1) 10 CFR 50 Appendix B establishes quality assurance requirements for nuclear power plants and fuel reprocessing plants. It requires applicants to describe their quality assurance programs for design, construction, testing, and operation.
2) The quality assurance program must be documented and implemented throughout the life of the plant. It provides control over safety-related activities to ensure structures, systems, and components meet their intended functions.
3) Design control measures include translating regulations and design basis into specifications and drawings, controlling deviations, selecting materials and processes, and verifying designs through reviews, alternate calculations, or testing.