SlideShare a Scribd company logo
1 of 9
Download to read offline
east london
line REBORN
MAJOR
PROJECT
REPORT
27|05|10
London’s new Railway
PLanning, design and
construction of a new
10km rail route for
London Overground
24 NEW CIVIL ENGINEER 27.05.1O | www.nce.co.uk
EAST LONDON LINE: INTRODUCTION
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 25
upgrade the East London Un-
derground Line that ran from
Shoreditch to New Cross Gate
since 1997. London Underground
had the idea to take a railway
into Hackney on a disused
viaduct that had once carried the
North London Overground Line
from Broad Street Station, which
had disappeared under the
Broadgate development in 1986.
It got Transport & Works Act
(TWA) powers for the scheme,
which was then expanded again
when it was realised the railway
could interconnect with the
North London Line. Another
Transport & Works Act was ac-
quired, and as the project by that
stage had effectively become
part of Overground rather than
Underground rail, it was passed
to the newly formed Strategic
Rail Authority (SRA) to manage.
ELL plans languished there
without a champion. But over
at Transport for London it did
have its backers – Smith and his
managing director Ian Brown
at TfL’s developing London Rail
division in particular. And when
the SRA wound up and the route
was bequeathed to TfL in 2004
they fought for, and won the
funding.
“There was pressure to make
a decision as the TWA powers
were about to run out, and then
the Olympics came along, which
finally tipped the balance and we
could get on with building the
project,” Smith says.
Peter Richards was brought
in from the SRA to run the job
as infrastructure director for the
now dubbed London Over-
ground, along with Mike Stubbs
as engineering director, and they
got stuck into design.
There had been a brief flirta-
tion with funding the route
through private finance. “But
the ELL is a grey asset,” Smith
says. “There is a lot of old in-
frastructure it would have been
difficult to box up for PFI, and a
PFI takes time to put together.”
With the 2012 Olympics fast ap-
proaching, it was decided to go
for a design and build option.
It was a good decision. The
scheme, built by a Balfour Beatty
Carillion joint venture (BBCJV),
opened early on 23 May. BBCJV
won the contract in October
2006, started design immedi-
ately, and then started the major
structures in 2007. It got onto the
tunnel and south sections of the
site when the old East London
Underground was closed in
December 2007 and handed over
in late January 2008.
“From the start, we stressed to
everyone that this job is about
delivering an operational railway
– infrastructure, rolling stock
and operations,” says Richards.
“We have managed the integra-
tion between these aspects and
given the responsibility for man-
aging the interface between the
existing infrastructure and main
works structures and rail sys-
tems to Balfour Beatty Carillion
as our main works contractor.
“That is why we went for a
single NEC3 design and build
main works contract.
“It has meant that BBCJV
has managed the interfaces, and
all the responsibility has rested
with one party to get on and do
the whole thing.”
When Richards set up the job
he wanted to create momentum,
so he formed an integrated client
team to manage the job and
drive its progress. This included
himself, Parsons Brincker-
hoff’s Ashok Kothari as head of
programme management and
designers from Mott MacDonald
as technical adviser to the
project.
Refurbishment work along
the route on some of the older
structures like the Kingsland
Viaduct was let as enabling
works contracts to Murphy and
Taylor Woodrow (now Vinci
Construction).
“Refurbishment is risky and
it was prudent to do some of
that first before we let the bigger
contract,” Richards says.
“And then, as a client team,
we worked very hard towards
letting the main works contract
to programme.
“We didn’t let ourselves slip.
By doing that we created float
for the rest of the project and
that has helped us come in early.
We are delighted to have opened
on 23 May, ahead of a pro-
gramme set back in 2004.”
O
ne day after the
opening of the core
route of the London
Overground East
London Line last month, pas-
sengers were wandering around
wide-eyed, taking in the wonder
of the capital’s newest rail route.
Londoners who know the
detail of the Underground better
than their bank pin numbers
were cooing contentedly to
themselves while looking at a
map of the route which revealed
a whole new circuit board of
travel possibilities. As the first
section of ELL opened they
could go from Dalston in Hack-
ney in the north, south to the
Docklands at Canada Water and
then on to New Cross. From this
week, since the full line opened
on 23 May, the route will take
them as far into the south Lon-
don suburbs as West Croydon
and Crystal Palace.
By early next year when phase
1a of the East London Line
opens, Croydon will have a direct
connection to Highbury and
Islington, and at Dalston travel-
lers will be able to switch onto a
newly upgraded North London
Line to go east to Stratford and
the Olympics or west to Willes-
den Junction and Richmond.
And by 2012, construction of a
link from the East London Line
at Surrey Quays to railway at Old
Kent Road will allow a western
trip to Clapham Junction via
Peckham Rye and Wandsworth
Road and link to the Overground
Clapham Junction to Willesden
Junction Line.
