1. 0390768 Peat 100 000 t(wet)/a Electricity Finland
Part 1 - Analyze the problem posed by the stakeholders
Target is to create preliminary design specification (requirements) to enable technical and commercial
selection in the next phases. Report to project management
0-2 outlook and form
0-1 description of fuel: Describe fuel chain to plant location - expand your initial values
0-1 description of location: Describe location - expand your initial values
0-1 description of target use: Describe target use - expand your initial values
0-1 define owner: Define the owners problem by describing their needs, expectations and
technical requirements
0-1 define environmental: Define the environmental pressure groups problem by describing their needs,
expectations and technical requirements
0-1 define governement: Define the governement's problem by describing its needs, expectations and
technical requirements
0-2 summary: Develop detailed technical requirements for possible technical solutions to the extent
necessary to enable technical and economical design solutions in
the next phases
You can select the excact location of your plant as you see best.
You can choose other parameters not given as you see best
You should try to seek realistic comments of various stakeholders from net
Aim: The aim is to learn how to extract from different interested parties what they desire from the
technical solution. i.e. What makes the best/optimal solution for each stakeholder.
The second aim is to learn how to combine different aims into one design specification.