ID    Task Name                                             Duration     Nov 20, '06                         Nov 27, '06                                 Dec 4, '06                           Dec 11, '06                        Dec 18, '06                     Dec 25, '06                     Jan
                                                                           M    T     W      T    F   S   S    M    T     W      T     F    S       S      M     T   W   T     F     S    S     M    T     W   T   F    S    S     M    T     W   T   F   S   S    M    T     W   T   F   S   S    M
  1    GROUP 1 (M. Najar)                                       85 days
  2         6923 - Hawthorne Cross (sign A1)                    15 days
  3         7075 - The Corridors                                18 days
  4         7119 - Panda Express Boulder City (pylon)            9 days
  5         7519 - Z-Mario                                       6 days
  6         7119 - Panda Express (face)                          2 days
  7         7444 - Navy Federal (sign A, B)                      3 days
  8         7401 - Graceland Wedding Chapel                      5 days
  9         7446 - Deser Inn (sign B2 - B3)                     12 days
 10         6913 - Oracle Mall (sign A1)                        15 days
 11
 12    GROUP 2 (Alfredo C.)                                   101 days
 13         6985 - Silverado & Maryland (sign A)                10 days
 14         6850 - Margarita Crossings (sign A1)                 5 days
 15         6850 - Margarita Crossings (sign A2)                 5 days
 16         7155 - Loehmann's Plaza (sign A1)                   12 days
 17         6985 - Silverado & Maryland (sign A rework)          2 days
 18         7321 - Eastside Town Center                          8 days
 19         7444 - Navy Federal (sign K)                        10 days
 20         6383 - Shops @ San Miguel (A1, A2)                   8 days
 21         7446 - Deser Inn (sign A)                           12 days
 22         7538 - San Ysidro 24 Hour Parking (sign B)          10 days
 23         6729 - Cielo Village (sign F)                        7 days
 24         6729 - Cielo Village (if needed)                     7 days
 25         6359 - Bear Creek (sign A)                          10 days
 26
 27    GROUP 3 (Gerson M.)                                      81 days
 28         7287 - Safari Business Park (sign A)                10 days
 29         7246 - Panda Express Maricopa, AZ                    6 days
 30         7153 - The Shops @ Cypress (sign B2)                 5 days
 31         7155 - Loehmann's Plaza (sign A2)                   12 days
 32         6271 - Paramount Plaza (sign B1)                     6 days
 33         7434 - Rancho Plaza Penasquitos (sign B1 - B2)       7 days
 34         7434 - Rancho Plaza Penasquitos (sign B3 - B4)       7 days
 35         7538 - San Ysidro 24 Hour Parking (sign A)          10 days
 36         7420 - Seacoast Comm Church                          5 days
 37         7299 - Shops @ Clinton Keith (sign A)               12 days
 38
 39    GROUP 4 (Alberto C.)                                     77 days
 40         6923 - Hawthorne Cross (sign B1)                    10 days
 41         7183 - Dollar Self Storage                           3 days
 42         7159 - Chevron San Marcos                            6 days
 43         6271 - Paramount Plaza (sign A1)                     5 days
 44         6271 - Paramount Plaza (sign A2)                     4 days



                                               Task                              Milestone                                    Rolled Up Split                                External Tasks                            Deadline
Project: SUBCA - All Jobs
                                               Split                             Summary                                      Rolled Up Milestone                            Project Summary
Date: Fri 1/26/07
                                               Progress                          Rolled Up Task                               Rolled Up Progress                             External Milestone

                                                                                                                                                        Page 1
ID    Task Name                                          Duration     Nov 20, '06                         Nov 27, '06                                 Dec 4, '06                           Dec 11, '06                        Dec 18, '06                     Dec 25, '06                     Jan
                                                                        M    T     W      T    F   S   S    M    T     W      T     F    S       S      M     T   W   T     F     S    S     M    T     W   T   F    S    S     M    T     W   T   F   S   S    M    T     W   T   F   S   S    M
 45         7362 - Saltgrass Steakhouse                       4 days
 46         6271 - Paramount Plaza (B2)                       5 days
 47         7453 - Madison Creek                              3 days
 48         7301 - Westfield Main Place (sign 3H)             5 days
 49         7301 - Westfield Main Place (sign 5)              5 days
 50         7301 - Westfield Main Place (sign 4A - 4F)        5 days
 51         7393 - Miramar Crossings (sign A)                 7 days
 52         7393 - Miramar Crossings (sign B)                 4 days
 53         6358 - Soquel Canyon (sign A1)                   10 days
 54
 55    GROUP 5 (Sergio S.)                                   84 days
 56         7144 - Seal Beach (sign B)                       10 days
 57         Raceways                                          2 days
 58         Golden Nugget Cashiers                             1 day
 59         Silverstone Brackets (32)                          1 day
 60         7386 - Destination O-Eight                        5 days
 61         Navy Federal Raceways                            10 days
 62         7142 - Village @ San Jacinto (sign C1, C2)       19 days
 63         7549 - Craig & Lamb (sign B)                      6 days
 64         7446 - Desert Inn (sign B1)                       8 days
 65         7347 - Mountain Green                            10 days
 66         6359 - Bear Creek (sign B)                       12 days
 67
 68    GROUP 6 (Edmundo M.)                                  73 days
 69         6923 - Hawthorne Crossings (sign D)               5 days
 70         7153 - The Shops @ Cypress (sign A1)             11 days
 71         7142 - Village @ San Jacinto (sign A1)           12 days
 72         7142 - Village @ San Jacinto (D1 - D2)           10 days
 73         7444 - Navy Federal (sign N1, N2)                 7 days
 74         7472 - Canyon Hills                               5 days
 75         6887 - Vail Ranch Town Square (sign GS1)          7 days
 76         6887 - Vail Ranch Town Square (sign GS2)          7 days
 77         6478 - Trail Crossings (sign C)                   8 days
 78
 79    GROUP 7 (Ismael P.)                                   98 days
 80         7287 - Safari Business Park (sign B)             16 days
 81         6923 - Hawthorne Cross (sign C)                   3 days
 82         7142 - Village @ San Jacinto (sign A2)           15 days
 83         7142 - Village @ San Jacinto (sign D3 - D4)      15 days
 84         7549 - Craig & Lamb (sign A)                      9 days
 85         7520 - Kalmia Plaza (sign A1)                    10 days
 86         7520 - Kalmia Plaza (sign A2)                    10 days
 87         7547 - The Campus                                 5 days
 88         7299 - Shops @ Clinton Keith (sign B1)           15 days



