SlideShare a Scribd company logo
1 of 34
Feasibility Study of laying Trunk & Gravity main,
design and costing
At Poundbury
25th April 2021
Contents
1) Introduction
2) Investigation of routes
3) Options considered
a. Justification for selection pipe routes
b. Pipe design
4) Costs
5) Pump
6) Pressure surges
7) Conclusions
8) Appendices
A. Plans and long sections (including the HGL) of all routes
considered
B. Design calculations
C. Cost spreadsheets
D. Information relevant to pump selection
E. Information relevant to pressure surge protection
1) Introduction:
Is to design two pipe system which includes pump trunk main
and gravity distribution main for supplying treated drinking
water to 2000 new houses at Poundbury. In view of the
increased developments in the area such as private housing,
retail shops, pubs, restaurants and other businesses in the area,
the current water supply will not be able to sustain for the
economic expansion of the town.
The design is provided a trunk main route from Borton PS
59.45m AOD to Lambert’s Hill (155.7m AOD) reservoir and a
gravity distribution main from Lambert’s Hill to Poundbury
110.0m AOD because the problem with the existing Dorchester
water tower is at a lower level 108mAOD compared to
Poundbury. The new water pipe system will be able to supply
drinking water to the community and sustain the booming
economy for decades to come. The design will be in
line/according to the Wessex-water standards and should also be
able to cater for future extension in it.
Project objective:
The aim is to provide a feasibility study on the pumped trunk
main design and the gravity main design from the two proposed
materials that is cast iron DI pipe and UPVC PE pipe. The
proposal will access the flow rate, pipe selective diameter from
industry, maximum pressure in the system, head loss in pipe and
pipe design arrangement by using the following methods.
Method 1: Darcy equation and Moddy Diagram
Method 2: C-W equation and H-R walling ford look up tables.
Project will incorporate the best suitable route design trunk
main from the pump station to the reservoir and gravity main
reservoir to Poundbury along with advice on the need for
pressure protection in the piping system. The feasibility study
will provide the most cost-effective solutions and economical
design to that the project if it will be feasible prior before the
approval and implementation.
2) Route Investigation:
When planning pipe layout there are several constraints that
must be assessed and considered as a form of site investigation.
The site feasibility will evaluate the ground condition and
geological factors of the surrounding are.
Ground condition:
According to geological map of Britain viewer: Bedrock and
superficial deposits. The soil condition for the proposed pipe
layout are composed of chalk material which are one of the
ideal soil condition for trench pipe laying. The pipe design from
trunk main and gravity main will be entirely lay on are
composed of chalk, so precaution needs to be taken not to lay
the pipe on other soil type that may cause geotechnical effect on
the piping system.
http://mapapps.bgs.ac.uk/geologyofbritain/home.html.
Crossing:
When preparing the design, consideration should be taken to
avoid road, railway, river crossing as much as possible. Farmed
land and private properties should be avoided but the issue with
Google earth is that its very difficult to identify private
property boundaries and the land used planned on the area. Any
crossing will be incorporated in to the cost and reinstated to its
original state.
Sensitive area:
Area such as scientific interests, historical monuments and
wildlife sanctuary which has aesthetic beauty should be avoided
completely as it may cause delay in the project due to the fact it
may take years to get approval to access these areas. Areas with
outstanding beauty must be integrated in the cost and restored
to its original natural state.
Site condition for the pipe
Slope:
The ground elevation must minimise crest and through as it may
create pressure drop in the pipe system.
Pipe access:
· Avoid meandering to reduce frictional head losses (hf) in
piping system.
· Pipe will be laid at the depth of 0.9m to 1.3m below ground
level.
· Lay pipe in field to minimise cost and reduce risk such as
siphon phenomenon and negative pressure development in the
trunk main design. (Negative pressure develop in pipe fitting
will absorb contaminants in the environment).
· Install twin pipe under road and rail crossing in case one is
damaged the other can be used as an alternative. First it will
increase the installation cost, but it will be a worthwhile
investment for the long term. (It to mitigate heavy civil work
when pipe are damaged in the future).
Hydraulic:
· The right pipe size should be designed in away as the friction
head losses is minimum, but the energy should be high enough
along hydraulic gradient so that water will be able to flow
above the house in accordance to the Wessex-Water
standard(check google for more information ) .
· Pump water by creating an artificial energy to carry water up
the pipe to the reservoir. The energy should be above the
reservoir to frictional losses of energy in the system would be
accounted for as water flow in the reservoir.
3) Options considered: (pipe disagen )
a) Justification for selection pipe routes
· Choose areas with less bends
· Avoid crossing areas that can inflate the project cost
· Avoid private properties/areas
· Prevent frictional loss
· Ensuring no stagnant water remains in the pipes for than 12
hours
· Maximum pressure in pipes should be less than 60 bar
· The pipe sizes diameters have a high sensitivity towards
frictional loss so the right size calculation is very important to
minimize loss. ( don’t use it )
b) Pipe design
· Pipe material: DI and PE pipe(google )
· DI Trunk Main
The objective is to design and select the appropriate pipe size
for trunk main route from Borton PS to Lambert’s Hill to
minimise the frictional head losses (hf).
Calculate frictional losses (hf) in pipe flow design (trunk
pumped main) by use of 2 methods:
· 1ST METHOD : Darcy Equation & Moody Diagram
· 2ND METHOD : C-W Equation & H-R Wallingford look up
tables
For selection of the appropriate pipe size the following values
should be available as followed
1) Design flow rate Q=7Ml/day
2) Length of pipe L(km) and type of material: DI; Galvanised
iron (normal condition) and PI; PVC
3) Start point Burton PS 59.45m AOD and end point at
Lambert’s Hill 155.7m AOD
4) Static lift = 155.70 - 59.47 = 96.23m
5) Assume velocity in pipe flow 1m/s according to Wessex-
water standards (
Trunk main design:
Eq.1:
Head-loss of pipe(hf), friction factor(f), length(l), diameter (d
or D), velocity(V) & acceleration due to gravity(g).
1st Method: Darcy Equation & Moody Diagram
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Darcy Equation (Refer to Appendix B)
Max pressure of total 10.71bars should be less than 16bars
according to Wessex-water standards. 10.71
(Where 1m=0.098041bars)
Pressure check: For min pressure in the system
Min pressure in the system should be equal least 6m
Min pressure = 6m everywhere, therefore will be installing
pressure sustaining valve (PSV) closers to end point of the
Reservoir where the risks is higher to experience pressure less
than 6m.
2nd Method: C-W Equation & H-R Wallingford look up tables
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Colebrook-White equation (0939) (C-
W) (Refer to Appendix B)
Eq.9
Velocity(V), Pipe diameter(d), Hydraulic gradient(S), Effective
roughness(K) and Kinematic viscosity (
(1) Step 1: Repeat 1st step from method 1:
(2) Step 2: Repeat 2nd Step from method 1: and Pipe Diameter:
350mm
· Gravity Main Design
The objective is to design and select the appropriate pipe size
for each selected gravity main routes from Lambert’s Hill to
Poundbury to minimise the frictional head losses (hf).
Calculate frictional losses (hf) in pipe flow design (trunk
pumped main) by use of 2 methods:
· 2ND METHOD : C-W Equation & H-R Wallingford look up
tables
For selection of the appropriate pipe size the following values
should be available as followed
a) Design flow rate Q=120 l/s
b) Length of pipe L(km) and type of material: DI; Galvanised
iron (normal condition) and PE; UPVC
c) Start point Lambert’s Hill SR 155.70m AOD and end point at
Poundbury 110.00m AOD
d) Lambert’s Hill SR – (Poundbury max elevation + required
delivery head) =
Assume hf = 155.7 – (110.0 + 20) = 155.7 – 130 = 25.7m
e) Assume velocity in pipe flow 1.0m/s according to Wessex-
water standards ()
Gravity main design:
Eq.9: Gradient
Head-loss of pipe(hf) and length(L)
DI and PE PIPE: Gravity Main
2nd Method: C-W Equation & H-R Wallingford look up tables:
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Darcy Equation (Refer to Appendix B)
Pressure check:
a) At area where pipe from ground elevation has troughs. The
lowest trough: risk of high pressure 35m(standard) therefore it
is recommended to install Pressure reducing valves (PRV). 3
b) There is highest risk to have max pressure to the downstream
end of pie, in times of very low flow, therefore it is
recommended to stall Pressure reducing valve (PRV) at the
downstream end of the pipe.
c) At area where pipe from ground elevation has peaks. Highest
