bps to 94bps
                              between May and August 2008. Volume based payment P3 projects had
                              average margins of 155bps in August 2008, which is increase of 50bps since
                              credit crunch.
                                                        Ernst&Young’s UK infrastructure report


 5
PPP economics have changed


 VfM might be lost at the current market, this can however be offset by fiscal
and macro economical benefits of PPP
                     PPP lifecycle cost            PSC: public model


                                                                         VfM lost
     equity


     debt



    “Greater emphasis also needs to be made towards the social economic
    benefits delivered to a country or region which could mean adopting a
    more visionary approach to PPP models to include agglomeration benefits.
    Failure to do so will mean that PPP projects may never get off the ground
    on a pure cost benefit basis.”
                                              EC Harris, Is PPP dead and buried?
                                                                                    6
PPP economics have changed


 is there evidence for change in economics of PPP?

                              Global project finance 2007/2008


                                    51.3
     Equity financing
                                       74.4


                              15
      Bond financing
                            5.7
                                                                                          2007
                                                                                          2008
                                                            212.1
      Loan borrowing
                                                               234.9


       Global project                                                  278.4
          finance                                                              315


                        0          50   100   150    200       250     300       350
                                              USD billion               Project finance 2009



                                                                                                 7
PPP economics have changed


 is there evidence for change in economics of PPP?


                                  Change in 2008 in %

           60
                                                         45
           40


           20         11

            0                                                               Loan borrowing
       %




                 Loan borrowing   Bond financing   Equity financing         Bond financing
           -20                                                              Equity financing


           -40


           -60
                                       -62
           -80                                                        Project finance 2009


                                                                                               8
Global PPP in 2008

 Volume of PPPs have stagnated in 2008 on the 2007 level with growth mainly
generated in North America region (203% growth), however the 4Q volume fell 38%
(in comparison to 4Q 2007 volume)

                                           Global PPP in 2008


           Midle East anhd North Africa        4.5

                                    Asia             11.3

                         North America           8.4

                                   Spain       4.6

                              Portugal          6.4

                                     UK              10.9

                           Global PPP                                             67

                                           0    10      20   30   40    50   60   70   80
            Project finance 2009                              USD billion



                                                                                            9
Case study: A1, Motorway in Germany

 This is 72 km of existing motorway that shall be widened and refurbished



                    PPP type: DBFO concession (design, build, finance and operate)
                    Length:            30 years
                    Contract value:    EUR 650 million
                    Financiers:        HVB, Caja Madrid, DZ Bank
                    Sponsors:John Laing, Bilfinger Berger, Johan Bunte
                    Financial closure: 10 July 2008



   Original banks “disappeared” (Bilfinger Berger)
   Bigger margin than expected, flexible rates (fixed were expected)
   Smaller commitments from banks
   However largest PPP in Germany so far




                                                                                     10
Case study: M6 Phase III Motorway in Hungary

 This is 65 km motorway extension in Hungary



                    PPP type: DBFMO (design, build, finance, maintain and operate)
                    Length:             30 years
                    Contract value:     EUR 520 million
                    Financiers:         EIB and consortium of banks
                    Sponsors:Bilfinger Berger, Porr Solutions, Egis Projects
                    Financial closure: 17 June 2008



   Larger number of banks than initially expected (10 instead of 4)
   Bigger margin than expected, flexible rates (fixed were expected)
   Smaller amount raised
   EIB refinanced EUR 200 mill. only two weeks after financial close
   “Financial closure delay of few weeks would kill the deal” Bilfinger Berger



                                                                                     11
Case study: Mexico’s Farac I and II projects show how market conditions
                           have changed at project level

•   Farac I (30 year concession)                 Farac II (30 year concession)
•   Characteristics: Four roads spanned 550 km   Characteristics: Three roads spanned 850km
    in west-central region. Construction cost    of which 370 km is new construction in
    US$137 million
                                                 Pacific coast.
•   Tender date: Aug 2007
                                                 Tender date: 27 Feb 2009
•   Number of bidders: 6 consortia
                                                 Number of bidders: 2 consortia
•   Sponsors ICA and Goldman Sachs
                                                 Minimum price: US$2.29 billion:
•   Winning bid: US$4.17 billion
•                       47% higher than gov
                                                 Public bank contribution: Banobras to
    and market expectations                      provide Pesos15-18 billion to successfully
•   Debt/equity: 80/20                           bidder and Fonadin to provide up to 30% of
•   Project revenues: Toll fees                  debt
•   Project funding sources:                     Issues other than financial crisis:
•            US$3.4 billion local denominated    Concerns over right of way
    currency, short-term mini perm financing     Sponsor skepticism over government traffic
    (Commercial banks)
•            Lending was done on the               projections
    expectation of refinancing through
    securitization which has not happen yet.     Status: Canceled. STC: both bids too low
                                                 Project will be restructured and retendered
                                                                                                     12
                                                   Source: Ada Karina Izaguirre, PPIAF, World Bank
Policy and Governance implications

