The document provides information on Dalradian Resources Inc.'s Curraghinalt Gold Project in Northern Ireland, including:
- The project features a large, high-grade vein system that is open in all directions and close to surface.
- A positive feasibility study shows robust economics for the base case with an after-tax IRR of 25.5% and CAPEX of $192 million.
- Recent work has increased the amount of mineable material above a 5 g/t gold cutoff by 32% through re-wireframing of major veins.
The document summarizes a presentation on high-grade gold deposits in Northern Ireland. It discusses Dalradian Resources' Curraghinalt gold project, which has over 5 million ounces of proven and probable reserves at an average grade of 8.54 g/t gold. A positive feasibility study showed production of 130,000 ounces per year over 10 years at an all-in sustaining cost of $653/oz and an after-tax IRR of 25.5%. The presentation notes opportunities to further improve project economics through additional drilling, ore sorting tests, and geotechnical studies.
The document provides an overview of Dalradian Resources Inc. and its Curraghinalt Gold Project in Northern Ireland. Key points include:
- Dalradian has advanced the Curraghinalt project through exploration permits, feasibility studies showing robust economics, and underground development including test stoping.
- The most recent feasibility study outlined proven and probable reserves of 5.24MT at 8.54g/t gold for 1.44M ounces, with additional measured, indicated and inferred resources totaling over 4.4M ounces.
- Revised modeling increased the amount of mineable material above a 5g/t gold cutoff by 32%, improving the potential for longhole mining methods.
Belo Sun is a Canadian-based mining company focused on generating long-term sustainable value for its shareholders by developing the Volta Grande Gold Project. A feasibility study completed in March 2015, demonstrates a straightforward open-pit heap leach mine with a long life, strong production profile, bottom quartile operating costs and robust economics.
On February 2, 2017, Belo Sun received the “Licenca de Instalacao” (“LI” or “Construction Licence”) for the Volta Grande Gold Project from the Brazilian State Government of Pará under the environmental authority, SEMAS.
Belo Sun’s executive management team has a long history of working together, and have earned a track-record of successfully advancing and developing mine projects, particularly in central and South America.
Belo Sun Mining trades on the Toronto Stock Exchange under the symbol "BSX".
For further information, please visit www.belosun.com.
The document discusses high-grade gold deposits in Northern Ireland, focusing on Dalradian Resources' Curraghinalt gold project. It summarizes the positive feasibility study for the project including reserves of 1.44 million ounces at 8.54 g/t gold. The project has a large high-grade resource open along strike and at depth that remains open for expansion. Dalradian has advanced the project through exploration, permitting, and engineering studies to define the resource and assess project economics.
50.1 falco presentation feasibility - final - v2FalcoCorporate
The presentation summarizes a feasibility study for the Horne 5 underground mine project in Canada. Key highlights include:
- Proven and probable reserves of 6.13 million ounces of gold equivalent across 80.9 million tonnes.
- Mine life of 15 years with average annual production of 219,000 ounces of gold, 1.7 million ounces of silver, 67 million pounds of zinc, and 16 million pounds of copper.
- Initial capital costs of $802 million USD with low operating costs of $260/oz for cash costs and $399/oz for all-in sustaining costs net of by-products.
- Project provides significant economic benefits and jobs to the region.
- Patrick F. N. Anderson, President and CEO of Dalradian Resources Inc., presented a corporate presentation in April 2018 highlighting their Curraghinalt Gold Project in Northern Ireland.
- The presentation outlined Dalradian's high-grade gold deposit which remains open for expansion, positive feasibility study results showing robust economics, and over $138 million in cash to advance permitting and further study work.
- Dalradian has defined over 4.4 million ounces of gold in the measured, indicated and inferred categories at their Curraghinalt deposit and see potential to increase resources through further exploration on their large land package.
The document summarizes a presentation on high-grade gold deposits in Northern Ireland. It discusses Dalradian Resources' Curraghinalt gold project, which has over 5 million ounces of proven and probable reserves at an average grade of 8.54 g/t gold. A positive feasibility study showed production of 130,000 ounces per year over 10 years at an all-in sustaining cost of $653/oz and an after-tax IRR of 25.5%. The presentation notes opportunities to further improve project economics through additional drilling, ore sorting tests, and geotechnical studies.
The document provides an overview of Dalradian Resources Inc. and its Curraghinalt Gold Project in Northern Ireland. Key points include:
- Dalradian has advanced the Curraghinalt project through exploration permits, feasibility studies showing robust economics, and underground development including test stoping.
- The most recent feasibility study outlined proven and probable reserves of 5.24MT at 8.54g/t gold for 1.44M ounces, with additional measured, indicated and inferred resources totaling over 4.4M ounces.
- Revised modeling increased the amount of mineable material above a 5g/t gold cutoff by 32%, improving the potential for longhole mining methods.
Belo Sun is a Canadian-based mining company focused on generating long-term sustainable value for its shareholders by developing the Volta Grande Gold Project. A feasibility study completed in March 2015, demonstrates a straightforward open-pit heap leach mine with a long life, strong production profile, bottom quartile operating costs and robust economics.
On February 2, 2017, Belo Sun received the “Licenca de Instalacao” (“LI” or “Construction Licence”) for the Volta Grande Gold Project from the Brazilian State Government of Pará under the environmental authority, SEMAS.
Belo Sun’s executive management team has a long history of working together, and have earned a track-record of successfully advancing and developing mine projects, particularly in central and South America.
Belo Sun Mining trades on the Toronto Stock Exchange under the symbol "BSX".
For further information, please visit www.belosun.com.
The document discusses high-grade gold deposits in Northern Ireland, focusing on Dalradian Resources' Curraghinalt gold project. It summarizes the positive feasibility study for the project including reserves of 1.44 million ounces at 8.54 g/t gold. The project has a large high-grade resource open along strike and at depth that remains open for expansion. Dalradian has advanced the project through exploration, permitting, and engineering studies to define the resource and assess project economics.
50.1 falco presentation feasibility - final - v2FalcoCorporate
The presentation summarizes a feasibility study for the Horne 5 underground mine project in Canada. Key highlights include:
- Proven and probable reserves of 6.13 million ounces of gold equivalent across 80.9 million tonnes.
- Mine life of 15 years with average annual production of 219,000 ounces of gold, 1.7 million ounces of silver, 67 million pounds of zinc, and 16 million pounds of copper.
- Initial capital costs of $802 million USD with low operating costs of $260/oz for cash costs and $399/oz for all-in sustaining costs net of by-products.