peak, risk of low pressure or even negative ones, therefore it is
recommended to install pressure increasing valves at this point.
· Pipe elements required for the routes; Calculating fitting
losses: Refer to Appendix B: Table 3.
Types of fittings:
· Pump manifold: Roughness value for 1 manifold is K1= 1.
· Swabbing chambers: ; Swabbing chambers @ every 2.5km of
pipe length
· Long radius bends:
· In line valves: In line valves every 2km of pipe length
· Air valves: one air valves needed
· Isolating valves for each crossing:
· In line tees for future expansion plans:
· Wash outs: to clear out sediment and prevent discoloration
4. Costs:
(refer appendix D)
The capital expenditure calculation for CAPX and OPEX are
based on input costing data available from Baro Happold. The
calculation expenditure is covered for 60 years project life cycle
with net present value of £1 at 6%.
Trunk main/Gravity main:
The cost expenditure for pipe design are from the same size and
the change in project cost are affected by the length of the pipe,
pipe passing through sensitive area and road/river crossing
because they have a high rate £/m compared to pipe lay in field
area. From the capital expenditure total cost, it clearly shows
pipes which are shorter in length cost less and are more cost
economic provided that the meet the design requirement with a
low operation cost.
· Trunk main DI pipe route 1 has the maximum CAPEX and
OPEX cost of £5,930,207/- compare to route 4 which has the
lowest CAPEX & OPEX cost of £5,580,854/-
· Gravity main PE pipe route 1 has the lowest CAPEX and
OPEX cost of £1,205,788/- compare to the same route 1 with DI
pipe which has the CAPEX & OPEX cost of £1,240,733/-. Base
on the analysis it more feasible and cost economic to select PE
pipe material for the gravity main
5. Pump Selection:
Pump type: 5no 200x290x280 – 81/75x5x18.5=100HW as per
appendix D
· The primary reason for not choosing less pump is that at the
beginning the cost of installation will be less but the power out
put is high, thus it will cause a high operation cost as it require
more energy to operate. That is why it is not feasible to
consider series 3no to 4no and any formation with high power
output. It is more advisable to consider a more cost economic
pump installation in series like 5m pump or 6pump which has
the lower power output of 100KW but if there are less pump in
series that produces the same power out put of 100KW or less it
might be considered in the design. As a result, it is more
economical to select the 5m.200x290x280 – with power output
of 100KW.
Pump selection: by appendix D
The selected type of pump that will be used is an Armstrong
4300 pump with specific spec.
Curve no: PT113-1-1-1500
Series: 4300 Starline
Size: 200-290
RPM: 1500
Power: 81/75x5x18.5=100KW
Efficiency: 85%
Pump in series: 5no.200x290x280.
The operating pump: The pump system in series have been
designed in by using the system curve and by looking at the
point where the performance curve and system curve intercept.
This is the point that define that the pump are suitable for the
design. (Operating point is the point where system curve and
operating curve cross.)
6. Pressure surge: (Refer to appendix E)
Is the sonic velocity, stiffness and fluid in the piping system
which the roughness depends on time and the materials used. If
the materials have more resistance to velocity, therefore any
change in pressure and that will create a pressure surge in the
pipe. Pressure surge consequence are fitting failure, pipe
bursting and pump damage.
The graphs in appendix E represent pressure in pipe from two
pipe size 350 and 400mm and from two different materials (D1
and PE).
· D1 pipe: Pressure surge: 350mm pipe (ps-sr)
Node1: The closer the water nears a valve changes the
stronger the pressure surge and it happens along the full length
of the pipe. The pressure rises from 90(m) up to 184(m) then,
down to 40(m). This happens consistence across the internal
length of the pipe when the pressure surge phenomenon to
place. More protection will be need to Node1 than to Node10.
Node1 is more likely to be from pump to reservoir and vice
versa.
Node3 & 6: The pipe system exerts pressure surge phenomenon
but not as intense as in Node1. In Node3 the pressure rises up
during a period of time until it reaches 162max and drop to near
zero, where as in Node 6 its maximum rise is 130m then i t drops
to 60 and stable for a period of time until it drop to -20.
Node 10: The pressure changes but does not happen through the
entire length of the pipe. It happens as a spick as the pressure
rise up from 10(m) to 90(m). It only happens at a single poi nt
(Need less protection than Node1). In Node 10 the pressure
takes longer period to form compared to Node 1.
· D1=400mm: Model: Has similar effect as in D1350mm (the
maximum pressure is near 150m and minimum is around -30(m).
Node3 & 6: Both pipe system in general experiences pressure
surge. Node 3 rise up to nearly 140(m) and has a minimum
pressure loss below -40(m) which equal to -3.9 bar which is
below ˂6m. Node 6 has similar effect. Therefore both pipe
system will require pressure increasing valves at the lowest
point.
Node 10: Same pressure surge as the Note 10 exert in D1 350m
only difference is the maximum and minimum.
· General:
The D1 350mm experience high pressure surge than in D1
400mm at different flow rates while D1 400mm experience
lower pressure surge than in D1 350mm. That means that the
size of pipe with different flow rates will experience pressure
surge differently but the comparison between D1 pipe with PE
pipe is that the PE has a high resistance to pressure surge due to
its elastic and plasticity of UPVC.
7. Conclusion
To conclude the design analysis using 2nd Method: C-W
Equation & H-R Wallingford look up tables to assess the flow
rate, gradient, pipe size, frictional loss and maximum powers
between DI and PE pipe along with capex and opex cost
expenditure:
Trunk main pipe analysis shows that the pipe with the shortest
length and less crossing are more feasible and economically
viable to be used for this design.
Trunk main route selection are mostly similar, but its advisable
to select the less cost effective that have less crossing and
bending to minimize frictional head loss.
Gravity main: These two types of material DI and PE does not
have much difference in comparison, when analysing route with
the same length the only issue that differs is the velocity and
retention time between them. PI material is more cost economic
and durable. In additional it has a greater resistance to pressure
surge compared to DI pipes. More thorough studies are needed
to determine the best optimal design for route selection.
On a final note, the feasibility assessment will help to identify
the best route that is more cost effective and sustainable and
environmentally friendly. The pipes should be laid and tested in
accordance with the manufacture’s instructions and the Town
and Country Planning Regulations.
8 Appendix A: Plans and long section
Trunk Main
Fig1: Route 1.Photo from Google [email protected] Google
Fig2: Route 2.Photo from Google [email protected] Google
Fig3: Route 3.Photo from Google [email protected] Google
Fig4: Route 4.Photo from Google [email protected] Google
Fig5: Route 5.Photo from Google [email protected] Google
Gravity Main
Fig6: Route 1.Photo from Google [email protected] Google
Fig7: Route 2.Photo from Google [email protected] Google
Fig8: Route 3.Photo from Google [email protected] Google
Appendix B. Calculation
Pump Trunk Main
Eq.1:
Head-loss of pipe(hf), friction factor(f), length(l), diameter (d
or D), velocity(V) & acceleration due to gravity(g).
DI Pipe: Trunk Main Route 1
1st Method: Darcy Equation & Moody Diagram
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Darcy Equation
1) Step 1: Design flow rate; Convert
Eq.2:
2) Step 2: Assumed velocity in pipe 1m/s; Calculate area of pipe
and pipe diameter
We must assume the velocity because we have not designed the
trunk-main and we do not have all the value in the system.
i) Eq.3: Area=Flow rate/Velocity,
Pipe Area(A)=
ii) Pipe Diameter: Eq.4:
Pipe diameter=
The possible D=0.321m = 321mm
From industry DI pipe: Possible pipe 300mm DI pipe or 350mm
DI pipe
Repeat Step 2:
Pipe Diameter: 350mm
Real Velocity(V): Eq.2
3) Step 3: Calculate Reynolds number (Re)
Kinematic viscosity (=1.14 (at typical value )
Eq.5
4) Step 4: Table 38. Recommended roughness values (K).
i) Galvanise iron-good condition K=0.06
Eq.6 K/d=0.06/350=
ii) Use Moody diagram to find friction factor(f) from k-value
Moody diagram F=0.0044
iii) Therefore, frictional head losses (hf).
Eq.1
The total hf losses due to pipe flow are hf=12.047m when
selecting DI pipe d=350mm.
Disregard the DI pipe d=300m has it has a higher frictional head
loss of hf=13.416m.
Route checks
Last checks to make sure the route is a good design:
(1) Velocity check: Fist assumed V=1m/s but re-calculated V=
0.842m/s
Check V=0.842m/s against Wessex-water standards
V=0.842m/s is less than 2m/s
(2) Retention time (RT). Calculate as followed:
Pipe Area (A), Length of pipe (L)=6630m and Velocity
(V)=0.842m/s
Eq.7 RT = L/V = 6630/0.842 =
Check RT=2h19mins against wassex-water standards. RT should
be less than 12hours
(3) Pressure check: For max pressure in the system.
Calculated Max pressure by summing up the following values:
