SlideShare a Scribd company logo
1 of 4
Download to read offline
ELP Arbitration Update
© Economic Laws Practice 2022
SUPREME COURT: ONCE STAMP DUTY HAS BEEN PAID, THE ISSUE OF WHETHER THE STAMP
DUTY PAID WAS INSUFFICIENT OR APPROPRIATE IS A QUESTION TO BE ANSWERED AT A
LATER STAGE AND NOT UNDER SECTION 11(6) OF THE ARBITRATION AND CONCILIATION
ACT, 1996
Intercontinental Hotels Group (India) Private Limited & Anr. v. Waterline Hotels Private Limited1
BACKGROUND OF DISPUTES
▪ Intercontinental Hotels Group (India) Private Limited (Petitioner No.1), Intercontinental Hotels Group (Asia-Pacific)
Pvt Ltd. (Petitioner No. 2) (collectively referred to as the Petitioners) and the Respondent entered into a Hotel
Management Agreement (HMA) to run and operate a hotel. The HMA inter alia provided the rights and obligations
of the parties for a ten-year period and provided for subsequent renewals. Additionally, the HMA provided for
payments to be made by the Respondent to the Petitioners towards various fees including ‘investment management
fee’, ‘technology service fee’. The Petitioners contended that the Respondent failed to fulfil the said payment
obligations. Further, the Respondent addressed an email dated October 12, 2018 (Notice) and terminated the HMA.
In response to the Notice, the Petitioners stated that unilateral termination of the HMA was invalid.
▪ Aggrieved by the Notice, the Petitioners invoked section 9 of the Arbitration and Conciliation Act, 1996 (Act) and
sought interim relief before the High Court of Karnataka (High Court). By an ad-interim order dated October 23, 2018,
the High Court directed the Respondent not to evict the Petitioners from the Hotel without due process of law until
further orders (Order). The Petitioners alleged that the Respondent failed to comply with the Order. Subsequently,
the Petitioners invoked the arbitration clause under the HMA and issued a notice of arbitration dated January 21,
2019 (Arbitration Notice). In response to the Arbitration Notice, the Respondent allegedly stated that the Arbitration
Notice was not a notice of arbitration and did not merit a response.
▪ The arbitration clause inter alia provided the procedure for constitution of the tribunal. Pursuant to the response
received from the Respondent, the Petitioners requested Singapore International Arbitration Centre to suggest
names of sole arbitrators or invoke the mechanism of appointing a three-member tribunal, as per the HMA, in the
event the Respondent did not agree to the name of a sole arbitrator. Although SIAC issued a notice dated February
1
Judgement dated 25 January 2022 in Arbitration Petition (Civil) No. 12 of 2019
ELP Arbitration: Update
ELP Arbitration Update
© Economic Laws Practice 2022
15, 2019 to the Respondent for the appointment of a suitable arbitrator, in response, the Respondent stated the
Arbitration Notice was defective and not curable. Aggrieved by the Respondent’s refusal to appoint an arbitrator, the
Petitioners filed the present petition under sections 11(6) read with 11(12)(a) of the Act to constitute the Tribunal,
before the Supreme Court (Section 11 Proceedings).
SUBMISSIONS OF THE PARTIES
▪ In the Section 11 Proceedings, the Respondent filed a counter-affidavit dated July 24, 2019 and contended that the
HMA which contained the arbitration agreement was an unstamped document. The Respondent submitted that, in
light of Garware Wall Ropes2
, an agreement which is not duly stamped cannot be relied on or acted upon unless the
unstamped document is impounded, and the applicable stamp duty/penalty is assessed and paid. On the other hand,
the Petitioners submitted that pursuant to the warranty clause in the HMA, the Respondent was obligated to ensure
that the agreement would be legally valid in India.
▪ The Petitioners filed an application for permission to file additional documents on June 23, 2020 (Application). By the
said Application, the Petitioners inter alia (i) stated that they had taken the requisite steps to pay the applicable stamp
duty along with the penalties that may be accruable under Karnataka Stamp Act, 1957 (Karnataka Stamp Act) on a
without prejudice basis; (ii) pointed out that the HMA was a services agreement, which would be covered under the
residuary provisions, i.e., Article 5(j) of the Karnataka Stamp Act; and (iii) requested the Supreme Court to appoint an
arbitrator.
▪ Objecting to the Application, the Respondent, submitted that by a letter dated February 28, 2020, the Petitioners had
previously stated that the HMA was classified as a “bond”. The Respondent further contended that (i) the Petitioners
had not been granted permission to file additional stamp papers under Article 5(j) of the Karnataka Stamp Act; (ii) the
Petitioners have not paid the proper stamp duty and penalty under the Karnataka Stamp Act; and (iii) the Petitioners
could not have self-adjudicated the proper stamp duty and penalty payable.
FINDINGS OF THE COURT
▪ The issue which arose for consideration before the Supreme Court was whether the issue of insufficient stamping
indicated an unworkable arbitration agreement under section 11(6) of the Act.
Reiterated the view in Vidya Drolia that ‘When in doubt, do refer’
▪ The Supreme Court concurred that Vidya Drolia3
established that (i) courts have a very limited jurisdiction under
section 11(6) of the Act; (ii) courts are to take a ‘prima facie’ view on issues relating to the existence of arbitration
agreements; (iii) issues of arbitrability/validity were usually to be adjudicated upon by arbitrators, with the only narrow