                                              Task                            Milestone                                    Rolled Up Split                                External Tasks                            Deadline
Project: SUBCA - All Jobs
                                              Split                           Summary                                      Rolled Up Milestone                            Project Summary
Date: Fri 1/26/07
                                              Progress                        Rolled Up Task                               Rolled Up Progress                             External Milestone

                                                                                                                                                     Page 2
ID    Task Name                                      Duration     Nov 20, '06                         Nov 27, '06                                 Dec 4, '06                           Dec 11, '06                        Dec 18, '06                     Dec 25, '06                     Jan
                                                                    M    T     W      T    F   S   S    M    T     W      T     F    S       S      M     T   W   T     F     S    S     M    T     W   T   F    S    S     M    T     W   T   F   S   S    M    T     W   T   F   S   S    M
 89
 90    GROUP 8 (Cesar M.)                                83 days
 91         7144 - Seal Beach (sign C2)                   4 days
 92         6985 - Silverado & Maryland (sign B)         10 days
 93         6616 - Orchard (repair)                        1 day
 94         7153 - The Shops @ Cypress (sign A2)          7 days
 95         7301 - Westfield (Main) sign 1A, 1B          12 days
 96         VACATION                                      5 days
 97         7142 - Village @ San Jacinto (sign E)         7 days
 98         7444 - Navy Federal (sign C1 - C4)            7 days
 99         7491 - Money Gram                             3 days
100         7520 - Kalmia Plaza (sign B)                  5 days
101         6358 - Soquel Canyon (sign A2)               10 days
102         7299 - Shops @ Clinton Keith (sign B2)       12 days




                                           Task                           Milestone                                    Rolled Up Split                                External Tasks                            Deadline
Project: SUBCA - All Jobs
                                           Split                          Summary                                      Rolled Up Milestone                            Project Summary
Date: Fri 1/26/07
                                           Progress                       Rolled Up Task                               Rolled Up Progress                             External Milestone

                                                                                                                                                 Page 3
ID    Task Name                                             Duration     , '07                            Jan 8, '07                             Jan 15, '07                         Jan 22, '07                      Jan 29, '07                     Feb 5, '07                       Feb 12, '0
                                                                            T     W   T       F    S   S    M     T     W   T      F     S    S    M    T     W   T   F     S     S    M    T     W   T   F   S    S    M    T     W   T   F   S   S    M     T     W   T   F   S   S    M    T
  1    GROUP 1 (M. Najar)                                       85 days
  2         6923 - Hawthorne Cross (sign A1)                    15 days
  3         7075 - The Corridors                                18 days
  4         7119 - Panda Express Boulder City (pylon)            9 days
  5         7519 - Z-Mario                                       6 days
  6         7119 - Panda Express (face)                          2 days
  7         7444 - Navy Federal (sign A, B)                      3 days
  8         7401 - Graceland Wedding Chapel                      5 days
  9         7446 - Deser Inn (sign B2 - B3)                     12 days
 10         6913 - Oracle Mall (sign A1)                        15 days
 11
 12    GROUP 2 (Alfredo C.)                                   101 days
 13         6985 - Silverado & Maryland (sign A)                10 days
 14         6850 - Margarita Crossings (sign A1)                 5 days
 15         6850 - Margarita Crossings (sign A2)                 5 days
 16         7155 - Loehmann's Plaza (sign A1)                   12 days
 17         6985 - Silverado & Maryland (sign A rework)          2 days
 18         7321 - Eastside Town Center                          8 days
 19         7444 - Navy Federal (sign K)                        10 days
 20         6383 - Shops @ San Miguel (A1, A2)                   8 days
 21         7446 - Deser Inn (sign A)                           12 days
 22         7538 - San Ysidro 24 Hour Parking (sign B)          10 days
 23         6729 - Cielo Village (sign F)                        7 days
 24         6729 - Cielo Village (if needed)                     7 days
 25         6359 - Bear Creek (sign A)                          10 days
 26
 27    GROUP 3 (Gerson M.)                                      81 days
 28         7287 - Safari Business Park (sign A)                10 days
 29         7246 - Panda Express Maricopa, AZ                    6 days
 30         7153 - The Shops @ Cypress (sign B2)                 5 days
 31         7155 - Loehmann's Plaza (sign A2)                   12 days
 32         6271 - Paramount Plaza (sign B1)                     6 days
 33         7434 - Rancho Plaza Penasquitos (sign B1 - B2)       7 days
 34         7434 - Rancho Plaza Penasquitos (sign B3 - B4)       7 days
 35         7538 - San Ysidro 24 Hour Parking (sign A)          10 days
 36         7420 - Seacoast Comm Church                          5 days
 37         7299 - Shops @ Clinton Keith (sign A)               12 days
 38
 39    GROUP 4 (Alberto C.)                                     77 days
 40         6923 - Hawthorne Cross (sign B1)                    10 days
 41         7183 - Dollar Self Storage                           3 days
 42         7159 - Chevron San Marcos                            6 days
 43         6271 - Paramount Plaza (sign A1)                     5 days
 44         6271 - Paramount Plaza (sign A2)                     4 days



