NUCLEAR PROGRAMME
DETERMINATION UNDER SECTION 34(1) OF THE ELECTRICITY REGULATION ACT 4 OF
2006
PART A
The Minister of Energy ("the Minister"), in consultation with the National Energy Regulator of South
Africa (NERSA"), acting under section 34(1) of the Electricity Regulation Act 4 of 2006 (as
amended) (the "ERA") has determined as follows:
1. that energy generation capacity needs to be procured to contribute towards energy security
and to facilitate achievement of the greenhouse gas emission targets for the Republic of
South Africa, accordingly, 9 600 megawatts (MW) should be procured to be generated from
nuclear energy ("nuclear programme"), which is in accordance with the capacity allocated
under the Integrated Resource Plan for Electricity 2010-2030 (published as GN 400 of 06
May 2011 in Government Gazette No, 34263) ("IRP 2010-2030" or as updated) [our
insertion];
2. electricity produced from the new generation capacity ("the electricity"), shall be procured
through tendering procedures which are fair, equitable, transparent, competitive and cost-
effective;
3. the nuclear programme shall target connection to the Grid as outlined in the IRP2010-2030
(or as updated), taking into account all relevant factors including the time required for
procurement;
4. the electricity may only be sold to the entity designated as the buyer in paragraph 7 below,
and only in accordance with the power purchase agreements and other project agreements
to be concluded in the course of the procurement programmes;
5. the procurement agency in respect of the nuclear programme will be the Department of
Energy;
This gazette is also available free online at www.gpwonline.co.za
4   No. 39541	 GOVERNMENT GAZETTE, 21 DECEMBER 2015
Government Notices • Goewermentskennisgewings
Energy, Department of/ Energie, Departement van
DEPARTMENT OF ENERGY
NO. 1268  21 DECEMBER 2015
1268	 Electricity Regulation Act (4/2006): Nuclear Programme: Determination under section 34(1) of the Electricity Regulation Act		 39541
6. the role of the procurement agency will be to conduct the procurement process, including
preparing any requests for qualification, requests for proposals and/or all related and
associated documentation, negotiating the power purchase agreements, facilitating the
conclusion of the other project agreements, and facilitating the satisfaction of any
conditions precedent to financial close which are within its control;
7. the electricity must be purchased by Eskom Holdings SOC Limited or by any successor
entity to be designated by the Minister of Energy, as buyer (off-taker); and
8. the electricity must be purchased from the special purpose vehicle(s) set up for the purpose
of developing the nuclear programme.
Concurrence to this Determination given
by the National Energy Regulator of South
Africa on the below mentioned date;
SIGNATURE:
MS CECILIA KHUZWAYO
CHAIRPERSON: NERSA
DATE: 1-1
Determination made by the Minister of
Energy on the below mentioned date:
SIGNATURE:
DIKOBE BEN MARTINS, MP
MINISTER: ENERGY
DATE: j 2.01;
This gazette is also available free online at www.gpwonline.co.za
	STAATSKOERANT, 21 DESEMBER 2015 No. 39541   5

More Related Content

What's hot

R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...
R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...
R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...
Finpro
 
Pocketbook energy 2016-web-final_final
Pocketbook energy 2016-web-final_finalPocketbook energy 2016-web-final_final
Pocketbook energy 2016-web-final_final
Robert Szymczak
 
Presentation Maksym Sysoiev Renewables_September 2013_ENG
Presentation Maksym Sysoiev Renewables_September 2013_ENGPresentation Maksym Sysoiev Renewables_September 2013_ENG
Presentation Maksym Sysoiev Renewables_September 2013_ENG
Irina Koroleva
 

What's hot (19)

R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...
R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...
R cleantech finland bd to hungary - hungarian energy market by finpro debrecz...
 
