2. ACTIVITY
I. Lathe Flank pipe diameter 600 mm
II. Grinding iron with a thick 20 mm and
diameter 150 mm
III. Mak a thread in thr tabs diameter at 8
mm.
IV. Installing lights in the factory
V. Lathe and drill steel in solo.
3. Lathe Flank pipe diameter 600 mm
a) 2 people
b) 3 days
c) Turning speed is too fast.
4. Grinding iron with a thick 20 mm and diameter
150 mm
a) 2 people
b) 2 days
c) incision is too small
5. Mak a thread in thr tabs diameter at 8
mm.
a) 3 people
b) 4 days
c) its tab broken
6. Installing lights in the factory
a) 2 people
b) 15 minutes
c) point of underexposed
7. a) 4 people
b) 1 day
c) wrong placement of the workpiece
8. CONCLUSION
After joining job training industry at PT.Batur Jaya I can run a lathe,
milling machine sekrap and well. I can be responsible.