i) Static lift = 155.70 - 59.45= 96.25m
ii) Freeboard= 0.5m
iii) Fitting losses = 0.398 (see
appendix xx)
iv) hf calculation from Darcy Method or C-W and look-up
tables. hf=12.047m
v) In total; Max pressure: Eq.8 Max pressure= Static lift+
Freeboard+ Fitting losses+ hf
Max pressure of total 10.71bars should be less than 16bars
according to Wessex-water standards. 10.71
(Where 1m=0.098041bars)
(4) Pressure check: For min pressure in the system
Min pressure in the system should be equal least 6m
Min pressure=6m everywhere, therefore will be installing
pressure sustaining valve (PSV) closers to end point of the
Reservoir where the risks is higher to experience pressure less
than 6m.
DI Pipe: Trunk Main Route 1
2nd Method: C-W Equation & H-R Wallingford look up tables
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Colebrook-White equation (0939) (C-
W)
Eq.9
Velocity(V), Pipe diameter(d), Hydraulic gradient(S), Effective
roughness(K) and Kinematic viscosity (
(3) Step 1: Repeat 1st step from method 1:
(4) Step 2: Repeat 2nd Step from method 1: and Pipe Diameter:
350mm
(5) Step 3:
(a) Table 38. Recommended roughness values (K).
Galvanise iron-good condition K=0.06
(b) Table 15 – HR Wallingford table for K=0.06, Pipe size
350mm and Q=0.081
Q1=0.079, HG1=0.00160……………………………..
(V=0.819m/s)
Q2=0.081, HG2=0.00170……………………………..
(V=0.846m/s)
Real: Q =0.081, HG = ……………………………..
(V=0.842m/s)
Linear interpolation gives following equation: Eq:10………..
= 0.0017
Energy losses per meter length of pipe(hf) where then length.
Therefore, total losses hf = 6630 x 0.0017 = 11.271m
Route checks
Last checks to make sure the route is a good design:
(1) Velocity check: Fist assumed V=1m/s but re-calculated V=
0.842m/s
Check V=0.842m/s against Wessex-water standards
V=0.842m/s is less than 2m/s
(2) Retention time (RT). Calculate as followed:
Pipe Area (A), Length of pipe (L)=6630m and Velocity
(V)=0.842m/s
Eq.7 RT = L/V = 6630/0.842 =
Check RT=2h18mins against wassex-water standards. RT should
be less than 12hours
(3) Pressure check: For max pressure in the system.
Calculated Max pressure by summing up the following values:
i) Static lift = 155.70 - 59.45= 96.25m
ii) Freeboard= 0.5m
iii) Fitting losses = 0.398 (see
appendix xx)
iv) hf calculation from Darcy Method or C-W and look-up
tables. hf=11.271m
v) In total; Max pressure: Eq.8 Max pressure= Static lift+
Freeboard+ Fitting losses+ hf
Max pressure of total 10.63bars should be less than 16bars
according to Wessex-water standards. 10.63
(Where 1m=0.098041bars)
(4) Pressure check: For min pressure in the system
Min pressure in the system should be equal least 6m
Min pressure=6m everywhere, therefore will be installing
pressure sustaining valve (PSV) closers to end point of the
Reservoir where the risks is higher to experience pressure less
than 6m.
Gravity Main Design
Eq.9: Gradient
Head-loss of pipe(hf) and length(L)
DI PIPE: Gravity Main Route 1
2nd Method: C-W Equation & H-R Wallingford look up tables:
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Darcy Equation
i) Step 1: Design flow rate; Convert
ii) Step 2: Assumed velocity in pipe 1m/s; Calculate area of
pipe and pipe diameter
a) Eq.3:
b) Pipe Diameter: Eq.4:
Pipe diameter=
The possible D=0.391m = 391mm
iii) Step 3: Gravity Main Route 1: From industry DI pipe:
Possible pipe 350mm, 400mm or 450mm
Table 38. Recommended roughness values (K)=0.06 good
condition
a) Pipe length L=3040m, hf=25.7m, Real: Q= , HG=0.00845 &
D=0.391m
From Table 1: HR Wallingford table
Pipe Size mm
Gradient HG
Assume Gradient HG
Flow rate Q(m^3/s)
Need Q(m^3/s)
Reject
350
0.0080
0.0085
0.184
0.120
0.0085
0.190
Do not Reject
400
0.0080
0.0085
0.262
0.120
0.0085
0.270
Reject
450
0.0080
0.0085
0.352
0.120
0.0085
0.368
(c) Table 15 – HR Wallingford table. D:350mm
Q1 = 0.118, HG1 = 0.00340
Q2 = 0.121, HG2 = 0.00360
Real: Q = 0.120, HG = …
Linear interpolation gives following equation:
Eq:10………..
= 0.00352
(The actual Q=0.120 and actual HG=0.00352 is less than the
initial assumed HG=0.00845)
Energy losses per meter length of pipe(hf) where then length
3040m
Therefore, total losses hf = 3040 x 0.00352 = 10.70m
Route checks
Last checks to make sure the route is a good design:
(1) Velocity check: Fist assumed V=1m/s but re-calculated
Vm/s
Check Q=0.120/s and D=0.350m
; V=1.25m/s is less than 1.5m/s
(2) Retention time (RT). Calculate as followed:
Length of pipe (L)=3040m and Velocity (V)=1.25m/s
Eq.7 RT = L/V = 3040/1.25 =
Check RT=1.06hrs against Wassex-water standards. RT should
be less than 12hours
(3) Pressure check:
5 At area where pipe from ground elevation has troughs. The
lowest trough: risk of high pressure 35m(standard) therefore it
is recommended to install Pressure reducing valves (PRV). 3
6 There is highest risk to have max pressure to the downstream
end of pie, in times of very low flow, therefore it is
recommended to stall Pressure reducing valve (PRV) at the
downstream end of the pipe.
7 At area where pipe from ground elevation has peaks. Highest
peak, risk of low pressure or even negative ones, therefore it is
recommended to install pressure increasing valves at this point.
PE PIPE: Gravity Main Route 2
2nd Method: C-W Equation & H-R Wallingford look up tables:
Calculation of frictional (head) losses hf in an existing pumped
main pipe flow by use of Darcy Equation
(1) Step 1: Design flow rate; Convert
Eq.9: Gradient =
(2) Step 2: Assumed velocity in pipe 1m/s; Calculate area of
pipe and pipe diameter
a) Eq.3:
b) Pipe Diameter: Eq.4:
Pipe diameter=
The possible D=0.396.9m = 396.9mm (from industry)
(3) Step 3: Gravity Main Rout 1: From industry PE pipe:
Possible pipe: 396.9mm
Table 38. Recommended roughness values (K)=0.03 good
condition
From Table 14: K=0.03, Q=, HG=0.0082 and range 375mm &
400mm.
Eq.9: Gradient = 25.7/3140 = 0.00818
b) Pipe length L=3140m, hf=25.7m, Real: Q= & HG=0.00818
c) From Table 2: HR Wallingford table
Pipe Size D/mm
Gradient HG
Assume Gradient HG
Flow rate Q(m^3/s)
Need Q(m^3/s)
Reject
375
0.0080
0.0085
0.229
0.120
0.0085
0.237
Reject
400
0.0080
0.0085
0.272
0.120
0.0085
0.280
(d) Eq:11………..
(e) HG1 = 0.00180: Q1 = 0.103, Q2 = 0.122: E Eq:11 Q=0.1196
HG2 = 0.00190: Q1 = 0.106, Q2 = 0.126: E Eq:11 Q=0.1235
(f) Cal for HG value for D:396.9mm
Q1 = 0.1196, HG1 = 0.00180
Q2 = 0.1235, HG2 = 0.00190
Real: Q = 0.120, HG = …
Linear interpolation gives following equation:
Eq:10………..
= 0.00181
(The actual Q=0.120 and actual HG=0.00181 is less than the
initial assumed HG=0.00818)
Energy losses per meter length of pipe(hf) where then length
3040m
Total losses hf = 3140 x 0.00181 = 5.68m
Route checks
Last checks to make sure the route is a good design:
(1) Velocity check: Fist assumed V=1m/s but re-calculated
Vm/s: Check Q=0.120/s and D=0.3969m
; V=0.97m/s is less than 1.5m/s
(2) Retention time (RT). Calculate as followed: Length of pipe
(L)=3140m and Velocity (V)=1.25m/s
Eq.7 RT = L/V = 3140/0.97 =
Check RT=1.06hrs against Wassex-water standards. RT less
than 12hours
(3) Pressure check:
8 At area where pipe from ground elevation has troughs. The
lowest trough: risk of high pressure 35m(standard) therefore it
is recommended to install Pressure reducing valves (PRV). 3
9 There is highest risk to have max pressure to the downstream
end of pie, in times of very low flow, therefore it is
recommended to stall Pressure reducing valve (PRV) at the
downstream end of the pipe.
10 At area where pipe from ground elevation has peaks. Highest
peak, risk of low pressure or even negative ones, therefore it is
recommended to install pressure increasing valves at this point.
Calculate of frictional losses in pipe fitting
Table3: Fitting Losses for Trunk Main and Gravity Main
Appendix C: Cost spreadsheet
Capital Expenditure Pump Main
Appendix D: Information for PUMP Selection
Pumps for UK civil engineering application licensed to be used
to pump portable water: 4300
Fig9: From lecture: Pump selection summary
Fig10: From lecture: Selected pump: 5 no. 200 x 290 x 280
Appendix E: Pressure surge protection:
Fig11.a: From lecture
Fig11.b: From lecture
Fig11.c : From lecture
Reference:
· http://armstrongfluidtechnology.com/en-gb/products-and-
services/heating-and-cooling/commercial-pumps
· Wessex Water DESIGN STANDARD DS 643 2008 Water
Supply Pressure Pipelines [Online]
N
o
Rout
Description
Rout
length
L/km
1 Pump
manifold K=1
(1 x 1=K1)
Swabbing
chambers @
every 2.5km
of pipe length
K=0.24
No. Long
radius bend
K=0.10
(0.10 x X=K3)
In line valves
every 2km of
pipe length
K=0.12
(0.12 x X=K4)
1 Air-valves
K=0.05
(0.05 x 1=K4)
Isolatating valves for
each crosing K=0.70
(Road+River)x0.70=K6
1 in line tees
for future
expension
K=0.12
(0.12 x 1=K7)
1 wash-out
K=0.59
(0.59 x 1=K7)
Total
K
values
K1K2K3K4K5K6K7K8ΣK
1Route 16.6310.480.70.360.057.70.120.5911.000.7090.398
2Route 26.6410.480.90.360.057.00.120.5910.500.7090.379
3Route 36.2910.480.70.360.056.30.120.599.600.7090.347
4Route 45.7910.480.50.240.056.30.120.599.280.7090.335
5Route 55.9210.480.70.240.056.30.120.599.480.7090.343
Gravity main
1DI: G.main 13.0400.240.40.120.052.80.120.594.321.5630.344
1PE: G.main 13.0400.240.40.120.052.80.120.594.320.9410.207
2PE: G.main 23.1400.240.50.120.052.80.120.594.420.9410.212
3PE: G.main 33.1300.240.40.120.052.80.120.594.320.9410.207
Type of fitting with Roughness value (K)Real
Velocity
0.842m/s
( V^2)
Fitting
losses/m
=ΣK(V^2/2g)
Trunk Main
PE:0.97&DI:1.25 m/s