- Project provides significant economic benefits and jobs to the region.
- Patrick F. N. Anderson, President and CEO of Dalradian Resources Inc., presented a corporate presentation in April 2018 highlighting their Curraghinalt Gold Project in Northern Ireland.
- The presentation outlined Dalradian's high-grade gold deposit which remains open for expansion, positive feasibility study results showing robust economics, and over $138 million in cash to advance permitting and further study work.
- Dalradian has defined over 4.4 million ounces of gold in the measured, indicated and inferred categories at their Curraghinalt deposit and see potential to increase resources through further exploration on their large land package.
1) The document proposes creating a leading mid-tier gold mining company through the combination of Trek Mining, NewCastle Gold, and Anfield Gold.
2) The transaction would result in a company with 5.8 million ounces of gold in M&I resources across multiple assets, including the Aurizona gold mine in Brazil which is expected to have its first gold pour by late 2018.
3) The combined company, to be called Equinox Gold, would have an experienced management team and board of directors, a strong financial position to fund growth projects, and exploration potential across its asset portfolio.
The document summarizes a feasibility study for the Curraghinalt Gold Project in Northern Ireland. Key highlights include proven and probable reserves of 5.24 million tonnes grading 8.54 g/t gold for 1.44 million ounces. The feasibility study estimates average annual gold production of 130,000 ounces over the first 10 years of the planned 14 year mine life. The study estimates an after-tax NPV of $301 million using a 5% discount rate and $1,250/ounce gold price. Exploration potential remains along a 12km trend with the deposit open for expansion.
Patrick Anderson's presentation highlights Dalradian Resources' Curraghinalt gold project in Northern Ireland, which has advanced to the permitting stage. The project features a large, high-grade vein system that has increased in size and grade through exploration. A positive feasibility study was completed previously, and opportunities exist to further improve the economics. Dalradian is undertaking additional technical work and community engagement to support an updated feasibility study and permitting process.
The document summarizes a presentation on high-grade gold deposits in Northern Ireland. It discusses Dalradian Resources' Curraghinalt gold deposit which has over 7 million ounces of gold in inferred and indicated resources. A recent feasibility study showed positive results for developing the deposit into a mine. The presentation also notes the large land package held by Dalradian that shows potential for further exploration success and resource growth around the Curraghinalt trend.
This document provides a summary of a preliminary economic assessment for the Curraghinalt high-grade gold deposit located in Northern Ireland. Key highlights from the PEA include average annual production of 145,000 ounces of gold over a 15-year mine life with an initial capital expenditure of $192 million and cash costs of $532 per ounce. The PEA shows the project has an after-tax internal rate of return of 41.9% based on a 3-year trailing average gold price of $1,378 per ounce. Additional drilling is planned to expand the current mineral resource.
The document discusses Dalradian Resources Inc.'s Curraghinalt gold deposit in Northern Ireland. It summarizes that Dalradian has grown the deposit's resource over 7-fold to over 2 million ounces of gold in the measured and indicated categories. Test stoping has validated long-hole open stoping as the primary mining method. The feasibility study is on schedule for Q4 2016. The permitting process involves submitting a planning application including an environmental and social impact assessment. Dalradian has a team with experience in mine building and exploration and notes Northern Ireland's business-friendly jurisdiction.
- Dalradian Resources is developing the Curraghinalt high-grade gold deposit in Northern Ireland which has over 3 million ounces in measured and indicated resources.
- A preliminary economic assessment showed strong economics for the project, with average annual production of 145,000 ounces over a 15-year mine life and low capital costs.
- The company is permitting an underground bulk sample to further prove the economics and advance the project towards production. Permitting in Northern Ireland is a thorough process but can be completed in a timely manner.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold resource base, near-term and growing gold production from two past-producing mines in Brazil and California, and a long-term growth platform with a diverse portfolio of gold and copper assets in North and South America. Construction is underway at the Company’s Aurizona project in Brazil with the objective of pouring gold by year-end 2018, and a prefeasibility study is underway at the Company’s Castle Mountain project in California with the objective of restarting production. Further information about Equinox Gold’s current portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by email at ir@equinoxgold.com.
The document provides an overview of Dalradian Resources' Curraghinalt gold deposit in Northern Ireland, including:
- A May 2016 resource update that more than doubled measured and indicated ounces to support an ongoing feasibility study.
- High-grade gold mineralization occurring in veins that are advantageous for underground mining.
- Ongoing underground development including 950m of new development and test stoping to inform the feasibility study.
- Potential for resource expansion along a 12km trend and from recent regional discoveries.
Patrick Anderson of Dalradian Resources presented on the company's Curraghinalt gold deposit in Northern Ireland. Key points included:
1) The deposit contains over 2 million ounces of gold in the measured and indicated categories according to a recent resource update. Underground development and drilling continue to expand the deposit.
2) Test stoping yielded positive results, validating the mining method and showing narrow widths can be achieved.
3) The feasibility study is on schedule for Q4 2016 and the company plans to submit its planning application by year-end for permits to construct a mine.
4) Dalradian is engaging stakeholders and moving through the permitting process, which is expected to take 1-2
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production growth from two past-producing mines in Brazil and California. Early commissioning is underway at the Company’s Aurizona Gold Mine in Brazil and on schedule to achieve commercial production around the end of Q1-2019, and the Company is advancing its Castle Mountain Gold Mine in California with the objective of achieving Phase 1 production in the first half of 2020.
Equinox Gold's 2018 report card summarizes production results and 2019 growth targets. In 2018, production was 26,000 ounces of gold from the Mesquite mine acquisition. 2019 guidance is for production of 230,000-265,000 ounces at an AISC of $900-$950 per ounce. Key 2019 objectives include ramping up the Aurizona mine in Brazil to commercial production, extending mine lives at Mesquite and Aurizona, and advancing the Phase 1 project at Castle Mountain. The report highlights growth from existing assets, the potential for mine life extensions and new discoveries, and the goal of becoming a multi-mine producer.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production growth from two past-producing mines in Brazil and California. Construction is well advanced at the Company’s Aurizona Gold Mine in Brazil and on schedule to achieve commercial production around the end of Q1-2019, and the Company is advancing its Castle Mountain Gold Mine in California with the objective of achieving Phase 1 production in the first half of 2020.
