Critical lifts ethylene brocure
- 2. Fractionator Tower
Project: ETHYDCO Petrochemical Complex.
(Ethylene Project)
Weight: 370 ton.
Total Length :101.3m
Lifting Crane: Liebherr LR11350 (1350 ton).
Configuration: SLDB2WV (102+12).
Crane capacity: 414 ton.
Capacity utilization: 95.1%
Auxiliary Crane: Terex CC2000 (300 ton).
Lifting date: 18th
of March 2014.
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem
- 3. Ethylene Heater
Project: ETHYDCO Petrochemical Complex
(Ethylene Project)
Weight: up to 50 ton.
Lifting Crane: TEREX TC2600 (450 ton).
Configuration: SWSL (48+42).
Crane capacity: up to 70 ton.
Lifting date: From: 14th
of January 2014
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem
- 4. Quench Tower
Project: ETHYDCO Petrochemical Complex.
(Ethylene Project)
Weight: 205 ton.
Total length: 47.3m
Lifting Crane: Liebherr LR11350 (1350 ton).
Configuration: S (70).
Crane capacity: 254 ton.
Capacity utilization: 85 %
Auxiliary Crane: Terex CC2000 (300 ton).
Lifting date: 9th
of April 2014.
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem
- 5. Water Wash Tower
Project: ETHYDCO Petrochemical Complex.
(Ethylene Project)
Weight: 180 ton.
Total Length: 57m
Lifting Crane: Liebherr LR11350 (1350 ton).
Configuration: SDB (102).
Crane capacity: 238 ton.
Capacity utilization: 84 %
Auxiliary Crane: Terex CC2000 (300 ton).
Lifting date: 18th
of February 2014.
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem
- 6. Amine striper Tower
Project: ETHYDCO Petrochemical Complex.
(Ethylene Project)
Weight: 106 ton.
Total Length: 41.8m
Lifting Crane: Terex CC2000 (300 ton)
Configuration: SSL (60m).
Crane capacity: 141 ton.
Capacity utilization: 78.7 %
Auxiliary Crane: Manitowic 999 (250 ton).
Lifting date: 11th
of July 2013.
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem
- 7. Acidic gas Absorber Tower
Project: ETHYDCO Petrochemical Complex.
(Ethylene Project)
Weight: 100 ton.
Total Length: 40m
Lifting Crane: Terex CC2000 (300 ton)
Configuration: SSL (60m).
Crane capacity: 141 ton.
Capacity utilization: 74 %
Auxiliary Crane: Manitowic 999 (250 ton).
Lifting date: 11th
of June 2013.
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem
- 8. Ethylene Cold Box
Project: ETHYDCO Petrochemical Complex.
(Ethylene Project)
Weight: 68.3 ton.
Total Length: 16m
Lifting Crane: Terex CC2000 (300 ton)
Configuration: SSL (60m).
Crane capacity: 110 ton.
Capacity utilization: 67.2 %
Auxiliary Crane: Manitowic 999 (250 ton).
Lifting date: 11th
of January 2014.
Lifting Engineer: Eng. Mina Labib
Supervisor: Mohamed abd el-minem