More Related Content

More from ChereCheek752

Please provide a statement that addresses your reasons for transferr.docx
Please provide a statement that addresses your reasons for transferr.docxPlease provide a statement that addresses your reasons for transferr.docx
Please provide a statement that addresses your reasons for transferr.docxChereCheek752
 
Please provide a brief response to the following questions1) How .docx
Please provide a brief response to the following questions1) How .docxPlease provide a brief response to the following questions1) How .docx
Please provide a brief response to the following questions1) How .docxChereCheek752
 
PLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docx
PLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docxPLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docx
PLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docxChereCheek752
 
Please note that the following vignettes represent samples of the ty.docx
Please note that the following vignettes represent samples of the ty.docxPlease note that the following vignettes represent samples of the ty.docx
Please note that the following vignettes represent samples of the ty.docxChereCheek752
 
Please no plagiarism. I have attached an example to go by. The popul.docx
Please no plagiarism. I have attached an example to go by. The popul.docxPlease no plagiarism. I have attached an example to go by. The popul.docx
Please no plagiarism. I have attached an example to go by. The popul.docxChereCheek752
 
PLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docx
PLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docxPLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docx
PLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docxChereCheek752
 
Please Paraphrase the following into a more scholarly toneI f.docx
Please Paraphrase the following into a more scholarly toneI f.docxPlease Paraphrase the following into a more scholarly toneI f.docx
Please Paraphrase the following into a more scholarly toneI f.docxChereCheek752
 
Please only respond if you are familiar with raspberry piIam loo.docx
Please only respond if you are familiar with raspberry piIam loo.docxPlease only respond if you are familiar with raspberry piIam loo.docx
Please only respond if you are familiar with raspberry piIam loo.docxChereCheek752
 
Please note this is 2 ASSIGNMENTS ......Please only orginial work on.docx
Please note this is 2 ASSIGNMENTS ......Please only orginial work on.docxPlease note this is 2 ASSIGNMENTS ......Please only orginial work on.docx
Please note this is 2 ASSIGNMENTS ......Please only orginial work on.docxChereCheek752
 
PLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docx
PLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docxPLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docx
PLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docxChereCheek752
 
Please no plagiarism and make sure you are able to access all resour.docx
Please no plagiarism and make sure you are able to access all resour.docxPlease no plagiarism and make sure you are able to access all resour.docx
Please no plagiarism and make sure you are able to access all resour.docxChereCheek752
 
Please need two posts of 200 words each. Discuss the ways in whi.docx
Please need two posts of 200 words each. Discuss the ways in whi.docxPlease need two posts of 200 words each. Discuss the ways in whi.docx
Please need two posts of 200 words each. Discuss the ways in whi.docxChereCheek752
 
Please look for the following errors in this document.ErrorsKeyb.docx
Please look for the following errors in this document.ErrorsKeyb.docxPlease look for the following errors in this document.ErrorsKeyb.docx
Please look for the following errors in this document.ErrorsKeyb.docxChereCheek752
 
Please make sure that your writers are properly writing the final re.docx
Please make sure that your writers are properly writing the final re.docxPlease make sure that your writers are properly writing the final re.docx
Please make sure that your writers are properly writing the final re.docxChereCheek752
 
Please identify the one sculpture from each of the following artist .docx
Please identify the one sculpture from each of the following artist .docxPlease identify the one sculpture from each of the following artist .docx
Please identify the one sculpture from each of the following artist .docxChereCheek752
 
Please I would like you to write a discussion with 200 words by answ.docx
Please I would like you to write a discussion with 200 words by answ.docxPlease I would like you to write a discussion with 200 words by answ.docx
Please I would like you to write a discussion with 200 words by answ.docxChereCheek752
 
Please identify the leadership traits, skills, and behaviors that yo.docx
Please identify the leadership traits, skills, and behaviors that yo.docxPlease identify the leadership traits, skills, and behaviors that yo.docx
Please identify the leadership traits, skills, and behaviors that yo.docxChereCheek752
 
Please i need a research paper about Langauge and Culture.( 1500 wor.docx
Please i need a research paper about Langauge and Culture.( 1500 wor.docxPlease i need a research paper about Langauge and Culture.( 1500 wor.docx
Please i need a research paper about Langauge and Culture.( 1500 wor.docxChereCheek752
 
