1. Dawson Airport
Runway Paving Info
Dawson Airport Runway Paving Update
SUNDAY, MAY 26, 2019 – Part II
Skookum Asphalt Ltd. is aiming to complete 1,700’
today instead of the originally planned 2,000’ feet of
the final lift on the runway. Depending on the
paving for the rest of today, this will leave about 900’
of the runway, the Runway 03 turn pad and Taxiway
Alpha to be done on Monday. Taxiways Bravo,
Delta and Echo will likely be done on Tuesday
evening during an overnight closure.
2. Dawson Airport
Runway Paving Info
The painting crew continues to paint the runway
centerline, touch down zone and aiming point
markings in behind the paving crew.
Sidhu Trucking Ltd. is now backfilling the two
taxiways for the new South Apron with clean gravel.
Transportation Aviation Branch, Transportation
Engineering Branch and Skookum Asphalt Ltd.
continue to expect the runway to open at 0700h on
Tuesday, May 28.
9. Wednesday, May 29th
5:30 - 6:30 p.m.
Location: Downtown Hotel Conference Room
DawsonCity
Media Cooperative
Are you a Dawson-area resident who has made films/videos? Do you
have an interest in film /video production and media training?
Come hear our plans, and learn about how our local community may be
able to bring more video production support to the Klondike!
Become a member! We are a Yukon-registered cooperative association.
10.
11.
12.
13.
14. DAWSON
FOOD BANK
Find us at the Brown Church
on 5th across from the RV Park
OPEN
Every Tuesday
12 to 2PM
Donation
drop-off box
located on
the church
porch!
15.
16.
17. Dawson Airport
Runway Paving Info
Dawson Airport Runway Paving Update
SUNDAY, MAY 26, 2019 – Part II
Skookum Asphalt Ltd. is aiming to complete 1,700’
today instead of the originally planned 2,000’ feet of
the final lift on the runway. Depending on the paving
for the rest of today, this will leave about 900’ of the
runway, the Runway 03 turn pad and Taxiway Alpha
to be done on Monday. Taxiways Bravo, Delta and
Echo will likely be done on Tuesday evening during
an overnight closure.
18. Dawson Airport
Runway Paving Info
The painting crew continues to paint the runway
centerline, touch down zone and aiming point
markings in behind the paving crew.
Sidhu Trucking Ltd. is now backfilling the two
taxiways for the new South Apron with clean gravel.
Transportation Aviation Branch, Transportation
Engineering Branch and Skookum Asphalt Ltd.
continue to expect the runway to open at 0700h on
Tuesday, May 28.
25.
The Dawson District Renewable Resource
Council
The Dawson District Renewable Resource Council is a council
formed under the Umbrella Final Agreement. In keeping with
section 16.1.1.2 of the Tr'ondëk Hwëch’in Final Agreement, our
mandate is “to preserve and enhance the renewable resource
economy”. Public input is very important to the Council and you are
welcome to drop in at our office in Madame Trembley’s, 3rd
& King, or
approach any of the following members with concerns you might
have.
Mark Wierda Co-chair Ian Fraser Co-chair
Peggy Kormendy Kyler Mather
Robert Farr John Mitchell
Phone 993-6976 email dawsonrrc@northwestel.net.
26.
27.
28.
29.
30.
31.
32. Alcoholics Anonymous
Thinking of Quitting? We Can
Help!
Dawson Health Centre – Fridays at 1:30pm
meet by videoconference
North Star Group – Saturdays at 7pm
at the Community Support Centre
Beginners Group – Meet Thursdays 6 –
7pm at the Hospital (upstairs Room
#2160)
Drop by one of these meetings!
Call 993-5095 or 993-3734
for more information.
33.
34.
35. ***New for the City of Dawson
E-NEWS
Information delivered straight to your email
There are three types of E-NEWS you can
choose to sign up for:
City Office News and Notices
Recreation News and Notices, and
Tenders
To sign up and start receiving City of Dawson E-NEWS
Visit www.cityofdawson.ca
Subscribe with your name and email.
43. Dawson Airport
Runway Paving Info
Dawson Airport Runway Paving Update
SUNDAY, MAY 26, 2019 – Part II
Skookum Asphalt Ltd. is aiming to complete 1,700’
today instead of the originally planned 2,000’ feet of
the final lift on the runway. Depending on the paving
for the rest of today, this will leave about 900’ of the
runway, the Runway 03 turn pad and Taxiway Alpha
to be done on Monday. Taxiways Bravo, Delta and
Echo will likely be done on Tuesday evening during
an overnight closure.
44. Dawson Airport
Runway Paving Info
The painting crew continues to paint the runway
centerline, touch down zone and aiming point
markings in behind the paving crew.
Sidhu Trucking Ltd. is now backfilling the two
taxiways for the new South Apron with clean gravel.
Transportation Aviation Branch, Transportation
Engineering Branch and Skookum Asphalt Ltd.
continue to expect the runway to open at 0700h on
Tuesday, May 28.
56. Yukon Order of Pioneers
Lodge # 1 Dawson City
Hall Rentals Available
Seating Capacity 100
Contact:
289-356-6193
Or email at
krsschmidt@hotmail.com
Meetings are held on the first Thursday
of every month at 8:00pm
57.
58. Downtown Depot Hours
Open 1:00 – 5:00 pm
Tuesday – Saturday
Closed Sunday and Monday
Reducing Reuse Recycle
65. Robert Service
School Council
June 12, 2019
Regular Meeting
6:30 pm
Agenda
1. Call to order
2. Accept Agenda
3. Correspondence
4. Delegations
5. Minutes
6. Business Arising
7. New Business
8. Reports
8.1 Principal
8.2 TH Report
8.3 Financial
8.4 Chair
9. Community Concerns
10. Round Table
66. Dawson Airport
Runway Paving Info
Dawson Airport Runway Paving Update
SUNDAY, MAY 26, 2019 – Part II
Skookum Asphalt Ltd. is aiming to complete 1,700’
today instead of the originally planned 2,000’ feet of
the final lift on the runway. Depending on the
paving for the rest of today, this will leave about 900’
of the runway, the Runway 03 turn pad and Taxiway
Alpha to be done on Monday. Taxiways Bravo,
Delta and Echo will likely be done on Tuesday
evening during an overnight closure.
67. Dawson Airport
Runway Paving Info
The painting crew continues to paint the runway
centerline, touch down zone and aiming point
markings in behind the paving crew.
Sidhu Trucking Ltd. is now backfilling the two
taxiways for the new South Apron with clean gravel.
Transportation Aviation Branch, Transportation
Engineering Branch and Skookum Asphalt Ltd.
continue to expect the runway to open at 0700h on
Tuesday, May 28.