                                               Task                               Milestone                                     Rolled Up Split                           External Tasks                          Deadline
Project: SUBCA - All Jobs
                                               Split                              Summary                                       Rolled Up Milestone                       Project Summary
Date: Fri 1/26/07
                                               Progress                           Rolled Up Task                                Rolled Up Progress                        External Milestone

                                                                                                                                                      Page 4
ID    Task Name                                          Duration     , '07                            Jan 8, '07                             Jan 15, '07                         Jan 22, '07                      Jan 29, '07                     Feb 5, '07                       Feb 12, '0
                                                                         T     W   T       F    S   S    M     T     W   T      F     S    S    M    T     W   T   F     S     S    M    T     W   T   F   S    S    M    T     W   T   F   S   S    M     T     W   T   F   S   S    M    T
 45         7362 - Saltgrass Steakhouse                       4 days
 46         6271 - Paramount Plaza (B2)                       5 days
 47         7453 - Madison Creek                              3 days
 48         7301 - Westfield Main Place (sign 3H)             5 days
 49         7301 - Westfield Main Place (sign 5)              5 days
 50         7301 - Westfield Main Place (sign 4A - 4F)        5 days
 51         7393 - Miramar Crossings (sign A)                 7 days
 52         7393 - Miramar Crossings (sign B)                 4 days
 53         6358 - Soquel Canyon (sign A1)                   10 days
 54
 55    GROUP 5 (Sergio S.)                                   84 days
 56         7144 - Seal Beach (sign B)                       10 days
 57         Raceways                                          2 days
 58         Golden Nugget Cashiers                             1 day
 59         Silverstone Brackets (32)                          1 day
 60         7386 - Destination O-Eight                        5 days
 61         Navy Federal Raceways                            10 days
 62         7142 - Village @ San Jacinto (sign C1, C2)       19 days
 63         7549 - Craig & Lamb (sign B)                      6 days
 64         7446 - Desert Inn (sign B1)                       8 days
 65         7347 - Mountain Green                            10 days
 66         6359 - Bear Creek (sign B)                       12 days
 67
 68    GROUP 6 (Edmundo M.)                                  73 days
 69         6923 - Hawthorne Crossings (sign D)               5 days
 70         7153 - The Shops @ Cypress (sign A1)             11 days
 71         7142 - Village @ San Jacinto (sign A1)           12 days
 72         7142 - Village @ San Jacinto (D1 - D2)           10 days
 73         7444 - Navy Federal (sign N1, N2)                 7 days
 74         7472 - Canyon Hills                               5 days
 75         6887 - Vail Ranch Town Square (sign GS1)          7 days
 76         6887 - Vail Ranch Town Square (sign GS2)          7 days
 77         6478 - Trail Crossings (sign C)                   8 days
 78
 79    GROUP 7 (Ismael P.)                                   98 days
 80         7287 - Safari Business Park (sign B)             16 days
 81         6923 - Hawthorne Cross (sign C)                   3 days
 82         7142 - Village @ San Jacinto (sign A2)           15 days
 83         7142 - Village @ San Jacinto (sign D3 - D4)      15 days
 84         7549 - Craig & Lamb (sign A)                      9 days
 85         7520 - Kalmia Plaza (sign A1)                    10 days
 86         7520 - Kalmia Plaza (sign A2)                    10 days
 87         7547 - The Campus                                 5 days
 88         7299 - Shops @ Clinton Keith (sign B1)           15 days



                                              Task                             Milestone                                     Rolled Up Split                           External Tasks                          Deadline
Project: SUBCA - All Jobs
                                              Split                            Summary                                       Rolled Up Milestone                       Project Summary
Date: Fri 1/26/07
                                              Progress                         Rolled Up Task                                Rolled Up Progress                        External Milestone

                                                                                                                                                   Page 5
ID    Task Name                                      Duration     , '07                            Jan 8, '07                             Jan 15, '07                         Jan 22, '07                      Jan 29, '07                     Feb 5, '07                       Feb 12, '0
                                                                     T     W   T       F    S   S    M     T     W   T      F     S    S    M    T     W   T   F     S     S    M    T     W   T   F   S    S    M    T     W   T   F   S   S    M     T     W   T   F   S   S    M    T
 89
 90    GROUP 8 (Cesar M.)                                83 days
 91         7144 - Seal Beach (sign C2)                   4 days
 92         6985 - Silverado & Maryland (sign B)         10 days
 93         6616 - Orchard (repair)                        1 day
 94         7153 - The Shops @ Cypress (sign A2)          7 days
 95         7301 - Westfield (Main) sign 1A, 1B          12 days
 96         VACATION                                      5 days
 97         7142 - Village @ San Jacinto (sign E)         7 days
 98         7444 - Navy Federal (sign C1 - C4)            7 days
 99         7491 - Money Gram                             3 days
100         7520 - Kalmia Plaza (sign B)                  5 days
101         6358 - Soquel Canyon (sign A2)               10 days
102         7299 - Shops @ Clinton Keith (sign B2)       12 days




                                           Task                            Milestone                                     Rolled Up Split                           External Tasks                          Deadline
Project: SUBCA - All Jobs
                                           Split                           Summary                                       Rolled Up Milestone                       Project Summary
Date: Fri 1/26/07
                                           Progress                        Rolled Up Task                                Rolled Up Progress                        External Milestone

