DR. AKHILESH DAS GUPTA INSTITUTE OF TECHNOLOGY & MANAGEMENT
A Practical training and industrial visit presentation
on
Residential building
Submitted to :- Submitted by:-
Mr. Ankur Tayal Suraj jha
(Industrial training incharge,CVE) (08415603416)
CONTENT
 Introduction
 Company overview
 Types of building
 Steps of constructions
 Material used
 Equipment used
 Building by law
 Conclusion
INTRODUCTION
 Name of project : Multi storey resendential building
 Company name : M k mehta enterprise
 Location of site : GH-05A, tech zone IV, Gautam budh
,greater noida , uttar pradesh
 No. of floors : 6 floors
 Project start : December 2018
 Project end : 2020 (estimated)
 Project manager : Mr Piyush Koley
COMPANY OVERVIEW
 The M K MEHTA govt. contractor & general order suppliers established
on August 2015.
 The CEO of company is MR. Mk Mehta , and the major work by this
company are
1) The construction of Irrigation & flood control department
located at Basai darapur punjabi bagh near ESI metro
stations.
2) The construction of public park equipped with ground
water table enhance technique.
TYPES OF BUILDING
 RESIDENTIAL BUILDING
 EDUCATIONAL BUILDING
 ISTITUTIONAL BUILDING
 INDUSTRIAL BUILDING
* I have worked in residential building construction
project in summer training.
FORM WORK
 Form work is a mould to support concrete for its shape
until it gets hardened.
 Contains 30% of cost and 60% of total time.
CHARACTERSTICS OF A GOOD FORMWORK
 Easy removal and smooth surface
 Strength and rigidity
 Economy
 Less leakage
 Light surface
TYPES OF FORM WORK
FLEX
FORMWORK
ALUFORM
FORMWORK
ALUMINIUM
FORMWORK
Aluminum form work
Used in construction
Column
shuttering
STEPS INVOLVED IN CONSTRUCTION
1) SITE CLEARANCE :
* Location of site
* local legally binding rules
2) SURVEYING AND LAYOUT:
* Total station
* Auto level
3) EXACAVATION
* Proper timbering while excavation
* Dewatering should be done earlier
4) FOUNDATION :
 SHALLOW FOUNDATION: - According to Terzagi
shallow foundation having ( Df / B) <= 2
e.g- * Raft foundation
* Isolated footing
* Combined footing
 PILE FOUNDATION:- According to Terzagi shallow
foundation having ( Df / B) >= 2
e.g- * End bearing pile foundation
* Friction pile foundation
Pile
foundation
Raft foundation
5) CONCRETING:-
Equipments: * Concrete mixer
* Mounted concrete pump
* Concrete vibrators
Instructions: *There should proper compaction of concrete
* Should be proper cover of reinforcement.
*Proper curing of concrete
6) BEAMS AND COLUMNS:-
* There should be fixed rigid joint in framed structure.
* Reinforcement provided in (+ve) & (-ve) area both.
Beam
Slab
Column
Lateral ties
Distribution bars
MATERIAL USED
1) CEMENT :
 53 Grades of portland cement used.
 Initial settiling time – 30 mins
 Final settling time- 10 hour
2) AGGREGATES:
 Fine aggregate (0.075 – 4.75 mm used)
 Coarse aggregate (12.5 – 20mm used)
Steel bars in
Retaining wall
3) BRICKS
 Burnt clay bricks
 Concrete bricks
 Engineering bricks
 Fly ash bricks
 Sand lime bricks
4) WATER
 Water should be free from salts and solid particles.
 Water which is fit for human consumption (potable).
5) ADMIXTURES:-
Types of admixtures: * Accelerators
* Retarders
*Water reducers / plasticizers
*Air entraining admixtures
6) FLY ASH :-
Main advantage are: * Free of cost.
* Its consumption reduces environment
pollution
* It has good bonding properties
EQUIPMENT USED
CONCRETE
PUMPER
CEMENT SILOS
BUILDING BY LAWS
 For the construction of any building, certain restrictions are
laid down by municipal body , urban development authority
, and other government departments as Town planning trusts
to clear open space to be left around the building .
PLINTH AREA REGULATIONS
CONCLUSION
 Durability of a building depends mainly on proper
constructions process and proper used of material .
 As per my training I have conclude that , during my
training days I was familiar with the main elements of the
structure such as beam , columns, slab etc.