exception carved out there being that courts could adjudicate to ‘cut the deadwood’; and (iv) the ‘watch word’ for the
courts is ‘when in doubt, do refer’.
The Supreme Court should ensure that arbitrations are carried on unless there is ‘deadwood’
▪ The Supreme Court examined Vidya Drolia’s affirmation of Garware Wall Ropes4
, where it had been held that an
arbitration agreement would not “exist” until the arbitration agreement had been duly stamped. In NN Mercantile5
,
the Supreme Court took a different view from its coordinate bench in Vidya Drolia6
and inter alia, held that (a) the
doctrine of separability would override the concern under respective stamp acts; (b) any concerns of non-stamping or
under stamping would not affect the validity of the arbitration agreement. [For a further read, please click here for
ELP’s earlier updates on NN Global Mercantile and Vidya Drolia.]
▪ The Supreme Court held that while there is a need for a larger bench to settle the jurisprudence, considering the “time
sensitive” nature of arbitration matters, all matters at pre-appointment stage could not be left hanging until the larger
bench settled the issue. In view of the same, Supreme Court held that until the larger bench decided on the interplay
between sections 11(6) and 16 of the Act, the Supreme Court should ensure that arbitrations are carried on unless the
issue before the Supreme Court patently indicates the existence of ‘deadwood’.
2 Garware Wall Ropes v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209
3 Vidya Drolia and Others v. Durga Trading Corporation, 2020 SCC OnLine SC 1018.
4 Garware Wall Ropes v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209
5 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13;
6
Vidya Drolia and Others v. Durga Trading Corporation, 2020 SCC OnLine SC 1018;
Vidya Drolia (at paragraph 92) had affirmed paragraphs 22 and 29 of Garware Wall Ropes, which in turn had followed the observations made in SMS
Tea Estates. However, in NN Global Mercantile, the Supreme Court overruled SMS Tea Estates. The correctness of the said paragraph in Vidya Drolia
was therefore doubted in NN Mercantile.
ELP Arbitration Update
© Economic Laws Practice 2022
The warranty provided by the Respondent in the HMA give rise to deeper issues which can be resolved at a later
stage. Therefore, the issue of insufficient stamping is not ‘deadwood’.
▪ The Supreme Court considered the Petitioners’ contention that the warranty clause in the HMA provided that the
Respondent was obligated to ensure that the agreement would be legally valid in India. The Supreme Court culled out
three issues which could be adjudicated at a later stage, i.e.: (a) whether the Respondent is estopped from raising the
contention of unenforceability of the HMA; (b) whether the HMA is insufficiently or incorrectly stamped; and (c) the
extent to which the Petitioners could rely on the Respondent’s warranty. The Supreme Court held that the foregoing
aspects demonstrated that the issue of insufficient stamping was not a matter of ‘deadwood’.
The Supreme Court did not delve into the adequacy of the stamp duty paid.
▪ The Supreme Court observed that to determine whether adequate stamp duty had been paid in terms of the Karnataka
Stamp Act, the court would need to examine (i) the nature of the substantive agreement, (ii) the nature of the
arbitration agreement; and (iii) whether a separate stamp fee is payable.
▪ Referring to Vidya Drolia, the Supreme Court held that the issue of ‘existence’ and/or ‘validity’ of the arbitration clause,
would not be needed to be looked into herein, as “payment of stamp duty, sufficient or otherwise, has taken place”.
▪ The Supreme Court concluded that “it was clear that stamp duty had been paid. Whether it was insufficient or
appropriate is a question to be answered at a later stage as the Court could not review this issue under section 11(6).
If it was a question of complete non stamping, then the Court, might have had an occasion to examine the concern
raised in N. N. Global, however, this case, is not one such scenario.”
CONCLUSION AND ANALYSIS
In view of the above, the Supreme Court referred the matter to arbitration and appointed a sole arbitrator to
adjudicate the issues.
Scope of intervention under Section 11(6) of the Act
The Supreme Court held that the question regarding the insufficiency of the stamp duty did not have to be considered
under section 11(6). The fact that stamp duty was paid, irrespective of whether the duty was insufficient or inadequate,
weighed in on the court. Therefore, once stamp duty is paid on the contract, irrespective of whether the stamp duty
is proper or improper, the same shall not be an issue for consideration under section 11(6) of the Act.
Different approach from N. N. Global Mercantile
In N.N. Global Mercantile, the Supreme Court held that the phrase “duly stamped” “implies that the instrument must
be stamped with the requisite amount of duty determined in accordance with the Schedule to the Act7
. If it is found
that the instrument is not stamped, or inadequately stamped, it is mandated by law to impound the instrument, and
deal with it in accordance with the provisions of the Stamp Act.”8
Then, the Supreme Court observed three scenarios
under which the authority could exercise the power of impounding the instrument albeit under the Maharashtra
Stamp Act. One of the scenarios being - the High Court, or the Supreme Court, as the case may be, while exercising
jurisdiction under Section 11, would “impound the substantive contract which is either unstamped or inadequately