The document summarizes a presentation on high-grade gold deposits in Northern Ireland, focusing on the Curraghinalt deposit. It provides details on the resource estimates which have grown to over 4 million ounces of gold. Exploration is ongoing along a 12km trend and new high-grade discoveries have been made regionally. A feasibility study is underway for the Curraghinalt deposit based on underground mining and flotation processing. Test stoping has been completed and the results support the mining methods proposed for the feasibility study.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold resource base, near-term and growing gold production from two past-producing mines in Brazil and California, and a long-term growth platform with a diverse portfolio of gold and copper assets in North and South America. Construction is underway at the Company’s Aurizona project in Brazil with the objective of pouring gold by year-end 2018, and a prefeasibility study is underway at the Company’s Castle Mountain project in California with the objective of restarting production. Further information about Equinox Gold’s current portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by email at ir@equinoxgold.com.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold resource base, near-term and growing gold production from two past-producing mines in Brazil and California, and a long-term growth platform with a diverse portfolio of gold and copper assets in North and South America. Construction is underway at the Company’s Aurizona project in Brazil with the objective of pouring gold by year-end 2018, and a prefeasibility study is underway at the Company’s Castle Mountain project in California with the objective of restarting production. Further information about Equinox Gold’s current portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by email at ir@equinoxgold.com.
The document provides an overview of Dalradian Resources' Curraghinalt gold deposit in Northern Ireland, including:
- A May 2016 resource update that more than doubled measured and indicated gold ounces to over 2 million ounces.
- High-grade gold mineralization within 16 identified veins that is amenable to underground mining.
- Ongoing feasibility study work including 950 meters of underground development and over 130,000 meters of drilling.
- Potential for resource expansion along a 12km mineralized trend that remains largely unexplored.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production growth from two past-producing mines in Brazil and California. Commissioning is underway at the Company’s Aurizona Gold Mine in Brazil and the Company is advancing its Castle Mountain Gold Mine in California with the objective of achieving Phase 1 production in the first half of 2020.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production from two past-producing mines in Brazil and California. Commissioning is underway at the Company’s Aurizona Gold Mine in Brazil and the Company is advancing its Castle Mountain Gold Mine in California with the objective of ramping-up Phase 1 operations in early 2020.
The document discusses a high-grade gold deposit in Northern Ireland. It summarizes the geology of the large, high-grade vein system which remains open in all directions. It also provides details on the engineering studies conducted, including a capital expenditure of US$192 million and an after-tax internal rate of return of 24%. Finally, it outlines the resources and reserves estimated for the deposit based on over 130,000 meters of drilling, including measured resources of 25,000 ounces grading 26.99 g/t gold and inferred resources of over 2.3 million ounces grading 10.06 g/t gold.
This document summarizes the presentation given by Patrick Anderson, President and CEO of Dalradian Resources, at the BMO 26th Global Metals & Mining Conference. Some key points include:
- Dalradian's Curraghinalt gold deposit in Northern Ireland has a high-grade resource open in multiple directions that is close to surface and accessible.
- The feasibility study showed an after-tax IRR of 24% with an AISC of $674/oz and CAPEX of $192M.
- Dalradian has raised over $200M CAD to date and sees potential to increase resources by continuing exploration along a 12km gold trend.
1) The document proposes creating a leading mid-tier gold mining company through the combination of Trek Mining, NewCastle Gold, and Anfield Gold.
2) The transaction would result in a company with 5.8 million ounces of gold in M&I resources across multiple assets, including the Aurizona gold mine in Brazil which is expected to have its first gold pour by late 2018.
3) The combined company, to be called Equinox Gold, would have an experienced management team and board of directors, a strong financial position to fund growth projects, and exploration potential across its asset portfolio.
The document summarizes a feasibility study for the Curraghinalt Gold Project in Northern Ireland. Key highlights include proven and probable reserves of 5.24 million tonnes grading 8.54 g/t gold for 1.44 million ounces. The feasibility study estimates average annual gold production of 130,000 ounces over the first 10 years of the planned 14 year mine life. The study estimates an after-tax NPV of $301 million using a 5% discount rate and $1,250/ounce gold price. Exploration potential remains along a 12km trend with the deposit open for expansion.
Patrick Anderson's presentation highlights Dalradian Resources' Curraghinalt gold project in Northern Ireland, which has advanced to the permitting stage. The project features a large, high-grade vein system that has increased in size and grade through exploration. A positive feasibility study was completed previously, and opportunities exist to further improve the economics. Dalradian is undertaking additional technical work and community engagement to support an updated feasibility study and permitting process.
The document summarizes a presentation on high-grade gold deposits in Northern Ireland. It discusses Dalradian Resources' Curraghinalt gold deposit which has over 7 million ounces of gold in inferred and indicated resources. A recent feasibility study showed positive results for developing the deposit into a mine. The presentation also notes the large land package held by Dalradian that shows potential for further exploration success and resource growth around the Curraghinalt trend.
This document provides a summary of a preliminary economic assessment for the Curraghinalt high-grade gold deposit located in Northern Ireland. Key highlights from the PEA include average annual production of 145,000 ounces of gold over a 15-year mine life with an initial capital expenditure of $192 million and cash costs of $532 per ounce. The PEA shows the project has an after-tax internal rate of return of 41.9% based on a 3-year trailing average gold price of $1,378 per ounce. Additional drilling is planned to expand the current mineral resource.
The document discusses Dalradian Resources Inc.'s Curraghinalt gold deposit in Northern Ireland. It summarizes that Dalradian has grown the deposit's resource over 7-fold to over 2 million ounces of gold in the measured and indicated categories. Test stoping has validated long-hole open stoping as the primary mining method. The feasibility study is on schedule for Q4 2016. The permitting process involves submitting a planning application including an environmental and social impact assessment. Dalradian has a team with experience in mine building and exploration and notes Northern Ireland's business-friendly jurisdiction.
- Dalradian Resources is developing the Curraghinalt high-grade gold deposit in Northern Ireland which has over 3 million ounces in measured and indicated resources.
- A preliminary economic assessment showed strong economics for the project, with average annual production of 145,000 ounces over a 15-year mine life and low capital costs.
- The company is permitting an underground bulk sample to further prove the economics and advance the project towards production. Permitting in Northern Ireland is a thorough process but can be completed in a timely manner.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold resource base, near-term and growing gold production from two past-producing mines in Brazil and California, and a long-term growth platform with a diverse portfolio of gold and copper assets in North and South America. Construction is underway at the Company’s Aurizona project in Brazil with the objective of pouring gold by year-end 2018, and a prefeasibility study is underway at the Company’s Castle Mountain project in California with the objective of restarting production. Further information about Equinox Gold’s current portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by email at ir@equinoxgold.com.