Please help me with this program1 – Hello WorldCreate a proj.docx
Please help me with this program1 – Hello WorldCreate a proj.docxPlease help me with this program1 – Hello WorldCreate a proj.docx
Please help me with this program1 – Hello WorldCreate a proj.docxChereCheek752
 
PLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docx
PLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docxPLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docx
PLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docxChereCheek752
 

More from ChereCheek752 (20)

Please provide a statement that addresses your reasons for transferr.docx
Please provide a statement that addresses your reasons for transferr.docxPlease provide a statement that addresses your reasons for transferr.docx
Please provide a statement that addresses your reasons for transferr.docx
 
Please provide a brief response to the following questions1) How .docx
Please provide a brief response to the following questions1) How .docxPlease provide a brief response to the following questions1) How .docx
Please provide a brief response to the following questions1) How .docx
 
PLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docx
PLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docxPLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docx
PLEASE NOTE OF SOURCESMATERIALS ALSO INCLUDED---USE THEMT.docx
 
Please note that the following vignettes represent samples of the ty.docx
Please note that the following vignettes represent samples of the ty.docxPlease note that the following vignettes represent samples of the ty.docx
Please note that the following vignettes represent samples of the ty.docx
 
Please no plagiarism. I have attached an example to go by. The popul.docx
Please no plagiarism. I have attached an example to go by. The popul.docxPlease no plagiarism. I have attached an example to go by. The popul.docx
Please no plagiarism. I have attached an example to go by. The popul.docx
 
PLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docx
PLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docxPLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docx
PLEASE NO PLAGIARIZE!! Have 10 hours to fullfil this work. 1page or .docx
 
Please Paraphrase the following into a more scholarly toneI f.docx
Please Paraphrase the following into a more scholarly toneI f.docxPlease Paraphrase the following into a more scholarly toneI f.docx
Please Paraphrase the following into a more scholarly toneI f.docx
 
Please only respond if you are familiar with raspberry piIam loo.docx
Please only respond if you are familiar with raspberry piIam loo.docxPlease only respond if you are familiar with raspberry piIam loo.docx
Please only respond if you are familiar with raspberry piIam loo.docx
 
Please note this is 2 ASSIGNMENTS ......Please only orginial work on.docx
Please note this is 2 ASSIGNMENTS ......Please only orginial work on.docxPlease note this is 2 ASSIGNMENTS ......Please only orginial work on.docx
Please note this is 2 ASSIGNMENTS ......Please only orginial work on.docx
 
PLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docx
PLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docxPLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docx
PLEASE NEED TWO RESPONSES TWO HUNDRED WORDS EACHDistinguish b.docx
 
Please no plagiarism and make sure you are able to access all resour.docx
Please no plagiarism and make sure you are able to access all resour.docxPlease no plagiarism and make sure you are able to access all resour.docx
Please no plagiarism and make sure you are able to access all resour.docx
 
Please need two posts of 200 words each. Discuss the ways in whi.docx
Please need two posts of 200 words each. Discuss the ways in whi.docxPlease need two posts of 200 words each. Discuss the ways in whi.docx
Please need two posts of 200 words each. Discuss the ways in whi.docx
 
Please look for the following errors in this document.ErrorsKeyb.docx
Please look for the following errors in this document.ErrorsKeyb.docxPlease look for the following errors in this document.ErrorsKeyb.docx
Please look for the following errors in this document.ErrorsKeyb.docx
 
Please make sure that your writers are properly writing the final re.docx
Please make sure that your writers are properly writing the final re.docxPlease make sure that your writers are properly writing the final re.docx
Please make sure that your writers are properly writing the final re.docx
 
Please identify the one sculpture from each of the following artist .docx
Please identify the one sculpture from each of the following artist .docxPlease identify the one sculpture from each of the following artist .docx
Please identify the one sculpture from each of the following artist .docx
 
Please I would like you to write a discussion with 200 words by answ.docx
Please I would like you to write a discussion with 200 words by answ.docxPlease I would like you to write a discussion with 200 words by answ.docx
Please I would like you to write a discussion with 200 words by answ.docx
 
Please identify the leadership traits, skills, and behaviors that yo.docx
Please identify the leadership traits, skills, and behaviors that yo.docxPlease identify the leadership traits, skills, and behaviors that yo.docx
Please identify the leadership traits, skills, and behaviors that yo.docx
 
Please i need a research paper about Langauge and Culture.( 1500 wor.docx
Please i need a research paper about Langauge and Culture.( 1500 wor.docxPlease i need a research paper about Langauge and Culture.( 1500 wor.docx
Please i need a research paper about Langauge and Culture.( 1500 wor.docx
 
Please help me with this program1 – Hello WorldCreate a proj.docx
Please help me with this program1 – Hello WorldCreate a proj.docxPlease help me with this program1 – Hello WorldCreate a proj.docx
Please help me with this program1 – Hello WorldCreate a proj.docx
 
PLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docx
PLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docxPLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docx
PLEASE HELP REVISE & STRUCTURENEED INTRODUCTIONANALYSISCO.docx
 