 Procurement has to be more flexible, shorter and financial market risk sensitive


        Market flexibility and procurement flexibility

       Procuring authorities are suffering from the higher financing costs and bank fees, as
       well as greater transaction costs from procedures and negotiations that are taking
       longer to conclude. One risk is that final bids that were thought to have committed
       financing are reopened as debt continues to be re-priced. It’s no longer realistic to
       insist on committed financing at the bid stage – most lenders require price flex, or
       indeed market flex clauses (in which most terms, not just pricing, can be adjusted).
       This makes it impossible to conclude the financial evaluation of private partner
       proposals until much later in the process, and sometimes not even until days before
       financial close.

       This creates significant headaches for procuring authorities. How can a preferred
       bidder be selected if the financial proposal is not known with great certainty? How can
       competitive tension be maintained in final lending negotiations until well after
       preferred bidder selection? Should government share the pricing risk to which the
       preferred bidder is currently exposed? In one current UK social infrastructure P3, the c.
       $150M debt package has been re-priced twice since April this year, and closing has
       been delayed.
                                                                         CCPPP, 2009               13
Policy and Governance implications: introducing DFC

 As one of potential policy measures to improve the financing of PPP projects
UK government used so called DFC (Debt Funding Competition)

                                            What is a DFC?

               A DFC is an initiative that has been employed in the UK a number of times
               since 2000 and has been championed by the UK HM Treasury as a
               mechanism for government to induce competition and thereby obtain more
               favorable debt funding terms.

               When using a DFC, government selects a preferred bidder and that preferred
               bidder, in consultation with government, then goes to the debt market
               seeking the best price for the debt funding for the project.
               The objective for the UK government was to increase the competitiveness of
               the lending market with a view to reducing the overall cost of the project.1
               We are now in a very different market where the primary focus of the DFC
               would be to source sufficient debt funders willing to lend to the project.


                                                         David Lester and Chris Keane, 2009


                                                                                              14
Policy and Governance implications: introducing new institutions
               and guarantee support mechanisms

 The solutions often suggest new institutions, from US discussion regarding the
Infrastructure bank, ideas of setting up national guarantee instruments to the
discussion on a new role of multilateral and development institutions.



            How to mitigate the impact of the financial crisis on PPPs2009

            The French Institute for PPP (IGD - Institute de la Gestion Déléguée) released in
            November its proposals to mitigate the impact of the financial crisis on PPPs in
            France. IGD suggests to address the issue of lack of liquidity through the delinking
            of the duration of contracts and the duration of loans that would allow the short-
            term financing of projects and its long-term refinancing when market conditions
            will be more favorable, and the creation of a special public vehicle that would be
            entitled to collect and provide long-term resources to support banks activities.

            IGD also proposes to reduce the impact on costs through a special state warranty
            on local authorities’ projects, and calls for a broader public support through
            investment subsidies when construction periods are important.
                                                         Pierre Van de Vyver, 2009


                                                                                                   15
Conclusions



 PPP economics jeopardized by financial crises impact, however this is
temporary impact

 PPP is not solution in time of financial crises – do not attempt to stimulate
economy using PPPs

 Smaller transactions and larger risk diversification are demanded by the
financial market

 Long maturities still available but costly

 Bigger role for development banks and multilateral institutions

 Governments should focus on building the pipeline for the future post financial
crises PPPs and improve policies and procedures for the bidding to accommodate
current situation, perhaps introduce debt funding competition (DFC)

 Bond, wrapped or privately insured financing not really available
                                                                                  16

More Related Content

What's hot

Financing the mozal project
Financing the mozal projectFinancing the mozal project
Financing the mozal projectVivek Kumar
 
Offshore toimialan mahdollisuudet Kaakkois Aasiassa
Offshore toimialan mahdollisuudet Kaakkois AasiassaOffshore toimialan mahdollisuudet Kaakkois Aasiassa
Offshore toimialan mahdollisuudet Kaakkois AasiassaBusiness Finland
 