stamped, and direct the parties to cure the defect before the arbitrator/tribunal can adjudicate upon the contract.” 9
Taking a different path from this view, in the present case, the Supreme Court did not examine the nature of the
contract and consequently, did not consider whether the HMA was duly stamped. Further, in exercise of its jurisdiction
under section 11, the apex court did not impound the substantive contract which was purportedly inadequately
stamped nor did it pass any directions to verify the assessment of stamp duty. The payment of stamp duty was
sufficient to satisfy the Supreme Court for the purpose of section 11(6) of the Act, irrespective of whether the stamp
duty was a proper/ appropriate assessment.
The apex court acknowledged that issues of substantive rights and obligations under the HMA would require
adjudication at a later stage. However, it did not clarify whether the adjudication of rights and obligations of the main
contract could proceed before complying with the mandatory provisions of the relevant stamp act. On the other hand,
in N.N. Global Mercantile, the Supreme Court held that “there is no legal impediment to the enforceability of the
arbitration agreement, pending payment of stamp duty on the substantive contract. The adjudication of the rights and
7 Black Pearl Hotels (P) Ltd. v. Planet M. Retail Ltd., (2017) 4 SCC 498.
8 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 10.5]
9
N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 36.2]
ELP Arbitration Update
© Economic Laws Practice 2022
obligations under the work order or the substantive commercial contract would, however, not proceed before
complying with the mandatory provisions of the Stamp Act.” 10
The Supreme Court, in the present judgement, has observed that it is only where a document is completely unstamped
that courts might have an occasion to examine the concerns raised in N.N. Global Mercantile and that the present case
was not one such scenario, since the Petitioners had paid an amount towards stamp duty. The Supreme Court
therefore distinguishes the applicability of N.N. Global Mercantile by seemingly drawing a distinction between
complete non-payment of stamp duty and part payment of stamp duty (even if insufficient). However, the
consequences envisaged in N.N. Global Mercantile are the same irrespective of whether there was complete non-
payment of stamp duty or inadequate payment of stamp duty i.e. as mentioned above, the findings were with respect
to an instrument/ contract that is unstamped “or inadequately stamped”. Hence, N.N Global Mercantile did not
contemplate impounding of instruments solely in cases where there is a question of complete non-stamping.
Further, although in the present judgement the Supreme Court declined to examine the nature of the substantive
contract to determine the adequacy of the duty paid, it would be worthwhile to note the Supreme Court’s observations
in Black Pearl Hotels11
. In Black Pearl Hotels the nature of the substantive agreement containing an arbitration clause
was disputed. The apex court in that matter held that the determination of the nature of an instrument is a judicial
function and ought to be determined by the court at the stage of appointment of an arbitrator under section 11 of the
Act. There was therefore, a precedent that allowed courts to pass a ruling on the nature of a document in proceedings
under section 11 of the Act, that was available to this Court.
Way Forward
The way forward in similar matters where allegations of inadequate payment of stamp duty are levelled in proceedings
under Section 11 of the Act is likely to change. In the present judgement, the Supreme Court has held that the question
of adequacy of stamp duty is not be delved into at the stage of proceedings under section 11 and consequently left it
to be determined at a later stage without passing any directions as to the impoundment of the underlying contract. In
doing so, has the Supreme Court opened doors for applicants in pending applications under section 11 (6) of the Act?
In similar situations where the arbitration agreement is in a contract, applicants may seek constitution of the tribunal
once payment of any amount of stamp duty is made (irrespective of whether the stamp duty is proper/adequate).
The present judgement has been delivered by a bench that is equal in strength to N.N. Global Mercantile and Vidya
Drolia. Therefore, the larger bench constituted pursuant to the reference made in N.N. Global Mercantile ought to
clarify the different views adopted in these three judgements and the road ahead.
We hope you have found this information useful. For any queries/clarifications please write to us at insights@elp-in.com
or write to our authors:
Ria Dalwani, Senior Associate – Email – riadalwani@elp-in.com
Sonia Dasgupta, Associate – Email – soniadasgupta@elp-in.com
Disclaimer: The information provided in this update is intended for informational purposes only and does not constitute legal opinion or advice. Readers
are requested to seek formal legal advice prior to acting upon any of the information provided herein. This update is not intended to address the
circumstances of any particular individual or corporate body. There can be no assurance that the judicial/quasi-judicial authorities may not take a position
contrary to the views mentioned herein.
10 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 26]
11
Black Pearl Hotels (P) Ltd. v. Planet M. Retail Ltd., (2017) 4 SCC 498.