                                                                                                                                               Page 6
ID    Task Name                                             Duration                              Feb 19, '07                          Feb 26, '07                         Mar 5, '07                         Mar 12, '07                     Mar 19, '07                     Mar 26, '07
                                                                          W   T   F       S    S    M    T     W   T   F      S     S    M    T     W     T   F   S     S    M     T       W   T   F   S   S    M    T     W   T   F   S   S    M    T     W   T   F   S   S    M    T     W
  1    GROUP 1 (M. Najar)                                       85 days
  2         6923 - Hawthorne Cross (sign A1)                    15 days
  3         7075 - The Corridors                                18 days
  4         7119 - Panda Express Boulder City (pylon)            9 days
  5         7519 - Z-Mario                                       6 days
  6         7119 - Panda Express (face)                          2 days
  7         7444 - Navy Federal (sign A, B)                      3 days
  8         7401 - Graceland Wedding Chapel                      5 days
  9         7446 - Deser Inn (sign B2 - B3)                     12 days
 10         6913 - Oracle Mall (sign A1)                        15 days
 11
 12    GROUP 2 (Alfredo C.)                                   101 days
 13         6985 - Silverado & Maryland (sign A)                10 days
 14         6850 - Margarita Crossings (sign A1)                 5 days
 15         6850 - Margarita Crossings (sign A2)                 5 days
 16         7155 - Loehmann's Plaza (sign A1)                   12 days
 17         6985 - Silverado & Maryland (sign A rework)          2 days
 18         7321 - Eastside Town Center                          8 days
 19         7444 - Navy Federal (sign K)                        10 days
 20         6383 - Shops @ San Miguel (A1, A2)                   8 days
 21         7446 - Deser Inn (sign A)                           12 days
 22         7538 - San Ysidro 24 Hour Parking (sign B)          10 days
 23         6729 - Cielo Village (sign F)                        7 days
 24         6729 - Cielo Village (if needed)                     7 days
 25         6359 - Bear Creek (sign A)                          10 days
 26
 27    GROUP 3 (Gerson M.)                                      81 days
 28         7287 - Safari Business Park (sign A)                10 days
 29         7246 - Panda Express Maricopa, AZ                    6 days
 30         7153 - The Shops @ Cypress (sign B2)                 5 days
 31         7155 - Loehmann's Plaza (sign A2)                   12 days
 32         6271 - Paramount Plaza (sign B1)                     6 days
 33         7434 - Rancho Plaza Penasquitos (sign B1 - B2)       7 days
 34         7434 - Rancho Plaza Penasquitos (sign B3 - B4)       7 days
 35         7538 - San Ysidro 24 Hour Parking (sign A)          10 days
 36         7420 - Seacoast Comm Church                          5 days
 37         7299 - Shops @ Clinton Keith (sign A)               12 days
 38
 39    GROUP 4 (Alberto C.)                                     77 days
 40         6923 - Hawthorne Cross (sign B1)                    10 days
 41         7183 - Dollar Self Storage                           3 days
 42         7159 - Chevron San Marcos                            6 days
 43         6271 - Paramount Plaza (sign A1)                     5 days
 44         6271 - Paramount Plaza (sign A2)                     4 days



                                               Task                           Milestone                                    Rolled Up Split                            External Tasks                           Deadline
Project: SUBCA - All Jobs
                                               Split                          Summary                                      Rolled Up Milestone                        Project Summary
Date: Fri 1/26/07
                                               Progress                       Rolled Up Task                               Rolled Up Progress                         External Milestone

                                                                                                                                                 Page 7
ID    Task Name                                          Duration                              Feb 19, '07                          Feb 26, '07                         Mar 5, '07                         Mar 12, '07                     Mar 19, '07                     Mar 26, '07
                                                                       W   T   F       S    S    M    T     W   T   F      S     S    M    T     W     T   F   S     S    M     T       W   T   F   S   S    M    T     W   T   F   S   S    M    T     W   T   F   S   S    M    T     W
 45         7362 - Saltgrass Steakhouse                       4 days
 46         6271 - Paramount Plaza (B2)                       5 days
 47         7453 - Madison Creek                              3 days
 48         7301 - Westfield Main Place (sign 3H)             5 days
 49         7301 - Westfield Main Place (sign 5)              5 days
 50         7301 - Westfield Main Place (sign 4A - 4F)        5 days
 51         7393 - Miramar Crossings (sign A)                 7 days
 52         7393 - Miramar Crossings (sign B)                 4 days
 53         6358 - Soquel Canyon (sign A1)                   10 days
 54
 55    GROUP 5 (Sergio S.)                                   84 days
 56         7144 - Seal Beach (sign B)                       10 days
 57         Raceways                                          2 days
 58         Golden Nugget Cashiers                             1 day
 59         Silverstone Brackets (32)                          1 day
 60         7386 - Destination O-Eight                        5 days
 61         Navy Federal Raceways                            10 days
 62         7142 - Village @ San Jacinto (sign C1, C2)       19 days
 63         7549 - Craig & Lamb (sign B)                      6 days
 64         7446 - Desert Inn (sign B1)                       8 days
 65         7347 - Mountain Green                            10 days
 66         6359 - Bear Creek (sign B)                       12 days
 67
 68    GROUP 6 (Edmundo M.)                                  73 days
 69         6923 - Hawthorne Crossings (sign D)               5 days
 70         7153 - The Shops @ Cypress (sign A1)             11 days
 71         7142 - Village @ San Jacinto (sign A1)           12 days
 72         7142 - Village @ San Jacinto (D1 - D2)           10 days
 73         7444 - Navy Federal (sign N1, N2)                 7 days
 74         7472 - Canyon Hills                               5 days
 75         6887 - Vail Ranch Town Square (sign GS1)          7 days
 76         6887 - Vail Ranch Town Square (sign GS2)          7 days
 77         6478 - Trail Crossings (sign C)                   8 days
 78
 79    GROUP 7 (Ismael P.)                                   98 days
 80         7287 - Safari Business Park (sign B)             16 days
 81         6923 - Hawthorne Cross (sign C)                   3 days
 82         7142 - Village @ San Jacinto (sign A2)           15 days
 83         7142 - Village @ San Jacinto (sign D3 - D4)      15 days
 84         7549 - Craig & Lamb (sign A)                      9 days
 85         7520 - Kalmia Plaza (sign A1)                    10 days
 86         7520 - Kalmia Plaza (sign A2)                    10 days
 87         7547 - The Campus                                 5 days
 88         7299 - Shops @ Clinton Keith (sign B1)           15 days