Airports Council International (ACI) Annual Meeting Marrakech October 2011
Airports Council International (ACI) Annual Meeting Marrakech October 2011Airports Council International (ACI) Annual Meeting Marrakech October 2011
Airports Council International (ACI) Annual Meeting Marrakech October 2011Thomas Frankl
 
Private sector participation in West Africa Container Terminals, World Bank
Private sector participation in West Africa Container Terminals, World BankPrivate sector participation in West Africa Container Terminals, World Bank
Private sector participation in West Africa Container Terminals, World BankAGPAOC- PMAWCA
 
Wales and the Atlantic Arc: Developing Ports
Wales and the Atlantic Arc: Developing PortsWales and the Atlantic Arc: Developing Ports
Wales and the Atlantic Arc: Developing PortsCláudio Carneiro
 

What's hot (8)

Financing the mozal project
Financing the mozal projectFinancing the mozal project
Financing the mozal project
 
Offshore toimialan mahdollisuudet Kaakkois Aasiassa
Offshore toimialan mahdollisuudet Kaakkois AasiassaOffshore toimialan mahdollisuudet Kaakkois Aasiassa
Offshore toimialan mahdollisuudet Kaakkois Aasiassa
 
Airports Council International (ACI) Annual Meeting Marrakech October 2011
Airports Council International (ACI) Annual Meeting Marrakech October 2011Airports Council International (ACI) Annual Meeting Marrakech October 2011
Airports Council International (ACI) Annual Meeting Marrakech October 2011
 
How To Become Financially Successful 2
How To Become Financially Successful 2How To Become Financially Successful 2
How To Become Financially Successful 2
 
GIB2015_Solid Standards and Ratings_Georgoulias
GIB2015_Solid Standards and Ratings_GeorgouliasGIB2015_Solid Standards and Ratings_Georgoulias
GIB2015_Solid Standards and Ratings_Georgoulias
 
Poten and partners
Poten and partnersPoten and partners
Poten and partners
 
Private sector participation in West Africa Container Terminals, World Bank
Private sector participation in West Africa Container Terminals, World BankPrivate sector participation in West Africa Container Terminals, World Bank
Private sector participation in West Africa Container Terminals, World Bank
 
Wales and the Atlantic Arc: Developing Ports
Wales and the Atlantic Arc: Developing PortsWales and the Atlantic Arc: Developing Ports
Wales and the Atlantic Arc: Developing Ports
 

Similar to How financial crises impacted PPP market

How the Financial Crisis has Changed the Market for Public Private Partnershi...
How the Financial Crisis has Changed the Market for Public Private Partnershi...How the Financial Crisis has Changed the Market for Public Private Partnershi...
How the Financial Crisis has Changed the Market for Public Private Partnershi...icgfmconference
 
SuperReturn 2010: Bumpy road ahead for Private Equity investors
SuperReturn 2010: Bumpy road ahead for Private Equity investorsSuperReturn 2010: Bumpy road ahead for Private Equity investors
SuperReturn 2010: Bumpy road ahead for Private Equity investorsValue Partners
 
GE-Financial Services Investor Meeting
GE-Financial Services Investor MeetingGE-Financial Services Investor Meeting
GE-Financial Services Investor MeetingManya Mohan
 
OECD, 7th Meeting on Public-Private Partnerships - Isabel RIAL
OECD, 7th Meeting on Public-Private Partnerships - Isabel RIALOECD, 7th Meeting on Public-Private Partnerships - Isabel RIAL
OECD, 7th Meeting on Public-Private Partnerships - Isabel RIALOECD Governance
 
Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...
Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...
Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...finance8
 
General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...
General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...
General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...Manya Mohan
 
Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...
Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...
Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...Zanders Treasury, Risk and Finance
 
CIT Presentation
CIT PresentationCIT Presentation
CIT Presentationfinance28
 
DTE_4Q07_earnings
DTE_4Q07_earningsDTE_4Q07_earnings
DTE_4Q07_earningsfinance41
 
DTE_4Q07_earnings
DTE_4Q07_earningsDTE_4Q07_earnings
DTE_4Q07_earningsfinance41
 
PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات
PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات
PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات Egyptian Engineers Association
 
Chicago Microfinance Conference 2010 Bga Presentation
Chicago Microfinance Conference 2010 Bga PresentationChicago Microfinance Conference 2010 Bga Presentation
Chicago Microfinance Conference 2010 Bga Presentationzeynepburcu
 
