Topics
 SWPA General Information
 SWPA Customers
 SWPA System
 U.S. Electric Grid Interconnections & SWPA System Map
 SWPA Rates
 Denison Hydropower
 Funds Returned to U.S. Treasury
 SWPA Denison Drought Operations
 Generation Data
 SWPA Denison Outlook
 Recap
Slide 3
SWPA General Information
Southwestern Power Administration (SWPA)
 Agency of the US Department of Energy
 Power Marketing Administration
 Section 5 of the Flood Control Act of 1944
“…encourage most widespread use at lowest
possible rates…
…sound business principles…
…preference to public bodies and cooperatives.”
 Cost based rates; not for profit
 Repay Federal Investment
Slide 4 Southwestern Power Administration
SWPA General Information
Slide 5 Southwestern Power Administration
SWPA Customers
 SWPA markets cost-based, wholesale power
to not-for-profit preference customers in six
states: Arkansas, Kansas, Louisiana,
Missouri, Oklahoma, and Texas.
 Over 100 customers
 21 Cooperatives
 78 Municipalities
 3 Military installations
 Over 8 million end users
Slide 6
Slide 7
SWPA System
 SWPA markets hydropower from 24 Federal, multi-
purpose hydropower projects owned by the U.S. Army
Corps of Engineers (Corps).
 Marketed capacity: 2,052.6 MW
 Average annual energy: 5,570,000 MWh
 SWPA operates 1,380 miles of high-voltage transmission
line, 25 substations, and 46 communications sites.
 Of the 24 hydropower projects, 19 are operated as an
Interconnected System within the Southwest Power Pool
(SPP) region (Eastern Interconnection).
 Denison (Lake Texoma), which is one of the 5 remaining
electrically isolated projects, is within the ERCOT region
(ERCOT Interconnection).
Southwestern Power Administration
Slide 8
U.S. Electric Grid Interconnections
Southwestern Power Administration
Slide 9 Southwestern Power Administration
SWPA System Map
Disconnected
Slide 10
SWPA Rates
 Cost Based – 100% of hydropower cost and the allocated
percent of joint-use costs unique to each project:
-Initial construction costs
-Interest during construction
-Interest on investment
-Annual operation and maintenance
-New replacement equipment
 22 of 24 projects – including Denison – are blended
together to make the “Integrated System Rate.” There
are 2 other rate systems, Sam Rayburn and Robert Willis,
both isolated projects in Texas.
 Although Denison, Narrows, and Whitney are electrically
isolated, they are financially integrated.
Southwestern Power Administration
Slide 11
Denison Hydropower
 Denison is located in the ERCOT region and contractually
its full output is received by two Texas Electric
Cooperatives: Tex-La and Rayburn Country
 Based on current SWPA rates and an average hydrological
year, the annual revenue returned to the U.S. Treasury
from Denison generation is about $6 million. The
estimated annual replacement cost is nearly $19 million.
 Important power resource for the region providing quick-
response peaking power.
 In an average hydrological year, the clean, renewable
generation from Denison prevents the emission of 182,200
tons of greenhouse gases by offsetting the need for fossil
fuel generation (1.9 billion cubic feet of natural gas or
113,900 tons of coal).
Southwestern Power Administration
Slide 12
Distribution of Funds Returned to
U.S. Treasury by SWPA
Southwestern Power Administration
24 Projects Denison
Original Investment $788 Million $30 Million
Interest $772 Million $25 Million
Operations & Maintenance $1,255 Million $75 Million
Total $2,815 Million $130 Million
As of fiscal year ending September 30, 2013 (unaudited)
Slide 13
Funds Returned to U.S. Treasury
from Lake Texoma
Southwestern Power Administration
Slide 14
Drought 2011-14 Texoma Inflow and Elev.
Southwestern Power Administration
Slide 15
SWPA Denison Drought Operations
Southwestern Power Administration
 SWPA strictly adheres to the Corps’ Lake Texoma Water
Control Manual and Drought Contingency Plan
 Southwestern operates in full compliance with Public Law
100-71
 Between 617-612 feet: Normal generation
 Between 612-607 feet: Rapid response, short term peaking
 Between 607-590 feet: Critical power needs
 The project is designed so that inflows combined with the
conservation pool storage provide a reliable water source
for the water supply and hydropower authorized purposes
to which conservation pool storage is allocated,
especially during times of drought.
Slide 16
SWPA Denison Drought Operations
Southwestern Power Administration
 SWPA has been operating in drought mode since
January 2011, generating only 25% of average.
 Since May 2012, generation has been even less,
about 19% of average.
 2013 – Lowest year of power generation ever
since generation began at Denison in 1945.
 In 2013, SWPA customers spent over
$5,000,000 to replace hydropower usually
produced at Denison.
Slide 17
Historical Generation
Southwestern Power Administration
Slide 18
2011-2014 Monthly Generation
Southwestern Power Administration
Slide 19
SWPA Denison Outlook
Southwestern Power Administration
 Will continue to operate the generation at
Denison pursuant to PL 100-71, Corps
regulations and approved plans, and SWPA’s
Federal contracts.
 Member of Lake Texoma Advisory Committee.
 Generation outlook is mindful of drought
conditions. SWPA customers predict that this
trend will continue in 2014 if low water levels
persist, and that they will continue replacing
hydropower usually generated out of Denison
with power purchased from other sources.
Slide 20
Lake Texoma Pool Elevation 2014 Outlook
Assumptions: Current level water supply use; 2011 evaporation; Median Inflow at 2, 4, and 6
hours/day generation; Historical Low Inflow (2011) at 2 and 4 hours/day generation.
Slide 21
Recap
Southwestern Power Administration
 Lake Texoma drought conditions: 2011-present.
 Denison hydropower generation at historical
lows.
 Lake Texoma conservation storage is working as
designed.
 SWPA will continue to operate in drought mode
until the Lake Texoma Red River watershed
recovers, pursuant to all applicable laws,
regulations, and Federal contracts.

