SlideShare a Scribd company logo
1 of 5
Download to read offline
Vietnam - Public – Private Partnerships - 2015
Overview
Modern, efficient infrastructure is vital to continued economic growth and lowers the costs of
doing business for all investors in Vietnam. Rapid economic growth and urbanisation is
driving high demand for roads, power, airports, ports, waste and water treatment, hospitals,
and other public infrastructure for goods and services. However, the State budget is estimated
to be able to meet only about 50% of Vietnam's infrastructure needs, which are estimated at
USD 170 billion from 2011-2020. The balance would need to come from other sources,
including from private investment in the form of Public-Private Partnerships (PPPs).
Although Vietnam has had a 'pilot' PPP programme since 2011, no PPP project has been
signed under this framework. The slightly more established Build-Operate-Transfer (BOT)
framework (most recently under Decree 108 has had more success, including, with the
financial close of Mong Duong 2 in 2011, making it the first significant foreign-invested
BOT power project to reach financial close in Vietnam since 2003. Furthermore, the market
has been encouraged by the financial close of the Nghi Son refinery project earlier in 2014,
which represents the largest financed project to ever close in Vietnam (although not under the
PPP/BOT regime). However, such successes are still limited, and foreign investment in
infrastructure in Vietnam continues to be low when compared with some other jurisdictions
in Southeast Asia.
Several factors contribute to the difficulties in financing PPPs/BOTs in Vietnam. One is the
lack of a clear legal framework. In this regard, the Government of Vietnam has made some
progress over the last year on the legal framework, including the issuance of a new Law on
Public Procurement that specifically applies to PPPs, and the preparation of a new PPP
decree (expected in late 2014), which is hoped to bring further clarity to the PPP legal
framework.
Secondly, to date the Government of Vietnam has had difficulty in bringing viable, attractive
PPP projects to the market. A number of tools are being set up to assist the Government in
their support for PPPs. These include the Project Development Facility (PDF), which is
envisioned to help undertake a rigorous assessment of potential projects, and the Viability
Gap Fund (VGF), which will provide needed Government support to make them financially
viable (if they are not otherwise). The Government has also recently released a List of
National Projects Calling for Foreign Investment which is a promising start to developing a
pipeline of viable projects.
Thirdly, the timeline for the negotiation of projects that have been awarded can often take
years. There are some concrete ways in which the Government of Vietnam could reduce the
timeline and uncertainty involved in the negotiation of PPPs. For example, it is important to
have precedent projects to look to, as well as consistent procedures and documents.
A clear legal framework for PPP Projects
Relevant State authorities: Ministry of Planning and Invest (MPI), authorised State bodies,
and other related
Issue description
Vietnam’s current regulation on Public-Private Partnership (PPPs), Decision 71, only
provides a basic framework for PPPs. It does not clarify key issues such as guarantees of
foreign currency convertibility, the use of foreign governing law, the availability of
Government support and guarantees, and other important bankability concerns. Where other
regulations do clarify an issue, it is often more worrying for investors (such as Letter 1604 on
BOT power projects, which arguably limits guarantees of foreign currency convertibility to
30%). Procurement rules for the selection of investors for PPPs have also been unclear, and
while there has been some improvement with the issuance of the new Law on Public
Procurement, many details are left for future implementing regulations.
The fact that there is a separate regulation on BOT projects, Decree 108, also creates
confusion. It is often unclear to investors which regime applies to a project, and there is no
cohesion within the various State bodies as to which regime to use.
The remaining legal framework relevant to PPPs, such as the Land Law , seems unable to
provide comfort on key bankability issues such as taking security over land under the Land
Law.
By the end of 2014, however, a new PPP Decree is expected to supersede Decision 71 and
Decree 108, and unify the two regimes into one comprehensive PPP regime. The new decree
is hoped to clarify some of the questions that persisted under the current PPP framework.
Among other things, it is expected to remove previous limits for State contribution,
permitting instead the level of State contribution to vary depending on the financial feasibility
of each project. It is also expected to set out a method for investors to propose projects, and
clarify the process of developing a project, including the institutional roles of each State body
involved in the project. The new PPP Decree will not have the legal reach, however, to solve
all of the legal issues that have affected the implementation of PPP programmes in Vietnam.
Potential gains/concerns for Vietnam
Other ASEAN countries such as the Philippines, Indonesia and Thailand have embarked on
ambitious PPP programmes (though not always under the ’PPP’ moniker) that start with a
foreign-investor friendly PPP legal framework. While Vietnam remains without a clear PPP
legal framework, these other countries will continue to become more attractive and it will be
difficult for investors to take the risk of deciding to invest in PPPs in Vietnam.
Recommendations
• Continue to develop detailed policies and guidelines related to PPPs that are attractive
to foreign investors looking to invest in infrastructure in the country, in cooperation with the
Government of Vietnam as a whole
• Test these regulations with actual projects, so that investors can get comfortable with
how they will be interpreted in the context of developing a PPP
Developing a Pipeline of Visible Projects
Relevant Ministries: Ministry of Planning and Invest (MPI), authorised State bodies, and
other related
Issue description
Currently, most Public-Private Partnership (PPP)/Build-Operate-Transfer (BOT) projects in
Vietnam are proposed by an investor to the Government of Vietnam and selected without a
transparent, competitive tender. To align Vietnam better with international best practices (and
its own policies), the Government may consider taking the lead in identifying potential PPP