Filip drapak ppp in financial crises english
Filip drapak ppp in financial crises englishFilip drapak ppp in financial crises english
Filip drapak ppp in financial crises englishicgfmconference
 
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309finance42
 
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309finance42
 
Deloitte Private Debt Conference Luxembourg | 17 November 2015
Deloitte Private Debt Conference Luxembourg | 17 November 2015Deloitte Private Debt Conference Luxembourg | 17 November 2015
Deloitte Private Debt Conference Luxembourg | 17 November 2015Thorsten Lederer 托尔斯滕
 

Similar to How financial crises impacted PPP market (20)

How the Financial Crisis has Changed the Market for Public Private Partnershi...
How the Financial Crisis has Changed the Market for Public Private Partnershi...How the Financial Crisis has Changed the Market for Public Private Partnershi...
How the Financial Crisis has Changed the Market for Public Private Partnershi...
 
Public Investment Management
Public Investment ManagementPublic Investment Management
Public Investment Management
 
Alkholifey
AlkholifeyAlkholifey
Alkholifey
 
SuperReturn 2010: Bumpy road ahead for Private Equity investors
SuperReturn 2010: Bumpy road ahead for Private Equity investorsSuperReturn 2010: Bumpy road ahead for Private Equity investors
SuperReturn 2010: Bumpy road ahead for Private Equity investors
 
GE-Financial Services Investor Meeting
GE-Financial Services Investor MeetingGE-Financial Services Investor Meeting
GE-Financial Services Investor Meeting
 
OECD, 7th Meeting on Public-Private Partnerships - Isabel RIAL
OECD, 7th Meeting on Public-Private Partnerships - Isabel RIALOECD, 7th Meeting on Public-Private Partnerships - Isabel RIAL
OECD, 7th Meeting on Public-Private Partnerships - Isabel RIAL
 
2012 MENA Project and PPP Finance
2012 MENA Project and PPP Finance2012 MENA Project and PPP Finance
2012 MENA Project and PPP Finance
 
Cobp Vie 2007
Cobp Vie 2007Cobp Vie 2007
Cobp Vie 2007
 
Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...
Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...
Eric Feldstein, CEO of GMAC LLC - Sale of Majority Interest in GMAC - Investo...
 
General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...
General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...
General Motors-Events & Presentations 2008 Deutsche Bank Leveraged Finance Co...
 
Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...
Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...
Capital Managment - Koos Timmermans (ING) voor Zanders Risicomanagement Semin...
 
CIT Presentation
CIT PresentationCIT Presentation
CIT Presentation
 
DTE_4Q07_earnings
DTE_4Q07_earningsDTE_4Q07_earnings
DTE_4Q07_earnings
 
DTE_4Q07_earnings
DTE_4Q07_earningsDTE_4Q07_earnings
DTE_4Q07_earnings
 
PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات
PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات
PPPم.48-#تواصل_تطوير-أ.د.هشام عبدالخالق-مقدمة في مشروعات
 
Chicago Microfinance Conference 2010 Bga Presentation
Chicago Microfinance Conference 2010 Bga PresentationChicago Microfinance Conference 2010 Bga Presentation
Chicago Microfinance Conference 2010 Bga Presentation
 
Filip drapak ppp in financial crises english
Filip drapak ppp in financial crises englishFilip drapak ppp in financial crises english
Filip drapak ppp in financial crises english
 
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
 
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
terex 818CD3A3-66E7-4B54-8F3A-347B1F8B4D68_JPMorgan020309
 
Deloitte Private Debt Conference Luxembourg | 17 November 2015
Deloitte Private Debt Conference Luxembourg | 17 November 2015Deloitte Private Debt Conference Luxembourg | 17 November 2015
Deloitte Private Debt Conference Luxembourg | 17 November 2015
 

Recently uploaded

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 

Recently uploaded (20)