Feasibility Study of laying Trunk & Gravity main, design and c

  • 1. Feasibility Study of laying Trunk & Gravity main, design and costing At Poundbury 25th April 2021 Contents 1) Introduction 2) Investigation of routes 3) Options considered a. Justification for selection pipe routes b. Pipe design
  • 2. 4) Costs 5) Pump 6) Pressure surges 7) Conclusions 8) Appendices A. Plans and long sections (including the HGL) of all routes considered B. Design calculations C. Cost spreadsheets D. Information relevant to pump selection E. Information relevant to pressure surge protection
  • 3. 1) Introduction: Is to design two pipe system which includes pump trunk main and gravity distribution main for supplying treated drinking water to 2000 new houses at Poundbury. In view of the increased developments in the area such as private housing, retail shops, pubs, restaurants and other businesses in the area, the current water supply will not be able to sustain for the economic expansion of the town. The design is provided a trunk main route from Borton PS 59.45m AOD to Lambert’s Hill (155.7m AOD) reservoir and a gravity distribution main from Lambert’s Hill to Poundbury 110.0m AOD because the problem with the existing Dorchester water tower is at a lower level 108mAOD compared to Poundbury. The new water pipe system will be able to supply drinking water to the community and sustain the booming economy for decades to come. The design will be in line/according to the Wessex-water standards and should also be able to cater for future extension in it. Project objective: The aim is to provide a feasibility study on the pumped trunk main design and the gravity main design from the two proposed materials that is cast iron DI pipe and UPVC PE pipe. The
  • 4. proposal will access the flow rate, pipe selective diameter from industry, maximum pressure in the system, head loss in pipe and pipe design arrangement by using the following methods. Method 1: Darcy equation and Moddy Diagram Method 2: C-W equation and H-R walling ford look up tables. Project will incorporate the best suitable route design trunk main from the pump station to the reservoir and gravity main reservoir to Poundbury along with advice on the need for pressure protection in the piping system. The feasibility study will provide the most cost-effective solutions and economical design to that the project if it will be feasible prior before the approval and implementation. 2) Route Investigation: When planning pipe layout there are several constraints that must be assessed and considered as a form of site investigation. The site feasibility will evaluate the ground condition and geological factors of the surrounding are. Ground condition: According to geological map of Britain viewer: Bedrock and superficial deposits. The soil condition for the proposed pipe layout are composed of chalk material which are one of the ideal soil condition for trench pipe laying. The pipe design from trunk main and gravity main will be entirely lay on are composed of chalk, so precaution needs to be taken not to lay the pipe on other soil type that may cause geotechnical effect on the piping system. http://mapapps.bgs.ac.uk/geologyofbritain/home.html. Crossing: When preparing the design, consideration should be taken to avoid road, railway, river crossing as much as possible. Farmed
  • 5. land and private properties should be avoided but the issue with Google earth is that its very difficult to identify private property boundaries and the land used planned on the area. Any crossing will be incorporated in to the cost and reinstated to its original state. Sensitive area: Area such as scientific interests, historical monuments and wildlife sanctuary which has aesthetic beauty should be avoided completely as it may cause delay in the project due to the fact it may take years to get approval to access these areas. Areas with outstanding beauty must be integrated in the cost and restored to its original natural state. Site condition for the pipe Slope: The ground elevation must minimise crest and through as it may create pressure drop in the pipe system. Pipe access: · Avoid meandering to reduce frictional head losses (hf) in piping system. · Pipe will be laid at the depth of 0.9m to 1.3m below ground level. · Lay pipe in field to minimise cost and reduce risk such as siphon phenomenon and negative pressure development in the trunk main design. (Negative pressure develop in pipe fitting will absorb contaminants in the environment). · Install twin pipe under road and rail crossing in case one is
  • 6. damaged the other can be used as an alternative. First it will increase the installation cost, but it will be a worthwhile investment for the long term. (It to mitigate heavy civil work when pipe are damaged in the future). Hydraulic: · The right pipe size should be designed in away as the friction head losses is minimum, but the energy should be high enough along hydraulic gradient so that water will be able to flow above the house in accordance to the Wessex-Water standard(check google for more information ) . · Pump water by creating an artificial energy to carry water up the pipe to the reservoir. The energy should be above the reservoir to frictional losses of energy in the system would be accounted for as water flow in the reservoir.
  • 7. 3) Options considered: (pipe disagen ) a) Justification for selection pipe routes · Choose areas with less bends · Avoid crossing areas that can inflate the project cost · Avoid private properties/areas · Prevent frictional loss · Ensuring no stagnant water remains in the pipes for than 12 hours · Maximum pressure in pipes should be less than 60 bar · The pipe sizes diameters have a high sensitivity towards frictional loss so the right size calculation is very important to minimize loss. ( don’t use it ) b) Pipe design · Pipe material: DI and PE pipe(google ) · DI Trunk Main The objective is to design and select the appropriate pipe size for trunk main route from Borton PS to Lambert’s Hill to minimise the frictional head losses (hf).
  • 8. Calculate frictional losses (hf) in pipe flow design (trunk pumped main) by use of 2 methods: · 1ST METHOD : Darcy Equation & Moody Diagram · 2ND METHOD : C-W Equation & H-R Wallingford look up tables For selection of the appropriate pipe size the following values should be available as followed 1) Design flow rate Q=7Ml/day 2) Length of pipe L(km) and type of material: DI; Galvanised iron (normal condition) and PI; PVC 3) Start point Burton PS 59.45m AOD and end point at Lambert’s Hill 155.7m AOD 4) Static lift = 155.70 - 59.47 = 96.23m 5) Assume velocity in pipe flow 1m/s according to Wessex- water standards ( Trunk main design: Eq.1: Head-loss of pipe(hf), friction factor(f), length(l), diameter (d or D), velocity(V) & acceleration due to gravity(g). 1st Method: Darcy Equation & Moody Diagram Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Darcy Equation (Refer to Appendix B) Max pressure of total 10.71bars should be less than 16bars according to Wessex-water standards. 10.71 (Where 1m=0.098041bars) Pressure check: For min pressure in the system Min pressure in the system should be equal least 6m
  • 9. Min pressure = 6m everywhere, therefore will be installing pressure sustaining valve (PSV) closers to end point of the Reservoir where the risks is higher to experience pressure less than 6m. 2nd Method: C-W Equation & H-R Wallingford look up tables Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Colebrook-White equation (0939) (C- W) (Refer to Appendix B) Eq.9 Velocity(V), Pipe diameter(d), Hydraulic gradient(S), Effective roughness(K) and Kinematic viscosity ( (1) Step 1: Repeat 1st step from method 1: (2) Step 2: Repeat 2nd Step from method 1: and Pipe Diameter: 350mm · Gravity Main Design The objective is to design and select the appropriate pipe size for each selected gravity main routes from Lambert’s Hill to Poundbury to minimise the frictional head losses (hf). Calculate frictional losses (hf) in pipe flow design (trunk pumped main) by use of 2 methods: · 2ND METHOD : C-W Equation & H-R Wallingford look up
  • 10. tables For selection of the appropriate pipe size the following values should be available as followed a) Design flow rate Q=120 l/s b) Length of pipe L(km) and type of material: DI; Galvanised iron (normal condition) and PE; UPVC c) Start point Lambert’s Hill SR 155.70m AOD and end point at Poundbury 110.00m AOD d) Lambert’s Hill SR – (Poundbury max elevation + required delivery head) = Assume hf = 155.7 – (110.0 + 20) = 155.7 – 130 = 25.7m e) Assume velocity in pipe flow 1.0m/s according to Wessex- water standards () Gravity main design: Eq.9: Gradient Head-loss of pipe(hf) and length(L) DI and PE PIPE: Gravity Main 2nd Method: C-W Equation & H-R Wallingford look up tables: Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Darcy Equation (Refer to Appendix B) Pressure check: a) At area where pipe from ground elevation has troughs. The lowest trough: risk of high pressure 35m(standard) therefore it is recommended to install Pressure reducing valves (PRV). 3 b) There is highest risk to have max pressure to the downstream end of pie, in times of very low flow, therefore it is recommended to stall Pressure reducing valve (PRV) at the downstream end of the pipe. c) At area where pipe from ground elevation has peaks. Highest peak, risk of low pressure or even negative ones, therefore it is
