The Network Diagram and Gantt Using the Open Source Program - OpenProj
Go into the Gantt window (not tracking Gantt) Then type in the dependencies under the relevant column  Then type in the durations under the relevant column 1 2
Now you can generate the “first draft” network diagram Click View and then network Diagram It will then generate the diagram showed in this slide 1 2
Now click View and then Gantt The result is as indicated on the screen Red indicates the critical path 1 2 3

Creating the Network Diagram and Gantt With OpenProj