Implementation of 5S in recycling area of Physical Plant.
Before Photos:
S1-Sort
In 5s sortingisone of the critical stepsto follow.Inthese picturesthere are acouple of thingsthat isnot
relevantorisnot beingusedinthisworkstation.One of whichisthe greencart onthe firstpicture that
isbrokenwhichisa hindrance wheneverthe truckisunloadingcardboardsbythe horizontal baileron
the leftside of the firstpicture.The secondwasthe brokenbike rackthat is alsonot relevanttowork
processesdone inthe station.Those twohindranceswere removedandplacedona scrap area where it
will notbe a hindrance tothe station.
S2- Set in Order
These are the picturestakenbefore andaftereverythingwassetinorder.On the left,there wasno
definitelocationandpropersegregationof toolsinthe workstationandtherefore createsmore time to
lookfortoolsand binsneededforrecycling.Onthe rightpicture the recyclingmaterialswere segregated
properlyintosections:whitepaper,newspaper,bins,andshreddedpapers.Inaddition,rackswere
placedunderneaththe shreddedpaperssoasto avoidpapersgettingsoakedinwaterwhenthe water
runs throughthe groundthroughheavyraining.Thiswasthe concern alsoforthe papers.Itis thatit gets
soakedinwaterwheneveritrainscreatingdelaytime todryitbefore itcan be recycled.The racks
eliminatedthisproblembecausethe papersdoesnottouchthe ground.
S3- Shine
Cleaningwillbe easierwiththe new orderthatwasplaced.These are the reasonswhy:
1. Shreddedpapers- workerswillhave lesstimecleaningthe underneathof the shreddedpapers
because theywon’tneedtoremove everysinglebagtocleanthe floor.The reasonthere isracks
isnot justbecause of rain butalso the workercan use a forklift tojustlifta whole sectionof
shreddedpaper,cleanthe floorand thenputthe racks back
2. The same processcan alsobe appliedinbottles,white papers,andnewspapers.Usingaforklift
to liftthe cagesand justcleanthe underneath.
3. In addition,adumpsterwasstrategicallyplacedbeside the shreddedpapersbecause the
concentrationof trashis nearthe shreddedpapers.
S4- Standardize
- Signswere placedabove eachrecyclable material groupsothateach workerwouldhave aneasy
understandingwhere to putthe recyclable materialscollected.
- Indicatorsforcleaning wasalsosetso that the workarea will be keptcleanandorganized.
- The standard alsoisthat everyworkerisresponsible of cleaningthe materialsandthe work
stationat the veryleastof once a week.
- Picturesof howeverypartof the stationwas alsoshownsothat wheneverthere isaworker
turnoverthere wouldbe noproblemrememberinghow the stationshouldbe organizedand
clean
S5- Sustain
Ensuringthat thisprojectissustainable is critical.Regulartrainingwill be crucial inmakingthe project
sustainable.Regularauditof the 5S projectbyCarlosSperanzawhichisthe site supervisorwill be
beneficial inhelpingthisprojectbe continuouslyeffectiveandefficient.
Checklist:
Cardboard
- CorrugatedCardboardsonly
- No ShinyCoatedbox
- No Cereal Boxes
- No WetCardboards
White Paper
- White Papersonly
- No CoatedPapers
- No Mail envelopes
- No Magazines
- No WetPapers
ShreddedPapers
- ShreddedPapersinRubbishbag
- ShreddedPapersOnly
- No WetShreddedPapers
- No Magazine ShreddedPapers
BottlesandCans
- EmptyBottlesand CansOnly
- Bottle Capsare not included
- No MilkBottles

More Related Content

Viewers also liked (6)

Final project cele
Final project celeFinal project cele
Final project cele
 
Music video script
Music video scriptMusic video script
Music video script
 
Censorship and Regulation of Music Videos
Censorship and Regulation of Music VideosCensorship and Regulation of Music Videos
Censorship and Regulation of Music Videos
 
1 single complete denture/endodontic courses
1 single complete denture/endodontic courses1 single complete denture/endodontic courses
1 single complete denture/endodontic courses
 
High speed technology is a boon in fpd /orthodontic courses by Indian dental ...
High speed technology is a boon in fpd /orthodontic courses by Indian dental ...High speed technology is a boon in fpd /orthodontic courses by Indian dental ...
High speed technology is a boon in fpd /orthodontic courses by Indian dental ...
 
