Exploring for Gold in Yukon and
Nevada
TSX-V:ATC
Forward-Looking Statements
2
FORWARD-LOOKING STATEMENTS
This presentation contains forward-looking information. Forward looking information contained in this presentation includes, but is not limited to, statements with respect to: (i) the
estimation of inferred and indicated mineral resources; (ii) the success of exploration activities; (iii) the results of the PEA including statements about future production, future
operating and capital costs, the projected IRR, NPV, payback period, and production timelines for the Tiger Deposit.
These statements are based on information currently available to ATAC Resources Ltd. (ā€œATACā€) and ATAC provides no assurance that actual results will meet managementā€™s
expectations. In certain cases, forward-looking information may be identified by such terms as "anticipates", "believes", "could", "estimates", "expects", "may", "shall", "will", or
"would". Forward-looking information contained in this presentation is based on certain factors and assumptions regarding, among other things, the estimation of mineral
resources, the realization of resource estimate, gold metal prices, the timing and amount of future exploration and development expenditures, the estimation of initial and
sustaining capital requirements, the estimation of labour and operating costs, the availability of necessary financing and materials to continue to explore and develop the Tiger
Deposit in the short and long-term, the progress of exploration and development activities, the receipt of necessary regulatory approvals, the completion of the environmental
assessment process, and assumptions with respect to currency fluctuations, environmental risks, title disputes or claims, and other similar matters. While ATAC considers these
assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.
Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of ATAC to be
materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks inherent in the
exploration and development of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined including the possibility that mining
operations may not commence at the Tiger Deposit, risks relating to variations in mineral resources, grade or recovery rates resulting from current exploration and development
activities, risks relating to changes in gold prices and the worldwide demand for and supply of gold, risks related to increased competition in the mining industry generally, risks
related to current global financial conditions, uncertainties inherent in the estimation of mineral resources, access and supply risks, reliance on key personnel, operational risks
inherent in the conduct of mining activities, including the risk of accidents, labour disputes, increases in capital and operating costs and the risk of delays or increased costs that
might be encountered during the development process, regulatory risks, including risks relating to the acquisition of the necessary licenses and permits, financing, capitalization
and liquidity risks, including the risk that the financing necessary to fund the exploration and development activities at the Tiger Deposit may not be available on satisfactory terms,
or at all, risks related to disputes concerning property titles and interest, and environmental risks. This list is not exhaustive of the factors that may affect any of ATAC's forward-
looking information. These and other factors should be considered carefully and readers should not place undue reliance on ATAC's forward-looking information. ATAC does not
undertake to update any forward-looking information that may be made from time to time by ATAC or on its behalf, except in accordance with applicable securities laws.
TECHNICAL DISCLOSURE
It should be noted that the Tiger Deposit PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the
economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA forecast will be realized or that any of
the resources will ever be upgraded to reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Additional information about the
Tiger Deposit PEA is summarized in ATACā€™s February 27, 2020 technical report titled ā€œTechnical Report and Preliminary Economic Assessment for the Tiger Deposit, Rackla Gold
Project, Yukon, Canadaā€, which can be viewed at www.sedar.com under the ATAC profile or on the ATAC website at www.atacresources.com. Additional information about the
Osiris Resource Estimate is summarized in ATACā€™s July 2, 2018 technical report titled ā€œTechnical Report and Estimate of Mineral Resources for the Osiris Project, Yukon,
Canada,ā€ which can be viewed at www.sedar.com under the ATAC profile or on the ATAC website at www.atacresources.com. Historical information for East Goldfield and the Val
Target rely on disclosure from previous operators and have not been independently verified.
QUALIFIED PERSON
Adam Coulter, M.Sc., P.Geo., ATACā€™s Vice President of Exploration, is a qualified person for the purposes of National Instrument 43-101. All technical information contained in this
presentation has been approved by Adam Coulter.
TRUE WIDTHS
True widths for diamond drill holes are estimated to be 30% - 100% of intersected widths. RAB drill hole intersections are drilled thicknesses and true widths are unknown.
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Osiris Deposit: 1,685,000 oz. Au at 4.23 g/t (Inferred)*
Tiger Deposit: 464,000 oz. Au at 3.19 g/t (M&I)*
East Goldfield Property in Nevada hosts multiple
gold-in-soil anomalies and strong historical drill
results
Road-accessible Connaught Property hosts high-
grade veins and promising early-stage Cu-MoĀ±Au
porphyry potential
Rackla Gold Property is a 100%-owned, district-
scale 185-km long polymetallic belt in Yukon with
no underlying royalties
3
2021 exploration plans include drilling in Nevada
and Yukon, and grassroots regional programs
Strategic Assets in Top Tier Jurisdictions
*Please see appendix for 43-101 compliant mineral resources.
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Corporate Overview
4
Share Structure*
Shares Outstanding 162,383,547
Fully Diluted 183,421,903
Options ($0.20 - $0.76) 12,967,500
Warrants ($0.23 - $0.425) 8,070,856
Working Capital C$5.5M
52-Week Range 0.11 ā€“ 0.315
200-Day Moving Average 0.28
* Share Structure as at November 1, 2020
Recent Financings
Flow-through Shares Proceeds
June 2020 4,347,827 @ $0.23/share ~$1.0 M
March 2019 10,507,143 @ $0.35/share ~$3.6 M
Significant Holders
Barrick Gold Corporation 17.2%*
Konwave Gold Equity Fund 3.4%**
Strategic Metals Ltd. 2.4%***
LF Ruffer Gold Fund 2.1%****
* As at October 9, 2020 ** As at June 30, 2020 *** As at November 2, 2020 **** As at September 30 2020
Exploring for Gold in Yukon and Nevada
Experienced Management
Graham Downs, President & CEO ā€“ Over 25 years in the junior mining sector
Ian Talbot, COO ā€“ Geologist & lawyer, formerly internal counsel with BHP Billiton World Exploration
Rob Carne, P.Geo, Executive Chairman of Technical Committee ā€“ Former President of ATAC
Ed Cope, Technical Advisor ā€“ Formerly VP Exploration, North America for Barrick Gold Corporation
Adam Coulter, P.Geo., VP Exploration ā€“ 9 years of exploration experience
Andrew Carne, P.Eng., VP Corporate & Project Development ā€“ 9 years of exploration experience
TSX-V:ATC
2021 Exploration Plans
5
Yukon Exploration
Nevada Exploration
Connaught Property
ā€¢ Geochemistry and geophysics
ā€¢ Evaluate Cu-MoĀ±Au porphyry to prepare for drilling
ā€¢ Continue to assess epithermal Au-Ag-Pb-Zn-Cu veins
Rackla Gold Property
ā€¢ Drill historical Val target
(20.12 m of 703 g/t Ag, 15.3% Pb, 22.1% Zn)
ā€¢ Re-log and re-sample historical Val drill core
Regional
ā€¢ Evaluate Rosy and grassroots regional gold targets
East Goldfield
ā€¢ Prospecting, mapping and drill targeting
ā€¢ Drill program permitting
ā€¢ 4,000m reverse circulation drill program:
ā€¢ Twin and step-out on historical holes
(22.86 m of 2.88 g/t Au)
ā€¢ Drill newly identified gold anomalies
Fully-Funded Exploration Program
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Yukon Territory
6
5 of the worldā€™s top gold producers have
invested in Yukon projects since 2016
Three producing mines: Eagle Gold,
Keno Hill Silver District, and Minto
Stable tax/royalty regime
Yukon general corporate tax rate cut from
15% to 12% in 2017
Yukon Resource Gateway Project: Over
$360 million in combined federal/territorial
funding to improve road access
Mining accounts for 20% of Yukon GDP
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
The Rau Project hosts the advanced-stage Tiger
Gold Deposit with a PEA pre-tax NPV(5%) of
$118.2 M and IRR of 54.5%
The Rackla Gold Property
7
The Osiris Project hosts Canadaā€™s first Carlin-type
gold discoveries with an inferred resource of
1,685,000 ounces at 4.23 g/t Au at the Osiris Deposit
The Orion Project hosts Carlin-type gold
mineralization over a 2.5 km strike length, along
the regional-scale Anubis Fault
The Rackla Gold Property is ~1,700 kmĀ² and is
comprised of three separate projects: Osiris, Orion
and Rau.
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Val Target, Rackla Gold Project
8
Advancing Yukonā€™s Premier Precious and Base Metal District
Big Red & South Hill Zones
Historical high-grade silver-lead-zincĀ±copperĀ±gold target
Drilled and trenched by several companies from 1978-1988 with sampling limited to high-grade galena
veins and no analysis of gold or copper
Historical drilling includes 20.12 m of 703 g/t Ag, 15.3% Pb, 22.1% Zn in hole 79-16
Potential for bulk-tonnage-grade silver-lead-zinc-copper mineralization outside high grade lenses
Unbiased rock transect sampling conducted in 2020 at the Big Red Zone with 27 rock samples averaging
201 g/t Ag, 1.9% Pb, 3.4% Zn, supporting the bulk tonnage hypothesis
Galena-Tetrahedrite-Malachite Vein
Orion Project
TSX-V:ATC
Val Target ā€“ 2021 Exploration Plan
9
Exploring for gold in Yukon and Nevada
Val 2021 Exploration
ā€¢ Twin and step-out on historical Big Red Zone holes
ā€¢ Assess bulk tonnage potential around high-grade veins
ā€¢ Re-log and re-sample historical drill core
Historical Drilling Highlights at Big Red and South Hill Zones
Zone Hole From (m) To (m) Interval (m) Ag (g/t) Pb (%) Zn (%)
Big Red 79-14 51.20 65.50 14.30 1,230 15.6 5.0
Big Red 79-16 10.36 30.48 20.12 703 15.3 22.1
South Hill 78-13 14.60 34.70 20.10 97 1.4 9.2
South Hill 79-03 80.50 87.65 7.15 550 5.5 11.7
Orion Project
TSX-V:ATC 10
Rau Project
Rau Project ā€“ Gold and Polymetallic Targets
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Osiris Project ā€“ Carlin-Style Gold Resources
11
Inferred Mineral Resource: 1,685,000 ounces gold at an average grade of 4.23 g/t (12.4Mt)
Includes the Conrad, Sunrise, Osiris, and Ibis Zones
Based on ~79,000m drilling
238 holes at an average depth of 330m
Pit-Constrained Resource: 1,055,000 ounces gold at an average grade of 4.08 g/t (8.0Mt)
Osiris Project
Exploring for Gold in Yukon and Nevada
Source: http://www.visualcapitalist.com/company-spotlight/atac-resources/
TSX-V:ATC
Connaught Project
12
Exploring for Gold in Yukon and Nevada
137 km2 road-accessible
property, located 65 km
west of Dawson City,
Yukon, in the headwaters
of the Sixtymile placer
gold camp.
26 distinct sub-
epithermal Ag-Pb-Zn-Au-
Cu veins identified to date
over 13 km of strike
length and 400 m vertical
extent of topography.
