Contents
Introduction.................................................................................................................................................3
Change Request Process Flow ...................................................................................................................3
Change Control Board ...............................................................................................................................4
Change Request Template: ........................................................................................................................5
Change Log..................................................................................................................................................6
3
Introduction
The Change Management Plan of our project documents and tracks the necessary information
required to effectively manage project change from project inception to delivery. The Change
Management Plan has been created during the Planning Phase of the project and is included in the
planning document.
Change Request Process Flow
Step Description
Generate Change
Request
A submitter completes a CR request and sends the completed request to the
Change Manager
Log Change
Request Status
The Change Manager enters the CR into the CR Log. The CR’s status is updated
throughout the CR process as needed.
Evaluate Change
Request
Project personnel review the CR and provide an estimated level of effort to
process, and develop a proposed solution for the suggested change
Authorize Approval to move forward with incorporating the suggested change into the
project
Implement If approved, make the necessary adjustments to carry out the requested change
and communicate CR status to the submitter and other stakeholders
Change requests are evaluated and assigned one or more of the following change types:
Scope Time Change affecting time Duration Change affecting duration Cost Change affecting
time Resources Change affecting resources Deliverables Change affecting deliverables Product
Change affecting product Processes product Quality Change affecting quality
Type Description
Scope Change affecting scope
Time Change affecting time
Duration Change affecting time
Cost Change affecting cost
Resources Change affecting resources
Deliverables Change affecting deliverables
Product Change affecting product
Processes Change affecting Processes
Quality Change affecting Quality
4
Change requests are evaluated and assigned one of the following status types:
Status Description
Open Entered/Open but not yet approved or assigned
Work in
Progress
CR approved, assigned, and work is progressing
In review CR approved, assigned, and work is progressing
Testing CR work has been reviewed and is being tested
Closed CR work is complete, has passed all tests, and updates have been released.
Change Control Board
Name Position CCB Role
Md. Adiluzzaman Adil Project Manager CCB Manager
Kishan kumar Ganguly
Md. Rakib Hossain
Software Architect & Developer CCB Member
Minhas Kamal
A.H.M. Azimul Haque
Designer & Developer CCB Member
Mostaque Ahmed
Israt Fatema Shantu
Documentation CCB Member
5
Change Request Template:
We have used the following form template for change request:
Change Request
Project: Date:
Change Requestor: Change No:
Change Category (Check all that apply):
□ Schedule □ Cost □ Scope □ Requirements/Deliverables
□ Testing/Quality □ Resources
Does this Change Affect (Check all that apply):
□ Corrective Action □ Preventative Action □ Defect Repair □ Updates
□ Other
Describe the Change Being Requested:
Describe the Reason for the Change:
Describe all Alternatives Considered:
Describe any Technical Changes Required to Implement this Change:
Describe Risks to be Considered for this Change:
Estimate Resources and Costs Needed to Implement this Change:
Describe the Implications to Quality:
Disposition:
□ Approve □ Reject □ Defer
Justification of Approval, Rejection, or Deferral:
Change Board Approval:
Name Signature Date
6
Change Log
Change Log
Project: Network Upgrade Project Date: 04/01/20xx
Change
No.
Change
Type
Description of
Change
Requestor Date
Submitted
Date
Approved
Status Comments
CR001 Equipment This change
request calls
for the
purchase of
wlan routers.
Minhas
Kamal
07/08/16 08/08/16 Denied This request was
denied by the
change control
board because
there is not
adequate funding
available for the
purchase of new
routers and
because the
request is outside
of the project's
scope.
CR002 Schedule This change
request calls
for delaying
the existing
schedule by
one week to
ensure all
applications
are backed up
which was not
considered in
the original
project plan.
Kishan
Kumar
Ganguly
03/11/16 08/11/16 Approved This request was
approved to
ensure the
security and
continuity of all
applications. One
week will be
added to the
project schedule
and the project
manager will
communicate the
impact of this
change to all
stakeholders.