projects, assessing them, and then offering them to investors through a competitive, open
tendering procedure.
The Government of Vietnam recently made significant progress in this regard through the
issuance of Decision 631, a list of 127 national projects seeking foreign investment,
approximately 35 of which are specified to be developed under the PPP investment form.
While Decision 631 provides guidance on the Government’s priorities, individual projects
will first need to be carefully studied for technical and financial feasibility before bringing
them to market.
One helpful tool will be the Project Development Facility (PDF), a donor-sponsored USD 20
million facility (due to be launched in 2015) that will be used to assess the feasibility of
potential PPPs. The facility will be a revolving fund that is paid into by the winning investor
of the projects that do reach market (i.e., the winning bidder will be expected to cover the
costs of preparing the project). The Government has also set aside a new Viability Gap Fund
(VGF) of up to USD 1 billion in order to support projects that would not otherwise be
financially viable.
These are good starts, but there will also be a need to coordinate among the various
Government bodies (possibly through the PPP Office under the MPI) to resolve some key
bankability issues before a project can be successfully tendered. For example, currently the
scope of a government guarantee is negotiated after the project is awarded. It would be more
efficient if such policies were set out in the bidding documentation (with a view to ensuring
developer and lender bankability upfront). Furthermore, the Government of Vietnam will
have to address the role that state-owned enterprises (SOEs) play in a new PPP framework.
Currently, the perception is that SOEs have an unfair advantage as they often are given
projects without a competitive tender.
Potential gains/concerns for Vietnam
The list of projects under Decision 631, the PDF and the VGF send a strong and positive
signal to the market that the Government of Vietnam is dedicated to developing PPPs.
However, bringing a viable project to the market will require a rigorous, independent analysis
of the project and significant commitment from all of the various State bodies involved to
ensure that the project is bankable. Investors already noted that there is a lack of projects
being brought for international competitive tender, and there is often an assumption that
SOEs have a 'special status’ against which foreign investors cannot compete. If the
Government of Vietnam wants to encourage foreign investment (and the foreign funding that
often comes with it), it will need to show a concerted commitment to foreign investment in
PPPs.
Recommendations
• Prioritise the projects slated as PPPs on the list in Decision 631
• Make use of the PDF and put potential projects through a rigorous assessment
(with the help of international technical and financial consultants)
• Rally the support of key State bodies for such projects, including developing the
scopes of guarantees and legal opinions early in the process (to remove uncertainty)
• Submit selected projects to a competitive, transparent tender as contemplated under
the new Law on Public Procurement
Reduce Negotiation Time for Projects
Relevant Ministries: Ministry of Planning and Invest (MPI), authorised State bodies, and
other related
One consistent issue raised by investors in Public-Private Partnership (PPPs) in Vietnam is
the length of the negotiation time for projects. For the independent power projects that have
been negotiated under the Build-Operate-Transfer (BOT) model, it usually takes several
years from the tender award to financial close. One foreign-invested power project currently
being negotiated had a recent hiatus of two years. This results in unnecessary costs for the
investors. Anecdotally, we understand that some investors, while eager for their projects to
move forward, are losing patience with the lack of progress.
The lack of a clear legal framework, which is the first issue raised in this Chapter, contributes
to the length of the negotiation time. Indeed, it is difficult for decision-makers to know which
rules to follow, resulting in delays as issues are decided on a case-by-case basis. As there are
many Government bodies involved in the development of PPPs, the Government of Vietnam
also faces bottlenecks from an institutional framework that can sometimes be inefficient. A
specified Authorised State body (ASB) leads the development of the PPP, the Ministry of
Justice is involved in the contract negotiation and subsequent issuance of a legal opinion, the
State Bank of Vietnam is involved where there is a need for foreign currency conversion, and
the local People’s Committees are involved where there is a land requirement. It would be
helpful if such State bodies coordinated more smoothly with one another under a high-level
direction.
The timeline is also slowed down by the need to negotiate the same issues with every project
'from scratch’ rather than relying on precedent or standardised documents as a starting point,
and the fact that the Government counterparties have not built up enough of a projects
portfolio to negotiate the contracts efficiently. Further capacity-building and experience in
negotiating PPPs would address these issues.
Potential gains/concerns for Vietnam
Multilateral banks and commercial banks are wary of Vietnam as a market for PPPs because
of the length of time it takes to negotiate documents. This is in comparison to some other
markets in Southeast Asia (such as Thailand, Indonesia and Laos) which have more robust
PPP frameworks and pipelines of projects and thus are much more attractive to investors.
Vietnam must present well-structured, attractive projects in an environment which reduces
risk and increases returns for investors, to better compete with its neighbours for a finite
amount of private sector capital for infrastructure.
Recommendations
• Concentrate on bringing a few 'landmark' projects to financial close, in order to set
expectations in the market (and build capacity for PPPs within key Government
bodies)
• Include key contracts and guidelines in the bidding documents to reduce negotiation
time after the tender is awarded
• Clarify roles of the various institutions related to the development of PPPs (especially
the role of the PPP Office under the Ministry of Planning and Investment) and ensure
that all ASBs have a consistent approach to PPPs
Please contact Oliver Massmann under Uomassmann@duanemorris.comU if you have any
questions.

