1. 1 LOCATION MAP
Jammu
section
15200
35400
Udhampur
section
35400 16452
1.2 INDEX MAP FOR JAMMU-UDHAMPUR SECTION OF
NH-1A
1. SALIENT FEATURES OF THE PROJECT
1 TYPE OF CONTRACT
DESIGN, BUILT, FINANCE, OPERATE AND TRANSFER ON
ANNUITY BASIS (DBFOT)
2 COST OF THE PROJECT Rs 918.39 CRORE
3 COST OF THE PROJECT EXCLUD PRELIMINARIES Rs. 887.89 CRORE
4 APPOINTMENT DATE 10TH
AUGUST 2011
5 COMPLETION DATE 9TH
FEB 2014
6 1st
MILE STONE 180 DAYS (10% OF PROJECT COST) : 09th
Feb-12
7 2ND
MILE STONE
450 DAYS (35% OF PROJECT COST) : 09th
Nov-12
(Commencement construction of all Bridges)
8 3RD
MILE STONE
750 DAYS (70% OF PROJECT COST) : 09th
Sep-13
(Commencement construction of all Project Facility)
9
SCHEDULED FOUR LANNING DATE AS PER BASE
LINE PROGRAM
900 DAYS (100% OF PROJECT COMPLETION) : 09th
Feb-14

NH-1A Details

  • 1.
  • 2.
  • 3.
    1. SALIENT FEATURESOF THE PROJECT 1 TYPE OF CONTRACT DESIGN, BUILT, FINANCE, OPERATE AND TRANSFER ON ANNUITY BASIS (DBFOT) 2 COST OF THE PROJECT Rs 918.39 CRORE 3 COST OF THE PROJECT EXCLUD PRELIMINARIES Rs. 887.89 CRORE 4 APPOINTMENT DATE 10TH AUGUST 2011 5 COMPLETION DATE 9TH FEB 2014 6 1st MILE STONE 180 DAYS (10% OF PROJECT COST) : 09th Feb-12 7 2ND MILE STONE 450 DAYS (35% OF PROJECT COST) : 09th Nov-12 (Commencement construction of all Bridges) 8 3RD MILE STONE 750 DAYS (70% OF PROJECT COST) : 09th Sep-13 (Commencement construction of all Project Facility) 9 SCHEDULED FOUR LANNING DATE AS PER BASE LINE PROGRAM 900 DAYS (100% OF PROJECT COMPLETION) : 09th Feb-14