Recent legislation of Ukraine in RE and EE (accepted from July 2014 till now)
Recent legislation of Ukraine in RE and EE (accepted from July 2014 till now)Recent legislation of Ukraine in RE and EE (accepted from July 2014 till now)
Recent legislation of Ukraine in RE and EE (accepted from July 2014 till now)
 
Pocketbook energy 2016-web-final_final
Pocketbook energy 2016-web-final_finalPocketbook energy 2016-web-final_final
Pocketbook energy 2016-web-final_final
 
Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...
 
Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
 
JackFaureIRCapstonePoster
JackFaureIRCapstonePosterJackFaureIRCapstonePoster
JackFaureIRCapstonePoster
 
Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...
 
Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?
 
Price of emergency electricity supply
Price of emergency electricity supplyPrice of emergency electricity supply
Price of emergency electricity supply
 
2010 Amendments to the Polish Energy Law
2010 Amendments to the Polish Energy Law2010 Amendments to the Polish Energy Law
2010 Amendments to the Polish Energy Law
 
Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...Monitoring report on Ukraine's progress in the implementation of the associat...
Monitoring report on Ukraine's progress in the implementation of the associat...
 
Protocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificateProtocol for submission of data to sldc for renewable energy certificate
Protocol for submission of data to sldc for renewable energy certificate
 
Presentation Maksym Sysoiev Renewables_September 2013_ENG
Presentation Maksym Sysoiev Renewables_September 2013_ENGPresentation Maksym Sysoiev Renewables_September 2013_ENG
Presentation Maksym Sysoiev Renewables_September 2013_ENG
 
New electricity market. How consumers will pay for the pas mistakes made at t...
New electricity market. How consumers will pay for the pas mistakes made at t...New electricity market. How consumers will pay for the pas mistakes made at t...
New electricity market. How consumers will pay for the pas mistakes made at t...
 
Fotovoltaika Bg
Fotovoltaika BgFotovoltaika Bg
Fotovoltaika Bg
 
Energy Reforms: October 2016 review
Energy Reforms: October 2016 reviewEnergy Reforms: October 2016 review
Energy Reforms: October 2016 review
 
FSM Power Plant Staus
FSM Power Plant StausFSM Power Plant Staus
FSM Power Plant Staus
 
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
tew (10.10.18) - Principles of regulatory setting prices for guaranteed suppl...
 

Similar to Nuclear deal

Power sector in nigeria
Power sector in nigeriaPower sector in nigeria
Power sector in nigeria
Machiraju Presentations Pvt. Ltd.
 
Ministerial Press Briefing 2014 Presentation by the MInister of Power, Prof....
Ministerial Press Briefing 2014 Presentation by the MInister of Power,  Prof....Ministerial Press Briefing 2014 Presentation by the MInister of Power,  Prof....
Ministerial Press Briefing 2014 Presentation by the MInister of Power, Prof....
FMINigeria
 
Ucraina green tariff
Ucraina  green tariffUcraina  green tariff
Ucraina green tariff
Carlo Scarpa
 
Aa32604610
Aa32604610Aa32604610
Aa32604610
IJMER
 
Consultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERCConsultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERC
Spark Network
 

Similar to Nuclear deal (20)

Case Study and Recommendations
Case Study and RecommendationsCase Study and Recommendations
Case Study and Recommendations
 
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GWBankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
 
Bankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa caseBankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa case
 
Power sector in nigeria
Power sector in nigeriaPower sector in nigeria
Power sector in nigeria
 
RCREEE-enerMENA_NREA Srategy_ jordan august 2013
RCREEE-enerMENA_NREA Srategy_ jordan august 2013RCREEE-enerMENA_NREA Srategy_ jordan august 2013
RCREEE-enerMENA_NREA Srategy_ jordan august 2013
 
Legal_Guide_2023_Chapter_9-compressed_2.pdf
Legal_Guide_2023_Chapter_9-compressed_2.pdfLegal_Guide_2023_Chapter_9-compressed_2.pdf
Legal_Guide_2023_Chapter_9-compressed_2.pdf
 