More Related Content

What's hot

Mafwenga-Taxability of Commission Under Destination-based VAT(1)
Mafwenga-Taxability of Commission Under Destination-based VAT(1)Mafwenga-Taxability of Commission Under Destination-based VAT(1)
Mafwenga-Taxability of Commission Under Destination-based VAT(1)
Prof Handley Mpoki Mafwenga
 

What's hot (20)

Procurement Procedures Manual for Public Procurement in Ekiti State
Procurement Procedures Manual for Public Procurement in Ekiti StateProcurement Procedures Manual for Public Procurement in Ekiti State
Procurement Procedures Manual for Public Procurement in Ekiti State
 
Important Definitions under GST
Important Definitions under GSTImportant Definitions under GST
Important Definitions under GST
 
VIETNAM – INVESTMENT IN THE HEALTHCARE AND MEDICAL DEVICE SECTORS
VIETNAM – INVESTMENT IN THE HEALTHCARE AND MEDICAL DEVICE SECTORSVIETNAM – INVESTMENT IN THE HEALTHCARE AND MEDICAL DEVICE SECTORS
VIETNAM – INVESTMENT IN THE HEALTHCARE AND MEDICAL DEVICE SECTORS
 
Mafwenga-Taxability of Commission Under Destination-based VAT(1)
Mafwenga-Taxability of Commission Under Destination-based VAT(1)Mafwenga-Taxability of Commission Under Destination-based VAT(1)
Mafwenga-Taxability of Commission Under Destination-based VAT(1)
 
SEC-Class note
SEC-Class noteSEC-Class note
SEC-Class note
 
Foreign trade law
Foreign trade lawForeign trade law
Foreign trade law
 
Planning for the Regional Public Procurement Market: The Legal Perspective - ...
Planning for the Regional Public Procurement Market: The Legal Perspective - ...Planning for the Regional Public Procurement Market: The Legal Perspective - ...
Planning for the Regional Public Procurement Market: The Legal Perspective - ...
 