Compelling early-stage
copper-molybdenum-
gold porphyry potential
Rock samples grade up to
4,050 g/t silver, 79.41%
lead, 10.90 g/t gold,
7.24% zinc and 1.98%
copper.
Yukon
TSX-V:ATC
Connaught Project ā€“ 2021 Exploration Plan
13
Exploring for Gold in Yukon and Nevada
Connaught 2021 Exploration
ā€¢ Advance Cu-MoĀ±Au porphyry target to drill stage
ā€¢ Soil sampling, prospecting and mapping
ā€¢ Geophysical surveys ā€“ IP and ground magnetics
ā€¢ Re-log and re-sample historical drill core
ā€¢ Digitization of historical data
2021 Focus Area 2021 Focus Area
Porphyry Potential:
Strong and extensive Cu-Mo soil anomalies,
overlying Prospector Mountain Suite intrusive rocks
Same age as Late Cretaceous Taurus Cu-Mo-Au
porphyry deposit in Alaska
Historical reports identified porphyry potential, but
systematic evaluation was never conducted
Yukon
TSX-V:ATC
Nevada
14
Top mining jurisdiction in the world ā€“ Fraser
Institute 2020 Investment Attractiveness rankings
Extensive history of mining, with numerous
currently operating mines
Well developed infrastructure
Strong community support for exploration and
development
Low-relief, road-accessible terrain and
straightforward permitting processes
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
East Goldfield Project
15
7.8 km2 road-accessible property, located
within the Goldfield Mining District in Nevada.
8 km east of the past producing Goldfield Main
Deposit (historic production of 4.2 million
ounces at 18.55 g/t gold*)
Extensive west-northwest trending high-
sulphidation epithermal alteration in favourable
volcanic stratigraphy
Adjacent to Watertonā€™s development-stage
Gemfield project (47.3 million tonnes of
Measured and Indicated at 1.03 g/t gold, totaling
1,574,000 ounces of gold)
Hosts the past-producing Tom Keane mine,
where historic 2003 RC drilling returned 22.86
m of 2.88 g/t gold
2020 soil sampling returned up to 0.77 g/t Au
Silicic ledges along existing road Historic Tom Keane Mine
Nevada
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
East Goldfield Project Location
16
Nevada
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
East Goldfield Mineral Alteration
17
Nevada
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
East Goldfield ā€“ 2021 Target Areas
18
Exploring for gold in Yukon and Nevada
East Goldfield 2021 Drill Targets
ā€¢ Twin and step-out on historical Tom Keane holes
ā€¢ Drill newly identified northwest gold anomalies
Nevada
TSX-V:ATC
2021 Work Summary
19
Exploring for Gold in Yukon in Nevada
Drill two priority projects, in Yukon and Nevada
Prepare a road-accessible Cu-MoĀ±Au porphyry target for drilling
Gold focus, with silver and base metal optionality
January February March April May June July August September October November December
Geochem &
Geophysics
EG Prospecting Assays RC Drilling
Permitting
East Goldfield
Connaught
Val
YK Regional
Regional
Fieldwork
Historical Data Digitization
Historical Data Digitization Drilling
Mapping & Targeting
Preliminary Timeline
TSX-V:ATC
Why Invest in ATAC?
20
Nevada exploration at the East Goldfield Property provides
opportunities for year-round results and news flow
Economic Tiger Deposit
Updated Tiger Deposit PEA demonstrates a pre-tax NPV(5%) of
$118.2M with an IRR of 54.5% at US$1,400/oz gold
Gold mineralization along 2.5 km strike at the Orion Project,
including: 19.85 g/t gold over 8.51 m (AN-12-001),
and 2.75 g/t gold over 61.29 m (AN-16-010)
100% ownership of two high-grade open-pit gold deposits in
Yukon, both open for expansion
Fully-funded 2021 exploration program with drilling in Yukon
and Nevada
Exploring for Gold in Yukon and Nevada
Thank you
TSX-V:ATC
APPENDIX
22
ATAC Mineral Inventory
23
24
25
26
27
28
29
30
Osiris Resource Sensitivity
Tiger Resource and PEA Gold Price Sensitivity
Tiger Capital and Operating Costs
Management & Directors
2020 Tiger Resource & PEA
Tiger Gold Deposit & PEA Pit Shell
Tiger Long Section
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Management & Directors
23
Graham Downs, President & CEO
23 years of Yukon mineral exploration experience
Director of Trifecta Gold
Adam Coulter, VP Exploration
Professional Geologist, working in mineral exploration and
development since 2012
Andrew Carne, VP Corporate & Project Development
Professional Engineer, working in mineral exploration and
development since 2012
Vice President of the Yukon Chamber of Mines
Ian Talbot, Chief Operating Officer
Formerly internal counsel with BHP Billiton World
Exploration
Larry Donaldson, Chief Financial Officer
Chartered Accountant with over 30 years accounting, audit,
and tax experience
Ed Cope, Technical Advisor
21 years with Barrick Gold Corporation; retired
as VP Exploration for North America in 2016
Bill Wengzynowski, Geological Consultant
30+ years of Yukon-focused exploration experience
Two-time recipient of Yukon Prospector of the Year award
Douglas Goss, Chairman & Director
Queen Elizabeth II Golden and Diamond Jubilee Medals
Alberta Order of Excellence
General Counsel & Corporate Secretary to Premium Brands since
1999
Rob Carne, Executive Chairman, Technical Committee & Director
Former President of ATAC and part of the Rackla Gold Project
discovery team
Bruce Youngman, Director
President and COO of Canplats Resources; acquired by Goldcorp
Former VP and director of Northern Dynasty Minerals
Don Poirier, Director
Former VP Corporate Development for Hecla Mining
Glenn Yeadon, Secretary & Director
34 years as a partner or associate of Tupper, Jonsson & Yeadon
Bruce Kenway, Director
Founding member of chartered accounting firm Kenway Mack
Slusarchuk Stewart LLP
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Total ATAC Mineral Inventory
24
Zone Tonnes Grade (Au g/t) Gold (oz)
Conrad 6,487,000 4.00 835,000
Osiris 474,000 4.61 70,000
Sunrise 309,000 4.23 42,000
Ibis 775,000 4.35 108,000
Total 8,045,000 4.08 1,055,000
Zone Tonnes Grade (Au g/t) Gold (oz)
Conrad 3,174,000 4.46 455,000
Osiris 427,000 3.79 52,000
Sunrise 531,000 5.53 95,000
Ibis 203,000 4.27 28,000
Total 4,335,000 4.52 630,000
Osiris Inferred Pit-Constrained Resources (1.30 g/t gold cut-off)*
Osiris Inferred Underground Resources (2.60 g/t gold cut-off)*
Tiger Measured and Indicated Resources (0.75 g/t gold open pit cut-off | 1.50 g/t gold underground cut-off)*
Zone Constraint Classification Tonnes Grade (Au g/t) Gold (oz)
Oxides Open Pit Indicated 1,980,000 3.74 238,000
Underground Indicated 165,000 3.09 16,000
Sulphides Open Pit Measured 799,000 2.92 75,000
Open Pit Indicated 847,000 2.68 73,000
Underground Measured 29,000 2.06 2,000
Underground Indicated 706,000 2.64 60,000
Total M+I 4,526,000 3.19 464,000
*See page 2 for 43-101 Technical Report disclosure
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Osiris Resource Sensitivity*
25
Inferred Gold Cut-Off Tonnes Grade (Au g/t) Gold (oz)
Pit-Constrained 1.30 g/t 8,045,000 4.08 1,055,000
Underground 2.60 g/t 4,335,000 4.52 630,000
TOTAL 12,380,000 4.23 1,685,000
Gold Cut-Off (g/t) Tonnes Grade (Au g/t) Gold (oz)
1 9,091,000 3.74 1,094,000
1.2 8,370,000 3.97 1,069,000
1.3 8,045,000 4.08 1,055,000
1.4 7,740,000 4.19 1,043,000
1.6 7,115,000 4.42 1,012,000
2 6,030,000 4.9 949,000
2.5 4,885,000 5.53 868,000
Gold Cut-Off (g/t) Tonnes Grade (Au g/t) Gold (oz)
2 6,337,000 3.81 776,000
2.3 5,223,000 4.16 699,000
2.5 4,612,000 4.4 652,000
2.6 4,335,000 4.52 630,000
2.7 4,076,000 4.63 607,000
3 3,392,000 4.99 545,000
Pit Constrained Cut-Off Sensitivity
Underground Cut-Off Sensitivity
*See page 2 for 43-101 Technical Report disclosure
Osiris Project
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
2020 Updated Tiger Resource & PEA
26
Parameter Value
Gold Price (US$/oz) $1400
Exchange Rate (US$:CA$) 0.77
Pre-tax NPV(5%) (millions) $118.2
Pre-tax IRR 54.5%
Post-tax NPV(5%) (millions) $85.4
Post-tax IRR 42.6%
Recovered Gold 267,090 oz
Average Gold Grade 3.82 g/t
Average Oxide Recovery 90.5%
Average Sulphide Recovery 61.1%
Pre-production Capital (millions) $110.1
Sustaining Capital (millions) $9.3
Payback (pre-tax) 1.24 years
Payback (post-tax) 1.40 years
Pre-production Period 1 year
Mine life 6 years
Process Carbon-in-Pulp Leach
Production Rate 1,500 tpd
Operational Period Year-round (365 days)
Strip Ratio 5.3:1
Access Method Tote Road: ~$11 million
*See page 2 for 43-101 Technical Report disclosure
ā€¢ Measured and Indicated Resources of
464,000 ounces of gold at 3.19 g/t
ā€¢ Pre-Tax NPV of $118.2 M with an IRR of
54.5% and a 1.24 year payback period
ā€¢ PEA envisions a small, high-grade,
conventional open pit operation
ā€¢ At US$1,550/oz gold price the NPV
increases to $161.4 M with an IRR of
69.2%
ā€¢ The deposit remains open for expansion
along strike and at depth
Rau Project
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Tiger Resources and PEA Gold Price Sensitivity
27
Type Constraint Classification
Au Cut-off
(g/t)
Tonnes
> Cut-off
Grade
> Cut-off
Contained
Metal
Au (g/t) Au (oz)
Oxide Open Pit Indicated 0.75 1,980,000 3.74 238,000
Underground Indicated 1.5 165,000 3.09 16,000
Sulphide Open Pit Measured 0.75 799,000 2.92 75,000
Open Pit Indicated 0.75 847,000 2.68 73,000
Underground Measured 1.5 29,000 2.06 2,000
Underground Indicated 1.5 706,000 2.64 60,000
Total M+I Variable 4,526,000 3.19 464,000
Oxide Open Pit Inferred 0.75 20,000 1.54 1,000
Underground Inferred 1.5 41,000 2.62 3,000
Sulphide Open Pit Inferred 0.75 7,000 2.41 500
Underground Inferred 1.5 97,000 2.26 7,000
Total Inferred Variable 165,000 2.17 11,500
Gold Price $US/oz (0.77 $US/CA$) $1,250 $1,300 $1,350 $1,400 $1,450 $1,500 $1,550
Pre-Tax NPV (5% discount rate) $M $74.9 $89.4 $103.8 $118.2 $132.6 $147.0 $161.4
Pre-Tax IRR 38.7% 44.1% 49.4% 54.5% 59.4% 64.3% 69.2%
The Mineral Resource estimate used in the updated PEA was completed by Steven Ristorcelli, C.P.G. (Mine Development Associates). The
effective date of this Mineral Resource estimate is January 3, 2020. Three dimensional polygonal models were constructed to constrain oxide and
sulphide mineralization, as well as model rock types and grade corridors. See page 2 for Technical Report disclosure.
Rau Project
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Tiger Capital and Operating Costs
28
* Totals may not add exactly due to rounding
** Includes capitalized pre-production mining costs.
Major mining equipment is leased
*** Contingencies were factored on an area-by-area basic depending on
the detail level of each estimate
Capital Costs
Pre Production
(Millions)*
Sustaining
Capital
LOM
Site Infrastructure $8.4 - $8.4
Tote Road $11.6 - $11.6
Open Pit Mining** $10.4 - $10.4
Materials Crushing
and Handling
$2.0 - $2.0
Process Plant $30.4 - $30.4
Tailings and Water
Management
$8.0 $9.3 $17.3
Project Indirects $20.8 - $20.8
Ownerā€™s Cost $1.3 - $1.3
Contingencies*** $17.2 - $17.2
TOTAL $110.1 $9.3 $119.4
Operating Costs
LOM
Avg.
Mining Costs
($/t mined)*
$4.28
Processing
($/t processed)
$29.88
G & A
($/t processed)
$15.33
Surface Services
($/t processed)
$4.68
Camp & Genset Leasing
($/t processed)
$0.64
Equipment Leasing
($/t processed)
$1.68
* Not including capitalized pre-production mining
costs
*See page 2 for 43-101 Technical Report disclosure
Rau Project
Exploring for Gold in Yukon and Nevada
TSX-V:ATC 29
29
Tiger Deposit Resource & PEA Pit Shell Rau Project
Exploring for Gold in Yukon and Nevada
TSX-V:ATC
Tiger Deposit Long Section
30
Rau Project
Exploring for Gold in Yukon and Nevada