More Related Content

Viewers also liked

Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...
Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...
Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...VanessaNoseda
 
Soal semifinal c'9 2k12
Soal semifinal c'9 2k12Soal semifinal c'9 2k12
Soal semifinal c'9 2k12
Delina Rahayu
 
1.4 alt uvea_y_cristalino
1.4 alt uvea_y_cristalino1.4 alt uvea_y_cristalino
1.4 alt uvea_y_cristalino
guillevarellano
 
Herramientas estrategias inclusivas ARCADIA III Póster
Herramientas estrategias inclusivas ARCADIA III PósterHerramientas estrategias inclusivas ARCADIA III Póster
Herramientas estrategias inclusivas ARCADIA III Póster
c3gc3g
 
Presentacion castillos 4 años
Presentacion castillos  4 añosPresentacion castillos  4 años
Presentacion castillos 4 años
otiguzman
 
Anugerah 2013 (1)
Anugerah 2013 (1)Anugerah 2013 (1)
Anugerah 2013 (1)
Sofia Wati
 
Presentaciã³n aztecas
Presentaciã³n aztecasPresentaciã³n aztecas
Presentaciã³n aztecas
nic0las
 
Aseguran científicos poder devolver la vida a los muertos.
Aseguran científicos poder devolver la vida a los muertos.Aseguran científicos poder devolver la vida a los muertos.
Aseguran científicos poder devolver la vida a los muertos.
Yaquelin Rodriguez
 
EGV - Legal structures - Lecture 1 & 2
EGV - Legal structures - Lecture 1 & 2EGV - Legal structures - Lecture 1 & 2
EGV - Legal structures - Lecture 1 & 2
Rohan Saraf
 
Caida moto
Caida motoCaida moto
Caida moto
iesavellaneda
 
Presentation about Hortatory Text
Presentation about Hortatory TextPresentation about Hortatory Text
Presentation about Hortatory Text
Ade Uswatun Hasanah
 

Viewers also liked (12)

Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...
Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...
Comunicare nei progetti europei. Sperimentazione all'Ufficio R.I. di Fondazio...
 