Vietnam - Investment Guide - All you must know from Lawyer in Vietnam Dr. Oli...
Vietnam - Investment Guide - All you must know from Lawyer in Vietnam Dr. Oli...Vietnam - Investment Guide - All you must know from Lawyer in Vietnam Dr. Oli...
Vietnam - Investment Guide - All you must know from Lawyer in Vietnam Dr. Oli...
 
VIETNAM – INFRASTRUCTURE AND PUBLIC PRIVATE PARTNERSHIPS – THE EVFTA AND CPTP...
VIETNAM – INFRASTRUCTURE AND PUBLIC PRIVATE PARTNERSHIPS – THE EVFTA AND CPTP...VIETNAM – INFRASTRUCTURE AND PUBLIC PRIVATE PARTNERSHIPS – THE EVFTA AND CPTP...
VIETNAM – INFRASTRUCTURE AND PUBLIC PRIVATE PARTNERSHIPS – THE EVFTA AND CPTP...
 
Asia Counsel Insights March 2019
Asia Counsel Insights March 2019Asia Counsel Insights March 2019
Asia Counsel Insights March 2019
 
TREATY BETWEEN THE UNITED STATES OF AMERICA AND THE PEOPLE S  REPUBLIC OF BA...
TREATY BETWEEN THE UNITED STATES OF AMERICA AND THE PEOPLE S  REPUBLIC OF BA...TREATY BETWEEN THE UNITED STATES OF AMERICA AND THE PEOPLE S  REPUBLIC OF BA...
TREATY BETWEEN THE UNITED STATES OF AMERICA AND THE PEOPLE S  REPUBLIC OF BA...
 
Ppra rules
Ppra rulesPpra rules
Ppra rules
 
Double Taxation Agreement between India and Bangladesh
Double Taxation Agreement between India and BangladeshDouble Taxation Agreement between India and Bangladesh
Double Taxation Agreement between India and Bangladesh
 
Lawyer in Vietnam Dr. Oliver Massmann SECURITIES AND BANKING GUIDE UPDATE 2018
Lawyer in Vietnam Dr. Oliver Massmann SECURITIES AND BANKING GUIDE UPDATE 2018Lawyer in Vietnam Dr. Oliver Massmann SECURITIES AND BANKING GUIDE UPDATE 2018
Lawyer in Vietnam Dr. Oliver Massmann SECURITIES AND BANKING GUIDE UPDATE 2018
 
PUBLIC PROCUREMENT REGIME & AN OVERVIEW OF PUBLIC PROCUREMENT RULES, 2004
PUBLIC PROCUREMENT REGIME  & AN OVERVIEW OF PUBLIC  PROCUREMENT   RULES, 2004 PUBLIC PROCUREMENT REGIME  & AN OVERVIEW OF PUBLIC  PROCUREMENT   RULES, 2004
PUBLIC PROCUREMENT REGIME & AN OVERVIEW OF PUBLIC PROCUREMENT RULES, 2004
 
MLI Comparative Analysis
MLI Comparative AnalysisMLI Comparative Analysis
MLI Comparative Analysis
 
Introduction and ppra ord & Rules
Introduction and ppra ord & RulesIntroduction and ppra ord & Rules
Introduction and ppra ord & Rules
 
Procurement
ProcurementProcurement
Procurement
 
Lawyer in Vietnam Dr. Oliver Massmann DOING BUSINESS IN VIETNAM
Lawyer in Vietnam Dr. Oliver Massmann DOING BUSINESS IN VIETNAMLawyer in Vietnam Dr. Oliver Massmann DOING BUSINESS IN VIETNAM
Lawyer in Vietnam Dr. Oliver Massmann DOING BUSINESS IN VIETNAM
 
Place of provision of service rules
Place of provision of service rulesPlace of provision of service rules
Place of provision of service rules
 

Similar to Vietnam – Public – Private Partnerships – 2015

Can PPPs solve Indonesias infrastructure needs
Can PPPs solve Indonesias infrastructure needsCan PPPs solve Indonesias infrastructure needs
Can PPPs solve Indonesias infrastructure needs
H2O Management
 
enhanced-infrastructure-distri
enhanced-infrastructure-distrienhanced-infrastructure-distri
enhanced-infrastructure-distri
Mike Debiak
 