Legal_Guide_2023_Chapter_9-compressed.pdf
Legal_Guide_2023_Chapter_9-compressed.pdfLegal_Guide_2023_Chapter_9-compressed.pdf
Legal_Guide_2023_Chapter_9-compressed.pdf
 
CCXG Forum, September 2023, Mawufemo Modjinous
CCXG Forum, September 2023, Mawufemo ModjinousCCXG Forum, September 2023, Mawufemo Modjinous
CCXG Forum, September 2023, Mawufemo Modjinous
 
Castle Terminal Co. (Pty) Ltd and Oupa Teke requesting a meeting with preside...
Castle Terminal Co. (Pty) Ltd and Oupa Teke requesting a meeting with preside...Castle Terminal Co. (Pty) Ltd and Oupa Teke requesting a meeting with preside...
Castle Terminal Co. (Pty) Ltd and Oupa Teke requesting a meeting with preside...
 
CCXG Forum, September 2023, Rachid Ennassiri
CCXG Forum, September 2023, Rachid EnnassiriCCXG Forum, September 2023, Rachid Ennassiri
CCXG Forum, September 2023, Rachid Ennassiri
 
Bringing Electricity To The Rural Areas Designig Laws And Policies That Work
Bringing Electricity To The Rural Areas  Designig Laws And Policies That WorkBringing Electricity To The Rural Areas  Designig Laws And Policies That Work
Bringing Electricity To The Rural Areas Designig Laws And Policies That Work
 
Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...
Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...
Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...
 
Ministerial Press Briefing 2014 Presentation by the MInister of Power, Prof....
Ministerial Press Briefing 2014 Presentation by the MInister of Power,  Prof....Ministerial Press Briefing 2014 Presentation by the MInister of Power,  Prof....
Ministerial Press Briefing 2014 Presentation by the MInister of Power, Prof....
 
Ucraina green tariff
Ucraina  green tariffUcraina  green tariff
Ucraina green tariff
 
Aa32604610
Aa32604610Aa32604610
Aa32604610
 
Session 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, JordanSession 2 Dr Ziad Jibril Sabra, Jordan
Session 2 Dr Ziad Jibril Sabra, Jordan
 
Draft Feed-In Tariffs
Draft Feed-In TariffsDraft Feed-In Tariffs
Draft Feed-In Tariffs
 
Consultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERCConsultative Paper for Solar Projects tariff by TNERC
Consultative Paper for Solar Projects tariff by TNERC
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
Montenegro
MontenegroMontenegro
Montenegro
 

More from SABC News

More from SABC News (20)

Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
Ministry of Justice Extradition Eswatini 3.pdf
Ministry of Justice Extradition Eswatini 3.pdfMinistry of Justice Extradition Eswatini 3.pdf
Ministry of Justice Extradition Eswatini 3.pdf
 
January’s Producer Price Index increases to 4.7%
January’s Producer Price Index increases to 4.7%January’s Producer Price Index increases to 4.7%
January’s Producer Price Index increases to 4.7%
 
MEC MAJUBA SADDENED BY THE PASSING AWAY OF THREE TEACHERS FOLLOWING A CAR ACC...
MEC MAJUBA SADDENED BY THE PASSING AWAY OF THREE TEACHERS FOLLOWING A CAR ACC...MEC MAJUBA SADDENED BY THE PASSING AWAY OF THREE TEACHERS FOLLOWING A CAR ACC...
MEC MAJUBA SADDENED BY THE PASSING AWAY OF THREE TEACHERS FOLLOWING A CAR ACC...
 