The capital will have an outer
orbital metro railway under the
banner of London Overground,
interconnecting along the way
with its Underground lines and
serving 20 of its 33 boroughs;
and commuters will have oppor-
tunities aplenty to avoid central
bottlenecks when they are trying
to cross the city.
The key to creating this will
have been a £1bn Transport for
London investment in infra-
structure and new rolling stock.
This has reinvigorated and
expanded the old East London
Line Tube line, reusing Victorian
infrastructure and introducing
some new modern landmarks
along the way.
There are going to be huge
benefits in terms of regeneration
and new jobs for some of the
less developed parts of the City,
rail-deprived Hackney will at
last have a metro, and east and
southeast London will acquire
some life changing infrastruc-
ture.
Around 33M passengers are
expected to be using the route
every year by 2011, rising to a
projected 39M by 2016.
“The really good part of this
job,” says London Rail chief
executive Howard Smith, under
who’s remit the East London
Line falls, “is that we are chang-
ing the face of London and the
way we think of and use London
in a permanent way. It is really
dramatic.”
There has been a plan to
east end
efficiencyThis week the London Overground
East London Line opened a full service
from West Croydon in south London
to Dalston in the north. In a remarkable
achievement, the project has been
delivered early. Jackie Whitelaw reports.
“As a client team, we
worked very hard
towards letting the
main works contract
to programme”
Peter Richards,
infrastructure director
London Overground
“We are changing the
face of London and
the way we think of
and use London in a
permanent way.
It is really dramatic”
Howard Smith,
London Rail
Client London Overground for
Transport for London
Other parties London
Underground, Network Rail
Contractor Balfour Beatty
Carillion joint venture
(BBCJV)
Contractor’s designers Scott
Wilson, Tony Gee & Partners
Programme manager Parsons
Brinckerhoff
Client’s technical adviser Mott
MacDonald
Rolling stock Bombardier
Operator LOROL
Signalling,communications and
power systems, 3.5km of new
or refurbished viaduct from
Whitechapel to Dalston Junction;
3.2km of track in tunnel south of
Whitechapel to Surrey Quay
New stations at Dalston
Junction, Haggerston, Hoxton
and Shoreditch High Street;
refurbishments at Whitechapel,
Shadwell, Wapping, Rotherhithe
and Surrey Quays; an
operational control centre;
depot; and 44 four car
Electrostar 378 trains – 20 for
the East London Line and 24 for
the North London Line.
WHO’S WHO
EAST LONDON LINE IN BRIEF
Stratford
Dalston Junction
Haggerston
Hoxton
Shoreditch High Street
Highbury &
Islington
Blackhorse Road
Whitechapel
Gospel
Oak
Shadwell
Canada Water
Surrey Quays
Queens Road
Peckham
Denmark Hill
West Brompton
Kensington (Olympia)
Shepherd’s Bush
EustonKensal Green
Queen’s Park
CENTRAL LONDON
Willesden
Junction
West Hampstead
Harlesden
Stonebridge Park
Clapham
High Street
Kew
Gardens
Gunnersbury
Clapham
Junction
New Cross
Brockley
Honor Oak Park
Forest Hill
Sydenham
Penge West
Anerley
Norwood Junction
Crystal Palace
West Croydon
New
Cross
Gate
Peckham
Rye
North West
to Watford
Junction
East to
Barking
To Richmond
KEY
Phase 1 opened 23 May 2010
Phase 1a completed by 2011
Phase 2 completed by 2012
OVERGROUND
East London Line is vital for creating
an outer orbital railway around the
capital. Phase 1 opened on 23 May.
City slicker: The East London Line is a
vital new link to London’s financial heart
east london
line REBORN
MAJOR
PROJECT
REPORT
LONDON OVERGROUND: THE FUTURE
venture finally got onto the line
three months early at the end of
January 2008.
That is when the scope of the
job began to develop. There was
the depot to add in. And two
bulk supply points for power.
“Those two 132kV bulk supply
points came on top of three 33kV
traction substations already in
the contract, and those three had
to change from pre-assembly
to larger built insitu on site
versions,” says Balfour Beatty
Carillion construction director
Adam Stuart.
An enabling works contract
had beefed up the Victorian
Kingsland brick arch viaduct
between Shoreditch High Street
and Dalston. “But that still left
BBCJV a lot of work in further
assessment and strengthening,”
says Stuart.
The six “tunnel” stations
between Whitechapel and
Surrey Quays also needed much
more work than originally
thought and London Over-
ground decided to properly
refurbish them, he adds.
“A grade separated junction
was also introduced to make the
link with phase 2 to Clapham
Junction so as not to disrupt
East London Line running when
that project goes ahead.
“One of the things I am most
proud of here is that the scope
has increased very significantly
yet our design, construction
and commissioning period
increased by only five months,”
says Stuart.
