13.1. valorizacion
- 1. OBRA:
ENTIDAD: MUNICIPALIDAD PROVINCIAL DE YUNGAY
UBICACIÓN: ACOBAMBA/COCHAHUAIN - YUNGAY - ANCASH
RES. TÉC.: ING. GERARDO M. REVELO SANCHEZ PRESUESTO ADICIONAL:
SUPERVISOR: ING. LENIN CAMPOS FELIX
METRADO VALORIZACION METRADO VALORIZACION % METRADO VALORIZACION %
01 CONTRUCCION DE CANAL TAPADO 10,134.62
01.01 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 13.50 0.99 13.37 0.00 0.00 13.50 13.37 100.00 13.50 13.37 100.00 0.00 0.00 0.00
01.02 CORTE DE LOSA DE CONCRETO m 15.00 29.78 446.70 0.00 0.00 15.00 446.70 100.00 15.00 446.70 100.00 0.00 0.00 0.00
01.03 DEMOLICION DE CANAL DE CONCRETO EXISTENTE m3 13.50 46.66 629.91 0.00 0.00 13.50 629.91 100.00 13.50 629.91 100.00 0.00 0.00 0.00
01.04 PERFILADO Y COMPACTADO MANUAL m2 13.50 5.20 70.20 0.00 0.00 13.50 70.20 100.00 13.50 70.20 100.00 0.00 0.00 0.00
01.05 RELLENO Y COMPACTADO MANUAL m3 3.15 7.80 24.57 0.00 0.00 3.15 24.57 100.00 3.15 24.57 100.00 0.00 0.00 0.00
01.06 ELIMINACION DE MATERIAL EXCEDENTES m3 14.22 3.68 52.33 0.00 0.00 14.22 52.33 100.00 14.22 52.33 100.00 0.00 0.00 0.00
01.07 SOLADO DE 4" m2 13.50 26.02 351.27 0.00 0.00 13.50 351.27 100.00 13.50 351.27 100.00 0.00 0.00 0.00
01.08 ACERO EN DRENAJE GRADO 60 kg 471.04 4.12 1,940.68 0.00 0.00 471.04 1,940.68 100.00 471.04 1,940.68 100.00 0.00 0.00 0.00
01.09 ENCOFRADO Y DESENCOFRADO m2 54.00 55.37 2,989.98 0.00 0.00 54.00 2,989.98 100.00 54.00 2,989.98 100.00 0.00 0.00 0.00
01.10 CONCRETO PARA DRENAJE F'C=210KG/CM2 INCLUYE ACABADOS m3 6.75 430.24 2,904.12 0.00 0.00 6.75 2,904.12 100.00 6.75 2,904.12 100.00 0.00 0.00 0.00
01.11 JUNTA ASFALTICA m 31.80 5.41 172.04 0.00 0.00 31.80 172.04 100.00 31.80 172.04 100.00 0.00 0.00 0.00
01.12 CURADO DE CONCRETO PARA DRENAJE m2 72.00 0.76 54.72 0.00 0.00 72.00 54.72 100.00 72.00 54.72 100.00 0.00 0.00 0.00
01.13 SUMINISTRO Y COLOCACION DE REJILLA METALICA m 1.00 484.73 484.73 0.00 0.00 1.00 484.73 100.00 1.00 484.73 100.00 0.00 0.00 0.00
COSTO DIRECTO 10,134.62 0.00 10,134.62 10,134.62 0.00
TOTAL PRESUPUESTO 10,134.62 0.00 10,134.62 10,134.62 0.00
AVANCE FISICO (%) 100.00 100.00 100.00 0.00
PARTIDA DESCRIPCIÓN UND. METRADO
PRES. BASE (S/.)
VALORIZACION FINAL DE ADICIONAL
"MEJORAMIENTO DE LA TRANSITABILIDAD DE LAS CALLES Y AVENIDAS DE SECTOR ACOBAMBA Y URBANIZACIÓN COCHAHUAIN, AFECTADA POR TEMPORADA DE LLUVIAS PERIODO 2017-2018, DISTRITO DE YUNGAY, PROVINCIA DE YUNGAY – ANCASH"
S/. 10,134.62
AVANCE SALDO
PRECIO
UNITARIO
TOTAL
ANTERIOR ACTUAL ACUMULADO
METRADO VALORIZACION %
INFORME FINAL DE LA ACTIVIDAD:
“MEJORAMIENTO DE LA TRANSITABILIDAD DE LAS CALLES Y AVENIDAS DE SECTOR ACOBAMBA Y URBANIZACIÓN COCHAHUAIN, AFECTADA POR TEMPO RADA DE LLUVIAS PERIODO 2017-2018,
DISTRITO DE YUNGAY, PROVINCIA DE YUNGAY – ANCASH”
MUNICIPALIDAD PROVINCIAL
DE YUNGAY