                                              Task                         Milestone                                    Rolled Up Split                            External Tasks                           Deadline
Project: SUBCA - All Jobs
                                              Split                        Summary                                      Rolled Up Milestone                        Project Summary
Date: Fri 1/26/07
                                              Progress                     Rolled Up Task                               Rolled Up Progress                         External Milestone

                                                                                                                                              Page 8
ID    Task Name                                      Duration                              Feb 19, '07                          Feb 26, '07                         Mar 5, '07                         Mar 12, '07                     Mar 19, '07                     Mar 26, '07
                                                                   W   T   F       S    S    M    T     W   T   F      S     S    M    T     W     T   F   S     S    M     T       W   T   F   S   S    M    T     W   T   F   S   S    M    T     W   T   F   S   S    M    T     W
 89
 90    GROUP 8 (Cesar M.)                                83 days
 91         7144 - Seal Beach (sign C2)                   4 days
 92         6985 - Silverado & Maryland (sign B)         10 days
 93         6616 - Orchard (repair)                        1 day
 94         7153 - The Shops @ Cypress (sign A2)          7 days
 95         7301 - Westfield (Main) sign 1A, 1B          12 days
 96         VACATION                                      5 days
 97         7142 - Village @ San Jacinto (sign E)         7 days
 98         7444 - Navy Federal (sign C1 - C4)            7 days
 99         7491 - Money Gram                             3 days
100         7520 - Kalmia Plaza (sign B)                  5 days
101         6358 - Soquel Canyon (sign A2)               10 days
102         7299 - Shops @ Clinton Keith (sign B2)       12 days




                                           Task                        Milestone                                    Rolled Up Split                            External Tasks                           Deadline
Project: SUBCA - All Jobs
                                           Split                       Summary                                      Rolled Up Milestone                        Project Summary
Date: Fri 1/26/07
                                           Progress                    Rolled Up Task                               Rolled Up Progress                         External Milestone

                                                                                                                                          Page 9

More Related Content

Recently uploaded

Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTSkajalroy875762
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...pujan9679
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...meghakumariji156
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubaijaehdlyzca
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecZurliaSoop
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 

Recently uploaded (20)

Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 

Featured

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by HubspotMarius Sescu
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTExpeed Software
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsPixeldarts
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthThinkNow
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfmarketingartwork
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024Neil Kimberley
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)contently
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024Albert Qian
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsKurio // The Social Media Age(ncy)
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Search Engine Journal
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summarySpeakerHub
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next Tessa Mero
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentLily Ray
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best PracticesVit Horky
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project managementMindGenius
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...RachelPearson36
 

Featured (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Production Schedule