The document provides an overview of Dalradian Resources' Curraghinalt gold deposit in Northern Ireland, including:
- A May 2016 resource update that more than doubled measured and indicated ounces to support an ongoing feasibility study.
- High-grade gold mineralization occurring in veins that are advantageous for underground mining.
- Ongoing underground development including 950m of new development and test stoping to inform the feasibility study.
- Potential for resource expansion along a 12km trend and from recent regional discoveries.
Patrick Anderson of Dalradian Resources presented on the company's Curraghinalt gold deposit in Northern Ireland. Key points included:
1) The deposit contains over 2 million ounces of gold in the measured and indicated categories according to a recent resource update. Underground development and drilling continue to expand the deposit.
2) Test stoping yielded positive results, validating the mining method and showing narrow widths can be achieved.
3) The feasibility study is on schedule for Q4 2016 and the company plans to submit its planning application by year-end for permits to construct a mine.
4) Dalradian is engaging stakeholders and moving through the permitting process, which is expected to take 1-2
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production growth from two past-producing mines in Brazil and California. Early commissioning is underway at the Company’s Aurizona Gold Mine in Brazil and on schedule to achieve commercial production around the end of Q1-2019, and the Company is advancing its Castle Mountain Gold Mine in California with the objective of achieving Phase 1 production in the first half of 2020.
Equinox Gold's 2018 report card summarizes production results and 2019 growth targets. In 2018, production was 26,000 ounces of gold from the Mesquite mine acquisition. 2019 guidance is for production of 230,000-265,000 ounces at an AISC of $900-$950 per ounce. Key 2019 objectives include ramping up the Aurizona mine in Brazil to commercial production, extending mine lives at Mesquite and Aurizona, and advancing the Phase 1 project at Castle Mountain. The report highlights growth from existing assets, the potential for mine life extensions and new discoveries, and the goal of becoming a multi-mine producer.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production growth from two past-producing mines in Brazil and California. Construction is well advanced at the Company’s Aurizona Gold Mine in Brazil and on schedule to achieve commercial production around the end of Q1-2019, and the Company is advancing its Castle Mountain Gold Mine in California with the objective of achieving Phase 1 production in the first half of 2020.
The document summarizes a presentation on high-grade gold deposits in Northern Ireland, focusing on the Curraghinalt deposit. It provides details on the resource estimates which have grown to over 4 million ounces of gold. Exploration is ongoing along a 12km trend and new high-grade discoveries have been made regionally. A feasibility study is underway for the Curraghinalt deposit based on underground mining and flotation processing. Test stoping has been completed and the results support the mining methods proposed for the feasibility study.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold resource base, near-term and growing gold production from two past-producing mines in Brazil and California, and a long-term growth platform with a diverse portfolio of gold and copper assets in North and South America. Construction is underway at the Company’s Aurizona project in Brazil with the objective of pouring gold by year-end 2018, and a prefeasibility study is underway at the Company’s Castle Mountain project in California with the objective of restarting production. Further information about Equinox Gold’s current portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by email at ir@equinoxgold.com.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold resource base, near-term and growing gold production from two past-producing mines in Brazil and California, and a long-term growth platform with a diverse portfolio of gold and copper assets in North and South America. Construction is underway at the Company’s Aurizona project in Brazil with the objective of pouring gold by year-end 2018, and a prefeasibility study is underway at the Company’s Castle Mountain project in California with the objective of restarting production. Further information about Equinox Gold’s current portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by email at ir@equinoxgold.com.
The document provides an overview of Dalradian Resources' Curraghinalt gold deposit in Northern Ireland, including:
- A May 2016 resource update that more than doubled measured and indicated gold ounces to over 2 million ounces.
- High-grade gold mineralization within 16 identified veins that is amenable to underground mining.
- Ongoing feasibility study work including 950 meters of underground development and over 130,000 meters of drilling.
- Potential for resource expansion along a 12km mineralized trend that remains largely unexplored.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production growth from two past-producing mines in Brazil and California. Commissioning is underway at the Company’s Aurizona Gold Mine in Brazil and the Company is advancing its Castle Mountain Gold Mine in California with the objective of achieving Phase 1 production in the first half of 2020.
Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its Mesquite Gold Mine in California, and near-term production from two past-producing mines in Brazil and California. Commissioning is underway at the Company’s Aurizona Gold Mine in Brazil and the Company is advancing its Castle Mountain Gold Mine in California with the objective of ramping-up Phase 1 operations in early 2020.
The document discusses a high-grade gold deposit in Northern Ireland. It summarizes the geology of the large, high-grade vein system which remains open in all directions. It also provides details on the engineering studies conducted, including a capital expenditure of US$192 million and an after-tax internal rate of return of 24%. Finally, it outlines the resources and reserves estimated for the deposit based on over 130,000 meters of drilling, including measured resources of 25,000 ounces grading 26.99 g/t gold and inferred resources of over 2.3 million ounces grading 10.06 g/t gold.
This document summarizes the presentation given by Patrick Anderson, President and CEO of Dalradian Resources, at the BMO 26th Global Metals & Mining Conference. Some key points include:
- Dalradian's Curraghinalt gold deposit in Northern Ireland has a high-grade resource open in multiple directions that is close to surface and accessible.
- The feasibility study showed an after-tax IRR of 24% with an AISC of $674/oz and CAPEX of $192M.
- Dalradian has raised over $200M CAD to date and sees potential to increase resources by continuing exploration along a 12km gold trend.
The document provides an overview of Dalradian Resources Inc., including its flagship Curraghinalt high-grade gold deposit in Northern Ireland. Key points include:
- The Curraghinalt deposit has a measured resource of 25,000 ounces grading 26.99 g/t gold, indicated resource of 2.07 million ounces grading 11.53 g/t gold, and inferred resource of 2.31 million ounces grading 10.06 g/t gold.
- Regional exploration has discovered additional high-grade veins up to 12km from the deposit along a prospective trend.
- A feasibility study is underway utilizing underground development, drilling, and test stoping to inform the mining plan.
The document provides an overview and update on Dalradian Resources Inc.'s Curraghinalt Gold Project in Northern Ireland. Some key points:
- Resources have expanded to over 4 million ounces of gold in the measured and indicated categories and over 2 million ounces in inferred. The deposit remains open.
- A feasibility study demonstrated the economic potential for developing a mine. Engineering studies showed a simple flowsheet and 94% gold recovery.
- The company raised $34 million through warrant exercises and has additional warrants that could provide up to $39 million more if exercised.
- Drilling continues to expand resources and test targets while permitting and community engagement move forward for mine development.