More Related Content

Similar to ELP Arbitration: Update - Intercontinental Hotels Group (India) Private Limited

World Journal of Arbitration
World Journal of ArbitrationWorld Journal of Arbitration
World Journal of Arbitration
Ritesh Singh
 
Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005
Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005
Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005
chithra venkatesan
 
Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881
merenjithr
 
Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881
merenjithr
 
Arbitration Presentation2009
Arbitration Presentation2009Arbitration Presentation2009
Arbitration Presentation2009
apdh1312
 

Similar to ELP Arbitration: Update - Intercontinental Hotels Group (India) Private Limited (20)

Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
 
calcutta-hc-443606.pdf
calcutta-hc-443606.pdfcalcutta-hc-443606.pdf
calcutta-hc-443606.pdf
 
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTUREADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
 
UK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletterUK Adjudicators April 2021 newsletter
UK Adjudicators April 2021 newsletter
 
UK Adjudicators March 2019 newsletter
UK Adjudicators March 2019 newsletterUK Adjudicators March 2019 newsletter
UK Adjudicators March 2019 newsletter
 
Assignment question in fulfillment of Business Law Paper for MBA Program- OPe...
Assignment question in fulfillment of Business Law Paper for MBA Program- OPe...Assignment question in fulfillment of Business Law Paper for MBA Program- OPe...
Assignment question in fulfillment of Business Law Paper for MBA Program- OPe...
 
Contemporary issues of banking law ppt
Contemporary issues of banking law pptContemporary issues of banking law ppt
Contemporary issues of banking law ppt
 
World Journal of Arbitration
World Journal of ArbitrationWorld Journal of Arbitration
World Journal of Arbitration
 
Recent IBC Judgments (July, 2021 to August, 2021)
Recent IBC Judgments (July, 2021 to August, 2021)Recent IBC Judgments (July, 2021 to August, 2021)
Recent IBC Judgments (July, 2021 to August, 2021)
 
Recent judgments under IBC
Recent judgments under IBC Recent judgments under IBC
Recent judgments under IBC
 
Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005
Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005
Popat and kotecha_property_vs_state_bank_of_india_staff_..._on_29_august,_2005
 
Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881
 
Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881
 
Arbitration Presentation2009
Arbitration Presentation2009Arbitration Presentation2009
Arbitration Presentation2009
 
December 2018 newsletter kp
December 2018 newsletter kpDecember 2018 newsletter kp
December 2018 newsletter kp
 
Adr ppt
Adr pptAdr ppt
Adr ppt
 
ADR
ADRADR
ADR
 
Lawweb.in when court should not set aside arbitration award
Lawweb.in when court should not set aside arbitration awardLawweb.in when court should not set aside arbitration award
Lawweb.in when court should not set aside arbitration award
 
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
DIGITAL-SECURITY-SERVICES-LTD-AND-MICHAEL-PEETS-vs-NEVIS-INTERNATIONAL-BANK-T...
 
Implied terms
Implied termsImplied terms
Implied terms
 

More from Economic Laws Practice

More from Economic Laws Practice (20)

Export Control Law Firm_ Customs Law Firm_ SCOMET assistance_ BIS assistance.pdf
Export Control Law Firm_ Customs Law Firm_ SCOMET assistance_ BIS assistance.pdfExport Control Law Firm_ Customs Law Firm_ SCOMET assistance_ BIS assistance.pdf
Export Control Law Firm_ Customs Law Firm_ SCOMET assistance_ BIS assistance.pdf
 
Maximizing Legal Compliance in Hospitality: ELP Law's Tailored Solutions
Maximizing Legal Compliance in Hospitality: ELP Law's Tailored SolutionsMaximizing Legal Compliance in Hospitality: ELP Law's Tailored Solutions
Maximizing Legal Compliance in Hospitality: ELP Law's Tailored Solutions
 
"Excellence in Hospitality Law: Economic Laws Practice - Premier Hospitality
"Excellence in Hospitality Law: Economic Laws Practice - Premier Hospitality"Excellence in Hospitality Law: Economic Laws Practice - Premier Hospitality
"Excellence in Hospitality Law: Economic Laws Practice - Premier Hospitality
 
Efficient Tax Planning: Economic Laws Practice - Your Path to Financial Succe...
Efficient Tax Planning: Economic Laws Practice - Your Path to Financial Succe...Efficient Tax Planning: Economic Laws Practice - Your Path to Financial Succe...
Efficient Tax Planning: Economic Laws Practice - Your Path to Financial Succe...
 