  • 1. ID Task Name Duration Nov 20, '06 Nov 27, '06 Dec 4, '06 Dec 11, '06 Dec 18, '06 Dec 25, '06 Jan M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M 1 GROUP 1 (M. Najar) 85 days 2 6923 - Hawthorne Cross (sign A1) 15 days 3 7075 - The Corridors 18 days 4 7119 - Panda Express Boulder City (pylon) 9 days 5 7519 - Z-Mario 6 days 6 7119 - Panda Express (face) 2 days 7 7444 - Navy Federal (sign A, B) 3 days 8 7401 - Graceland Wedding Chapel 5 days 9 7446 - Deser Inn (sign B2 - B3) 12 days 10 6913 - Oracle Mall (sign A1) 15 days 11 12 GROUP 2 (Alfredo C.) 101 days 13 6985 - Silverado & Maryland (sign A) 10 days 14 6850 - Margarita Crossings (sign A1) 5 days 15 6850 - Margarita Crossings (sign A2) 5 days 16 7155 - Loehmann's Plaza (sign A1) 12 days 17 6985 - Silverado & Maryland (sign A rework) 2 days 18 7321 - Eastside Town Center 8 days 19 7444 - Navy Federal (sign K) 10 days 20 6383 - Shops @ San Miguel (A1, A2) 8 days 21 7446 - Deser Inn (sign A) 12 days 22 7538 - San Ysidro 24 Hour Parking (sign B) 10 days 23 6729 - Cielo Village (sign F) 7 days 24 6729 - Cielo Village (if needed) 7 days 25 6359 - Bear Creek (sign A) 10 days 26 27 GROUP 3 (Gerson M.) 81 days 28 7287 - Safari Business Park (sign A) 10 days 29 7246 - Panda Express Maricopa, AZ 6 days 30 7153 - The Shops @ Cypress (sign B2) 5 days 31 7155 - Loehmann's Plaza (sign A2) 12 days 32 6271 - Paramount Plaza (sign B1) 6 days 33 7434 - Rancho Plaza Penasquitos (sign B1 - B2) 7 days 34 7434 - Rancho Plaza Penasquitos (sign B3 - B4) 7 days 35 7538 - San Ysidro 24 Hour Parking (sign A) 10 days 36 7420 - Seacoast Comm Church 5 days 37 7299 - Shops @ Clinton Keith (sign A) 12 days 38 39 GROUP 4 (Alberto C.) 77 days 40 6923 - Hawthorne Cross (sign B1) 10 days 41 7183 - Dollar Self Storage 3 days 42 7159 - Chevron San Marcos 6 days 43 6271 - Paramount Plaza (sign A1) 5 days 44 6271 - Paramount Plaza (sign A2) 4 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 1
  • 2. ID Task Name Duration Nov 20, '06 Nov 27, '06 Dec 4, '06 Dec 11, '06 Dec 18, '06 Dec 25, '06 Jan M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M 45 7362 - Saltgrass Steakhouse 4 days 46 6271 - Paramount Plaza (B2) 5 days 47 7453 - Madison Creek 3 days 48 7301 - Westfield Main Place (sign 3H) 5 days 49 7301 - Westfield Main Place (sign 5) 5 days 50 7301 - Westfield Main Place (sign 4A - 4F) 5 days 51 7393 - Miramar Crossings (sign A) 7 days 52 7393 - Miramar Crossings (sign B) 4 days 53 6358 - Soquel Canyon (sign A1) 10 days 54 55 GROUP 5 (Sergio S.) 84 days 56 7144 - Seal Beach (sign B) 10 days 57 Raceways 2 days 58 Golden Nugget Cashiers 1 day 59 Silverstone Brackets (32) 1 day 60 7386 - Destination O-Eight 5 days 61 Navy Federal Raceways 10 days 62 7142 - Village @ San Jacinto (sign C1, C2) 19 days 63 7549 - Craig & Lamb (sign B) 6 days 64 7446 - Desert Inn (sign B1) 8 days 65 7347 - Mountain Green 10 days 66 6359 - Bear Creek (sign B) 12 days 67 68 GROUP 6 (Edmundo M.) 73 days 69 6923 - Hawthorne Crossings (sign D) 5 days 70 7153 - The Shops @ Cypress (sign A1) 11 days 71 7142 - Village @ San Jacinto (sign A1) 12 days 72 7142 - Village @ San Jacinto (D1 - D2) 10 days 73 7444 - Navy Federal (sign N1, N2) 7 days 74 7472 - Canyon Hills 5 days 75 6887 - Vail Ranch Town Square (sign GS1) 7 days 76 6887 - Vail Ranch Town Square (sign GS2) 7 days 77 6478 - Trail Crossings (sign C) 8 days 78 79 GROUP 7 (Ismael P.) 98 days 80 7287 - Safari Business Park (sign B) 16 days 81 6923 - Hawthorne Cross (sign C) 3 days 82 7142 - Village @ San Jacinto (sign A2) 15 days 83 7142 - Village @ San Jacinto (sign D3 - D4) 15 days 84 7549 - Craig & Lamb (sign A) 9 days 85 7520 - Kalmia Plaza (sign A1) 10 days 86 7520 - Kalmia Plaza (sign A2) 10 days 87 7547 - The Campus 5 days 88 7299 - Shops @ Clinton Keith (sign B1) 15 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 2
  • 3. ID Task Name Duration Nov 20, '06 Nov 27, '06 Dec 4, '06 Dec 11, '06 Dec 18, '06 Dec 25, '06 Jan M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M 89 90 GROUP 8 (Cesar M.) 83 days 91 7144 - Seal Beach (sign C2) 4 days 92 6985 - Silverado & Maryland (sign B) 10 days 93 6616 - Orchard (repair) 1 day 94 7153 - The Shops @ Cypress (sign A2) 7 days 95 7301 - Westfield (Main) sign 1A, 1B 12 days 96 VACATION 5 days 97 7142 - Village @ San Jacinto (sign E) 7 days 98 7444 - Navy Federal (sign C1 - C4) 7 days 99 7491 - Money Gram 3 days 100 7520 - Kalmia Plaza (sign B) 5 days 101 6358 - Soquel Canyon (sign A2) 10 days 102 7299 - Shops @ Clinton Keith (sign B2) 12 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 3