The document discusses Dalradian Resources' Curraghinalt gold deposit in Northern Ireland. It provides an overview of the deposit's growing resource, which more than doubled its measured and indicated gold ounces in a 2016 update. The deposit remains open in multiple directions and has district-scale exploration potential along a 12km trend. Dalradian is advancing a feasibility study on the project to support mine construction permitting in the second half of 2016.
- Dalradian Resources is developing the Curraghinalt high-grade gold deposit in Northern Ireland.
- The 2016 resource update more than doubled the measured and indicated gold ounces at Curraghinalt.
- A feasibility study is underway and targeted for completion in the second half of 2016 to assess developing an underground mine at Curraghinalt.
- The document discusses Dalradian Resources' Curraghinalt high-grade gold deposit in Northern Ireland, which has a measured resource of 15,100 ounces of gold and an indicated resource of 989,000 ounces, with additional inferred ounces.
- A preliminary economic assessment showed strong economics for the project, with an after-tax IRR of 41.9% using a 3-year gold price average of $1,378/ounce. Initial capex was estimated at $192 million.
- Dalradian plans to advance the project towards production by continuing exploration drilling to expand resources, permitting the mine, and financing construction.
The document discusses Dalradian Resources' Curraghinalt gold deposit in Northern Ireland. It announces that Dalradian has grown the resource at Curraghinalt over six-fold since 2010 through four updates. The May 2016 resource update more than doubled the measured and indicated ounces to support an upcoming feasibility study, while maintaining most of the inferred ounces. The high-grade resource includes over 2 million ounces of gold in the measured and indicated categories. Dalradian plans to submit a mine construction permit and feasibility study for Curraghinalt in the second half of 2016.
The document provides an overview of Dalradian Resources Inc.'s high-grade gold project in Northern Ireland. It summarizes the Curraghinalt deposit's May 2016 resource estimate which more than doubled measured and indicated ounces. The deposit is open in all directions and has potential for expansion along a 12km trend. Dalradian is advancing a feasibility study involving underground development and drilling as well as test stoping.
The document provides an overview of Dalradian Resources' Curraghinalt gold deposit in Northern Ireland and discusses the company's feasibility study and permitting process. Some key points:
- The feasibility study is progressing on schedule and will incorporate longhole mining, flotation processing recovering over 94% of gold, dry stack tailings, and 50% of waste rock returned underground.
- Underground development includes 950m of new ramps and raises with test stoping and 130,000m of drilling to support the study.
- Permit submission for mine construction is on target for the second half of 2016.
The document provides an overview of Dalradian Resources' Curraghinalt gold deposit in Northern Ireland, including:
- A May 2016 resource update that more than doubled measured and indicated ounces to 2.07 million ounces.
- Deposit characteristics including high grade veins amenable to underground mining.
- A 12km mineralized trend with regional discoveries highlighting district potential.
- Progress on a feasibility study including 950m of underground development and test stoping.
- Plans for the feasibility study to incorporate longhole mining, flotation processing, and paste backfill.
The document discusses Dalradian Resources' Curraghinalt high-grade gold deposit located in Northern Ireland. Key points include:
- Curraghinalt is ranked #7 worldwide in undeveloped gold deposits by grade. A PEA shows potential for a high margin, low capex producer.
- The deposit covers only a fraction of a 12km gold trend. Resources include 2.23M oz inferred at 12.74 g/t Au.
- Permitting for an underground bulk sample was granted in under a year with strong local support. Regular community engagement occurs.
- The document presents information on Dalradian Resources' Curraghinalt high-grade gold deposit in Northern Ireland, which it is aiming to develop into a profitable mine.
- Key highlights of the deposit based on technical studies include an indicated resource of nearly 1 million ounces of gold, with additional inferred ounces. A preliminary economic assessment shows strong economics for the project.
- Dalradian plans to advance the project through underground exploration and drilling in 2014-2015 to further define the resource and assess mining methods, with the goal of completing permitting and advancing to production.
Dalradian Resources presented information on its Curraghinalt high-grade gold deposit in Northern Ireland. Key points include:
- The deposit contains over 1 million ounces of gold in the indicated resource category.
- A preliminary economic assessment showed strong economics, with an after-tax NPV of US$504 million at a gold price of US$1,200/ounce.
- Dalradian is undertaking a feasibility study and underground drilling program to further define and expand the deposit.
- Dalradian Resources is exploring for high-grade gold deposits in Northern Ireland. Its flagship project is the Curraghinalt gold deposit.
- The Preliminary Economic Assessment showed strong economics for the Curraghinalt deposit, including an after-tax NPV of $504 million at a gold price of $1,200/ounce.
- Dalradian is advancing the Curraghinalt deposit with infill drilling, underground development and a feasibility study. It plans to submit a mine construction permit application in Q3 2016.
The document provides an overview of Dalradian Resources Inc., a gold mining company developing the Curraghinalt high-grade gold deposit in Northern Ireland. Some key points:
- The Curraghinalt deposit has over 1 million ounces of gold in the measured, indicated and inferred categories. Underground drilling is planned in 2015 to support a pre-feasibility study.
- A preliminary economic assessment shows strong economics for the project, with an after-tax IRR of 41.9% using a 3-year gold price average.
- Dalradian is advancing permitting for the project and expects to submit an Environmental Impact Assessment for the mine in early 2015.
- Upcoming milestones
- Dalradian Resources is exploring for high-grade gold deposits in Northern Ireland. Its flagship project is the Curraghinalt gold deposit.
- The Preliminary Economic Assessment showed strong economics for the Curraghinalt deposit, including an after-tax NPV of $504 million and IRR of 36.2% at a gold price of $1,200/ounce.
- Drilling continues to expand the deposit, which remains open in all directions, and a Feasibility Study is underway to advance the project towards obtaining permits and making a construction decision.
Dalradian Resources presented information on its Curraghinalt gold deposit in Northern Ireland. The deposit contains a high-grade gold resource of over 3 million ounces, including a measured resource of 15,100 ounces grading 20.15 g/t gold, an indicated resource of 989,000 ounces grading 10.34 g/t gold, and an inferred resource of 2.49 million ounces grading 9.67 g/t gold. Dalradian has a strong board and management team with experience developing mines and has raised billions of dollars for past projects. The presentation provided an overview of the project's geology and resource along with the company's financing and shareholder structure as it advances the high-grade Curraghinal
The document discusses Dalradian Resources' Curraghinalt high-grade gold deposit in Northern Ireland. A 2014 preliminary economic assessment shows strong economics for the project, including a 36.2% internal rate of return at a $1,200/ounce gold price. The deposit currently contains over 1 million ounces of gold in the measured and indicated categories and over 2.5 million ounces in inferred. The company plans a $30 million work program in 2015 including a pre-feasibility study, environmental assessment, and drilling to further expand resources.