ActionSA Files Public Protector Complaint Amidst Western Cape Government.docx
ActionSA Files Public Protector Complaint Amidst Western Cape Government.docxActionSA Files Public Protector Complaint Amidst Western Cape Government.docx
ActionSA Files Public Protector Complaint Amidst Western Cape Government.docx
 
Minister Gordhan Announces New Transnet Board Appointments_11 July 2023.pdf
Minister Gordhan Announces New Transnet Board Appointments_11 July 2023.pdfMinister Gordhan Announces New Transnet Board Appointments_11 July 2023.pdf
Minister Gordhan Announces New Transnet Board Appointments_11 July 2023.pdf
 
SA unemployment rate drops slightly to 32.7%
SA unemployment rate drops slightly to 32.7%SA unemployment rate drops slightly to 32.7%
SA unemployment rate drops slightly to 32.7%
 
REMNANTS OF FREDDY BRINGS HEAVY RAINS IN SOME PARTS OF SOUTH AFRICA WHICH MIG...
REMNANTS OF FREDDY BRINGS HEAVY RAINS IN SOME PARTS OF SOUTH AFRICA WHICH MIG...REMNANTS OF FREDDY BRINGS HEAVY RAINS IN SOME PARTS OF SOUTH AFRICA WHICH MIG...
REMNANTS OF FREDDY BRINGS HEAVY RAINS IN SOME PARTS OF SOUTH AFRICA WHICH MIG...
 
Letter to the Speaker re extension 14 November 2022.pdf
Letter to the Speaker re extension 14 November 2022.pdfLetter to the Speaker re extension 14 November 2022.pdf
Letter to the Speaker re extension 14 November 2022.pdf
 
Minister of Justice and Correctional Services Ronald Lamola’s Keynote Address...
Minister of Justice and Correctional Services Ronald Lamola’s Keynote Address...Minister of Justice and Correctional Services Ronald Lamola’s Keynote Address...
Minister of Justice and Correctional Services Ronald Lamola’s Keynote Address...
 
ANC Social Peace and Stability Policy Document
ANC Social Peace and Stability Policy DocumentANC Social Peace and Stability Policy Document
ANC Social Peace and Stability Policy Document
 
Education, Health, Science and Technology.pdf
Education, Health, Science and Technology.pdfEducation, Health, Science and Technology.pdf
Education, Health, Science and Technology.pdf
 
ANC Legislature and Governance Policy Document
ANC Legislature and Governance Policy DocumentANC Legislature and Governance Policy Document
ANC Legislature and Governance Policy Document
 
ANC Social Transformation Policy Document
ANC Social Transformation Policy DocumentANC Social Transformation Policy Document
ANC Social Transformation Policy Document
 
ANC Progressive Internationalism in a Changing World Policy Document
ANC Progressive Internationalism in a Changing World Policy DocumentANC Progressive Internationalism in a Changing World Policy Document
ANC Progressive Internationalism in a Changing World Policy Document
 
ANC Arts, Culture and Heritage Policy Document
ANC Arts, Culture and Heritage Policy DocumentANC Arts, Culture and Heritage Policy Document
ANC Arts, Culture and Heritage Policy Document
 
ANC Organisational Renewal Policy Document
ANC Organisational Renewal Policy DocumentANC Organisational Renewal Policy Document
ANC Organisational Renewal Policy Document
 
ANC Digital Communications and Battle of Ideas Policy Document
ANC Digital Communications and Battle of Ideas Policy DocumentANC Digital Communications and Battle of Ideas Policy Document
ANC Digital Communications and Battle of Ideas Policy Document
 
ANC Strengthening Economic Recovery and Reconstruction to Build an Inclusive ...
ANC Strengthening Economic Recovery and Reconstruction to Build an Inclusive ...ANC Strengthening Economic Recovery and Reconstruction to Build an Inclusive ...
ANC Strengthening Economic Recovery and Reconstruction to Build an Inclusive ...
 