  • 4. ID Task Name Duration , '07 Jan 8, '07 Jan 15, '07 Jan 22, '07 Jan 29, '07 Feb 5, '07 Feb 12, '0 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T 1 GROUP 1 (M. Najar) 85 days 2 6923 - Hawthorne Cross (sign A1) 15 days 3 7075 - The Corridors 18 days 4 7119 - Panda Express Boulder City (pylon) 9 days 5 7519 - Z-Mario 6 days 6 7119 - Panda Express (face) 2 days 7 7444 - Navy Federal (sign A, B) 3 days 8 7401 - Graceland Wedding Chapel 5 days 9 7446 - Deser Inn (sign B2 - B3) 12 days 10 6913 - Oracle Mall (sign A1) 15 days 11 12 GROUP 2 (Alfredo C.) 101 days 13 6985 - Silverado & Maryland (sign A) 10 days 14 6850 - Margarita Crossings (sign A1) 5 days 15 6850 - Margarita Crossings (sign A2) 5 days 16 7155 - Loehmann's Plaza (sign A1) 12 days 17 6985 - Silverado & Maryland (sign A rework) 2 days 18 7321 - Eastside Town Center 8 days 19 7444 - Navy Federal (sign K) 10 days 20 6383 - Shops @ San Miguel (A1, A2) 8 days 21 7446 - Deser Inn (sign A) 12 days 22 7538 - San Ysidro 24 Hour Parking (sign B) 10 days 23 6729 - Cielo Village (sign F) 7 days 24 6729 - Cielo Village (if needed) 7 days 25 6359 - Bear Creek (sign A) 10 days 26 27 GROUP 3 (Gerson M.) 81 days 28 7287 - Safari Business Park (sign A) 10 days 29 7246 - Panda Express Maricopa, AZ 6 days 30 7153 - The Shops @ Cypress (sign B2) 5 days 31 7155 - Loehmann's Plaza (sign A2) 12 days 32 6271 - Paramount Plaza (sign B1) 6 days 33 7434 - Rancho Plaza Penasquitos (sign B1 - B2) 7 days 34 7434 - Rancho Plaza Penasquitos (sign B3 - B4) 7 days 35 7538 - San Ysidro 24 Hour Parking (sign A) 10 days 36 7420 - Seacoast Comm Church 5 days 37 7299 - Shops @ Clinton Keith (sign A) 12 days 38 39 GROUP 4 (Alberto C.) 77 days 40 6923 - Hawthorne Cross (sign B1) 10 days 41 7183 - Dollar Self Storage 3 days 42 7159 - Chevron San Marcos 6 days 43 6271 - Paramount Plaza (sign A1) 5 days 44 6271 - Paramount Plaza (sign A2) 4 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 4
  • 5. ID Task Name Duration , '07 Jan 8, '07 Jan 15, '07 Jan 22, '07 Jan 29, '07 Feb 5, '07 Feb 12, '0 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T 45 7362 - Saltgrass Steakhouse 4 days 46 6271 - Paramount Plaza (B2) 5 days 47 7453 - Madison Creek 3 days 48 7301 - Westfield Main Place (sign 3H) 5 days 49 7301 - Westfield Main Place (sign 5) 5 days 50 7301 - Westfield Main Place (sign 4A - 4F) 5 days 51 7393 - Miramar Crossings (sign A) 7 days 52 7393 - Miramar Crossings (sign B) 4 days 53 6358 - Soquel Canyon (sign A1) 10 days 54 55 GROUP 5 (Sergio S.) 84 days 56 7144 - Seal Beach (sign B) 10 days 57 Raceways 2 days 58 Golden Nugget Cashiers 1 day 59 Silverstone Brackets (32) 1 day 60 7386 - Destination O-Eight 5 days 61 Navy Federal Raceways 10 days 62 7142 - Village @ San Jacinto (sign C1, C2) 19 days 63 7549 - Craig & Lamb (sign B) 6 days 64 7446 - Desert Inn (sign B1) 8 days 65 7347 - Mountain Green 10 days 66 6359 - Bear Creek (sign B) 12 days 67 68 GROUP 6 (Edmundo M.) 73 days 69 6923 - Hawthorne Crossings (sign D) 5 days 70 7153 - The Shops @ Cypress (sign A1) 11 days 71 7142 - Village @ San Jacinto (sign A1) 12 days 72 7142 - Village @ San Jacinto (D1 - D2) 10 days 73 7444 - Navy Federal (sign N1, N2) 7 days 74 7472 - Canyon Hills 5 days 75 6887 - Vail Ranch Town Square (sign GS1) 7 days 76 6887 - Vail Ranch Town Square (sign GS2) 7 days 77 6478 - Trail Crossings (sign C) 8 days 78 79 GROUP 7 (Ismael P.) 98 days 80 7287 - Safari Business Park (sign B) 16 days 81 6923 - Hawthorne Cross (sign C) 3 days 82 7142 - Village @ San Jacinto (sign A2) 15 days 83 7142 - Village @ San Jacinto (sign D3 - D4) 15 days 84 7549 - Craig & Lamb (sign A) 9 days 85 7520 - Kalmia Plaza (sign A1) 10 days 86 7520 - Kalmia Plaza (sign A2) 10 days 87 7547 - The Campus 5 days 88 7299 - Shops @ Clinton Keith (sign B1) 15 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 5
  • 6. ID Task Name Duration , '07 Jan 8, '07 Jan 15, '07 Jan 22, '07 Jan 29, '07 Feb 5, '07 Feb 12, '0 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T 89 90 GROUP 8 (Cesar M.) 83 days 91 7144 - Seal Beach (sign C2) 4 days 92 6985 - Silverado & Maryland (sign B) 10 days 93 6616 - Orchard (repair) 1 day 94 7153 - The Shops @ Cypress (sign A2) 7 days 95 7301 - Westfield (Main) sign 1A, 1B 12 days 96 VACATION 5 days 97 7142 - Village @ San Jacinto (sign E) 7 days 98 7444 - Navy Federal (sign C1 - C4) 7 days 99 7491 - Money Gram 3 days 100 7520 - Kalmia Plaza (sign B) 5 days 101 6358 - Soquel Canyon (sign A2) 10 days 102 7299 - Shops @ Clinton Keith (sign B2) 12 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 6