- Dalradian Resources owns the Curraghinalt high-grade gold deposit in Northern Ireland, which hosts a measured and indicated resource of over 1 million ounces of gold at grades of 10-20 g/t.
- Since 2010, Dalradian has grown the Curraghinalt resource more than 5-fold through exploration programs.
- The deposit is located in a region with excellent infrastructure and a mining-friendly jurisdiction. Dalradian is advancing studies toward a production decision, with a feasibility study and mine permit application targeted for 2016.
Similar to Dalradian Corporate Presentation November 2017 (20)
The document provides an overview of Dalradian Resources Inc. and its flagship Curraghinalt gold deposit in Northern Ireland. It discusses the high-grade nature of the deposit's resource, positive preliminary economic assessment results, and ongoing work including a feasibility study and underground program to expand resources. Analyst coverage and the management team's track record in mine building are also summarized.
The document discusses a presentation given by Patrick F.N. Anderson, Chairman & CEO of Dalradian Resources Inc., at a BMO conference in March 2016 regarding Dalradian's Curraghinalt high-grade gold deposit in Northern Ireland. It provides an overview of the deposit's resource which has grown to over 3 million ounces of gold, positive preliminary economic assessment results, and the ongoing work program including a feasibility study and underground development.
- Dalradian Resources is exploring and developing the Curraghinalt high-grade gold deposit in Northern Ireland.
- Recent work at the site includes 130 blasts, 675 meters of underground development, and 46,000 meters of infill drilling.
- A feasibility study and submission of a mine construction permit are targeted for the second half of 2016.
- The Curraghinalt deposit hosts a measured resource of 15,100 ounces of gold, an indicated resource of 989,000 ounces, and an inferred resource of 2.49 million ounces.
- Dalradian Resources is a gold mining company focused on developing its Curraghinalt gold deposit in Northern Ireland.
- The Curraghinalt deposit hosts a high-grade gold resource that has grown over 5-fold since 2010 through exploration programs.
- Dalradian is currently undertaking a major work program including a feasibility study and permitting activities aimed at submitting a mine construction permit application in the second half of 2016.
- Dalradian Resources is a gold mining company focused on developing its Curraghinalt gold deposit in Northern Ireland.
- The Curraghinalt deposit hosts a high-grade gold resource of over 1 million ounces. Dalradian is working to advance the project with ongoing exploration drilling and studies aimed at submitting permits for mine construction in 2016.
- The company is led by an experienced management team with a track record of building and operating mines. It is well funded with $24 million in cash and advancing one of the few sizable gold deposits in Europe located in a politically stable jurisdiction.
- Dalradian Resources is a gold mining company focused on developing its Curraghinalt gold deposit in Northern Ireland.
- The Curraghinalt deposit hosts a high-grade gold resource with measured resources of 15,100 ounces and indicated resources of 989,000 ounces.
- Dalradian is currently undertaking a major work program at Curraghinalt, including underground development, drilling, and engineering studies, with the goal of submitting a construction permit application for the project in 2016.
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfSOFTTECHHUB
The world of blockchain and decentralized technologies is about to witness a groundbreaking event. ZKsync, the pioneering Ethereum Layer 2 network, has announced the highly anticipated airdrop of its native token, ZK. This move marks a significant milestone in the protocol's journey, empowering the community to take the reins and shape the future of this revolutionary ecosystem.
Methanex is the world's largest producer and supplier of methanol. We create value through our leadership in the global production, marketing and delivery of methanol to customers. View our latest Investor Presentation for more details.
UnityNet World Environment Day Abraham Project 2024 Press ReleaseLHelferty
June 12, 2024 UnityNet International (#UNI) World Environment Day Abraham Project 2024 Press Release from Markham / Mississauga, Ontario in the, Greater Tkaronto Bioregion, Canada in the North American Great Lakes Watersheds of North America (Turtle Island).
2. 2
FORWARD-LOOKING INFORMATION AND QUALIFIED PERSON
2
This presentation contains “forward looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance of
the Company and its subsidiaries (collectively, “Dalradian”) and its mineral projects, the future price of metals, the estimation of mineral resources, the realization of mineral
resource estimates, the timing and amount of estimated future production, costs of production, capital, operating and exploration expenditures, costs and timing of the
development of new deposits, costs and timing of future exploration, requirements for additional capital, government regulation of mining operations, environmental risks,
reclamation expenses, title disputes or claims, limitations of insurance coverage and the timing and possible outcome of pending regulatory matters. Often, but not always,
forward looking statements can be identified by the use of words and phrases such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”,
“intends”, “anticipates”, or “believes” or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “may”, “could”,
“would”, “might” or “will” be taken, occur or be achieved.
Forward looking statements are based on the opinions and estimates of management as of the date such statements are made and are based on various assumptions such as
the continued political stability in Northern Ireland, that permits required for Dalradian’s operations will be obtained on a timely basis in order to permit Dalradian to proceed on
schedule with its planned exploration and development programs, that skilled personnel and contractors will be available as Dalradian’s operations continue to grow, that the
price of gold will be at levels that render Dalradian’s mineral projects economic, that the Company will be able to continue raising the necessary capital to finance its operations
and realize on mineral resource estimates and current mine plans and that the assumptions, qualifications, parameters and methods contained, or to be contained, in the 2016
Technical Report, the FS Announcement and the 2017 Feasibility Study (each as defined below) are accurate and complete.
Forward looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Dalradian to
be materially different from any future results, performance or achievements expressed or implied by the forward looking statements. Such factors include, among others,
general business, economic, competitive, political and social uncertainties; the actual results of current and future exploration activities; the actual results of reclamation
activities; conclusions of economic evaluations; changes in project parameters and/or economic assessments as plans continue to be refined; future prices of metals; possible
variations of mineral grade or recovery rates; the risk that actual costs may exceed estimated costs; failure of plant, equipment or processes to operate as anticipated; accidents,
labour disputes and other risks of the mining industry; political instability; delays in obtaining governmental approvals or financing or in the completion of development or
construction activities, as well as those factors discussed in the section entitled “Risk Factors” in the Company’s Annual Information Form for the year ended December 31, 2015
dated March 23, 2016 (the “AIF”).
Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward looking
statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward looking statements contained
herein are made as of the date of this presentation and the Company disclaims any obligation to update any forward looking statements, whether as a result of new
information, future events or results, except as may be required by applicable securities laws. There can be no assurance that forward looking statements will prove to be
accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward
looking statements.
On December 12, 2016, Dalradian announced certain highlights from the results of its positive feasibility study on its Curraghinalt Gold Project (the “FS Announcement”). A NI
43-101 compliant technical report to support the FS Announcement and summarizing the results of the Feasibility Study is currently being prepared and will be filed under the
Company's profile on SEDAR by January 25, 2017 (the “2017 Feasibility Study”). The Qualified Persons (as defined by NI 43-101) responsible for the FS Announcement and the
2017 Feasibility Study include: JDS Energy & Mining: Garett Macdonald, P. Eng.; Michael Makarenko, P. Eng.; Stacy Freudigmann, P. Eng.; Indi Gopinathan, P. Eng.; SRK
Consulting (UK): Jane Joughin, M. Sc., PrSciNat; R. J. Bowell Ph.D., C. Chem MRSC, C. Geol FGS FIMMM; William Harding, M. Sc.; SRK Consulting (Canada): Cam Scott, P. Eng.;
Bruce Murphy, P. Eng.; WSP Canada: Annie Lavoie, P. Eng.; Jean-Philippe Grenier, P. Eng.
Certain scientific and technical data in this presentation was derived from both the FS Announcement and the Company’s current NI 43-101 technical report entitled,
“Technical Report for the Northern Ireland Gold Project, Northern Ireland”, dated June 17, 2016 (the “2016 Technical Report”) prepared by Dr. Jean-Francois Couture, PGeo
(APGO#0197) and Dr. Oy Leuangthong, PEng (PEO#90563867), both of SRK Consulting (Canada) Inc. and Stacy Freudigmann, PEng (APEGBC #33972) of JDS Energy & Mining Inc.,
all of whom are independent Qualified Persons. The exploration data contained herein was based on the procedures described in the 2016 Technical Report. The scientific and
technical data contained herein is subject to and qualified by all of the assumptions, qualifications and procedures described in the FS Announcement and the 2016 Technical
Report, as applicable. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
Eric Tremblay, P.Eng., Chief Operating Officer, and Greg Hope, M.Sc., MAIG, Exploration and Geology Manager with Dalradian Resources Inc., are the Qualified Persons who
have reviewed and approved the scientific and technical information in this presentation.
3. 3
▪Large, high-grade vein system
open in all directions
▪Close to surface and easily
accessible
▪120,000 ha land package with
many gold showings
Geology
▪Permit a mine
▪Improve economics from
positive FS base-case
Strategy
▪AISC of US$653 per ounce
▪Simple flow sheet and
metallurgy
▪94% gold recovery
Engineering
▪All political parties focused on
economy and job creation
▪Transparent permitting
process
Jurisdiction
▪Base-case FS shows robust
economics, supported by
test-mining
▪Positive geotechnical and
ore-sorting results to be fed
into FS update
▪CAPEX of US$192M
and after-tax IRR of 25.5%
▪Raised over CAD$240 M
since 2010
▪$78 million investment from
Orion and Osisko announced
FS Improvement Financial Strength
HIGH-GRADE GOLD IN NORTHERN IRELAND
4. 4
STOCK PRICE PERFORMANCE
$0.50
$0.75
$1.00
$1.25
$1.50
$1.75
$2.00
$2.25
$2.50
$2.75
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17
Michael Curran$2.00
Tyron Breytenbach$2.70
$2.00 Andrew Mikitchook
$2.50 Eric Zaunscherb
$2.50 Stephen Walker
Ryan Walker$2.05
Analyst targets range from
$1.70-$2.70
$1.25
Nov 3, 2017
SHARE CAPITALIZATION AND
CASH POSITION
Shares outstanding of
302 million and fully diluted of
314 million as of October 2017
Cash position of $34 million*
as of June 30, 2016
All dollars quoted in $ CAD
$1.70 Craig Stanley
140p Jonathan Guy
$2.60 Gary Sidhu
$2.25
*Figure does not include funds from recently announced financing or funds received from recent warrant exercises
6. 6
MINERAL PROJECTS IN IRELAND AND THE UK
Gortin
Omagh
Curraghinalt
BELFAST
Galantas
Gold
Conroy
Diamonds
& Gold
Lonmin
Irish Salt
Mining
Curraghinalt Gold
Deposit
Gold
Base Metals
Other
Exploration
In Production
Permitted
Past Producer
Stage Commodity
United Kingdom
Republic of Ireland
Northern Ireland
7. 7
OUR PROGRESS AT CURRAGHINALT
▪ UG exploration permits granted;
ESIA and planning application
nearing completion
▪ 2 PEAs and a positive base-case
feasibility study released over
5 years
▪ 5 resource updates resulting in a
7x increase in resources
▪ Completed 2,000 metres of
underground development with
3 test stopes
0.0
1.0
2.0
3.0
4.0
5.0
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
2007 Pre-
DNA
2010 DNA
Year 1
2011 DNA
Year 2
2014 DNA
Year 4
2016 DNA
Year 6
27 Years
of Work
6 Years of Work
Metres of Drilling
Inferred Resource (Moz)
Measured and Indicated Resource (Moz)
8. 8
RESOURCES AND RESERVES
Proven and Probable Reserves:
5.24 MT grading 8.54 g/t Au for 1.44 million ounces
High-grade 4.4M ounce gold resource1
Measured: 0.03 MT grading 26.99 g/t Au
for 25,000 contained ounces
Indicated: 5.58 MT grading 11.53 g/t Au
for 2.07 million contained ounces
Inferred: 7.13 MT grading 10.06 g/t Au
for 2.30 million contained ounces
1 Refer to technical report dated January 2 2017, and entitled “43-101 Feasibility Study Technical Report on the Curraghinalt Gole Project Northern Ireland” prepared by JDS Energy
and Mining Inc. at www.dalradian.com
9. 9
REVISED MODELING – 32% MORE OUNCES IN MINEABLE MATERIAL
▪ Re-wireframing with shorter
composite length on two
major veins
▪ Increased amount of