Similar to Vietnam – Public – Private Partnerships – 2015 (20)

VIETNAM - PUBLIC-PRIVATE PARTNERSHIPS – What you must know:
VIETNAM - PUBLIC-PRIVATE PARTNERSHIPS – What you must know:VIETNAM - PUBLIC-PRIVATE PARTNERSHIPS – What you must know:
VIETNAM - PUBLIC-PRIVATE PARTNERSHIPS – What you must know:
 
New PPP Decree Coming Soon
New PPP Decree Coming SoonNew PPP Decree Coming Soon
New PPP Decree Coming Soon
 
Public Private Partnerships - - Copy.docx
Public Private Partnerships - - Copy.docxPublic Private Partnerships - - Copy.docx
Public Private Partnerships - - Copy.docx
 
Public Private Partnerships -.docx
Public Private Partnerships -.docxPublic Private Partnerships -.docx
Public Private Partnerships -.docx
 
12-Public Private Partnerships.docx
12-Public Private Partnerships.docx12-Public Private Partnerships.docx
12-Public Private Partnerships.docx
 
Can PPPs solve Indonesias infrastructure needs
Can PPPs solve Indonesias infrastructure needsCan PPPs solve Indonesias infrastructure needs
Can PPPs solve Indonesias infrastructure needs
 
VIETNAM - THE NEW LAW ON PUBLIC PRIVATE PARTNERSHIPS - MAIN IMPROVEMENTS OVER...
VIETNAM - THE NEW LAW ON PUBLIC PRIVATE PARTNERSHIPS - MAIN IMPROVEMENTS OVER...VIETNAM - THE NEW LAW ON PUBLIC PRIVATE PARTNERSHIPS - MAIN IMPROVEMENTS OVER...
VIETNAM - THE NEW LAW ON PUBLIC PRIVATE PARTNERSHIPS - MAIN IMPROVEMENTS OVER...
 
Vietnam Infrastructure
Vietnam InfrastructureVietnam Infrastructure
Vietnam Infrastructure
 
Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private Partnership
 
LAWYER IN VIETNAM DR. OLIVER MASSMANN KEY COMMENTS ON DRAFT PUBLIC PRIVATE PA...
LAWYER IN VIETNAM DR. OLIVER MASSMANN KEY COMMENTS ON DRAFT PUBLIC PRIVATE PA...LAWYER IN VIETNAM DR. OLIVER MASSMANN KEY COMMENTS ON DRAFT PUBLIC PRIVATE PA...
LAWYER IN VIETNAM DR. OLIVER MASSMANN KEY COMMENTS ON DRAFT PUBLIC PRIVATE PA...
 
Lawyer in Vietnam Dr. Oliver Massmann Public-Private Partnerships in Infrastr...
Lawyer in Vietnam Dr. Oliver Massmann Public-Private Partnerships in Infrastr...Lawyer in Vietnam Dr. Oliver Massmann Public-Private Partnerships in Infrastr...
Lawyer in Vietnam Dr. Oliver Massmann Public-Private Partnerships in Infrastr...
 
Filip drapak ppp in financial crises english
Filip drapak ppp in financial crises englishFilip drapak ppp in financial crises english
Filip drapak ppp in financial crises english
 
VIETNAM – WATER PROJECTS – LAWS ON PUBLIC PRIVATE PARTNERSHIPS – GLOBAL WATER...
VIETNAM – WATER PROJECTS – LAWS ON PUBLIC PRIVATE PARTNERSHIPS – GLOBAL WATER...VIETNAM – WATER PROJECTS – LAWS ON PUBLIC PRIVATE PARTNERSHIPS – GLOBAL WATER...
VIETNAM – WATER PROJECTS – LAWS ON PUBLIC PRIVATE PARTNERSHIPS – GLOBAL WATER...
 