COP28-Key-Takeaways-and-Implications.pdf
COP28-Key-Takeaways-and-Implications.pdfCOP28-Key-Takeaways-and-Implications.pdf
COP28-Key-Takeaways-and-Implications.pdf
 
ELP-Tax-Alert-SC-ruling-on-MFN-clause-.pdf
ELP-Tax-Alert-SC-ruling-on-MFN-clause-.pdfELP-Tax-Alert-SC-ruling-on-MFN-clause-.pdf
ELP-Tax-Alert-SC-ruling-on-MFN-clause-.pdf
 
Competition-Newsletter-Q3-of-2023-Final.pdf
Competition-Newsletter-Q3-of-2023-Final.pdfCompetition-Newsletter-Q3-of-2023-Final.pdf
Competition-Newsletter-Q3-of-2023-Final.pdf
 
Climate-newsletter.pdf
Climate-newsletter.pdfClimate-newsletter.pdf
Climate-newsletter.pdf
 
BIS newsletter – September Edition.pdf
BIS newsletter – September Edition.pdfBIS newsletter – September Edition.pdf
BIS newsletter – September Edition.pdf
 
TradeWatch-Weekly-Bulletin-October-9-2023.pdf
TradeWatch-Weekly-Bulletin-October-9-2023.pdfTradeWatch-Weekly-Bulletin-October-9-2023.pdf
TradeWatch-Weekly-Bulletin-October-9-2023.pdf
 
TradeWatch-Weekly-Bulletin-September-25-2023.pdf
TradeWatch-Weekly-Bulletin-September-25-2023.pdfTradeWatch-Weekly-Bulletin-September-25-2023.pdf
TradeWatch-Weekly-Bulletin-September-25-2023.pdf
 
Business-Expenditure-The-Chamber-Journal.pdf
Business-Expenditure-The-Chamber-Journal.pdfBusiness-Expenditure-The-Chamber-Journal.pdf
Business-Expenditure-The-Chamber-Journal.pdf
 
IMPORTANT JUDGMENTS UNDER SARFAESI ACT, DRBT ACT & IBC.pdf
IMPORTANT JUDGMENTS UNDER SARFAESI ACT, DRBT ACT & IBC.pdfIMPORTANT JUDGMENTS UNDER SARFAESI ACT, DRBT ACT & IBC.pdf
IMPORTANT JUDGMENTS UNDER SARFAESI ACT, DRBT ACT & IBC.pdf
 
SCOMET-Update-Amendment-to-Appendix-3-List-of-SCOMET-Items-to-Schedule-2-of-I...
SCOMET-Update-Amendment-to-Appendix-3-List-of-SCOMET-Items-to-Schedule-2-of-I...SCOMET-Update-Amendment-to-Appendix-3-List-of-SCOMET-Items-to-Schedule-2-of-I...
SCOMET-Update-Amendment-to-Appendix-3-List-of-SCOMET-Items-to-Schedule-2-of-I...
 
Indirect Tax Newsletter – July 2023.pdf
Indirect Tax Newsletter – July 2023.pdfIndirect Tax Newsletter – July 2023.pdf
Indirect Tax Newsletter – July 2023.pdf
 
Overview of the Digital Personal Data Protection DPDP Bill 2023.pdf
Overview of the Digital Personal Data Protection DPDP Bill 2023.pdfOverview of the Digital Personal Data Protection DPDP Bill 2023.pdf
Overview of the Digital Personal Data Protection DPDP Bill 2023.pdf
 
E-invoicing-Whether the relevant provisions of GST law require patchwork.pdf
E-invoicing-Whether the relevant provisions of GST law require patchwork.pdfE-invoicing-Whether the relevant provisions of GST law require patchwork.pdf
E-invoicing-Whether the relevant provisions of GST law require patchwork.pdf
 
FSR-Book-Final.pdf
FSR-Book-Final.pdfFSR-Book-Final.pdf
FSR-Book-Final.pdf
 
MARKET ACCESS BARRIERS IN THE PHARMACEUTICAL SECTOR IN INDIA’S KEY EXPORT DES...
MARKET ACCESS BARRIERS IN THE PHARMACEUTICAL SECTOR IN INDIA’S KEY EXPORT DES...MARKET ACCESS BARRIERS IN THE PHARMACEUTICAL SECTOR IN INDIA’S KEY EXPORT DES...
MARKET ACCESS BARRIERS IN THE PHARMACEUTICAL SECTOR IN INDIA’S KEY EXPORT DES...
 
SEBI tightens compliances and disclosures for listed entities - Amends LODR R...
SEBI tightens compliances and disclosures for listed entities - Amends LODR R...SEBI tightens compliances and disclosures for listed entities - Amends LODR R...
SEBI tightens compliances and disclosures for listed entities - Amends LODR R...
 