Thank you

Industrial training report of construction of the residential building

  • 1.
    DR. AKHILESH DASGUPTA INSTITUTE OF TECHNOLOGY & MANAGEMENT A Practical training and industrial visit presentation on Residential building Submitted to :- Submitted by:- Mr. Ankur Tayal Suraj jha (Industrial training incharge,CVE) (08415603416)
  • 2.
    CONTENT  Introduction  Companyoverview  Types of building  Steps of constructions  Material used  Equipment used  Building by law  Conclusion
  • 3.
    INTRODUCTION  Name ofproject : Multi storey resendential building  Company name : M k mehta enterprise  Location of site : GH-05A, tech zone IV, Gautam budh ,greater noida , uttar pradesh  No. of floors : 6 floors  Project start : December 2018  Project end : 2020 (estimated)  Project manager : Mr Piyush Koley
  • 4.
    COMPANY OVERVIEW  TheM K MEHTA govt. contractor & general order suppliers established on August 2015.  The CEO of company is MR. Mk Mehta , and the major work by this company are 1) The construction of Irrigation & flood control department located at Basai darapur punjabi bagh near ESI metro stations. 2) The construction of public park equipped with ground water table enhance technique.
  • 5.
    TYPES OF BUILDING RESIDENTIAL BUILDING  EDUCATIONAL BUILDING  ISTITUTIONAL BUILDING  INDUSTRIAL BUILDING * I have worked in residential building construction project in summer training.
  • 6.
    FORM WORK  Formwork is a mould to support concrete for its shape until it gets hardened.  Contains 30% of cost and 60% of total time. CHARACTERSTICS OF A GOOD FORMWORK  Easy removal and smooth surface  Strength and rigidity  Economy  Less leakage  Light surface
  • 7.
    TYPES OF FORMWORK FLEX FORMWORK ALUFORM FORMWORK ALUMINIUM FORMWORK
  • 8.
    Aluminum form work Usedin construction Column shuttering
  • 9.
    STEPS INVOLVED INCONSTRUCTION 1) SITE CLEARANCE : * Location of site * local legally binding rules 2) SURVEYING AND LAYOUT: * Total station * Auto level 3) EXACAVATION * Proper timbering while excavation * Dewatering should be done earlier
  • 10.
    4) FOUNDATION : SHALLOW FOUNDATION: - According to Terzagi shallow foundation having ( Df / B) <= 2 e.g- * Raft foundation * Isolated footing * Combined footing  PILE FOUNDATION:- According to Terzagi shallow foundation having ( Df / B) >= 2 e.g- * End bearing pile foundation * Friction pile foundation
  • 11.
  • 12.
    5) CONCRETING:- Equipments: *Concrete mixer * Mounted concrete pump * Concrete vibrators Instructions: *There should proper compaction of concrete * Should be proper cover of reinforcement. *Proper curing of concrete 6) BEAMS AND COLUMNS:- * There should be fixed rigid joint in framed structure. * Reinforcement provided in (+ve) & (-ve) area both.
  • 13.
  • 14.
    MATERIAL USED 1) CEMENT:  53 Grades of portland cement used.  Initial settiling time – 30 mins  Final settling time- 10 hour 2) AGGREGATES:  Fine aggregate (0.075 – 4.75 mm used)  Coarse aggregate (12.5 – 20mm used)
  • 15.
  • 16.
    3) BRICKS  Burntclay bricks  Concrete bricks  Engineering bricks  Fly ash bricks  Sand lime bricks 4) WATER  Water should be free from salts and solid particles.  Water which is fit for human consumption (potable).
  • 17.
    5) ADMIXTURES:- Types ofadmixtures: * Accelerators * Retarders *Water reducers / plasticizers *Air entraining admixtures 6) FLY ASH :- Main advantage are: * Free of cost. * Its consumption reduces environment pollution * It has good bonding properties
  • 18.
  • 19.
    BUILDING BY LAWS For the construction of any building, certain restrictions are laid down by municipal body , urban development authority , and other government departments as Town planning trusts to clear open space to be left around the building . PLINTH AREA REGULATIONS
  • 20.
    CONCLUSION  Durability ofa building depends mainly on proper constructions process and proper used of material .  As per my training I have conclude that , during my training days I was familiar with the main elements of the structure such as beam , columns, slab etc.
  • 21.