Soal semifinal c'9 2k12
Soal semifinal c'9 2k12Soal semifinal c'9 2k12
Soal semifinal c'9 2k12
 
1.4 alt uvea_y_cristalino
1.4 alt uvea_y_cristalino1.4 alt uvea_y_cristalino
1.4 alt uvea_y_cristalino
 
Herramientas estrategias inclusivas ARCADIA III Póster
Herramientas estrategias inclusivas ARCADIA III PósterHerramientas estrategias inclusivas ARCADIA III Póster
Herramientas estrategias inclusivas ARCADIA III Póster
 
Presentacion castillos 4 años
Presentacion castillos  4 añosPresentacion castillos  4 años
Presentacion castillos 4 años
 
Anugerah 2013 (1)
Anugerah 2013 (1)Anugerah 2013 (1)
Anugerah 2013 (1)
 
Presentaciã³n aztecas
Presentaciã³n aztecasPresentaciã³n aztecas
Presentaciã³n aztecas
 
Bentuk 2 dimensi
Bentuk 2 dimensiBentuk 2 dimensi
Bentuk 2 dimensi
 
Aseguran científicos poder devolver la vida a los muertos.
Aseguran científicos poder devolver la vida a los muertos.Aseguran científicos poder devolver la vida a los muertos.
Aseguran científicos poder devolver la vida a los muertos.
 
EGV - Legal structures - Lecture 1 & 2
EGV - Legal structures - Lecture 1 & 2EGV - Legal structures - Lecture 1 & 2
EGV - Legal structures - Lecture 1 & 2
 
Caida moto
Caida motoCaida moto
Caida moto
 
Presentation about Hortatory Text
Presentation about Hortatory TextPresentation about Hortatory Text
Presentation about Hortatory Text
 