Recently uploaded

一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
bd2c5966a56d
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
MollyBrown86
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
Airst S
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
mahikaanand16
 

Recently uploaded (20)

一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
 
Presentation on Corporate SOCIAL RESPONSIBILITY- PPT.pptx
Presentation on Corporate SOCIAL RESPONSIBILITY- PPT.pptxPresentation on Corporate SOCIAL RESPONSIBILITY- PPT.pptx
Presentation on Corporate SOCIAL RESPONSIBILITY- PPT.pptx
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
一比一原版(UC毕业证书)堪培拉大学毕业证如何办理
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
 
Police Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. SteeringPolice Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. Steering
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt
 
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueAndrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
 
Hely-Hutchinson v. Brayhead Ltd .pdf
Hely-Hutchinson v. Brayhead Ltd         .pdfHely-Hutchinson v. Brayhead Ltd         .pdf
Hely-Hutchinson v. Brayhead Ltd .pdf
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction Fails
 
Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo for
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 

ELP Arbitration: Update - Intercontinental Hotels Group (India) Private Limited

  • 1. ELP Arbitration Update © Economic Laws Practice 2022 SUPREME COURT: ONCE STAMP DUTY HAS BEEN PAID, THE ISSUE OF WHETHER THE STAMP DUTY PAID WAS INSUFFICIENT OR APPROPRIATE IS A QUESTION TO BE ANSWERED AT A LATER STAGE AND NOT UNDER SECTION 11(6) OF THE ARBITRATION AND CONCILIATION ACT, 1996 Intercontinental Hotels Group (India) Private Limited & Anr. v. Waterline Hotels Private Limited1 BACKGROUND OF DISPUTES ▪ Intercontinental Hotels Group (India) Private Limited (Petitioner No.1), Intercontinental Hotels Group (Asia-Pacific) Pvt Ltd. (Petitioner No. 2) (collectively referred to as the Petitioners) and the Respondent entered into a Hotel Management Agreement (HMA) to run and operate a hotel. The HMA inter alia provided the rights and obligations of the parties for a ten-year period and provided for subsequent renewals. Additionally, the HMA provided for payments to be made by the Respondent to the Petitioners towards various fees including ‘investment management fee’, ‘technology service fee’. The Petitioners contended that the Respondent failed to fulfil the said payment obligations. Further, the Respondent addressed an email dated October 12, 2018 (Notice) and terminated the HMA. In response to the Notice, the Petitioners stated that unilateral termination of the HMA was invalid. ▪ Aggrieved by the Notice, the Petitioners invoked section 9 of the Arbitration and Conciliation Act, 1996 (Act) and sought interim relief before the High Court of Karnataka (High Court). By an ad-interim order dated October 23, 2018, the High Court directed the Respondent not to evict the Petitioners from the Hotel without due process of law until further orders (Order). The Petitioners alleged that the Respondent failed to comply with the Order. Subsequently, the Petitioners invoked the arbitration clause under the HMA and issued a notice of arbitration dated January 21, 2019 (Arbitration Notice). In response to the Arbitration Notice, the Respondent allegedly stated that the Arbitration Notice was not a notice of arbitration and did not merit a response. ▪ The arbitration clause inter alia provided the procedure for constitution of the tribunal. Pursuant to the response received from the Respondent, the Petitioners requested Singapore International Arbitration Centre to suggest names of sole arbitrators or invoke the mechanism of appointing a three-member tribunal, as per the HMA, in the event the Respondent did not agree to the name of a sole arbitrator. Although SIAC issued a notice dated February 1 Judgement dated 25 January 2022 in Arbitration Petition (Civil) No. 12 of 2019 ELP Arbitration: Update
  • 2. ELP Arbitration Update © Economic Laws Practice 2022 15, 2019 to the Respondent for the appointment of a suitable arbitrator, in response, the Respondent stated the Arbitration Notice was defective and not curable. Aggrieved by the Respondent’s refusal to appoint an arbitrator, the Petitioners filed the present petition under sections 11(6) read with 11(12)(a) of the Act to constitute the Tribunal, before the Supreme Court (Section 11 Proceedings). SUBMISSIONS OF THE PARTIES ▪ In the Section 11 Proceedings, the Respondent filed a counter-affidavit dated July 24, 2019 and contended that the HMA which contained the arbitration agreement was an unstamped document. The Respondent submitted that, in light of Garware Wall Ropes2 , an agreement which is not duly stamped cannot be relied on or acted upon unless the unstamped document is impounded, and the applicable stamp duty/penalty is assessed and paid. On the other hand, the Petitioners submitted that pursuant to the warranty clause in the HMA, the Respondent was obligated to ensure that the agreement would be legally valid in India. ▪ The Petitioners filed an application for permission to file additional documents on June 23, 2020 (Application). By the said Application, the Petitioners inter alia (i) stated that they had taken the requisite steps to pay the applicable stamp duty along with the penalties that may be accruable under Karnataka Stamp Act, 1957 (Karnataka Stamp Act) on a without prejudice basis; (ii) pointed out that the HMA was a services agreement, which would be covered under the residuary provisions, i.e., Article 5(j) of the Karnataka Stamp Act; and (iii) requested the Supreme Court to appoint an arbitrator. ▪ Objecting to the Application, the Respondent, submitted that by a letter dated February 28, 2020, the Petitioners had previously stated that the HMA was classified as a “bond”. The Respondent further contended that (i) the Petitioners