  • 11. recommended to install pressure increasing valves at this point. · Pipe elements required for the routes; Calculating fitting losses: Refer to Appendix B: Table 3. Types of fittings: · Pump manifold: Roughness value for 1 manifold is K1= 1. · Swabbing chambers: ; Swabbing chambers @ every 2.5km of pipe length · Long radius bends: · In line valves: In line valves every 2km of pipe length · Air valves: one air valves needed · Isolating valves for each crossing: · In line tees for future expansion plans: · Wash outs: to clear out sediment and prevent discoloration 4. Costs: (refer appendix D) The capital expenditure calculation for CAPX and OPEX are based on input costing data available from Baro Happold. The calculation expenditure is covered for 60 years project life cycle with net present value of £1 at 6%. Trunk main/Gravity main: The cost expenditure for pipe design are from the same size and the change in project cost are affected by the length of the pipe, pipe passing through sensitive area and road/river crossing because they have a high rate £/m compared to pipe lay in field area. From the capital expenditure total cost, it clearly shows pipes which are shorter in length cost less and are more cost economic provided that the meet the design requirement with a low operation cost. · Trunk main DI pipe route 1 has the maximum CAPEX and
  • 12. OPEX cost of £5,930,207/- compare to route 4 which has the lowest CAPEX & OPEX cost of £5,580,854/- · Gravity main PE pipe route 1 has the lowest CAPEX and OPEX cost of £1,205,788/- compare to the same route 1 with DI pipe which has the CAPEX & OPEX cost of £1,240,733/-. Base on the analysis it more feasible and cost economic to select PE pipe material for the gravity main 5. Pump Selection: Pump type: 5no 200x290x280 – 81/75x5x18.5=100HW as per appendix D · The primary reason for not choosing less pump is that at the beginning the cost of installation will be less but the power out put is high, thus it will cause a high operation cost as it require more energy to operate. That is why it is not feasible to consider series 3no to 4no and any formation with high power output. It is more advisable to consider a more cost economic pump installation in series like 5m pump or 6pump which has the lower power output of 100KW but if there are less pump in series that produces the same power out put of 100KW or less it might be considered in the design. As a result, it is more economical to select the 5m.200x290x280 – with power output of 100KW. Pump selection: by appendix D The selected type of pump that will be used is an Armstrong 4300 pump with specific spec. Curve no: PT113-1-1-1500 Series: 4300 Starline Size: 200-290 RPM: 1500 Power: 81/75x5x18.5=100KW Efficiency: 85%
  • 13. Pump in series: 5no.200x290x280. The operating pump: The pump system in series have been designed in by using the system curve and by looking at the point where the performance curve and system curve intercept. This is the point that define that the pump are suitable for the design. (Operating point is the point where system curve and operating curve cross.) 6. Pressure surge: (Refer to appendix E) Is the sonic velocity, stiffness and fluid in the piping system which the roughness depends on time and the materials used. If the materials have more resistance to velocity, therefore any change in pressure and that will create a pressure surge in the pipe. Pressure surge consequence are fitting failure, pipe bursting and pump damage. The graphs in appendix E represent pressure in pipe from two pipe size 350 and 400mm and from two different materials (D1 and PE). · D1 pipe: Pressure surge: 350mm pipe (ps-sr) Node1: The closer the water nears a valve changes the stronger the pressure surge and it happens along the full length of the pipe. The pressure rises from 90(m) up to 184(m) then, down to 40(m). This happens consistence across the internal length of the pipe when the pressure surge phenomenon to place. More protection will be need to Node1 than to Node10. Node1 is more likely to be from pump to reservoir and vice versa. Node3 & 6: The pipe system exerts pressure surge phenomenon but not as intense as in Node1. In Node3 the pressure rises up
  • 14. during a period of time until it reaches 162max and drop to near zero, where as in Node 6 its maximum rise is 130m then i t drops to 60 and stable for a period of time until it drop to -20. Node 10: The pressure changes but does not happen through the entire length of the pipe. It happens as a spick as the pressure rise up from 10(m) to 90(m). It only happens at a single poi nt (Need less protection than Node1). In Node 10 the pressure takes longer period to form compared to Node 1. · D1=400mm: Model: Has similar effect as in D1350mm (the maximum pressure is near 150m and minimum is around -30(m). Node3 & 6: Both pipe system in general experiences pressure surge. Node 3 rise up to nearly 140(m) and has a minimum pressure loss below -40(m) which equal to -3.9 bar which is below ˂6m. Node 6 has similar effect. Therefore both pipe system will require pressure increasing valves at the lowest point. Node 10: Same pressure surge as the Note 10 exert in D1 350m only difference is the maximum and minimum. · General: The D1 350mm experience high pressure surge than in D1 400mm at different flow rates while D1 400mm experience lower pressure surge than in D1 350mm. That means that the size of pipe with different flow rates will experience pressure surge differently but the comparison between D1 pipe with PE pipe is that the PE has a high resistance to pressure surge due to its elastic and plasticity of UPVC. 7. Conclusion To conclude the design analysis using 2nd Method: C-W Equation & H-R Wallingford look up tables to assess the flow rate, gradient, pipe size, frictional loss and maximum powers
  • 15. between DI and PE pipe along with capex and opex cost expenditure: Trunk main pipe analysis shows that the pipe with the shortest length and less crossing are more feasible and economically viable to be used for this design. Trunk main route selection are mostly similar, but its advisable to select the less cost effective that have less crossing and bending to minimize frictional head loss. Gravity main: These two types of material DI and PE does not have much difference in comparison, when analysing route with the same length the only issue that differs is the velocity and retention time between them. PI material is more cost economic and durable. In additional it has a greater resistance to pressure surge compared to DI pipes. More thorough studies are needed to determine the best optimal design for route selection. On a final note, the feasibility assessment will help to identify the best route that is more cost effective and sustainable and environmentally friendly. The pipes should be laid and tested in accordance with the manufacture’s instructions and the Town and Country Planning Regulations. 8 Appendix A: Plans and long section Trunk Main Fig1: Route 1.Photo from Google [email protected] Google Fig2: Route 2.Photo from Google [email protected] Google Fig3: Route 3.Photo from Google [email protected] Google Fig4: Route 4.Photo from Google [email protected] Google
  • 16. Fig5: Route 5.Photo from Google [email protected] Google Gravity Main Fig6: Route 1.Photo from Google [email protected] Google Fig7: Route 2.Photo from Google [email protected] Google Fig8: Route 3.Photo from Google [email protected] Google Appendix B. Calculation
  • 17. Pump Trunk Main Eq.1: Head-loss of pipe(hf), friction factor(f), length(l), diameter (d or D), velocity(V) & acceleration due to gravity(g). DI Pipe: Trunk Main Route 1 1st Method: Darcy Equation & Moody Diagram Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Darcy Equation 1) Step 1: Design flow rate; Convert Eq.2: 2) Step 2: Assumed velocity in pipe 1m/s; Calculate area of pipe and pipe diameter We must assume the velocity because we have not designed the trunk-main and we do not have all the value in the system. i) Eq.3: Area=Flow rate/Velocity, Pipe Area(A)= ii) Pipe Diameter: Eq.4: Pipe diameter= The possible D=0.321m = 321mm From industry DI pipe: Possible pipe 300mm DI pipe or 350mm DI pipe Repeat Step 2: Pipe Diameter: 350mm Real Velocity(V): Eq.2 3) Step 3: Calculate Reynolds number (Re) Kinematic viscosity (=1.14 (at typical value ) Eq.5 4) Step 4: Table 38. Recommended roughness values (K).
  • 18. i) Galvanise iron-good condition K=0.06 Eq.6 K/d=0.06/350= ii) Use Moody diagram to find friction factor(f) from k-value Moody diagram F=0.0044 iii) Therefore, frictional head losses (hf). Eq.1 The total hf losses due to pipe flow are hf=12.047m when selecting DI pipe d=350mm. Disregard the DI pipe d=300m has it has a higher frictional head loss of hf=13.416m. Route checks Last checks to make sure the route is a good design: (1) Velocity check: Fist assumed V=1m/s but re-calculated V= 0.842m/s Check V=0.842m/s against Wessex-water standards V=0.842m/s is less than 2m/s (2) Retention time (RT). Calculate as followed: Pipe Area (A), Length of pipe (L)=6630m and Velocity (V)=0.842m/s Eq.7 RT = L/V = 6630/0.842 = Check RT=2h19mins against wassex-water standards. RT should be less than 12hours (3) Pressure check: For max pressure in the system.