More Related Content

What's hot

ATAC Resources Ltd. Corporate Presentation December 2020
ATAC Resources Ltd. Corporate Presentation December 2020ATAC Resources Ltd. Corporate Presentation December 2020
ATAC Resources Ltd. Corporate Presentation December 2020ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation May 2020
ATAC Resources Ltd. Corporate Presentation May 2020ATAC Resources Ltd. Corporate Presentation May 2020
ATAC Resources Ltd. Corporate Presentation May 2020ATAC Resources Ltd
Ā 
2022.03.08 prb presentation final
2022.03.08 prb presentation final2022.03.08 prb presentation final
2022.03.08 prb presentation finalProbe Gold
Ā 
ATAC Resources Ltd. Corporate Presentation June 2020
ATAC Resources Ltd. Corporate Presentation June 2020ATAC Resources Ltd. Corporate Presentation June 2020
ATAC Resources Ltd. Corporate Presentation June 2020ATAC Resources Ltd
Ā 
Atac corporate ppt__november_2020_with_2020_rab_hole
Atac corporate ppt__november_2020_with_2020_rab_holeAtac corporate ppt__november_2020_with_2020_rab_hole
Atac corporate ppt__november_2020_with_2020_rab_holeAdnet Communications
Ā 
ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020ATAC Resources Ltd
Ā 
Atac corporate ppt__october_2020
Atac corporate ppt__october_2020Atac corporate ppt__october_2020
Atac corporate ppt__october_2020Adnet Communications
Ā 
ATAC Resources Ltd. Corporate Presentation January 2021
ATAC Resources Ltd. Corporate Presentation January 2021ATAC Resources Ltd. Corporate Presentation January 2021
ATAC Resources Ltd. Corporate Presentation January 2021ATAC Resources Ltd
Ā 
ATAC Corporate Presentation October 2020
ATAC Corporate Presentation October 2020ATAC Corporate Presentation October 2020
ATAC Corporate Presentation October 2020Adnet Communications
Ā 
ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020ATAC Resources Ltd
Ā 
ATAC Resources Corporate Presentation November 2020
ATAC Resources Corporate Presentation November 2020ATAC Resources Corporate Presentation November 2020
ATAC Resources Corporate Presentation November 2020Adnet Communications
Ā 
ATAC Resources Ltd. Corporate Presentation March 2020
ATAC Resources Ltd. Corporate Presentation March 2020ATAC Resources Ltd. Corporate Presentation March 2020
ATAC Resources Ltd. Corporate Presentation March 2020ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation March 2022
ATAC Resources Ltd. Corporate Presentation March 2022ATAC Resources Ltd. Corporate Presentation March 2022
ATAC Resources Ltd. Corporate Presentation March 2022ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation July 2020
ATAC Resources Ltd. Corporate Presentation July 2020ATAC Resources Ltd. Corporate Presentation July 2020
ATAC Resources Ltd. Corporate Presentation July 2020ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation August 2020
ATAC Resources Ltd. Corporate Presentation August 2020ATAC Resources Ltd. Corporate Presentation August 2020
ATAC Resources Ltd. Corporate Presentation August 2020Adnet Communications
Ā 
TriStar Gold Corporate Presentation - February 2022
TriStar Gold Corporate Presentation - February 2022TriStar Gold Corporate Presentation - February 2022
TriStar Gold Corporate Presentation - February 2022Adnet Communications
Ā 
ATAC Resources Ltd. Corporate Presentation September 2021
ATAC Resources Ltd. Corporate Presentation September 2021ATAC Resources Ltd. Corporate Presentation September 2021
ATAC Resources Ltd. Corporate Presentation September 2021ATAC Resources Ltd
Ā 
QMX Corporate Presentation (English)
QMX Corporate Presentation (English)QMX Corporate Presentation (English)
QMX Corporate Presentation (English)QMX Gold Corporation
Ā 
Silver One - Corporate Presentation - November 2021 short
Silver One - Corporate Presentation - November 2021 shortSilver One - Corporate Presentation - November 2021 short
Silver One - Corporate Presentation - November 2021 shortAdnet Communications
Ā 