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 

How financial crises impacted PPP market

  • 1. How has financial crises changed PPP market? Filip Drapak World Bank Institute May 2009
  • 2. quot;Infrastructure offers significant investment opportunities for long-term investors, even in a time of global crisisquot; Ngozi N. Okonjo-Iweala, Managing Director, World Bank, December 2008 “Recent review of infrastructure projects for the last six months, 
including social projects, statistics revealed that 50% were unaffected by the global financial crisis, 25% had had substantial increases and 25% had been cancelled.” Tadesse Admassu, Development Bank of Southern Africa (DBSA) international division executive vice- president, April 2009 2
  • 3. Key issues of PPP in financial crises  PPP economics have changed  Lack of funding on both equity and debt side  Lack of interest of investors and operators “The monoline wrapped bond market, which has been the financial structure of choice for large PFI projects over the past 10 years, is now effectively closed to new transactions. This has increased reliance on the banking market. The combination of capital adequacy requirements, reduced liquidity and higher funding costs has increased the strain on the project finance banking model. While the banks’ views of the PFI risk profile have not changed materially, funding availability is limited and credit margins have moved up.” Andy Rose, Executive Director, PUK 3
  • 4. PPP economics have changed  Economic cycle has to be taken in to the account “Equity price bubble busts every 13 years on average, last for 2 ½ years and are associated with GDP losses of 4 percent of GDP. Housing price busts are less frequent, but lasted nearly twice as long and were associated with output losses that were less twice as large…” World Economic Outlook  Risk management and mitigation implication (a) Country risk (b) On project risk (c) Refinancing risk 4
  • 5. PPP economics have changed  Implications for the VfM (a) Projects less likely to achieve VfM - Increased cost of equity - Increased role of equity and proportion of equity financing - Increased cost of debt (offset by lower interest rates?) (b) Fiscal space implications to VfM (c) Some governments more rigorous on VfM and can be more keen on litigation Ernst & Young’s P3 team in the UK infrastructure reports that the average margin for availability payment-based P3s, increased from 82bps to 94bps between May and August 2008. Volume based payment P3 projects had average margins of 155bps in August 2008, which is increase of 50bps since credit crunch. Ernst&Young’s UK infrastructure report 5
  • 6. PPP economics have changed  VfM might be lost at the current market, this can however be offset by fiscal and macro economical benefits of PPP PPP lifecycle cost PSC: public model VfM lost equity debt “Greater emphasis also needs to be made towards the social economic benefits delivered to a country or region which could mean adopting a more visionary approach to PPP models to include agglomeration benefits. Failure to do so will mean that PPP projects may never get off the ground on a pure cost benefit basis.” EC Harris, Is PPP dead and buried? 6
  • 7. PPP economics have changed  is there evidence for change in economics of PPP? Global project finance 2007/2008 51.3 Equity financing 74.4 15 Bond financing 5.7 2007 2008 212.1 Loan borrowing 234.9 Global project 278.4 finance 315 0 50 100 150 200 250 300 350 USD billion Project finance 2009 7
  • 8. PPP economics have changed  is there evidence for change in economics of PPP? Change in 2008 in % 60 45 40 20 11 0 Loan borrowing % Loan borrowing Bond financing Equity financing Bond financing -20 Equity financing -40 -60 -62 -80 Project finance 2009 8
  • 9. Global PPP in 2008  Volume of PPPs have stagnated in 2008 on the 2007 level with growth mainly generated in North America region (203% growth), however the 4Q volume fell 38% (in comparison to 4Q 2007 volume) Global PPP in 2008 Midle East anhd North Africa 4.5 Asia 11.3 North America 8.4 Spain 4.6 Portugal 6.4 UK 10.9 Global PPP 67 0 10 20 30 40 50 60 70 80 Project finance 2009 USD billion 9
  • 10. Case study: A1, Motorway in Germany  This is 72 km of existing motorway that shall be widened and refurbished PPP type: DBFO concession (design, build, finance and operate) Length: 30 years Contract value: EUR 650 million Financiers: HVB, Caja Madrid, DZ Bank Sponsors:John Laing, Bilfinger Berger, Johan Bunte Financial closure: 10 July 2008  Original banks “disappeared” (Bilfinger Berger)  Bigger margin than expected, flexible rates (fixed were expected)  Smaller commitments from banks  However largest PPP in Germany so far 10
  • 11. Case study: M6 Phase III Motorway in Hungary  This is 65 km motorway extension in Hungary PPP type: DBFMO (design, build, finance, maintain and operate) Length: 30 years Contract value: EUR 520 million Financiers: EIB and consortium of banks Sponsors:Bilfinger Berger, Porr Solutions, Egis Projects Financial closure: 17 June 2008  Larger number of banks than initially expected (10 instead of 4)  Bigger margin than expected, flexible rates (fixed were expected)  Smaller amount raised  EIB refinanced EUR 200 mill. only two weeks after financial close  “Financial closure delay of few weeks would kill the deal” Bilfinger Berger 11