Alesha Townsend (1)
Alesha Townsend (1)Alesha Townsend (1)
Alesha Townsend (1)
 

5S Project

  • 1. 5S Project Isaiah Villalon BUSM 390R Dr. Ben Neve Implementation of 5S in recycling area of Physical Plant. Before Photos:
  • 2. S1-Sort In 5s sortingisone of the critical stepsto follow.Inthese picturesthere are acouple of thingsthat isnot relevantorisnot beingusedinthisworkstation.One of whichisthe greencart onthe firstpicture that isbrokenwhichisa hindrance wheneverthe truckisunloadingcardboardsbythe horizontal baileron the leftside of the firstpicture.The secondwasthe brokenbike rackthat is alsonot relevanttowork processesdone inthe station.Those twohindranceswere removedandplacedona scrap area where it will notbe a hindrance tothe station.
  • 3. S2- Set in Order These are the picturestakenbefore andaftereverythingwassetinorder.On the left,there wasno definitelocationandpropersegregationof toolsinthe workstationandtherefore createsmore time to lookfortoolsand binsneededforrecycling.Onthe rightpicture the recyclingmaterialswere segregated properlyintosections:whitepaper,newspaper,bins,andshreddedpapers.Inaddition,rackswere placedunderneaththe shreddedpaperssoasto avoidpapersgettingsoakedinwaterwhenthe water runs throughthe groundthroughheavyraining.Thiswasthe concern alsoforthe papers.Itis thatit gets soakedinwaterwheneveritrainscreatingdelaytime todryitbefore itcan be recycled.The racks eliminatedthisproblembecausethe papersdoesnottouchthe ground.
  • 4. S3- Shine Cleaningwillbe easierwiththe new orderthatwasplaced.These are the reasonswhy: 1. Shreddedpapers- workerswillhave lesstimecleaningthe underneathof the shreddedpapers because theywon’tneedtoremove everysinglebagtocleanthe floor.The reasonthere isracks isnot justbecause of rain butalso the workercan use a forklift tojustlifta whole sectionof shreddedpaper,cleanthe floorand thenputthe racks back 2. The same processcan alsobe appliedinbottles,white papers,andnewspapers.Usingaforklift to liftthe cagesand justcleanthe underneath. 3. In addition,adumpsterwasstrategicallyplacedbeside the shreddedpapersbecause the concentrationof trashis nearthe shreddedpapers. S4- Standardize - Signswere placedabove eachrecyclable material groupsothateach workerwouldhave aneasy understandingwhere to putthe recyclable materialscollected. - Indicatorsforcleaning wasalsosetso that the workarea will be keptcleanandorganized. - The standard alsoisthat everyworkerisresponsible of cleaningthe materialsandthe work stationat the veryleastof once a week. - Picturesof howeverypartof the stationwas alsoshownsothat wheneverthere isaworker turnoverthere wouldbe noproblemrememberinghow the stationshouldbe organizedand clean S5- Sustain Ensuringthat thisprojectissustainable is critical.Regulartrainingwill be crucial inmakingthe project sustainable.Regularauditof the 5S projectbyCarlosSperanzawhichisthe site supervisorwill be beneficial inhelpingthisprojectbe continuouslyeffectiveandefficient.
  • 5. Checklist: Cardboard - CorrugatedCardboardsonly - No ShinyCoatedbox - No Cereal Boxes - No WetCardboards White Paper - White Papersonly - No CoatedPapers - No Mail envelopes - No Magazines - No WetPapers ShreddedPapers - ShreddedPapersinRubbishbag - ShreddedPapersOnly - No WetShreddedPapers - No Magazine ShreddedPapers BottlesandCans - EmptyBottlesand CansOnly - Bottle Capsare not included - No MilkBottles