Southwestern Power Administration Briefing- Texoma Region Public Meeting

  • 1. Texoma Regional Public Meeting April 4, 2014 Fritha Ohlson Director, Division of Resources & Rates
  • 2. Slide 2 Southwestern Power Administration Topics  SWPA General Information  SWPA Customers  SWPA System  U.S. Electric Grid Interconnections & SWPA System Map  SWPA Rates  Denison Hydropower  Funds Returned to U.S. Treasury  SWPA Denison Drought Operations  Generation Data  SWPA Denison Outlook  Recap
  • 3. Slide 3 SWPA General Information Southwestern Power Administration (SWPA)  Agency of the US Department of Energy  Power Marketing Administration  Section 5 of the Flood Control Act of 1944 “…encourage most widespread use at lowest possible rates… …sound business principles… …preference to public bodies and cooperatives.”  Cost based rates; not for profit  Repay Federal Investment
  • 4. Slide 4 Southwestern Power Administration SWPA General Information
  • 5. Slide 5 Southwestern Power Administration SWPA Customers  SWPA markets cost-based, wholesale power to not-for-profit preference customers in six states: Arkansas, Kansas, Louisiana, Missouri, Oklahoma, and Texas.  Over 100 customers  21 Cooperatives  78 Municipalities  3 Military installations  Over 8 million end users
  • 7. Slide 7 SWPA System  SWPA markets hydropower from 24 Federal, multi- purpose hydropower projects owned by the U.S. Army Corps of Engineers (Corps).  Marketed capacity: 2,052.6 MW  Average annual energy: 5,570,000 MWh  SWPA operates 1,380 miles of high-voltage transmission line, 25 substations, and 46 communications sites.  Of the 24 hydropower projects, 19 are operated as an Interconnected System within the Southwest Power Pool (SPP) region (Eastern Interconnection).  Denison (Lake Texoma), which is one of the 5 remaining electrically isolated projects, is within the ERCOT region (ERCOT Interconnection). Southwestern Power Administration
  • 8. Slide 8 U.S. Electric Grid Interconnections Southwestern Power Administration
  • 9. Slide 9 Southwestern Power Administration SWPA System Map Disconnected
  • 10. Slide 10 SWPA Rates  Cost Based – 100% of hydropower cost and the allocated percent of joint-use costs unique to each project: -Initial construction costs -Interest during construction -Interest on investment -Annual operation and maintenance -New replacement equipment  22 of 24 projects – including Denison – are blended together to make the “Integrated System Rate.” There are 2 other rate systems, Sam Rayburn and Robert Willis, both isolated projects in Texas.  Although Denison, Narrows, and Whitney are electrically isolated, they are financially integrated. Southwestern Power Administration
  • 11. Slide 11 Denison Hydropower  Denison is located in the ERCOT region and contractually its full output is received by two Texas Electric Cooperatives: Tex-La and Rayburn Country  Based on current SWPA rates and an average hydrological year, the annual revenue returned to the U.S. Treasury from Denison generation is about $6 million. The estimated annual replacement cost is nearly $19 million.  Important power resource for the region providing quick- response peaking power.  In an average hydrological year, the clean, renewable generation from Denison prevents the emission of 182,200 tons of greenhouse gases by offsetting the need for fossil fuel generation (1.9 billion cubic feet of natural gas or 113,900 tons of coal). Southwestern Power Administration
  • 12. Slide 12 Distribution of Funds Returned to U.S. Treasury by SWPA Southwestern Power Administration 24 Projects Denison Original Investment $788 Million $30 Million Interest $772 Million $25 Million Operations & Maintenance $1,255 Million $75 Million Total $2,815 Million $130 Million As of fiscal year ending September 30, 2013 (unaudited)
  • 13. Slide 13 Funds Returned to U.S. Treasury from Lake Texoma Southwestern Power Administration
  • 14. Slide 14 Drought 2011-14 Texoma Inflow and Elev. Southwestern Power Administration
  • 15. Slide 15 SWPA Denison Drought Operations Southwestern Power Administration  SWPA strictly adheres to the Corps’ Lake Texoma Water Control Manual and Drought Contingency Plan  Southwestern operates in full compliance with Public Law 100-71  Between 617-612 feet: Normal generation  Between 612-607 feet: Rapid response, short term peaking  Between 607-590 feet: Critical power needs  The project is designed so that inflows combined with the conservation pool storage provide a reliable water source for the water supply and hydropower authorized purposes to which conservation pool storage is allocated, especially during times of drought.
  • 16. Slide 16 SWPA Denison Drought Operations Southwestern Power Administration  SWPA has been operating in drought mode since January 2011, generating only 25% of average.  Since May 2012, generation has been even less, about 19% of average.  2013 – Lowest year of power generation ever since generation began at Denison in 1945.  In 2013, SWPA customers spent over $5,000,000 to replace hydropower usually produced at Denison.
  • 18. Slide 18 2011-2014 Monthly Generation Southwestern Power Administration
  • 19. Slide 19 SWPA Denison Outlook Southwestern Power Administration  Will continue to operate the generation at Denison pursuant to PL 100-71, Corps regulations and approved plans, and SWPA’s Federal contracts.  Member of Lake Texoma Advisory Committee.  Generation outlook is mindful of drought conditions. SWPA customers predict that this trend will continue in 2014 if low water levels persist, and that they will continue replacing hydropower usually generated out of Denison with power purchased from other sources.
  • 20. Slide 20 Lake Texoma Pool Elevation 2014 Outlook Assumptions: Current level water supply use; 2011 evaporation; Median Inflow at 2, 4, and 6 hours/day generation; Historical Low Inflow (2011) at 2 and 4 hours/day generation.
  • 21. Slide 21 Recap Southwestern Power Administration  Lake Texoma drought conditions: 2011-present.  Denison hydropower generation at historical lows.  Lake Texoma conservation storage is working as designed.  SWPA will continue to operate in drought mode until the Lake Texoma Red River watershed recovers, pursuant to all applicable laws, regulations, and Federal contracts.