  • 12. Case study: Mexico’s Farac I and II projects show how market conditions have changed at project level • Farac I (30 year concession) Farac II (30 year concession) • Characteristics: Four roads spanned 550 km Characteristics: Three roads spanned 850km in west-central region. Construction cost of which 370 km is new construction in US$137 million Pacific coast. • Tender date: Aug 2007 Tender date: 27 Feb 2009 • Number of bidders: 6 consortia Number of bidders: 2 consortia • Sponsors ICA and Goldman Sachs Minimum price: US$2.29 billion: • Winning bid: US$4.17 billion • 47% higher than gov Public bank contribution: Banobras to and market expectations provide Pesos15-18 billion to successfully • Debt/equity: 80/20 bidder and Fonadin to provide up to 30% of • Project revenues: Toll fees debt • Project funding sources: Issues other than financial crisis: • US$3.4 billion local denominated Concerns over right of way currency, short-term mini perm financing Sponsor skepticism over government traffic (Commercial banks) • Lending was done on the projections expectation of refinancing through securitization which has not happen yet. Status: Canceled. STC: both bids too low Project will be restructured and retendered 12 Source: Ada Karina Izaguirre, PPIAF, World Bank
  • 13. Policy and Governance implications  Procurement has to be more flexible, shorter and financial market risk sensitive Market flexibility and procurement flexibility Procuring authorities are suffering from the higher financing costs and bank fees, as well as greater transaction costs from procedures and negotiations that are taking longer to conclude. One risk is that final bids that were thought to have committed financing are reopened as debt continues to be re-priced. It’s no longer realistic to insist on committed financing at the bid stage – most lenders require price flex, or indeed market flex clauses (in which most terms, not just pricing, can be adjusted). This makes it impossible to conclude the financial evaluation of private partner proposals until much later in the process, and sometimes not even until days before financial close. This creates significant headaches for procuring authorities. How can a preferred bidder be selected if the financial proposal is not known with great certainty? How can competitive tension be maintained in final lending negotiations until well after preferred bidder selection? Should government share the pricing risk to which the preferred bidder is currently exposed? In one current UK social infrastructure P3, the c. $150M debt package has been re-priced twice since April this year, and closing has been delayed. CCPPP, 2009 13
  • 14. Policy and Governance implications: introducing DFC  As one of potential policy measures to improve the financing of PPP projects UK government used so called DFC (Debt Funding Competition) What is a DFC? A DFC is an initiative that has been employed in the UK a number of times since 2000 and has been championed by the UK HM Treasury as a mechanism for government to induce competition and thereby obtain more favorable debt funding terms. When using a DFC, government selects a preferred bidder and that preferred bidder, in consultation with government, then goes to the debt market seeking the best price for the debt funding for the project. The objective for the UK government was to increase the competitiveness of the lending market with a view to reducing the overall cost of the project.1 We are now in a very different market where the primary focus of the DFC would be to source sufficient debt funders willing to lend to the project. David Lester and Chris Keane, 2009 14
  • 15. Policy and Governance implications: introducing new institutions and guarantee support mechanisms  The solutions often suggest new institutions, from US discussion regarding the Infrastructure bank, ideas of setting up national guarantee instruments to the discussion on a new role of multilateral and development institutions. How to mitigate the impact of the financial crisis on PPPs2009 The French Institute for PPP (IGD - Institute de la Gestion Déléguée) released in November its proposals to mitigate the impact of the financial crisis on PPPs in France. IGD suggests to address the issue of lack of liquidity through the delinking of the duration of contracts and the duration of loans that would allow the short- term financing of projects and its long-term refinancing when market conditions will be more favorable, and the creation of a special public vehicle that would be entitled to collect and provide long-term resources to support banks activities. IGD also proposes to reduce the impact on costs through a special state warranty on local authorities’ projects, and calls for a broader public support through investment subsidies when construction periods are important. Pierre Van de Vyver, 2009 15
  • 16. Conclusions  PPP economics jeopardized by financial crises impact, however this is temporary impact  PPP is not solution in time of financial crises – do not attempt to stimulate economy using PPPs  Smaller transactions and larger risk diversification are demanded by the financial market  Long maturities still available but costly  Bigger role for development banks and multilateral institutions  Governments should focus on building the pipeline for the future post financial crises PPPs and improve policies and procedures for the bidding to accommodate current situation, perhaps introduce debt funding competition (DFC)  Bond, wrapped or privately insured financing not really available 16