VIETNAM - PUBLIC-PRIVATE-PARTNERSHIPS (PPP) AND CPTPP AND EVFTA/IPA DISPUTE S...
VIETNAM - PUBLIC-PRIVATE-PARTNERSHIPS (PPP) AND CPTPP AND EVFTA/IPA DISPUTE S...VIETNAM - PUBLIC-PRIVATE-PARTNERSHIPS (PPP) AND CPTPP AND EVFTA/IPA DISPUTE S...
VIETNAM - PUBLIC-PRIVATE-PARTNERSHIPS (PPP) AND CPTPP AND EVFTA/IPA DISPUTE S...
 
enhanced-infrastructure-distri
enhanced-infrastructure-distrienhanced-infrastructure-distri
enhanced-infrastructure-distri
 
VIETNAM – NEW LAW ON INVESTMENT PROVES THE GOVERNMENT’S EFFORT TO ATTRACT FOR...
VIETNAM – NEW LAW ON INVESTMENT PROVES THE GOVERNMENT’S EFFORT TO ATTRACT FOR...VIETNAM – NEW LAW ON INVESTMENT PROVES THE GOVERNMENT’S EFFORT TO ATTRACT FOR...
VIETNAM – NEW LAW ON INVESTMENT PROVES THE GOVERNMENT’S EFFORT TO ATTRACT FOR...
 
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – THE GOVERNMENT RELEASED NEW...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – THE GOVERNMENT RELEASED NEW...LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – THE GOVERNMENT RELEASED NEW...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – THE GOVERNMENT RELEASED NEW...
 
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS I...
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS I...VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS I...
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS I...
 
understand challenges for infrastructure
understand challenges for infrastructureunderstand challenges for infrastructure
understand challenges for infrastructure
 
Financial for development final project
Financial for development final projectFinancial for development final project
Financial for development final project
 

More from Dr. Oliver Massmann

More from Dr. Oliver Massmann (20)

Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key Highlights
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
 
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
 
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
 

Recently uploaded

一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
Airst S
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
RRR Chambers
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
JosephCanama
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
MollyBrown86
 

Recently uploaded (20)

一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
MOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptx
MOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptxMOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptx
MOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptx
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptx
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction Fails
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxAnalysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
Hely-Hutchinson v. Brayhead Ltd .pdf
Hely-Hutchinson v. Brayhead Ltd         .pdfHely-Hutchinson v. Brayhead Ltd         .pdf
Hely-Hutchinson v. Brayhead Ltd .pdf
 
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam TakersPhilippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
 