Changing Balance of Forces
Changing Balance of ForcesChanging Balance of Forces
Changing Balance of Forces
 

Recently uploaded

Recently uploaded (8)

Textile Waste In India/managing-textile-waste-in-India
Textile Waste In India/managing-textile-waste-in-IndiaTextile Waste In India/managing-textile-waste-in-India
Textile Waste In India/managing-textile-waste-in-India
 
11052024_First India Newspaper Jaipur.pdf
11052024_First India Newspaper Jaipur.pdf11052024_First India Newspaper Jaipur.pdf
11052024_First India Newspaper Jaipur.pdf
 
Income Tax Regime Dilemma – New VS. Old pdf
Income Tax Regime Dilemma – New VS. Old pdfIncome Tax Regime Dilemma – New VS. Old pdf
Income Tax Regime Dilemma – New VS. Old pdf
 
12052024_First India Newspaper Jaipur.pdf
12052024_First India Newspaper Jaipur.pdf12052024_First India Newspaper Jaipur.pdf
12052024_First India Newspaper Jaipur.pdf
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
10052024_First India Newspaper Jaipur.pdf
10052024_First India Newspaper Jaipur.pdf10052024_First India Newspaper Jaipur.pdf
10052024_First India Newspaper Jaipur.pdf
 

Nuclear deal

  • 1. NUCLEAR PROGRAMME DETERMINATION UNDER SECTION 34(1) OF THE ELECTRICITY REGULATION ACT 4 OF 2006 PART A The Minister of Energy ("the Minister"), in consultation with the National Energy Regulator of South Africa (NERSA"), acting under section 34(1) of the Electricity Regulation Act 4 of 2006 (as amended) (the "ERA") has determined as follows: 1. that energy generation capacity needs to be procured to contribute towards energy security and to facilitate achievement of the greenhouse gas emission targets for the Republic of South Africa, accordingly, 9 600 megawatts (MW) should be procured to be generated from nuclear energy ("nuclear programme"), which is in accordance with the capacity allocated under the Integrated Resource Plan for Electricity 2010-2030 (published as GN 400 of 06 May 2011 in Government Gazette No, 34263) ("IRP 2010-2030" or as updated) [our insertion]; 2. electricity produced from the new generation capacity ("the electricity"), shall be procured through tendering procedures which are fair, equitable, transparent, competitive and cost- effective; 3. the nuclear programme shall target connection to the Grid as outlined in the IRP2010-2030 (or as updated), taking into account all relevant factors including the time required for procurement; 4. the electricity may only be sold to the entity designated as the buyer in paragraph 7 below, and only in accordance with the power purchase agreements and other project agreements to be concluded in the course of the procurement programmes; 5. the procurement agency in respect of the nuclear programme will be the Department of Energy; This gazette is also available free online at www.gpwonline.co.za 4   No. 39541 GOVERNMENT GAZETTE, 21 DECEMBER 2015 Government Notices • Goewermentskennisgewings Energy, Department of/ Energie, Departement van DEPARTMENT OF ENERGY NO. 1268 21 DECEMBER 2015 1268 Electricity Regulation Act (4/2006): Nuclear Programme: Determination under section 34(1) of the Electricity Regulation Act 39541
  • 2. 6. the role of the procurement agency will be to conduct the procurement process, including preparing any requests for qualification, requests for proposals and/or all related and associated documentation, negotiating the power purchase agreements, facilitating the conclusion of the other project agreements, and facilitating the satisfaction of any conditions precedent to financial close which are within its control; 7. the electricity must be purchased by Eskom Holdings SOC Limited or by any successor entity to be designated by the Minister of Energy, as buyer (off-taker); and 8. the electricity must be purchased from the special purpose vehicle(s) set up for the purpose of developing the nuclear programme. Concurrence to this Determination given by the National Energy Regulator of South Africa on the below mentioned date; SIGNATURE: MS CECILIA KHUZWAYO CHAIRPERSON: NERSA DATE: 1-1 Determination made by the Minister of Energy on the below mentioned date: SIGNATURE: DIKOBE BEN MARTINS, MP MINISTER: ENERGY DATE: j 2.01; This gazette is also available free online at www.gpwonline.co.za STAATSKOERANT, 21 DESEMBER 2015 No. 39541   5