What's hot (20)

ATAC Resources Ltd. Corporate Presentation December 2020
ATAC Resources Ltd. Corporate Presentation December 2020ATAC Resources Ltd. Corporate Presentation December 2020
ATAC Resources Ltd. Corporate Presentation December 2020
Ā 
ATAC Resources Ltd. Corporate Presentation May 2020
ATAC Resources Ltd. Corporate Presentation May 2020ATAC Resources Ltd. Corporate Presentation May 2020
ATAC Resources Ltd. Corporate Presentation May 2020
Ā 
2022.03.08 prb presentation final
2022.03.08 prb presentation final2022.03.08 prb presentation final
2022.03.08 prb presentation final
Ā 
ATAC Resources Ltd. Corporate Presentation June 2020
ATAC Resources Ltd. Corporate Presentation June 2020ATAC Resources Ltd. Corporate Presentation June 2020
ATAC Resources Ltd. Corporate Presentation June 2020
Ā 
Atac corporate ppt__november_2020_with_2020_rab_hole
Atac corporate ppt__november_2020_with_2020_rab_holeAtac corporate ppt__november_2020_with_2020_rab_hole
Atac corporate ppt__november_2020_with_2020_rab_hole
Ā 
ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020
Ā 
Atac corporate ppt__october_2020
Atac corporate ppt__october_2020Atac corporate ppt__october_2020
Atac corporate ppt__october_2020
Ā 
ATAC Resources Ltd. Corporate Presentation January 2021
ATAC Resources Ltd. Corporate Presentation January 2021ATAC Resources Ltd. Corporate Presentation January 2021
ATAC Resources Ltd. Corporate Presentation January 2021
Ā 
ATAC Corporate Presentation October 2020
ATAC Corporate Presentation October 2020ATAC Corporate Presentation October 2020
ATAC Corporate Presentation October 2020
Ā 
ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020ATAC Resources Ltd. Corporate Presentation September 2020
ATAC Resources Ltd. Corporate Presentation September 2020
Ā 
ATAC Resources Corporate Presentation November 2020
ATAC Resources Corporate Presentation November 2020ATAC Resources Corporate Presentation November 2020
ATAC Resources Corporate Presentation November 2020
Ā 
ATAC Resources Ltd. Corporate Presentation March 2020
ATAC Resources Ltd. Corporate Presentation March 2020ATAC Resources Ltd. Corporate Presentation March 2020
ATAC Resources Ltd. Corporate Presentation March 2020
Ā 
ATAC Resources Ltd. Corporate Presentation March 2022
ATAC Resources Ltd. Corporate Presentation March 2022ATAC Resources Ltd. Corporate Presentation March 2022
ATAC Resources Ltd. Corporate Presentation March 2022
Ā 
ATAC Resources Ltd. Corporate Presentation July 2020
ATAC Resources Ltd. Corporate Presentation July 2020ATAC Resources Ltd. Corporate Presentation July 2020
ATAC Resources Ltd. Corporate Presentation July 2020
Ā 
ATAC Resources Ltd. Corporate Presentation August 2020
ATAC Resources Ltd. Corporate Presentation August 2020ATAC Resources Ltd. Corporate Presentation August 2020
ATAC Resources Ltd. Corporate Presentation August 2020
Ā 
TriStar Gold Corporate Presentation - February 2022
TriStar Gold Corporate Presentation - February 2022TriStar Gold Corporate Presentation - February 2022
TriStar Gold Corporate Presentation - February 2022
Ā 
Atac Corporate January 2020
Atac Corporate January 2020Atac Corporate January 2020
Atac Corporate January 2020
Ā 
ATAC Resources Ltd. Corporate Presentation September 2021
ATAC Resources Ltd. Corporate Presentation September 2021ATAC Resources Ltd. Corporate Presentation September 2021
ATAC Resources Ltd. Corporate Presentation September 2021
Ā 
QMX Corporate Presentation (English)
QMX Corporate Presentation (English)QMX Corporate Presentation (English)
QMX Corporate Presentation (English)
Ā 
Silver One - Corporate Presentation - November 2021 short
Silver One - Corporate Presentation - November 2021 shortSilver One - Corporate Presentation - November 2021 short
Silver One - Corporate Presentation - November 2021 short
Ā 

Similar to ATAC Resources Ltd. Corporate Presentation March 2021

ATAC Resources Ltd. Corporate Presentation August 2021
ATAC Resources Ltd. Corporate Presentation August 2021ATAC Resources Ltd. Corporate Presentation August 2021
ATAC Resources Ltd. Corporate Presentation August 2021ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd
Ā 
Atac corporate ppt__august_2020
Atac corporate ppt__august_2020Atac corporate ppt__august_2020
Atac corporate ppt__august_2020Adnet Communications
Ā 
ATAC Resources Ltd. Corporate Presentation May 2022
ATAC Resources Ltd. Corporate Presentation May 2022ATAC Resources Ltd. Corporate Presentation May 2022
ATAC Resources Ltd. Corporate Presentation May 2022ATAC Resources Ltd
Ā 
ATAC Corporate Presentation September 2022
ATAC Corporate Presentation September 2022ATAC Corporate Presentation September 2022
ATAC Corporate Presentation September 2022ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation November 2022
ATAC Resources Ltd. Corporate Presentation November 2022ATAC Resources Ltd. Corporate Presentation November 2022
ATAC Resources Ltd. Corporate Presentation November 2022ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation 2 January 2019
ATAC Resources Ltd. Corporate Presentation 2 January 2019ATAC Resources Ltd. Corporate Presentation 2 January 2019
ATAC Resources Ltd. Corporate Presentation 2 January 2019ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation January 2019
ATAC Resources Ltd. Corporate Presentation January 2019ATAC Resources Ltd. Corporate Presentation January 2019
ATAC Resources Ltd. Corporate Presentation January 2019ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation February 2019
ATAC Resources Ltd. Corporate Presentation February 2019ATAC Resources Ltd. Corporate Presentation February 2019
ATAC Resources Ltd. Corporate Presentation February 2019ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation December 2018
ATAC Resources Ltd. Corporate Presentation December 2018ATAC Resources Ltd. Corporate Presentation December 2018
ATAC Resources Ltd. Corporate Presentation December 2018ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation March 2019
ATAC Resources Ltd. Corporate Presentation March 2019ATAC Resources Ltd. Corporate Presentation March 2019
ATAC Resources Ltd. Corporate Presentation March 2019ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation February 2023
ATAC Resources Ltd. Corporate Presentation February 2023ATAC Resources Ltd. Corporate Presentation February 2023
ATAC Resources Ltd. Corporate Presentation February 2023ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation July 2022
ATAC Resources Ltd. Corporate Presentation July 2022ATAC Resources Ltd. Corporate Presentation July 2022
ATAC Resources Ltd. Corporate Presentation July 2022ATAC Resources Ltd
Ā 
ATAC Resources Ltd. Corporate Presentation April 2019
ATAC Resources Ltd. Corporate Presentation April 2019ATAC Resources Ltd. Corporate Presentation April 2019
ATAC Resources Ltd. Corporate Presentation April 2019ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018ATAC Resources
Ā 
ATAC Resources Ltd. Corporate Presentation September 2018
ATAC Resources Ltd. Corporate Presentation September 2018ATAC Resources Ltd. Corporate Presentation September 2018
ATAC Resources Ltd. Corporate Presentation September 2018ATAC Resources
Ā 