Vietnam – Public – Private Partnerships – 2015

  • 1. Vietnam - Public – Private Partnerships - 2015 Overview Modern, efficient infrastructure is vital to continued economic growth and lowers the costs of doing business for all investors in Vietnam. Rapid economic growth and urbanisation is driving high demand for roads, power, airports, ports, waste and water treatment, hospitals, and other public infrastructure for goods and services. However, the State budget is estimated to be able to meet only about 50% of Vietnam's infrastructure needs, which are estimated at USD 170 billion from 2011-2020. The balance would need to come from other sources, including from private investment in the form of Public-Private Partnerships (PPPs). Although Vietnam has had a 'pilot' PPP programme since 2011, no PPP project has been signed under this framework. The slightly more established Build-Operate-Transfer (BOT) framework (most recently under Decree 108 has had more success, including, with the financial close of Mong Duong 2 in 2011, making it the first significant foreign-invested BOT power project to reach financial close in Vietnam since 2003. Furthermore, the market has been encouraged by the financial close of the Nghi Son refinery project earlier in 2014, which represents the largest financed project to ever close in Vietnam (although not under the PPP/BOT regime). However, such successes are still limited, and foreign investment in infrastructure in Vietnam continues to be low when compared with some other jurisdictions in Southeast Asia. Several factors contribute to the difficulties in financing PPPs/BOTs in Vietnam. One is the lack of a clear legal framework. In this regard, the Government of Vietnam has made some progress over the last year on the legal framework, including the issuance of a new Law on Public Procurement that specifically applies to PPPs, and the preparation of a new PPP decree (expected in late 2014), which is hoped to bring further clarity to the PPP legal framework. Secondly, to date the Government of Vietnam has had difficulty in bringing viable, attractive PPP projects to the market. A number of tools are being set up to assist the Government in their support for PPPs. These include the Project Development Facility (PDF), which is envisioned to help undertake a rigorous assessment of potential projects, and the Viability Gap Fund (VGF), which will provide needed Government support to make them financially viable (if they are not otherwise). The Government has also recently released a List of National Projects Calling for Foreign Investment which is a promising start to developing a pipeline of viable projects. Thirdly, the timeline for the negotiation of projects that have been awarded can often take years. There are some concrete ways in which the Government of Vietnam could reduce the timeline and uncertainty involved in the negotiation of PPPs. For example, it is important to have precedent projects to look to, as well as consistent procedures and documents.
  • 2. A clear legal framework for PPP Projects Relevant State authorities: Ministry of Planning and Invest (MPI), authorised State bodies, and other related Issue description Vietnam’s current regulation on Public-Private Partnership (PPPs), Decision 71, only provides a basic framework for PPPs. It does not clarify key issues such as guarantees of foreign currency convertibility, the use of foreign governing law, the availability of Government support and guarantees, and other important bankability concerns. Where other regulations do clarify an issue, it is often more worrying for investors (such as Letter 1604 on BOT power projects, which arguably limits guarantees of foreign currency convertibility to 30%). Procurement rules for the selection of investors for PPPs have also been unclear, and while there has been some improvement with the issuance of the new Law on Public Procurement, many details are left for future implementing regulations. The fact that there is a separate regulation on BOT projects, Decree 108, also creates confusion. It is often unclear to investors which regime applies to a project, and there is no cohesion within the various State bodies as to which regime to use. The remaining legal framework relevant to PPPs, such as the Land Law , seems unable to provide comfort on key bankability issues such as taking security over land under the Land Law. By the end of 2014, however, a new PPP Decree is expected to supersede Decision 71 and Decree 108, and unify the two regimes into one comprehensive PPP regime. The new decree is hoped to clarify some of the questions that persisted under the current PPP framework. Among other things, it is expected to remove previous limits for State contribution, permitting instead the level of State contribution to vary depending on the financial feasibility of each project. It is also expected to set out a method for investors to propose projects, and clarify the process of developing a project, including the institutional roles of each State body involved in the project. The new PPP Decree will not have the legal reach, however, to solve all of the legal issues that have affected the implementation of PPP programmes in Vietnam. Potential gains/concerns for Vietnam Other ASEAN countries such as the Philippines, Indonesia and Thailand have embarked on ambitious PPP programmes (though not always under the ’PPP’ moniker) that start with a foreign-investor friendly PPP legal framework. While Vietnam remains without a clear PPP legal framework, these other countries will continue to become more attractive and it will be difficult for investors to take the risk of deciding to invest in PPPs in Vietnam. Recommendations