mineable material above
5 g/t Au cutoff
▪ Increased ability to use
longhole mining
▪ Methodology to be applied
to next resource update and
feasibility update
T-17 Section 2016
T-17 Section 2017
Longhole (Uppers and Stopes)
Longhole Pillars
Cut and Fill
Development
10. 10
RESOURCE EXPANSION
Vein and Vein Intersections
Curraghinalt Deposit
Attagh Burn
Alwories
Proposed
mill site
Curraghinalt
Deposit
12km
Curraghinalt
Trend
Rylagh
Bounds of Current Resource
11. 11
Curraghinalt
Deposit
Attagh Burn
2.47m @ 18.99 g/t Au
3
Golan Burn
0.6m @ 61.43 g/t Au
Gold Anomalies
1
kilometres
0 2
Scotch Town
Peak of 10.52 g/t Au
In mineralized boulders
400 m Step-out
3.2m @ 5.34 g/t Au
2
1 1a 12-CT-173 drilled at 150/-60; 1b and 1c 12-CT-162 drilled at 180/-55; 1b from 186.00m - 188.22m, 1c from 229.08m - 230.55m; true width undetermined
2 11-CT-99 drilled at 200/-60, from 471.14-474.34 m
3 12-CT-167 drilled from 201.93-204.40 m
Vein and Vein Intersections
Glaciated Terrain with Minimal Outcrop
Alwories Discovery Holes
1
4.72m @ 14.82 g/t Au
1a
2.22m @ 14.10 g/t Au
1b
1.47m @ 23.60 g/t Au
1c
12KM GOLD TREND IS MOSTLY UNEXPLORED
Proposed
mill site
Curraghinalt
Deposit
12km
Curraghinalt
Trend
Rylagh
12. 12
HIGH GRADE REGIONAL DISCOVERIES
Fallagh
Rylagh
1
kilometres
0 2
1
kilometres
0 2
kilometres
0 5
SAMPLES - New Discovery
50cm @ 139.5 g/t Au (F11601)
10-15cm @ 1.37 g/t Au (F11627)
50cm @ 168 g/t Au (F36011)
50cm @ 42.4 g/t Au (F36011)
SAMPLES
30.30 g/t Au (B0641)
29.20 g/t Au (B0633)
17.25 g/t Au (B0625)
11.65 g/t Au (B0627)
Curraghinalt
Deposit
Curraghinalt
Deposit
12km
Curraghinalt
Trend
Rylagh
13. 13
▪ New licence areas
DG5/DG6 added in
June 2016
▪ DG5 and DG6 anomalies
are the largest on our
licences outside of
Curraghinalt
▪ Soil sampling, panning
and stream sediment
sampling on all
six licences
▪ Over 120,000 hectares
under licence or
application
REGIONAL EXPLORATION
15. 15
SITE PLAN
Curraghinalt has been designed to fit in with the natural topography
with a low profile design, using trees, berms and building wall sound
panels to buffer noise.
16. 16
FEASIBILITY STUDY SNAPSHOT
Feasibility details after Minco transaction have not been verified by an independent technical report. All figures in US$ unless otherwise stated
Proven & Probable Reserves 5.24 Mt @ 8.54 g/t Au for 1.44 Moz
Gold Recovery 94.3%
Average Mine Production Rate 1,400 tpd (511,000 tpy)
Average Gold Production 130,000 oz/y over first 10 years (1.36 Moz)
Total Operating Cost/tonne of Ore $143.94 $137.46
Pre-Production Capital Costs $192.0 Million
LOM Sustaining Capital $165.1 Million
All-In Sustaining Cost (AISC) $674/oz Au $653/oz Au
Metal pricing assumptions $1,250/oz Au, $17/oz Ag
After Tax Economics
$301 Million $322 Million NPV(5%) – C$429 Million
24.4% 25.5% IRR
4.0 year 3.8 year payback
After the closing of the Minco
acquisition:
• AISC decreased US$21/oz
• NPV Increased US$21 million
• IRR increased 1.1%
17. 17
LIFE OF MINE GOLD PRODUCTION
LOM gold production totals 1.36 million ounces, averaging 130,000 oz/year over
the first 10 years with maximum production of 170,000 oz expected in Year 7.
-
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
-
25,000
50,000
75,000
100,000
125,000
150,000
175,000
200,000
-2 -1 1 2 3 4 5 6 7 8 9 10 11
AverageMinedGrade(g/t)
PayableGoldOunces
Operating Year
Production profile
target
18. 18
OPPORTUNITIES FOR IMPROVEMENT
Area Opportunity
Ore sorting
Test results demonstrated a 55% increase in
grade with a 99.3% recovery rate and a 36%
reduction in waste material. Further evaluation is
ongoing.
Focused geotechnical program in zones
currently classified as poor ground
Potential to convert more cut & fill methods to
longhole, reducing OPEX and improving NPV.
Infill drilling to enhance grade
Additional reserves will increase the mine life and
project economics.
Conversion of Inferred resource into M&I and
reserves
Potential to increase reserve grade with higher
density drilling. Test stoping showed 50%-plus
higher ounces compared to block model.
Production rate
With additional reserves, possible to push near-
plant capacity of 1,500 tpd.
Au recovery
Additional metallurgical testing may increase
recovery. Small changes add a lot of value.
Used “new” equipment
Used process plant to reduce initial capital,
shorten lead times and speed up detailed
engineering.
20. 20
2017 WORK PROGRAM
▪ 40,000 metres of infill, step-out and
geotechnical drilling
▪ Additional geotechnical studies and
ore-sorting tests to support updated
Feasibility Study
22. 22
FOCUS ON JOBS AND ECONOMY
▪ Top priority of all NI political parties is jobs and investment
▪ Successfully permitted underground exploration at Curraghinalt
▪ Numerous government officials have visited our project, including over 70 site visits by
regulators during UG program
▪ In the past year, more than 40 pre-submission meeting with regulators for new application
Stormont, NI Parliament Building
23. Planning
decision
PERMITTING PROCESS
Draft Project
Description
(pre-consultation with
stakeholders via PAD)
Prepare ESIA
Submit
Planning
Application
Planning NI
Review
Permission to construct a mine will be
based on a Planning Application, which
will consist of a Project Description and an
Environmental and Social Impact
Assessment (ESIA)
Curraghinalt has been designated a project
of “regional significance”, which allows
ministerial involvement in the planning
decision
Pre-engage with DfI
via a Pre-Application
Discussion (PAD)
Granted
Refused
Referred to Public
Local Inquiry
25. DNA HIGHLIGHTS
▪ Team of mine builders,
explorers, financiers and local
expertise
▪ Business-friendly jurisdiction
with transparent permitting
▪ Dual-listed in Toronto &
London
▪ Large, high-grade vein system
▪ Positive Feasibility Study, with
multiple opportunities for
improvement