Similar to ATAC Resources Ltd. Corporate Presentation March 2021 (17)

ATAC Resources Ltd. Corporate Presentation August 2021
ATAC Resources Ltd. Corporate Presentation August 2021ATAC Resources Ltd. Corporate Presentation August 2021
ATAC Resources Ltd. Corporate Presentation August 2021
Ā 
ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021
Ā 
Atac corporate ppt__august_2020
Atac corporate ppt__august_2020Atac corporate ppt__august_2020
Atac corporate ppt__august_2020
Ā 
ATAC Resources Ltd. Corporate Presentation May 2022
ATAC Resources Ltd. Corporate Presentation May 2022ATAC Resources Ltd. Corporate Presentation May 2022
ATAC Resources Ltd. Corporate Presentation May 2022
Ā 
ATAC Corporate Presentation September 2022
ATAC Corporate Presentation September 2022ATAC Corporate Presentation September 2022
ATAC Corporate Presentation September 2022
Ā 
ATAC Resources Ltd. Corporate Presentation November 2022
ATAC Resources Ltd. Corporate Presentation November 2022ATAC Resources Ltd. Corporate Presentation November 2022
ATAC Resources Ltd. Corporate Presentation November 2022
Ā 
ATAC Resources Ltd. Corporate Presentation 2 January 2019
ATAC Resources Ltd. Corporate Presentation 2 January 2019ATAC Resources Ltd. Corporate Presentation 2 January 2019
ATAC Resources Ltd. Corporate Presentation 2 January 2019
Ā 
ATAC Resources Ltd. Corporate Presentation January 2019
ATAC Resources Ltd. Corporate Presentation January 2019ATAC Resources Ltd. Corporate Presentation January 2019
ATAC Resources Ltd. Corporate Presentation January 2019
Ā 
ATAC Resources Ltd. Corporate Presentation February 2019
ATAC Resources Ltd. Corporate Presentation February 2019ATAC Resources Ltd. Corporate Presentation February 2019
ATAC Resources Ltd. Corporate Presentation February 2019
Ā 
ATAC Resources Ltd. Corporate Presentation December 2018
ATAC Resources Ltd. Corporate Presentation December 2018ATAC Resources Ltd. Corporate Presentation December 2018
ATAC Resources Ltd. Corporate Presentation December 2018
Ā 
ATAC Resources Ltd. Corporate Presentation March 2019
ATAC Resources Ltd. Corporate Presentation March 2019ATAC Resources Ltd. Corporate Presentation March 2019
ATAC Resources Ltd. Corporate Presentation March 2019
Ā 
ATAC Resources Ltd. Corporate Presentation February 2023
ATAC Resources Ltd. Corporate Presentation February 2023ATAC Resources Ltd. Corporate Presentation February 2023
ATAC Resources Ltd. Corporate Presentation February 2023
Ā 
ATAC Resources Ltd. Corporate Presentation July 2022
ATAC Resources Ltd. Corporate Presentation July 2022ATAC Resources Ltd. Corporate Presentation July 2022
ATAC Resources Ltd. Corporate Presentation July 2022
Ā 
ATAC Resources Ltd. Corporate Presentation April 2019
ATAC Resources Ltd. Corporate Presentation April 2019ATAC Resources Ltd. Corporate Presentation April 2019
ATAC Resources Ltd. Corporate Presentation April 2019
Ā 
ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018
Ā 
ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018ATAC Resources Ltd. Corporate Presentation November 2018
ATAC Resources Ltd. Corporate Presentation November 2018
Ā 
ATAC Resources Ltd. Corporate Presentation September 2018
ATAC Resources Ltd. Corporate Presentation September 2018ATAC Resources Ltd. Corporate Presentation September 2018
ATAC Resources Ltd. Corporate Presentation September 2018
Ā 

Recently uploaded

VIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our Escortssonatiwari757
Ā 
Sustainability Leadership, April 26 2024
Sustainability Leadership, April 26 2024Sustainability Leadership, April 26 2024
Sustainability Leadership, April 26 2024TeckResourcesLtd
Ā 
Teck Investor Presentation, April 24, 2024
Teck Investor Presentation, April 24, 2024Teck Investor Presentation, April 24, 2024
Teck Investor Presentation, April 24, 2024TeckResourcesLtd
Ā 
Corporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdfCorporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdfProbe Gold
Ā 
Russian Call Girls Kolkata Amaira šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkata
Russian Call Girls Kolkata Amaira šŸ¤Œ  8250192130 šŸš€ Vip Call Girls KolkataRussian Call Girls Kolkata Amaira šŸ¤Œ  8250192130 šŸš€ Vip Call Girls Kolkata
Russian Call Girls Kolkata Amaira šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkataanamikaraghav4
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girladitipandeya
Ā 
VIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130 Available With Roomdivyansh0kumar0
Ā 
Malad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls ServiceMalad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls ServicePooja Nehwal
Ā 
Call Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In Amritsar
Call Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In AmritsarCall Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In Amritsar
Call Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In Amritsaronly4webmaster01
Ā 
Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857 āž”ļø Delhi šŸ«¦ Russian Escorts FULL ...
Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857  āž”ļø Delhi šŸ«¦  Russian Escorts FULL ...Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857  āž”ļø Delhi šŸ«¦  Russian Escorts FULL ...
Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857 āž”ļø Delhi šŸ«¦ Russian Escorts FULL ...Call Girls In Delhi Whatsup 9873940964 Enjoy Unlimited Pleasure
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girladitipandeya
Ā 
High Profile Call Girls Kolkata Gayatri šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkata
High Profile Call Girls Kolkata Gayatri šŸ¤Œ  8250192130 šŸš€ Vip Call Girls KolkataHigh Profile Call Girls Kolkata Gayatri šŸ¤Œ  8250192130 šŸš€ Vip Call Girls Kolkata
High Profile Call Girls Kolkata Gayatri šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkataanamikaraghav4
Ā 
Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024CollectiveMining1
Ā 
Short-, Mid-, and Long-term gxxoals.pptx
Short-, Mid-, and Long-term gxxoals.pptxShort-, Mid-, and Long-term gxxoals.pptx
Short-, Mid-, and Long-term gxxoals.pptxHenryBriggs2
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...aditipandeya
Ā 

Recently uploaded (20)

VIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Amritsar 7001035870 Enjoy Call Girls With Our Escorts
Ā 
Sustainability Leadership, April 26 2024
Sustainability Leadership, April 26 2024Sustainability Leadership, April 26 2024
Sustainability Leadership, April 26 2024
Ā 
Teck Investor Presentation, April 24, 2024
Teck Investor Presentation, April 24, 2024Teck Investor Presentation, April 24, 2024
Teck Investor Presentation, April 24, 2024
Ā 
Corporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdfCorporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdf
Ā 
Rohini Sector 17 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 17 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 17 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 17 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Ā 
Russian Call Girls Kolkata Amaira šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkata
Russian Call Girls Kolkata Amaira šŸ¤Œ  8250192130 šŸš€ Vip Call Girls KolkataRussian Call Girls Kolkata Amaira šŸ¤Œ  8250192130 šŸš€ Vip Call Girls Kolkata
Russian Call Girls Kolkata Amaira šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkata
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
Ā 
VIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rishra šŸ‘‰ 8250192130 Available With Room
Ā 
Russian Call Girls Rohini Sector 3 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 3 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODEL...Russian Call Girls Rohini Sector 3 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 3 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODEL...
Ā 
Malad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls ServiceMalad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls Service
Ā 
Call Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In Amritsar
Call Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In AmritsarCall Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In Amritsar
Call Girls In Amritsar šŸ’ÆCall Us šŸ” 76967 34778šŸ” šŸ’ƒ Independent Escort In Amritsar
Ā 
Call Girls In Kalkaji šŸ“± 9999965857 šŸ¤© Delhi šŸ«¦ HOT AND SEXY VVIP šŸŽ SERVICE
Call Girls In Kalkaji šŸ“±  9999965857  šŸ¤© Delhi šŸ«¦ HOT AND SEXY VVIP šŸŽ SERVICECall Girls In Kalkaji šŸ“±  9999965857  šŸ¤© Delhi šŸ«¦ HOT AND SEXY VVIP šŸŽ SERVICE
Call Girls In Kalkaji šŸ“± 9999965857 šŸ¤© Delhi šŸ«¦ HOT AND SEXY VVIP šŸŽ SERVICE
Ā 
Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857 āž”ļø Delhi šŸ«¦ Russian Escorts FULL ...
Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857  āž”ļø Delhi šŸ«¦  Russian Escorts FULL ...Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857  āž”ļø Delhi šŸ«¦  Russian Escorts FULL ...
Call Girls šŸ«¤ Mukherjee Nagar āž”ļø 9999965857 āž”ļø Delhi šŸ«¦ Russian Escorts FULL ...
Ā 
Russian Call Girls Rohini Sector 22 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODE...
Russian Call Girls Rohini Sector 22 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODE...Russian Call Girls Rohini Sector 22 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODE...
Russian Call Girls Rohini Sector 22 šŸ’“ Delhi 9999965857 @Sabina Modi VVIP MODE...
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
Ā 
High Profile Call Girls Kolkata Gayatri šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkata
High Profile Call Girls Kolkata Gayatri šŸ¤Œ  8250192130 šŸš€ Vip Call Girls KolkataHigh Profile Call Girls Kolkata Gayatri šŸ¤Œ  8250192130 šŸš€ Vip Call Girls Kolkata
High Profile Call Girls Kolkata Gayatri šŸ¤Œ 8250192130 šŸš€ Vip Call Girls Kolkata
Ā 
Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024
Ā 
Short-, Mid-, and Long-term gxxoals.pptx
Short-, Mid-, and Long-term gxxoals.pptxShort-, Mid-, and Long-term gxxoals.pptx
Short-, Mid-, and Long-term gxxoals.pptx
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...
VIP 7001035870 Find & Meet Hyderabad Call Girls Shamshabad high-profile Call ...
Ā 
Sensual Moments: +91 9999965857 Independent Call Girls Noida Delhi {{ Monika}...
Sensual Moments: +91 9999965857 Independent Call Girls Noida Delhi {{ Monika}...Sensual Moments: +91 9999965857 Independent Call Girls Noida Delhi {{ Monika}...
Sensual Moments: +91 9999965857 Independent Call Girls Noida Delhi {{ Monika}...
Ā 