  • 3. • Continue to develop detailed policies and guidelines related to PPPs that are attractive to foreign investors looking to invest in infrastructure in the country, in cooperation with the Government of Vietnam as a whole • Test these regulations with actual projects, so that investors can get comfortable with how they will be interpreted in the context of developing a PPP Developing a Pipeline of Visible Projects Relevant Ministries: Ministry of Planning and Invest (MPI), authorised State bodies, and other related Issue description Currently, most Public-Private Partnership (PPP)/Build-Operate-Transfer (BOT) projects in Vietnam are proposed by an investor to the Government of Vietnam and selected without a transparent, competitive tender. To align Vietnam better with international best practices (and its own policies), the Government may consider taking the lead in identifying potential PPP projects, assessing them, and then offering them to investors through a competitive, open tendering procedure. The Government of Vietnam recently made significant progress in this regard through the issuance of Decision 631, a list of 127 national projects seeking foreign investment, approximately 35 of which are specified to be developed under the PPP investment form. While Decision 631 provides guidance on the Government’s priorities, individual projects will first need to be carefully studied for technical and financial feasibility before bringing them to market. One helpful tool will be the Project Development Facility (PDF), a donor-sponsored USD 20 million facility (due to be launched in 2015) that will be used to assess the feasibility of potential PPPs. The facility will be a revolving fund that is paid into by the winning investor of the projects that do reach market (i.e., the winning bidder will be expected to cover the costs of preparing the project). The Government has also set aside a new Viability Gap Fund (VGF) of up to USD 1 billion in order to support projects that would not otherwise be financially viable. These are good starts, but there will also be a need to coordinate among the various Government bodies (possibly through the PPP Office under the MPI) to resolve some key bankability issues before a project can be successfully tendered. For example, currently the scope of a government guarantee is negotiated after the project is awarded. It would be more efficient if such policies were set out in the bidding documentation (with a view to ensuring developer and lender bankability upfront). Furthermore, the Government of Vietnam will have to address the role that state-owned enterprises (SOEs) play in a new PPP framework. Currently, the perception is that SOEs have an unfair advantage as they often are given projects without a competitive tender. Potential gains/concerns for Vietnam
  • 4. The list of projects under Decision 631, the PDF and the VGF send a strong and positive signal to the market that the Government of Vietnam is dedicated to developing PPPs. However, bringing a viable project to the market will require a rigorous, independent analysis of the project and significant commitment from all of the various State bodies involved to ensure that the project is bankable. Investors already noted that there is a lack of projects being brought for international competitive tender, and there is often an assumption that SOEs have a 'special status’ against which foreign investors cannot compete. If the Government of Vietnam wants to encourage foreign investment (and the foreign funding that often comes with it), it will need to show a concerted commitment to foreign investment in PPPs. Recommendations • Prioritise the projects slated as PPPs on the list in Decision 631 • Make use of the PDF and put potential projects through a rigorous assessment (with the help of international technical and financial consultants) • Rally the support of key State bodies for such projects, including developing the scopes of guarantees and legal opinions early in the process (to remove uncertainty) • Submit selected projects to a competitive, transparent tender as contemplated under the new Law on Public Procurement Reduce Negotiation Time for Projects Relevant Ministries: Ministry of Planning and Invest (MPI), authorised State bodies, and other related One consistent issue raised by investors in Public-Private Partnership (PPPs) in Vietnam is the length of the negotiation time for projects. For the independent power projects that have been negotiated under the Build-Operate-Transfer (BOT) model, it usually takes several years from the tender award to financial close. One foreign-invested power project currently being negotiated had a recent hiatus of two years. This results in unnecessary costs for the investors. Anecdotally, we understand that some investors, while eager for their projects to move forward, are losing patience with the lack of progress. The lack of a clear legal framework, which is the first issue raised in this Chapter, contributes to the length of the negotiation time. Indeed, it is difficult for decision-makers to know which rules to follow, resulting in delays as issues are decided on a case-by-case basis. As there are many Government bodies involved in the development of PPPs, the Government of Vietnam also faces bottlenecks from an institutional framework that can sometimes be inefficient. A specified Authorised State body (ASB) leads the development of the PPP, the Ministry of Justice is involved in the contract negotiation and subsequent issuance of a legal opinion, the State Bank of Vietnam is involved where there is a need for foreign currency conversion, and the local People’s Committees are involved where there is a land requirement. It would be
  • 5. helpful if such State bodies coordinated more smoothly with one another under a high-level direction. The timeline is also slowed down by the need to negotiate the same issues with every project 'from scratch’ rather than relying on precedent or standardised documents as a starting point, and the fact that the Government counterparties have not built up enough of a projects portfolio to negotiate the contracts efficiently. Further capacity-building and experience in negotiating PPPs would address these issues. Potential gains/concerns for Vietnam Multilateral banks and commercial banks are wary of Vietnam as a market for PPPs because of the length of time it takes to negotiate documents. This is in comparison to some other markets in Southeast Asia (such as Thailand, Indonesia and Laos) which have more robust PPP frameworks and pipelines of projects and thus are much more attractive to investors. Vietnam must present well-structured, attractive projects in an environment which reduces risk and increases returns for investors, to better compete with its neighbours for a finite amount of private sector capital for infrastructure. Recommendations • Concentrate on bringing a few 'landmark' projects to financial close, in order to set expectations in the market (and build capacity for PPPs within key Government bodies) • Include key contracts and guidelines in the bidding documents to reduce negotiation time after the tender is awarded • Clarify roles of the various institutions related to the development of PPPs (especially the role of the PPP Office under the Ministry of Planning and Investment) and ensure that all ASBs have a consistent approach to PPPs Please contact Oliver Massmann under Uomassmann@duanemorris.comU if you have any questions.