had not been granted permission to file additional stamp papers under Article 5(j) of the Karnataka Stamp Act; (ii) the Petitioners have not paid the proper stamp duty and penalty under the Karnataka Stamp Act; and (iii) the Petitioners could not have self-adjudicated the proper stamp duty and penalty payable. FINDINGS OF THE COURT ▪ The issue which arose for consideration before the Supreme Court was whether the issue of insufficient stamping indicated an unworkable arbitration agreement under section 11(6) of the Act. Reiterated the view in Vidya Drolia that ‘When in doubt, do refer’ ▪ The Supreme Court concurred that Vidya Drolia3 established that (i) courts have a very limited jurisdiction under section 11(6) of the Act; (ii) courts are to take a ‘prima facie’ view on issues relating to the existence of arbitration agreements; (iii) issues of arbitrability/validity were usually to be adjudicated upon by arbitrators, with the only narrow exception carved out there being that courts could adjudicate to ‘cut the deadwood’; and (iv) the ‘watch word’ for the courts is ‘when in doubt, do refer’. The Supreme Court should ensure that arbitrations are carried on unless there is ‘deadwood’ ▪ The Supreme Court examined Vidya Drolia’s affirmation of Garware Wall Ropes4 , where it had been held that an arbitration agreement would not “exist” until the arbitration agreement had been duly stamped. In NN Mercantile5 , the Supreme Court took a different view from its coordinate bench in Vidya Drolia6 and inter alia, held that (a) the doctrine of separability would override the concern under respective stamp acts; (b) any concerns of non-stamping or under stamping would not affect the validity of the arbitration agreement. [For a further read, please click here for ELP’s earlier updates on NN Global Mercantile and Vidya Drolia.] ▪ The Supreme Court held that while there is a need for a larger bench to settle the jurisprudence, considering the “time sensitive” nature of arbitration matters, all matters at pre-appointment stage could not be left hanging until the larger bench settled the issue. In view of the same, Supreme Court held that until the larger bench decided on the interplay between sections 11(6) and 16 of the Act, the Supreme Court should ensure that arbitrations are carried on unless the issue before the Supreme Court patently indicates the existence of ‘deadwood’. 2 Garware Wall Ropes v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209 3 Vidya Drolia and Others v. Durga Trading Corporation, 2020 SCC OnLine SC 1018. 4 Garware Wall Ropes v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209 5 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13; 6 Vidya Drolia and Others v. Durga Trading Corporation, 2020 SCC OnLine SC 1018; Vidya Drolia (at paragraph 92) had affirmed paragraphs 22 and 29 of Garware Wall Ropes, which in turn had followed the observations made in SMS Tea Estates. However, in NN Global Mercantile, the Supreme Court overruled SMS Tea Estates. The correctness of the said paragraph in Vidya Drolia was therefore doubted in NN Mercantile.
  • 3. ELP Arbitration Update © Economic Laws Practice 2022 The warranty provided by the Respondent in the HMA give rise to deeper issues which can be resolved at a later stage. Therefore, the issue of insufficient stamping is not ‘deadwood’. ▪ The Supreme Court considered the Petitioners’ contention that the warranty clause in the HMA provided that the Respondent was obligated to ensure that the agreement would be legally valid in India. The Supreme Court culled out three issues which could be adjudicated at a later stage, i.e.: (a) whether the Respondent is estopped from raising the contention of unenforceability of the HMA; (b) whether the HMA is insufficiently or incorrectly stamped; and (c) the extent to which the Petitioners could rely on the Respondent’s warranty. The Supreme Court held that the foregoing aspects demonstrated that the issue of insufficient stamping was not a matter of ‘deadwood’. The Supreme Court did not delve into the adequacy of the stamp duty paid. ▪ The Supreme Court observed that to determine whether adequate stamp duty had been paid in terms of the Karnataka Stamp Act, the court would need to examine (i) the nature of the substantive agreement, (ii) the nature of the arbitration agreement; and (iii) whether a separate stamp fee is payable. ▪ Referring to Vidya Drolia, the Supreme Court held that the issue of ‘existence’ and/or ‘validity’ of the arbitration clause, would not be needed to be looked into herein, as “payment of stamp duty, sufficient or otherwise, has taken place”. ▪ The Supreme Court concluded that “it was clear that stamp duty had been paid. Whether it was insufficient or appropriate is a question to be answered at a later stage as the Court could not review this issue under section 11(6). If it was a question of complete non stamping, then the Court, might have had an occasion to examine the concern raised in N. N. Global, however, this case, is not one such scenario.” CONCLUSION AND ANALYSIS In view of the above, the Supreme Court referred the matter to arbitration and appointed a sole arbitrator to adjudicate the issues. Scope of intervention under Section 11(6) of the Act The Supreme Court held that the question regarding the insufficiency of the stamp duty did not have to be considered under section 11(6). The fact that stamp duty was paid, irrespective of whether the duty was insufficient or inadequate, weighed in on the court. Therefore, once stamp duty is paid on the contract, irrespective of whether the stamp duty is proper or improper, the same shall not be an issue for consideration under section 11(6) of the Act. Different approach from N. N. Global Mercantile In N.N. Global Mercantile, the Supreme Court held that the phrase “duly stamped” “implies that the instrument must be stamped with the requisite amount of duty determined in accordance with the Schedule to the Act7 . If it is found that the instrument is not stamped, or inadequately stamped, it is mandated by law to impound the instrument, and deal with it in accordance with the provisions of the Stamp Act.”8 Then, the Supreme Court observed three scenarios under which the authority could exercise the power of impounding the instrument albeit under the Maharashtra Stamp Act. One of the scenarios being - the High Court, or the Supreme Court, as the case may be, while exercising jurisdiction under Section 11, would “impound the substantive contract which is either unstamped or inadequately stamped, and direct the parties to cure the defect before the arbitrator/tribunal can adjudicate upon the contract.” 