Call sheet date time and location of music videos each time recorded updated
1. Crew Information Contacts and Information
Company name A.C.D.J Chris Owens
Jack Rogers Mobile number 07429165408
Mobile number 07775273767 Social network
Facebook CHRIS OWENS
Social network
Twitter CARTOON_CHRIS
Facebook Jack Rogers https://twitter.com/Cartoon_Chris
Twitter Jack Rogers Email addresschristian.owens123@gmail.com
Email addressjack.rogers13@sky.com Production duties and roles production
Production duties and roles Actor Alex Clare producer and Actor
runner and
Danny watt Mobile number 07873280005
Facebook ALEX CLARE
Mobile number 07718047609
Twitter AL_CLARE https://twitter.com/Al_Clare
Facebook Danny Watt
Email Addressalexclare96@gmail.com
Texting 07718047609
Production duties and roles Actor /
Address emailred.dan@live.com
Production duties and roles Actor
1|Page
2. Call Sheet Date Time and Location of Music Videos each Time Recorded
Date:Thursday the 28thh febuary 2012
Start Time and End Time:
Start: 12pm
End time: 5pm
Location:Worsly woods pathway and
Walkden pathways
2|Page
3. Schedule of the Day
Scenes being shot :1, 2, 3
Script pages being shot: 1
Address of the location for the day of filming music video:
Worsly woods pathway
Cast transportation and arrangements:Walking straight after college together
Walking straight ater college
3|Page
4. Call Sheet Date Time and Location of Music Videos each Time Recorded
Date:Wednesdaythe 27thh febuary 2012
Start Time and End Time:
Start :2pm
End time:5pm
Location:Worsly woods pathways
4|Page
5. Schedule of the Day
Scenes being shot :4,5,6,7
Script pages being shot: 1 and 2
Address of the location for the day of filming music video:
Worsly woods pathway and Walkden pathways
Cast transportation and arrangements:Meeting there on day off college at 2pm
5|Page
6. Call Sheet Date Time and Location of Music Videos each Time Recorded
Date:Thursday the 28thh febuary 2012
Start Time and End Time:
Start:12pm
End time: 5pm
Location:Worsly woods pathway and
Walkden pathways
6|Page
7. Schedule of the Day
Scenes being shot :8,9,10
Script pages being shot: 1 and 2
Address of the location for the day of filming music video:
Worsly woods pathway and Walkden pathways
Cast transportation and arrangements:Meeting there
7|Page
8. Call Sheet Date Time and Location of Music Videos each Time Recorded
Date:Friday 29th febuary 2012
Start Time and End Time:
Start 12pm
End time: 1pm
Location: Worsly woods pathway and
Walkden pathways
8|Page
9. Schedule of the Day
Scenes being shot :11,12
Script pages being shot: 1 and 2
Address of the location for the day of filming music video:
Worsly woods pathway and Walkden pathways
Cast transportation and arrangements:Meeting there on day off college at 12pm
9|Page
10. Call Sheet Date Time and Location of Music Videos each Time Recorded
Date:Sunday the 31st febuary 2012
Start Time and End Time:
Start 4pm
End time: 5pm
Location: Worsly woods pathway and
Walkden pathways
10 | P a g e
11. Schedule of the Day
Scenes being shot :13
Script pages being shot: 1 and 2
Address of the location for the day of filming music video:
Worsly woods pathway and Walkden pathways
Cast transportation and arrangements:Meeting there on day off college at 12pm
11 | P a g e
12. Safety notes (for example slippery surfaces) see the risk assessment chart:
Planned schedule dates of when and what time the filming will take place and for how many hours per day and week commencing from
25th to the 3rd March 2013
Scenes 10 am 11am 12pm 1pm 2pm 3pm 4pm 5pm 6pm 7pm
being shot
Monday 1 2,3, 13
Tuesday
Wednesday 4 5 6 7
Thursday 8 9,10
Friday
Saturday
Sunday 11,12,
12 | P a g e