  • 7. ID Task Name Duration Feb 19, '07 Feb 26, '07 Mar 5, '07 Mar 12, '07 Mar 19, '07 Mar 26, '07 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W 1 GROUP 1 (M. Najar) 85 days 2 6923 - Hawthorne Cross (sign A1) 15 days 3 7075 - The Corridors 18 days 4 7119 - Panda Express Boulder City (pylon) 9 days 5 7519 - Z-Mario 6 days 6 7119 - Panda Express (face) 2 days 7 7444 - Navy Federal (sign A, B) 3 days 8 7401 - Graceland Wedding Chapel 5 days 9 7446 - Deser Inn (sign B2 - B3) 12 days 10 6913 - Oracle Mall (sign A1) 15 days 11 12 GROUP 2 (Alfredo C.) 101 days 13 6985 - Silverado & Maryland (sign A) 10 days 14 6850 - Margarita Crossings (sign A1) 5 days 15 6850 - Margarita Crossings (sign A2) 5 days 16 7155 - Loehmann's Plaza (sign A1) 12 days 17 6985 - Silverado & Maryland (sign A rework) 2 days 18 7321 - Eastside Town Center 8 days 19 7444 - Navy Federal (sign K) 10 days 20 6383 - Shops @ San Miguel (A1, A2) 8 days 21 7446 - Deser Inn (sign A) 12 days 22 7538 - San Ysidro 24 Hour Parking (sign B) 10 days 23 6729 - Cielo Village (sign F) 7 days 24 6729 - Cielo Village (if needed) 7 days 25 6359 - Bear Creek (sign A) 10 days 26 27 GROUP 3 (Gerson M.) 81 days 28 7287 - Safari Business Park (sign A) 10 days 29 7246 - Panda Express Maricopa, AZ 6 days 30 7153 - The Shops @ Cypress (sign B2) 5 days 31 7155 - Loehmann's Plaza (sign A2) 12 days 32 6271 - Paramount Plaza (sign B1) 6 days 33 7434 - Rancho Plaza Penasquitos (sign B1 - B2) 7 days 34 7434 - Rancho Plaza Penasquitos (sign B3 - B4) 7 days 35 7538 - San Ysidro 24 Hour Parking (sign A) 10 days 36 7420 - Seacoast Comm Church 5 days 37 7299 - Shops @ Clinton Keith (sign A) 12 days 38 39 GROUP 4 (Alberto C.) 77 days 40 6923 - Hawthorne Cross (sign B1) 10 days 41 7183 - Dollar Self Storage 3 days 42 7159 - Chevron San Marcos 6 days 43 6271 - Paramount Plaza (sign A1) 5 days 44 6271 - Paramount Plaza (sign A2) 4 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 7
  • 8. ID Task Name Duration Feb 19, '07 Feb 26, '07 Mar 5, '07 Mar 12, '07 Mar 19, '07 Mar 26, '07 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W 45 7362 - Saltgrass Steakhouse 4 days 46 6271 - Paramount Plaza (B2) 5 days 47 7453 - Madison Creek 3 days 48 7301 - Westfield Main Place (sign 3H) 5 days 49 7301 - Westfield Main Place (sign 5) 5 days 50 7301 - Westfield Main Place (sign 4A - 4F) 5 days 51 7393 - Miramar Crossings (sign A) 7 days 52 7393 - Miramar Crossings (sign B) 4 days 53 6358 - Soquel Canyon (sign A1) 10 days 54 55 GROUP 5 (Sergio S.) 84 days 56 7144 - Seal Beach (sign B) 10 days 57 Raceways 2 days 58 Golden Nugget Cashiers 1 day 59 Silverstone Brackets (32) 1 day 60 7386 - Destination O-Eight 5 days 61 Navy Federal Raceways 10 days 62 7142 - Village @ San Jacinto (sign C1, C2) 19 days 63 7549 - Craig & Lamb (sign B) 6 days 64 7446 - Desert Inn (sign B1) 8 days 65 7347 - Mountain Green 10 days 66 6359 - Bear Creek (sign B) 12 days 67 68 GROUP 6 (Edmundo M.) 73 days 69 6923 - Hawthorne Crossings (sign D) 5 days 70 7153 - The Shops @ Cypress (sign A1) 11 days 71 7142 - Village @ San Jacinto (sign A1) 12 days 72 7142 - Village @ San Jacinto (D1 - D2) 10 days 73 7444 - Navy Federal (sign N1, N2) 7 days 74 7472 - Canyon Hills 5 days 75 6887 - Vail Ranch Town Square (sign GS1) 7 days 76 6887 - Vail Ranch Town Square (sign GS2) 7 days 77 6478 - Trail Crossings (sign C) 8 days 78 79 GROUP 7 (Ismael P.) 98 days 80 7287 - Safari Business Park (sign B) 16 days 81 6923 - Hawthorne Cross (sign C) 3 days 82 7142 - Village @ San Jacinto (sign A2) 15 days 83 7142 - Village @ San Jacinto (sign D3 - D4) 15 days 84 7549 - Craig & Lamb (sign A) 9 days 85 7520 - Kalmia Plaza (sign A1) 10 days 86 7520 - Kalmia Plaza (sign A2) 10 days 87 7547 - The Campus 5 days 88 7299 - Shops @ Clinton Keith (sign B1) 15 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 8
  • 9. ID Task Name Duration Feb 19, '07 Feb 26, '07 Mar 5, '07 Mar 12, '07 Mar 19, '07 Mar 26, '07 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W 89 90 GROUP 8 (Cesar M.) 83 days 91 7144 - Seal Beach (sign C2) 4 days 92 6985 - Silverado & Maryland (sign B) 10 days 93 6616 - Orchard (repair) 1 day 94 7153 - The Shops @ Cypress (sign A2) 7 days 95 7301 - Westfield (Main) sign 1A, 1B 12 days 96 VACATION 5 days 97 7142 - Village @ San Jacinto (sign E) 7 days 98 7444 - Navy Federal (sign C1 - C4) 7 days 99 7491 - Money Gram 3 days 100 7520 - Kalmia Plaza (sign B) 5 days 101 6358 - Soquel Canyon (sign A2) 10 days 102 7299 - Shops @ Clinton Keith (sign B2) 12 days Task Milestone Rolled Up Split External Tasks Deadline Project: SUBCA - All Jobs Split Summary Rolled Up Milestone Project Summary Date: Fri 1/26/07 Progress Rolled Up Task Rolled Up Progress External Milestone Page 9