ATAC Resources Ltd. Corporate Presentation March 2021

  • 1. TSX-V: ATC March 2021 Exploring for Gold in Yukon and Nevada
  • 2. TSX-V:ATC Forward-Looking Statements 2 FORWARD-LOOKING STATEMENTS This presentation contains forward-looking information. Forward looking information contained in this presentation includes, but is not limited to, statements with respect to: (i) the estimation of inferred and indicated mineral resources; (ii) the success of exploration activities; (iii) the results of the PEA including statements about future production, future operating and capital costs, the projected IRR, NPV, payback period, and production timelines for the Tiger Deposit. These statements are based on information currently available to ATAC Resources Ltd. (ā€œATACā€) and ATAC provides no assurance that actual results will meet managementā€™s expectations. In certain cases, forward-looking information may be identified by such terms as "anticipates", "believes", "could", "estimates", "expects", "may", "shall", "will", or "would". Forward-looking information contained in this presentation is based on certain factors and assumptions regarding, among other things, the estimation of mineral resources, the realization of resource estimate, gold metal prices, the timing and amount of future exploration and development expenditures, the estimation of initial and sustaining capital requirements, the estimation of labour and operating costs, the availability of necessary financing and materials to continue to explore and develop the Tiger Deposit in the short and long-term, the progress of exploration and development activities, the receipt of necessary regulatory approvals, the completion of the environmental assessment process, and assumptions with respect to currency fluctuations, environmental risks, title disputes or claims, and other similar matters. While ATAC considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect. Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of ATAC to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks inherent in the exploration and development of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined including the possibility that mining operations may not commence at the Tiger Deposit, risks relating to variations in mineral resources, grade or recovery rates resulting from current exploration and development activities, risks relating to changes in gold prices and the worldwide demand for and supply of gold, risks related to increased competition in the mining industry generally, risks related to current global financial conditions, uncertainties inherent in the estimation of mineral resources, access and supply risks, reliance on key personnel, operational risks inherent in the conduct of mining activities, including the risk of accidents, labour disputes, increases in capital and operating costs and the risk of delays or increased costs that might be encountered during the development process, regulatory risks, including risks relating to the acquisition of the necessary licenses and permits, financing, capitalization and liquidity risks, including the risk that the financing necessary to fund the exploration and development activities at the Tiger Deposit may not be available on satisfactory terms, or at all, risks related to disputes concerning property titles and interest, and environmental risks. This list is not exhaustive of the factors that may affect any of ATAC's forward- looking information. These and other factors should be considered carefully and readers should not place undue reliance on ATAC's forward-looking information. ATAC does not undertake to update any forward-looking information that may be made from time to time by ATAC or on its behalf, except in accordance with applicable securities laws. TECHNICAL DISCLOSURE It should be noted that the Tiger Deposit PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA forecast will be realized or that any of the resources will ever be upgraded to reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Additional information about the Tiger Deposit PEA is summarized in ATACā€™s February 27, 2020 technical report titled ā€œTechnical Report and Preliminary Economic Assessment for the Tiger Deposit, Rackla Gold Project, Yukon, Canadaā€, which can be viewed at www.sedar.com under the ATAC profile or on the ATAC website at www.atacresources.com. Additional information about the Osiris Resource Estimate is summarized in ATACā€™s July 2, 2018 technical report titled ā€œTechnical Report and Estimate of Mineral Resources for the Osiris Project, Yukon, Canada,ā€ which can be viewed at www.sedar.com under the ATAC profile or on the ATAC website at www.atacresources.com. Historical information for East Goldfield and the Val Target rely on disclosure from previous operators and have not been independently verified. QUALIFIED PERSON Adam Coulter, M.Sc., P.Geo., ATACā€™s Vice President of Exploration, is a qualified person for the purposes of National Instrument 43-101. All technical information contained in this presentation has been approved by Adam Coulter. TRUE WIDTHS True widths for diamond drill holes are estimated to be 30% - 100% of intersected widths. RAB drill hole intersections are drilled thicknesses and true widths are unknown. Exploring for Gold in Yukon and Nevada
  • 3. TSX-V:ATC Osiris Deposit: 1,685,000 oz. Au at 4.23 g/t (Inferred)* Tiger Deposit: 464,000 oz. Au at 3.19 g/t (M&I)* East Goldfield Property in Nevada hosts multiple gold-in-soil anomalies and strong historical drill results Road-accessible Connaught Property hosts high- grade veins and promising early-stage Cu-MoĀ±Au porphyry potential Rackla Gold Property is a 100%-owned, district- scale 185-km long polymetallic belt in Yukon with no underlying royalties 3 2021 exploration plans include drilling in Nevada and Yukon, and grassroots regional programs Strategic Assets in Top Tier Jurisdictions *Please see appendix for 43-101 compliant mineral resources. Exploring for Gold in Yukon and Nevada
  • 4. TSX-V:ATC Corporate Overview 4 Share Structure* Shares Outstanding 162,383,547 Fully Diluted 183,421,903 Options ($0.20 - $0.76) 12,967,500 Warrants ($0.23 - $0.425) 8,070,856 Working Capital C$5.5M 52-Week Range 0.11 ā€“ 0.315 200-Day Moving Average 0.28 * Share Structure as at November 1, 2020 Recent Financings Flow-through Shares Proceeds June 2020 4,347,827 @ $0.23/share ~$1.0 M March 2019 10,507,143 @ $0.35/share ~$3.6 M Significant Holders Barrick Gold Corporation 17.2%* Konwave Gold Equity Fund 3.4%** Strategic Metals Ltd. 2.4%*** LF Ruffer Gold Fund 2.1%**** * As at October 9, 2020 ** As at June 30, 2020 *** As at November 2, 2020 **** As at September 30 2020 Exploring for Gold in Yukon and Nevada Experienced Management Graham Downs, President & CEO ā€“ Over 25 years in the junior mining sector Ian Talbot, COO ā€“ Geologist & lawyer, formerly internal counsel with BHP Billiton World Exploration Rob Carne, P.Geo, Executive Chairman of Technical Committee ā€“ Former President of ATAC Ed Cope, Technical Advisor ā€“ Formerly VP Exploration, North America for Barrick Gold Corporation Adam Coulter, P.Geo., VP Exploration ā€“ 9 years of exploration experience Andrew Carne, P.Eng., VP Corporate & Project Development ā€“ 9 years of exploration experience
