The document outlines a renovation project to convert an 850 square foot terrace area into 2 bedrooms, a living room, balcony, and toilet. The work will include electrical, plumbing, tiling, partition walls, and other renovation work. Brick and concrete work will not be permitted. The final budget for the project is 20,00,000 INR.
2. -NEED TO CONVERT 850SQ.FT.TERRACE AREA IN TO 2 BEDROOMS,LIVING ROOM,BALCONY AND
A TOILET WHICH WILL BE ACCESABLE FROM BEDROOM AS WELL FROM COMMON AREA.
-ALL NECCESSORY ELECTRICAL WORK,POP WORK,PLUMBING,TILING,CONSTRUCTING DUMMY
WALLS(PARTITIONS)FABRICATION WORK FOR COLOR COATED SHEETS COVERING POP
(DIDN’T GET FSI TO CONSTUCT ANY EXTARA WORK IN RCC-NO RCC CEILING ,NO RCC WALLS) AND
RENOVATION WORK FOR THE 2 BHK FLAT CONNECTING TERRACE FLAT.
-FURNITURE DESIGNING,PAINTING,WALL PUNNING,WATERPROOFING WORK INCLUDED.
CONDITIONS:
-BRICK WORK WILL NOT BE ALLOW.
-RCC WORK NOT PERMMITED
-BUILDING ELEVATION SHOULD NOT BE CHANGE WHILE ENCLOSING THE TERRACE AREA.
FINAL BUDGET REACHED 20,00000/-
3.
4. WINDOW AND OUTER GLASS PARTITION
IN GUEST BEDROOM
WINDOW AND OUTER GLASS PARTITION
IN MASTER BEDROOM
7. KADAPPA FIXED ABOVE THE WALL TO FILL THE GAP BETWEEN WALL AND
ROOFING.’Z’BRACKETS OF 5MM THICKNESS HAVE BEEN USED FOR THE JOINERY.
VERTICAL
KADAPPA5MM ‘Z’ BRACKETS
BRICK WALL
POP
WINDOW
FFL
8. KADAPPA FIXED ABOVE THE WALL TO FILL THE GAP BETWEEN WALL AND
ROOFING.’Z’BRACKETS OF 5MM THICKNESS HAVE BEEN USED FOR THE JOINERY.