Main specifications :
       -Renovation of the main dome with no support on it
       -Castle opened to the visitors
       -Access of the working site above the river

       -Scaffold with canopy on each face
       -Keder roof at the top




Damien VUILLET                                       Technical and sales meeting – April 2012
3D view




Damien VUILLET   Technical and sales meeting – April 2012
3D view with only steel deck




Damien VUILLET                         Technical and sales meeting – April 2012
The footbridge access
    -Length of 19m
    -Assembled on ground then
    put in by crane
    -7T500 of ballast for the
    stability




Damien VUILLET                       Technical and sales meeting – April 2012
Principle of the scaffold
                           Top view




                 Creation of 4 scaffolds beams
Damien VUILLET                           Technical and sales meeting – April 2012
Front view         Middle view




                              No support on the dome



Damien VUILLET                   Technical and sales meeting – April 2012
Rear view




    Fixation on the wooden
            skeleton
Damien VUILLET                  Technical and sales meeting – April 2012
Section in the middle of the dome




    Fixation on the wooden
            skeleton          Last level of anchoring (3 plugs)
Damien VUILLET                               Technical and sales meeting – April 2012
Damien VUILLET   Technical and sales meeting – April 2012
Damien VUILLET   Technical and sales meeting – April 2012
Damien VUILLET   Technical and sales meeting – April 2012
Damien VUILLET   Technical and sales meeting – April 2012
-150t of LAYHER scaffold system
                 -760kg of wind force by plug
                 -1160kg on each wooden fixation
                 -Maximum load per standard : 3580kg




Damien VUILLET                Technical and sales meeting – April 2012

More Related Content

More from bert vanden eynde

DE EN Layher Ladder Manual 8118.031 04.18
DE EN Layher Ladder Manual 8118.031 04.18DE EN Layher Ladder Manual 8118.031 04.18
DE EN Layher Ladder Manual 8118.031 04.18
bert vanden eynde
 
LAYHER Rolsteigers & ladders katalog 8118.229 04.18
LAYHER Rolsteigers & ladders katalog 8118.229 04.18LAYHER Rolsteigers & ladders katalog 8118.229 04.18
LAYHER Rolsteigers & ladders katalog 8118.229 04.18
bert vanden eynde
 
En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17
bert vanden eynde
 
En afscherm systemen katalog 8121.257 04.18
En afscherm systemen katalog 8121.257 04.18En afscherm systemen katalog 8121.257 04.18
En afscherm systemen katalog 8121.257 04.18
bert vanden eynde
 
Presentatie bert vanden eynde constructiv @ layher
Presentatie bert vanden eynde   constructiv @ layherPresentatie bert vanden eynde   constructiv @ layher
Presentatie bert vanden eynde constructiv @ layher
bert vanden eynde
 
En event systeem katalog 8111.229 04.17
En event systeem katalog 8111.229 04.17En event systeem katalog 8111.229 04.17
En event systeem katalog 8111.229 04.17
bert vanden eynde
 
Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17
Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17
Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17
bert vanden eynde
 
Allround® turss system for bridging ppt matexpo-all scaff
Allround® turss system for bridging ppt matexpo-all scaffAllround® turss system for bridging ppt matexpo-all scaff
Allround® turss system for bridging ppt matexpo-all scaffbert vanden eynde
 
Layher tijdelijke voetgangersbrug tijdelijke overspanningen - vliegende pod...
Layher tijdelijke voetgangersbrug   tijdelijke overspanningen - vliegende pod...Layher tijdelijke voetgangersbrug   tijdelijke overspanningen - vliegende pod...
Layher tijdelijke voetgangersbrug tijdelijke overspanningen - vliegende pod...
bert vanden eynde
 
zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010
zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010 zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010
zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010
bert vanden eynde
 
Mining in bxl layher-bert vanden eynde
Mining in bxl layher-bert vanden eyndeMining in bxl layher-bert vanden eynde
Mining in bxl layher-bert vanden eynde
bert vanden eynde
 
Layher Allround® Mobile Disco creatie van Total Event Creations - Kruibeke
Layher Allround® Mobile Disco creatie van Total Event Creations - KruibekeLayher Allround® Mobile Disco creatie van Total Event Creations - Kruibeke
Layher Allround® Mobile Disco creatie van Total Event Creations - Kruibeke
bert vanden eynde
 
Allround® Truss System For Bridging Ppt Matexpo
Allround® Truss System For Bridging Ppt   MatexpoAllround® Truss System For Bridging Ppt   Matexpo
Allround® Truss System For Bridging Ppt Matexpo
bert vanden eynde
 
Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk Bert Vanden Eynde ...
Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk   Bert Vanden Eynde ...Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk   Bert Vanden Eynde ...
Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk Bert Vanden Eynde ...
bert vanden eynde
 
Mining In Bxl Layher Bert Vanden Eynde
Mining In Bxl Layher Bert Vanden EyndeMining In Bxl Layher Bert Vanden Eynde
Mining In Bxl Layher Bert Vanden Eyndebert vanden eynde
 
Terplaatse Gestorte Nagespannen Kokerbrug Layher Bert Vanden Eynde
Terplaatse Gestorte Nagespannen Kokerbrug   Layher   Bert Vanden EyndeTerplaatse Gestorte Nagespannen Kokerbrug   Layher   Bert Vanden Eynde
Terplaatse Gestorte Nagespannen Kokerbrug Layher Bert Vanden Eynde
bert vanden eynde
 
Watertoren Layher Bert Vanden Eynde
Watertoren Layher Bert Vanden EyndeWatertoren Layher Bert Vanden Eynde
Watertoren Layher Bert Vanden Eynde
bert vanden eynde
 

More from bert vanden eynde (17)