Software Project Management: Change Control

  • 1.
    1 ResearchColab Change Control Team: Reckless7 Institute of Information Technology University of Dhaka 25th November, 2016
  • 2.
    2 Contents Introduction.................................................................................................................................................3 Change Request ProcessFlow ...................................................................................................................3 Change Control Board ...............................................................................................................................4 Change Request Template: ........................................................................................................................5 Change Log..................................................................................................................................................6
  • 3.
    3 Introduction The Change ManagementPlan of our project documents and tracks the necessary information required to effectively manage project change from project inception to delivery. The Change Management Plan has been created during the Planning Phase of the project and is included in the planning document. Change Request Process Flow Step Description Generate Change Request A submitter completes a CR request and sends the completed request to the Change Manager Log Change Request Status The Change Manager enters the CR into the CR Log. The CR’s status is updated throughout the CR process as needed. Evaluate Change Request Project personnel review the CR and provide an estimated level of effort to process, and develop a proposed solution for the suggested change Authorize Approval to move forward with incorporating the suggested change into the project Implement If approved, make the necessary adjustments to carry out the requested change and communicate CR status to the submitter and other stakeholders Change requests are evaluated and assigned one or more of the following change types: Scope Time Change affecting time Duration Change affecting duration Cost Change affecting time Resources Change affecting resources Deliverables Change affecting deliverables Product Change affecting product Processes product Quality Change affecting quality Type Description Scope Change affecting scope Time Change affecting time Duration Change affecting time Cost Change affecting cost Resources Change affecting resources Deliverables Change affecting deliverables Product Change affecting product Processes Change affecting Processes Quality Change affecting Quality
  • 4.
    4 Change requests areevaluated and assigned one of the following status types: Status Description Open Entered/Open but not yet approved or assigned Work in Progress CR approved, assigned, and work is progressing In review CR approved, assigned, and work is progressing Testing CR work has been reviewed and is being tested Closed CR work is complete, has passed all tests, and updates have been released. Change Control Board Name Position CCB Role Md. Adiluzzaman Adil Project Manager CCB Manager Kishan kumar Ganguly Md. Rakib Hossain Software Architect & Developer CCB Member Minhas Kamal A.H.M. Azimul Haque Designer & Developer CCB Member Mostaque Ahmed Israt Fatema Shantu Documentation CCB Member
  • 5.
    5 Change Request Template: Wehave used the following form template for change request: Change Request Project: Date: Change Requestor: Change No: Change Category (Check all that apply): □ Schedule □ Cost □ Scope □ Requirements/Deliverables □ Testing/Quality □ Resources Does this Change Affect (Check all that apply): □ Corrective Action □ Preventative Action □ Defect Repair □ Updates □ Other Describe the Change Being Requested: Describe the Reason for the Change: Describe all Alternatives Considered: Describe any Technical Changes Required to Implement this Change: Describe Risks to be Considered for this Change: Estimate Resources and Costs Needed to Implement this Change: Describe the Implications to Quality: Disposition: □ Approve □ Reject □ Defer Justification of Approval, Rejection, or Deferral: Change Board Approval: Name Signature Date
  • 6.
    6 Change Log Change Log Project:Network Upgrade Project Date: 04/01/20xx Change No. Change Type Description of Change Requestor Date Submitted Date Approved Status Comments CR001 Equipment This change request calls for the purchase of wlan routers. Minhas Kamal 07/08/16 08/08/16 Denied This request was denied by the change control board because there is not adequate funding available for the purchase of new routers and because the request is outside of the project's scope. CR002 Schedule This change request calls for delaying the existing schedule by one week to ensure all applications are backed up which was not considered in the original project plan. Kishan Kumar Ganguly 03/11/16 08/11/16 Approved This request was approved to ensure the security and continuity of all applications. One week will be added to the project schedule and the project manager will communicate the impact of this change to all stakeholders.