  • 5. TSX-V:ATC 2021 Exploration Plans 5 Yukon Exploration Nevada Exploration Connaught Property ā€¢ Geochemistry and geophysics ā€¢ Evaluate Cu-MoĀ±Au porphyry to prepare for drilling ā€¢ Continue to assess epithermal Au-Ag-Pb-Zn-Cu veins Rackla Gold Property ā€¢ Drill historical Val target (20.12 m of 703 g/t Ag, 15.3% Pb, 22.1% Zn) ā€¢ Re-log and re-sample historical Val drill core Regional ā€¢ Evaluate Rosy and grassroots regional gold targets East Goldfield ā€¢ Prospecting, mapping and drill targeting ā€¢ Drill program permitting ā€¢ 4,000m reverse circulation drill program: ā€¢ Twin and step-out on historical holes (22.86 m of 2.88 g/t Au) ā€¢ Drill newly identified gold anomalies Fully-Funded Exploration Program Exploring for Gold in Yukon and Nevada
  • 6. TSX-V:ATC Yukon Territory 6 5 of the worldā€™s top gold producers have invested in Yukon projects since 2016 Three producing mines: Eagle Gold, Keno Hill Silver District, and Minto Stable tax/royalty regime Yukon general corporate tax rate cut from 15% to 12% in 2017 Yukon Resource Gateway Project: Over $360 million in combined federal/territorial funding to improve road access Mining accounts for 20% of Yukon GDP Exploring for Gold in Yukon and Nevada
  • 7. TSX-V:ATC The Rau Project hosts the advanced-stage Tiger Gold Deposit with a PEA pre-tax NPV(5%) of $118.2 M and IRR of 54.5% The Rackla Gold Property 7 The Osiris Project hosts Canadaā€™s first Carlin-type gold discoveries with an inferred resource of 1,685,000 ounces at 4.23 g/t Au at the Osiris Deposit The Orion Project hosts Carlin-type gold mineralization over a 2.5 km strike length, along the regional-scale Anubis Fault The Rackla Gold Property is ~1,700 kmĀ² and is comprised of three separate projects: Osiris, Orion and Rau. Exploring for Gold in Yukon and Nevada
  • 8. TSX-V:ATC Val Target, Rackla Gold Project 8 Advancing Yukonā€™s Premier Precious and Base Metal District Big Red & South Hill Zones Historical high-grade silver-lead-zincĀ±copperĀ±gold target Drilled and trenched by several companies from 1978-1988 with sampling limited to high-grade galena veins and no analysis of gold or copper Historical drilling includes 20.12 m of 703 g/t Ag, 15.3% Pb, 22.1% Zn in hole 79-16 Potential for bulk-tonnage-grade silver-lead-zinc-copper mineralization outside high grade lenses Unbiased rock transect sampling conducted in 2020 at the Big Red Zone with 27 rock samples averaging 201 g/t Ag, 1.9% Pb, 3.4% Zn, supporting the bulk tonnage hypothesis Galena-Tetrahedrite-Malachite Vein Orion Project
  • 9. TSX-V:ATC Val Target ā€“ 2021 Exploration Plan 9 Exploring for gold in Yukon and Nevada Val 2021 Exploration ā€¢ Twin and step-out on historical Big Red Zone holes ā€¢ Assess bulk tonnage potential around high-grade veins ā€¢ Re-log and re-sample historical drill core Historical Drilling Highlights at Big Red and South Hill Zones Zone Hole From (m) To (m) Interval (m) Ag (g/t) Pb (%) Zn (%) Big Red 79-14 51.20 65.50 14.30 1,230 15.6 5.0 Big Red 79-16 10.36 30.48 20.12 703 15.3 22.1 South Hill 78-13 14.60 34.70 20.10 97 1.4 9.2 South Hill 79-03 80.50 87.65 7.15 550 5.5 11.7 Orion Project
  • 10. TSX-V:ATC 10 Rau Project Rau Project ā€“ Gold and Polymetallic Targets Exploring for Gold in Yukon and Nevada
  • 11. TSX-V:ATC Osiris Project ā€“ Carlin-Style Gold Resources 11 Inferred Mineral Resource: 1,685,000 ounces gold at an average grade of 4.23 g/t (12.4Mt) Includes the Conrad, Sunrise, Osiris, and Ibis Zones Based on ~79,000m drilling 238 holes at an average depth of 330m Pit-Constrained Resource: 1,055,000 ounces gold at an average grade of 4.08 g/t (8.0Mt) Osiris Project Exploring for Gold in Yukon and Nevada Source: http://www.visualcapitalist.com/company-spotlight/atac-resources/
  • 12. TSX-V:ATC Connaught Project 12 Exploring for Gold in Yukon and Nevada 137 km2 road-accessible property, located 65 km west of Dawson City, Yukon, in the headwaters of the Sixtymile placer gold camp. 26 distinct sub- epithermal Ag-Pb-Zn-Au- Cu veins identified to date over 13 km of strike length and 400 m vertical extent of topography. Compelling early-stage copper-molybdenum- gold porphyry potential Rock samples grade up to 4,050 g/t silver, 79.41% lead, 10.90 g/t gold, 7.24% zinc and 1.98% copper. Yukon
  • 13. TSX-V:ATC Connaught Project ā€“ 2021 Exploration Plan 13 Exploring for Gold in Yukon and Nevada Connaught 2021 Exploration ā€¢ Advance Cu-MoĀ±Au porphyry target to drill stage ā€¢ Soil sampling, prospecting and mapping ā€¢ Geophysical surveys ā€“ IP and ground magnetics ā€¢ Re-log and re-sample historical drill core ā€¢ Digitization of historical data 2021 Focus Area 2021 Focus Area Porphyry Potential: Strong and extensive Cu-Mo soil anomalies, overlying Prospector Mountain Suite intrusive rocks Same age as Late Cretaceous Taurus Cu-Mo-Au porphyry deposit in Alaska Historical reports identified porphyry potential, but systematic evaluation was never conducted Yukon
  • 14. TSX-V:ATC Nevada 14 Top mining jurisdiction in the world ā€“ Fraser Institute 2020 Investment Attractiveness rankings Extensive history of mining, with numerous currently operating mines Well developed infrastructure Strong community support for exploration and development Low-relief, road-accessible terrain and straightforward permitting processes Exploring for Gold in Yukon and Nevada
  • 15. TSX-V:ATC East Goldfield Project 15 7.8 km2 road-accessible property, located within the Goldfield Mining District in Nevada. 8 km east of the past producing Goldfield Main Deposit (historic production of 4.2 million ounces at 18.55 g/t gold*) Extensive west-northwest trending high- sulphidation epithermal alteration in favourable volcanic stratigraphy Adjacent to Watertonā€™s development-stage Gemfield project (47.3 million tonnes of Measured and Indicated at 1.03 g/t gold, totaling 1,574,000 ounces of gold) Hosts the past-producing Tom Keane mine, where historic 2003 RC drilling returned 22.86 m of 2.88 g/t gold 2020 soil sampling returned up to 0.77 g/t Au Silicic ledges along existing road Historic Tom Keane Mine Nevada Exploring for Gold in Yukon and Nevada
  • 16. TSX-V:ATC East Goldfield Project Location 16 Nevada Exploring for Gold in Yukon and Nevada
  • 17. TSX-V:ATC East Goldfield Mineral Alteration 17 Nevada Exploring for Gold in Yukon and Nevada
  • 18. TSX-V:ATC East Goldfield ā€“ 2021 Target Areas 18 Exploring for gold in Yukon and Nevada East Goldfield 2021 Drill Targets ā€¢ Twin and step-out on historical Tom Keane holes ā€¢ Drill newly identified northwest gold anomalies Nevada
  • 19. TSX-V:ATC 2021 Work Summary 19 Exploring for Gold in Yukon in Nevada Drill two priority projects, in Yukon and Nevada Prepare a road-accessible Cu-MoĀ±Au porphyry target for drilling Gold focus, with silver and base metal optionality January February March April May June July August September October November December Geochem & Geophysics EG Prospecting Assays RC Drilling Permitting East Goldfield Connaught Val YK Regional Regional Fieldwork Historical Data Digitization Historical Data Digitization Drilling Mapping & Targeting Preliminary Timeline
  • 20. TSX-V:ATC Why Invest in ATAC? 20 Nevada exploration at the East Goldfield Property provides opportunities for year-round results and news flow Economic Tiger Deposit Updated Tiger Deposit PEA demonstrates a pre-tax NPV(5%) of $118.2M with an IRR of 54.5% at US$1,400/oz gold Gold mineralization along 2.5 km strike at the Orion Project, including: 19.85 g/t gold over 8.51 m (AN-12-001), and 2.75 g/t gold over 61.29 m (AN-16-010) 100% ownership of two high-grade open-pit gold deposits in Yukon, both open for expansion Fully-funded 2021 exploration program with drilling in Yukon and Nevada Exploring for Gold in Yukon and Nevada