DE EN Layher Ladder Manual 8118.031 04.18
DE EN Layher Ladder Manual 8118.031 04.18DE EN Layher Ladder Manual 8118.031 04.18
DE EN Layher Ladder Manual 8118.031 04.18
 
LAYHER Rolsteigers & ladders katalog 8118.229 04.18
LAYHER Rolsteigers & ladders katalog 8118.229 04.18LAYHER Rolsteigers & ladders katalog 8118.229 04.18
LAYHER Rolsteigers & ladders katalog 8118.229 04.18
 
En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17En au v_kassettendach nr.8112.260 02.17
En au v_kassettendach nr.8112.260 02.17
 
En afscherm systemen katalog 8121.257 04.18
En afscherm systemen katalog 8121.257 04.18En afscherm systemen katalog 8121.257 04.18
En afscherm systemen katalog 8121.257 04.18
 
Presentatie bert vanden eynde constructiv @ layher
Presentatie bert vanden eynde   constructiv @ layherPresentatie bert vanden eynde   constructiv @ layher
Presentatie bert vanden eynde constructiv @ layher
 
En event systeem katalog 8111.229 04.17
En event systeem katalog 8111.229 04.17En event systeem katalog 8111.229 04.17
En event systeem katalog 8111.229 04.17
 
Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17
Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17
Van Roey @ LayherBenelux (Kontich - Belgium) 2-11-17
 
Allround® turss system for bridging ppt matexpo-all scaff
Allround® turss system for bridging ppt matexpo-all scaffAllround® turss system for bridging ppt matexpo-all scaff
Allround® turss system for bridging ppt matexpo-all scaff
 
Layher tijdelijke voetgangersbrug tijdelijke overspanningen - vliegende pod...
Layher tijdelijke voetgangersbrug   tijdelijke overspanningen - vliegende pod...Layher tijdelijke voetgangersbrug   tijdelijke overspanningen - vliegende pod...
Layher tijdelijke voetgangersbrug tijdelijke overspanningen - vliegende pod...
 
zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010
zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010 zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010
zeer zware ondersteuningen met Layher Allround - presentatie Betonvakdagen 2010
 
Mining in bxl layher-bert vanden eynde
Mining in bxl layher-bert vanden eyndeMining in bxl layher-bert vanden eynde
Mining in bxl layher-bert vanden eynde
 
Layher Allround® Mobile Disco creatie van Total Event Creations - Kruibeke
Layher Allround® Mobile Disco creatie van Total Event Creations - KruibekeLayher Allround® Mobile Disco creatie van Total Event Creations - Kruibeke
Layher Allround® Mobile Disco creatie van Total Event Creations - Kruibeke
 
Allround® Truss System For Bridging Ppt Matexpo
Allround® Truss System For Bridging Ppt   MatexpoAllround® Truss System For Bridging Ppt   Matexpo
Allround® Truss System For Bridging Ppt Matexpo
 
Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk Bert Vanden Eynde ...
Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk   Bert Vanden Eynde ...Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk   Bert Vanden Eynde ...
Layher Kaefer Thv Wijngaard Shoppingcenter K Te Kortrijk Bert Vanden Eynde ...
 
Mining In Bxl Layher Bert Vanden Eynde
Mining In Bxl Layher Bert Vanden EyndeMining In Bxl Layher Bert Vanden Eynde
Mining In Bxl Layher Bert Vanden Eynde
 
Terplaatse Gestorte Nagespannen Kokerbrug Layher Bert Vanden Eynde
Terplaatse Gestorte Nagespannen Kokerbrug   Layher   Bert Vanden EyndeTerplaatse Gestorte Nagespannen Kokerbrug   Layher   Bert Vanden Eynde
Terplaatse Gestorte Nagespannen Kokerbrug Layher Bert Vanden Eynde
 
Watertoren Layher Bert Vanden Eynde
Watertoren Layher Bert Vanden EyndeWatertoren Layher Bert Vanden Eynde
Watertoren Layher Bert Vanden Eynde
 

Vaux le vicomte

  • 1. Technical and sales meeting Vaux le Vicomte Castle Damien VUILLET Technical and sales meeting – April 2012
  • 2. Main specifications : -Renovation of the main dome with no support on it -Castle opened to the visitors -Access of the working site above the river -Scaffold with canopy on each face -Keder roof at the top Damien VUILLET Technical and sales meeting – April 2012
  • 3. 3D view Damien VUILLET Technical and sales meeting – April 2012
  • 4. 3D view with only steel deck Damien VUILLET Technical and sales meeting – April 2012
  • 5. The footbridge access -Length of 19m -Assembled on ground then put in by crane -7T500 of ballast for the stability Damien VUILLET Technical and sales meeting – April 2012
  • 6. Principle of the scaffold Top view Creation of 4 scaffolds beams Damien VUILLET Technical and sales meeting – April 2012
  • 7. Front view Middle view No support on the dome Damien VUILLET Technical and sales meeting – April 2012
  • 8. Rear view Fixation on the wooden skeleton Damien VUILLET Technical and sales meeting – April 2012
  • 9. Section in the middle of the dome Fixation on the wooden skeleton Last level of anchoring (3 plugs) Damien VUILLET Technical and sales meeting – April 2012
  • 10. Damien VUILLET Technical and sales meeting – April 2012
  • 11. Damien VUILLET Technical and sales meeting – April 2012
  • 12. Damien VUILLET Technical and sales meeting – April 2012
  • 13. Damien VUILLET Technical and sales meeting – April 2012
  • 14. -150t of LAYHER scaffold system -760kg of wind force by plug -1160kg on each wooden fixation -Maximum load per standard : 3580kg Damien VUILLET Technical and sales meeting – April 2012