  • 19. Calculated Max pressure by summing up the following values: i) Static lift = 155.70 - 59.45= 96.25m ii) Freeboard= 0.5m iii) Fitting losses = 0.398 (see appendix xx) iv) hf calculation from Darcy Method or C-W and look-up tables. hf=12.047m v) In total; Max pressure: Eq.8 Max pressure= Static lift+ Freeboard+ Fitting losses+ hf Max pressure of total 10.71bars should be less than 16bars according to Wessex-water standards. 10.71 (Where 1m=0.098041bars) (4) Pressure check: For min pressure in the system Min pressure in the system should be equal least 6m Min pressure=6m everywhere, therefore will be installing pressure sustaining valve (PSV) closers to end point of the Reservoir where the risks is higher to experience pressure less than 6m. DI Pipe: Trunk Main Route 1 2nd Method: C-W Equation & H-R Wallingford look up tables Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Colebrook-White equation (0939) (C- W) Eq.9 Velocity(V), Pipe diameter(d), Hydraulic gradient(S), Effective roughness(K) and Kinematic viscosity ( (3) Step 1: Repeat 1st step from method 1:
  • 20. (4) Step 2: Repeat 2nd Step from method 1: and Pipe Diameter: 350mm (5) Step 3: (a) Table 38. Recommended roughness values (K). Galvanise iron-good condition K=0.06 (b) Table 15 – HR Wallingford table for K=0.06, Pipe size 350mm and Q=0.081 Q1=0.079, HG1=0.00160…………………………….. (V=0.819m/s) Q2=0.081, HG2=0.00170…………………………….. (V=0.846m/s) Real: Q =0.081, HG = …………………………….. (V=0.842m/s) Linear interpolation gives following equation: Eq:10……….. = 0.0017 Energy losses per meter length of pipe(hf) where then length. Therefore, total losses hf = 6630 x 0.0017 = 11.271m Route checks Last checks to make sure the route is a good design: (1) Velocity check: Fist assumed V=1m/s but re-calculated V= 0.842m/s Check V=0.842m/s against Wessex-water standards V=0.842m/s is less than 2m/s (2) Retention time (RT). Calculate as followed: Pipe Area (A), Length of pipe (L)=6630m and Velocity (V)=0.842m/s
  • 21. Eq.7 RT = L/V = 6630/0.842 = Check RT=2h18mins against wassex-water standards. RT should be less than 12hours (3) Pressure check: For max pressure in the system. Calculated Max pressure by summing up the following values: i) Static lift = 155.70 - 59.45= 96.25m ii) Freeboard= 0.5m iii) Fitting losses = 0.398 (see appendix xx) iv) hf calculation from Darcy Method or C-W and look-up tables. hf=11.271m v) In total; Max pressure: Eq.8 Max pressure= Static lift+ Freeboard+ Fitting losses+ hf Max pressure of total 10.63bars should be less than 16bars according to Wessex-water standards. 10.63 (Where 1m=0.098041bars) (4) Pressure check: For min pressure in the system Min pressure in the system should be equal least 6m Min pressure=6m everywhere, therefore will be installing pressure sustaining valve (PSV) closers to end point of the Reservoir where the risks is higher to experience pressure less than 6m.
  • 22. Gravity Main Design Eq.9: Gradient Head-loss of pipe(hf) and length(L) DI PIPE: Gravity Main Route 1 2nd Method: C-W Equation & H-R Wallingford look up tables: Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Darcy Equation i) Step 1: Design flow rate; Convert ii) Step 2: Assumed velocity in pipe 1m/s; Calculate area of pipe and pipe diameter a) Eq.3: b) Pipe Diameter: Eq.4: Pipe diameter= The possible D=0.391m = 391mm iii) Step 3: Gravity Main Route 1: From industry DI pipe: Possible pipe 350mm, 400mm or 450mm Table 38. Recommended roughness values (K)=0.06 good condition a) Pipe length L=3040m, hf=25.7m, Real: Q= , HG=0.00845 &
  • 23. D=0.391m From Table 1: HR Wallingford table Pipe Size mm Gradient HG Assume Gradient HG Flow rate Q(m^3/s) Need Q(m^3/s) Reject 350 0.0080 0.0085 0.184 0.120 0.0085 0.190 Do not Reject 400 0.0080 0.0085 0.262 0.120 0.0085 0.270 Reject 450 0.0080
  • 24. 0.0085 0.352 0.120 0.0085 0.368 (c) Table 15 – HR Wallingford table. D:350mm Q1 = 0.118, HG1 = 0.00340 Q2 = 0.121, HG2 = 0.00360 Real: Q = 0.120, HG = … Linear interpolation gives following equation: Eq:10……….. = 0.00352 (The actual Q=0.120 and actual HG=0.00352 is less than the initial assumed HG=0.00845) Energy losses per meter length of pipe(hf) where then length 3040m Therefore, total losses hf = 3040 x 0.00352 = 10.70m Route checks Last checks to make sure the route is a good design:
  • 25. (1) Velocity check: Fist assumed V=1m/s but re-calculated Vm/s Check Q=0.120/s and D=0.350m ; V=1.25m/s is less than 1.5m/s (2) Retention time (RT). Calculate as followed: Length of pipe (L)=3040m and Velocity (V)=1.25m/s Eq.7 RT = L/V = 3040/1.25 = Check RT=1.06hrs against Wassex-water standards. RT should be less than 12hours (3) Pressure check: 5 At area where pipe from ground elevation has troughs. The lowest trough: risk of high pressure 35m(standard) therefore it is recommended to install Pressure reducing valves (PRV). 3 6 There is highest risk to have max pressure to the downstream end of pie, in times of very low flow, therefore it is recommended to stall Pressure reducing valve (PRV) at the downstream end of the pipe. 7 At area where pipe from ground elevation has peaks. Highest peak, risk of low pressure or even negative ones, therefore it is recommended to install pressure increasing valves at this point. PE PIPE: Gravity Main Route 2 2nd Method: C-W Equation & H-R Wallingford look up tables: Calculation of frictional (head) losses hf in an existing pumped main pipe flow by use of Darcy Equation (1) Step 1: Design flow rate; Convert Eq.9: Gradient =
  • 26. (2) Step 2: Assumed velocity in pipe 1m/s; Calculate area of pipe and pipe diameter a) Eq.3: b) Pipe Diameter: Eq.4: Pipe diameter= The possible D=0.396.9m = 396.9mm (from industry) (3) Step 3: Gravity Main Rout 1: From industry PE pipe: Possible pipe: 396.9mm Table 38. Recommended roughness values (K)=0.03 good condition From Table 14: K=0.03, Q=, HG=0.0082 and range 375mm & 400mm. Eq.9: Gradient = 25.7/3140 = 0.00818 b) Pipe length L=3140m, hf=25.7m, Real: Q= & HG=0.00818 c) From Table 2: HR Wallingford table Pipe Size D/mm Gradient HG Assume Gradient HG Flow rate Q(m^3/s) Need Q(m^3/s) Reject 375 0.0080 0.0085 0.229 0.120 0.0085
  • 27. 0.237 Reject 400 0.0080 0.0085 0.272 0.120 0.0085 0.280 (d) Eq:11……….. (e) HG1 = 0.00180: Q1 = 0.103, Q2 = 0.122: E Eq:11 Q=0.1196 HG2 = 0.00190: Q1 = 0.106, Q2 = 0.126: E Eq:11 Q=0.1235 (f) Cal for HG value for D:396.9mm Q1 = 0.1196, HG1 = 0.00180 Q2 = 0.1235, HG2 = 0.00190 Real: Q = 0.120, HG = … Linear interpolation gives following equation: Eq:10……….. = 0.00181 (The actual Q=0.120 and actual HG=0.00181 is less than the initial assumed HG=0.00818)
  • 28. Energy losses per meter length of pipe(hf) where then length 3040m Total losses hf = 3140 x 0.00181 = 5.68m Route checks Last checks to make sure the route is a good design: (1) Velocity check: Fist assumed V=1m/s but re-calculated Vm/s: Check Q=0.120/s and D=0.3969m ; V=0.97m/s is less than 1.5m/s (2) Retention time (RT). Calculate as followed: Length of pipe (L)=3140m and Velocity (V)=1.25m/s Eq.7 RT = L/V = 3140/0.97 = Check RT=1.06hrs against Wassex-water standards. RT less than 12hours (3) Pressure check: 8 At area where pipe from ground elevation has troughs. The lowest trough: risk of high pressure 35m(standard) therefore it is recommended to install Pressure reducing valves (PRV). 3 9 There is highest risk to have max pressure to the downstream end of pie, in times of very low flow, therefore it is recommended to stall Pressure reducing valve (PRV) at the downstream end of the pipe. 10 At area where pipe from ground elevation has peaks. Highest peak, risk of low pressure or even negative ones, therefore it is recommended to install pressure increasing valves at this point.
  • 29. Calculate of frictional losses in pipe fitting Table3: Fitting Losses for Trunk Main and Gravity Main
  • 30. Appendix C: Cost spreadsheet Capital Expenditure Pump Main Appendix D: Information for PUMP Selection
  • 31. Pumps for UK civil engineering application licensed to be used to pump portable water: 4300 Fig9: From lecture: Pump selection summary Fig10: From lecture: Selected pump: 5 no. 200 x 290 x 280 Appendix E: Pressure surge protection: Fig11.a: From lecture Fig11.b: From lecture Fig11.c : From lecture Reference: · http://armstrongfluidtechnology.com/en-gb/products-and- services/heating-and-cooling/commercial-pumps · Wessex Water DESIGN STANDARD DS 643 2008 Water Supply Pressure Pipelines [Online]
  • 33. Swabbing chambers @ every 2.5km of pipe length K=0.24 No. Long radius bend K=0.10 (0.10 x X=K3) In line valves every 2km of pipe length K=0.12 (0.12 x X=K4) 1 Air-valves K=0.05 (0.05 x 1=K4) Isolatating valves for each crosing K=0.70 (Road+River)x0.70=K6 1 in line tees for future expension K=0.12 (0.12 x 1=K7) 1 wash-out K=0.59 (0.59 x 1=K7) Total K values K1K2K3K4K5K6K7K8ΣK 1Route 16.6310.480.70.360.057.70.120.5911.000.7090.398 2Route 26.6410.480.90.360.057.00.120.5910.500.7090.379 3Route 36.2910.480.70.360.056.30.120.599.600.7090.347
  • 34. 4Route 45.7910.480.50.240.056.30.120.599.280.7090.335 5Route 55.9210.480.70.240.056.30.120.599.480.7090.343 Gravity main 1DI: G.main 13.0400.240.40.120.052.80.120.594.321.5630.344 1PE: G.main 13.0400.240.40.120.052.80.120.594.320.9410.207 2PE: G.main 23.1400.240.50.120.052.80.120.594.420.9410.212 3PE: G.main 33.1300.240.40.120.052.80.120.594.320.9410.207 Type of fitting with Roughness value (K)Real Velocity 0.842m/s ( V^2) Fitting losses/m =ΣK(V^2/2g) Trunk Main PE:0.97&DI:1.25 m/s