  • 22. TSX-V:ATC APPENDIX 22 ATAC Mineral Inventory 23 24 25 26 27 28 29 30 Osiris Resource Sensitivity Tiger Resource and PEA Gold Price Sensitivity Tiger Capital and Operating Costs Management & Directors 2020 Tiger Resource & PEA Tiger Gold Deposit & PEA Pit Shell Tiger Long Section Exploring for Gold in Yukon and Nevada
  • 23. TSX-V:ATC Management & Directors 23 Graham Downs, President & CEO 23 years of Yukon mineral exploration experience Director of Trifecta Gold Adam Coulter, VP Exploration Professional Geologist, working in mineral exploration and development since 2012 Andrew Carne, VP Corporate & Project Development Professional Engineer, working in mineral exploration and development since 2012 Vice President of the Yukon Chamber of Mines Ian Talbot, Chief Operating Officer Formerly internal counsel with BHP Billiton World Exploration Larry Donaldson, Chief Financial Officer Chartered Accountant with over 30 years accounting, audit, and tax experience Ed Cope, Technical Advisor 21 years with Barrick Gold Corporation; retired as VP Exploration for North America in 2016 Bill Wengzynowski, Geological Consultant 30+ years of Yukon-focused exploration experience Two-time recipient of Yukon Prospector of the Year award Douglas Goss, Chairman & Director Queen Elizabeth II Golden and Diamond Jubilee Medals Alberta Order of Excellence General Counsel & Corporate Secretary to Premium Brands since 1999 Rob Carne, Executive Chairman, Technical Committee & Director Former President of ATAC and part of the Rackla Gold Project discovery team Bruce Youngman, Director President and COO of Canplats Resources; acquired by Goldcorp Former VP and director of Northern Dynasty Minerals Don Poirier, Director Former VP Corporate Development for Hecla Mining Glenn Yeadon, Secretary & Director 34 years as a partner or associate of Tupper, Jonsson & Yeadon Bruce Kenway, Director Founding member of chartered accounting firm Kenway Mack Slusarchuk Stewart LLP Exploring for Gold in Yukon and Nevada
  • 24. TSX-V:ATC Total ATAC Mineral Inventory 24 Zone Tonnes Grade (Au g/t) Gold (oz) Conrad 6,487,000 4.00 835,000 Osiris 474,000 4.61 70,000 Sunrise 309,000 4.23 42,000 Ibis 775,000 4.35 108,000 Total 8,045,000 4.08 1,055,000 Zone Tonnes Grade (Au g/t) Gold (oz) Conrad 3,174,000 4.46 455,000 Osiris 427,000 3.79 52,000 Sunrise 531,000 5.53 95,000 Ibis 203,000 4.27 28,000 Total 4,335,000 4.52 630,000 Osiris Inferred Pit-Constrained Resources (1.30 g/t gold cut-off)* Osiris Inferred Underground Resources (2.60 g/t gold cut-off)* Tiger Measured and Indicated Resources (0.75 g/t gold open pit cut-off | 1.50 g/t gold underground cut-off)* Zone Constraint Classification Tonnes Grade (Au g/t) Gold (oz) Oxides Open Pit Indicated 1,980,000 3.74 238,000 Underground Indicated 165,000 3.09 16,000 Sulphides Open Pit Measured 799,000 2.92 75,000 Open Pit Indicated 847,000 2.68 73,000 Underground Measured 29,000 2.06 2,000 Underground Indicated 706,000 2.64 60,000 Total M+I 4,526,000 3.19 464,000 *See page 2 for 43-101 Technical Report disclosure Exploring for Gold in Yukon and Nevada
  • 25. TSX-V:ATC Osiris Resource Sensitivity* 25 Inferred Gold Cut-Off Tonnes Grade (Au g/t) Gold (oz) Pit-Constrained 1.30 g/t 8,045,000 4.08 1,055,000 Underground 2.60 g/t 4,335,000 4.52 630,000 TOTAL 12,380,000 4.23 1,685,000 Gold Cut-Off (g/t) Tonnes Grade (Au g/t) Gold (oz) 1 9,091,000 3.74 1,094,000 1.2 8,370,000 3.97 1,069,000 1.3 8,045,000 4.08 1,055,000 1.4 7,740,000 4.19 1,043,000 1.6 7,115,000 4.42 1,012,000 2 6,030,000 4.9 949,000 2.5 4,885,000 5.53 868,000 Gold Cut-Off (g/t) Tonnes Grade (Au g/t) Gold (oz) 2 6,337,000 3.81 776,000 2.3 5,223,000 4.16 699,000 2.5 4,612,000 4.4 652,000 2.6 4,335,000 4.52 630,000 2.7 4,076,000 4.63 607,000 3 3,392,000 4.99 545,000 Pit Constrained Cut-Off Sensitivity Underground Cut-Off Sensitivity *See page 2 for 43-101 Technical Report disclosure Osiris Project Exploring for Gold in Yukon and Nevada
  • 26. TSX-V:ATC 2020 Updated Tiger Resource & PEA 26 Parameter Value Gold Price (US$/oz) $1400 Exchange Rate (US$:CA$) 0.77 Pre-tax NPV(5%) (millions) $118.2 Pre-tax IRR 54.5% Post-tax NPV(5%) (millions) $85.4 Post-tax IRR 42.6% Recovered Gold 267,090 oz Average Gold Grade 3.82 g/t Average Oxide Recovery 90.5% Average Sulphide Recovery 61.1% Pre-production Capital (millions) $110.1 Sustaining Capital (millions) $9.3 Payback (pre-tax) 1.24 years Payback (post-tax) 1.40 years Pre-production Period 1 year Mine life 6 years Process Carbon-in-Pulp Leach Production Rate 1,500 tpd Operational Period Year-round (365 days) Strip Ratio 5.3:1 Access Method Tote Road: ~$11 million *See page 2 for 43-101 Technical Report disclosure ā€¢ Measured and Indicated Resources of 464,000 ounces of gold at 3.19 g/t ā€¢ Pre-Tax NPV of $118.2 M with an IRR of 54.5% and a 1.24 year payback period ā€¢ PEA envisions a small, high-grade, conventional open pit operation ā€¢ At US$1,550/oz gold price the NPV increases to $161.4 M with an IRR of 69.2% ā€¢ The deposit remains open for expansion along strike and at depth Rau Project Exploring for Gold in Yukon and Nevada
  • 27. TSX-V:ATC Tiger Resources and PEA Gold Price Sensitivity 27 Type Constraint Classification Au Cut-off (g/t) Tonnes > Cut-off Grade > Cut-off Contained Metal Au (g/t) Au (oz) Oxide Open Pit Indicated 0.75 1,980,000 3.74 238,000 Underground Indicated 1.5 165,000 3.09 16,000 Sulphide Open Pit Measured 0.75 799,000 2.92 75,000 Open Pit Indicated 0.75 847,000 2.68 73,000 Underground Measured 1.5 29,000 2.06 2,000 Underground Indicated 1.5 706,000 2.64 60,000 Total M+I Variable 4,526,000 3.19 464,000 Oxide Open Pit Inferred 0.75 20,000 1.54 1,000 Underground Inferred 1.5 41,000 2.62 3,000 Sulphide Open Pit Inferred 0.75 7,000 2.41 500 Underground Inferred 1.5 97,000 2.26 7,000 Total Inferred Variable 165,000 2.17 11,500 Gold Price $US/oz (0.77 $US/CA$) $1,250 $1,300 $1,350 $1,400 $1,450 $1,500 $1,550 Pre-Tax NPV (5% discount rate) $M $74.9 $89.4 $103.8 $118.2 $132.6 $147.0 $161.4 Pre-Tax IRR 38.7% 44.1% 49.4% 54.5% 59.4% 64.3% 69.2% The Mineral Resource estimate used in the updated PEA was completed by Steven Ristorcelli, C.P.G. (Mine Development Associates). The effective date of this Mineral Resource estimate is January 3, 2020. Three dimensional polygonal models were constructed to constrain oxide and sulphide mineralization, as well as model rock types and grade corridors. See page 2 for Technical Report disclosure. Rau Project Exploring for Gold in Yukon and Nevada
  • 28. TSX-V:ATC Tiger Capital and Operating Costs 28 * Totals may not add exactly due to rounding ** Includes capitalized pre-production mining costs. Major mining equipment is leased *** Contingencies were factored on an area-by-area basic depending on the detail level of each estimate Capital Costs Pre Production (Millions)* Sustaining Capital LOM Site Infrastructure $8.4 - $8.4 Tote Road $11.6 - $11.6 Open Pit Mining** $10.4 - $10.4 Materials Crushing and Handling $2.0 - $2.0 Process Plant $30.4 - $30.4 Tailings and Water Management $8.0 $9.3 $17.3 Project Indirects $20.8 - $20.8 Ownerā€™s Cost $1.3 - $1.3 Contingencies*** $17.2 - $17.2 TOTAL $110.1 $9.3 $119.4 Operating Costs LOM Avg. Mining Costs ($/t mined)* $4.28 Processing ($/t processed) $29.88 G & A ($/t processed) $15.33 Surface Services ($/t processed) $4.68 Camp & Genset Leasing ($/t processed) $0.64 Equipment Leasing ($/t processed) $1.68 * Not including capitalized pre-production mining costs *See page 2 for 43-101 Technical Report disclosure Rau Project Exploring for Gold in Yukon and Nevada
  • 29. TSX-V:ATC 29 29 Tiger Deposit Resource & PEA Pit Shell Rau Project Exploring for Gold in Yukon and Nevada
  • 30. TSX-V:ATC Tiger Deposit Long Section 30 Rau Project Exploring for Gold in Yukon and Nevada