9 Taking a different path from this view, in the present case, the Supreme Court did not examine the nature of the contract and consequently, did not consider whether the HMA was duly stamped. Further, in exercise of its jurisdiction under section 11, the apex court did not impound the substantive contract which was purportedly inadequately stamped nor did it pass any directions to verify the assessment of stamp duty. The payment of stamp duty was sufficient to satisfy the Supreme Court for the purpose of section 11(6) of the Act, irrespective of whether the stamp duty was a proper/ appropriate assessment. The apex court acknowledged that issues of substantive rights and obligations under the HMA would require adjudication at a later stage. However, it did not clarify whether the adjudication of rights and obligations of the main contract could proceed before complying with the mandatory provisions of the relevant stamp act. On the other hand, in N.N. Global Mercantile, the Supreme Court held that “there is no legal impediment to the enforceability of the arbitration agreement, pending payment of stamp duty on the substantive contract. The adjudication of the rights and 7 Black Pearl Hotels (P) Ltd. v. Planet M. Retail Ltd., (2017) 4 SCC 498. 8 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 10.5] 9 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 36.2]
  • 4. ELP Arbitration Update © Economic Laws Practice 2022 obligations under the work order or the substantive commercial contract would, however, not proceed before complying with the mandatory provisions of the Stamp Act.” 10 The Supreme Court, in the present judgement, has observed that it is only where a document is completely unstamped that courts might have an occasion to examine the concerns raised in N.N. Global Mercantile and that the present case was not one such scenario, since the Petitioners had paid an amount towards stamp duty. The Supreme Court therefore distinguishes the applicability of N.N. Global Mercantile by seemingly drawing a distinction between complete non-payment of stamp duty and part payment of stamp duty (even if insufficient). However, the consequences envisaged in N.N. Global Mercantile are the same irrespective of whether there was complete non- payment of stamp duty or inadequate payment of stamp duty i.e. as mentioned above, the findings were with respect to an instrument/ contract that is unstamped “or inadequately stamped”. Hence, N.N Global Mercantile did not contemplate impounding of instruments solely in cases where there is a question of complete non-stamping. Further, although in the present judgement the Supreme Court declined to examine the nature of the substantive contract to determine the adequacy of the duty paid, it would be worthwhile to note the Supreme Court’s observations in Black Pearl Hotels11 . In Black Pearl Hotels the nature of the substantive agreement containing an arbitration clause was disputed. The apex court in that matter held that the determination of the nature of an instrument is a judicial function and ought to be determined by the court at the stage of appointment of an arbitrator under section 11 of the Act. There was therefore, a precedent that allowed courts to pass a ruling on the nature of a document in proceedings under section 11 of the Act, that was available to this Court. Way Forward The way forward in similar matters where allegations of inadequate payment of stamp duty are levelled in proceedings under Section 11 of the Act is likely to change. In the present judgement, the Supreme Court has held that the question of adequacy of stamp duty is not be delved into at the stage of proceedings under section 11 and consequently left it to be determined at a later stage without passing any directions as to the impoundment of the underlying contract. In doing so, has the Supreme Court opened doors for applicants in pending applications under section 11 (6) of the Act? In similar situations where the arbitration agreement is in a contract, applicants may seek constitution of the tribunal once payment of any amount of stamp duty is made (irrespective of whether the stamp duty is proper/adequate). The present judgement has been delivered by a bench that is equal in strength to N.N. Global Mercantile and Vidya Drolia. Therefore, the larger bench constituted pursuant to the reference made in N.N. Global Mercantile ought to clarify the different views adopted in these three judgements and the road ahead. We hope you have found this information useful. For any queries/clarifications please write to us at insights@elp-in.com or write to our authors: Ria Dalwani, Senior Associate – Email – riadalwani@elp-in.com Sonia Dasgupta, Associate – Email – soniadasgupta@elp-in.com Disclaimer: The information provided in this update is intended for informational purposes only and does not constitute legal opinion or advice. Readers are requested to seek formal legal advice prior to acting upon any of the information provided herein. This update is not intended to address the circumstances of any particular individual or corporate body. There can be no assurance that the judicial/quasi-judicial authorities may not take a position contrary to the views mentioned herein. 10 N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 26] 11 Black Pearl Hotels (P) Ltd. v. Planet M. Retail Ltd., (2017) 4 SCC 498.