BBCJV drove itself along,
and for added momentum it
had a set of about one hundred
non-contractual milestones to
hit, worked out with Parsons
Brinckerhoff.
“In December 2008 we said
that we’d have all the structures,
track, and operational systems
complete to start test train
running 10 months later on 5
October 09, and we did,” says
Stuart. “And from that date we
ran up to six of the new trains
every day for four months during
which we finished the new
station buildings behind the
platforms; our track gives a very
smooth ride and the Invensys
signalling system proved fault-
less.”
“Also in December 2008 we
gave a date of 17 January 2010 to
hand over to trial operations and
on that very date we started the
week long process of handover
to Transport for London for trial
operations,” adds Casebourne.
“In parallel the refurbishment
of the tunnel stations was
completed and the customer
information systems were
finished. Now customers are on
board and everything is working
reliably.”
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 2726 NEW CIVIL ENGINEER 27.05.1O | www.nce.co.uk
EAST LONDON LINE: Management
W
hat is remark-
able about the
management
of the London
Overground East London Line
construction work is that the job
has so successfully beaten its
deadlines; particularly when the
scope of the scheme was some-
what fluid when the job was
tendered.
Balfour Beatty Carillion Joint
Venture (BBCJV) bid for and
won the basic project against
strong competition and with
the addition of many changes.
The final job is coming in at
£700M or thereabouts after new
elements were added in and the
amount of work required became
clearer as the construction teams
got stuck in on site.
“We knew there would be
additional work in the central
section but we couldn’t find out
how much until we took posses-
sion of the railway from London
Underground (LUL),” says
London Overground Infrastruc-
ture director Peter Richards.
“We also knew the depot, for
instance, had to be added in
but the contractor could not
price that in the original tender
because the designs from
[rolling stock supplier] Bombar-
dier were still being developed.
“That is why we went for a
target cost design and build
contract rather than fixed price.”
But Richards points out that
there was always a total budget
and as the work grew, “we
adjusted the scope to suit the
budget.”
“Is it safety critical?” was the
mantra. If it was, then the money
was found, if not, then as much
cash was saved on each opera-
tion as possible so there was
some to spare when needed.
That approach required close
collaboration between the client
team, BBCJV and its supply
chain throughout the works.
“The closely cooperative
culture of the job has been vital,”
says Balfour Beatty Carillion
project director Mike Case-
bourne. “It is one of complete
openness; no secrets, shared
decisions and facing and solving
problems together.”
Richards agrees: “We have
some very dedicated people on
this project. There is a collabora-
tive, positive culture which has
all helped towards getting the
job out the door on time and on
budget.”
Actually the railway is two
months ahead of schedule. The
original opening date set at the
start of the job in 2004 was 30
June 2010. The full line opened
on 23 May to coincide with
the seasonal timetable change;
and passengers were using the
central section of the route from
27 April. Not bad for a complex,
modern railway squeezed into a
packed capital city.
“We are particularly pleased
about getting the route into
service early as it will have a
huge benefit to the travelling
public,” Richards says.
“Right from the start,
when we signed the contract
on 20 October 2006 we had
to remember that we had
committed to design, construct,
test, commission and deliver
an operational railway, not just
its separate structures and rail
systems,” says Casebourne.
“It was a requirement driven
contract – for example to design
for three minute headways
between trains.”
“There were 6,000 require-
ments and about two thirds of
them were changed or modified
as we all got on with the job,”
says Balfour Beatty Carillion
engineering director Andy
Nettleton. “Without strong
management of a resilient,
responsive design organisation
we would never have achieved so
much in such a short time.”
The key to pinning down the
scope was gaining access to the
old Underground section of the
route between Shoreditch and
New Cross Gate.
“We pushed to get London
Underground to agree to get the
route closed as early as possible,”
says Parsons Brinckerhoff head
of programme management
Ashok Kothari . LU agreed to
shut down the line in December
2007 although it had originally
wanted to keep it open until the
following April.
There was a slight delay
while Underground upgrade
contractor Metronet stripped
out all of its assets but the joint
Working
Together
as a team
SAFETY
The London Overground East
London Line scheme has had
an excellent safety record over
the duration of the project.
The site has twice recorded 1M
accident free hours under the
Reporting of Injuries, Diseases
and Dangerous Occurrences
Regulations (Riddor) 1995.
This was achieved in
December 2008 and again in
November 2009.
The job hit over 1.5M
continuous Riddor-free hours,
and the current accident
frequency ratio of reportable
accidents to 100,000 man hours
worked is an excellent 0.12, a
performance which recently
landed a coveted Rospa Gold
Award.
“We have had a really big
push on the safety culture on
this project,” says health and
safety manager Mike Davies.
“We have focused on the
supervisors and gangers and put
in some fun incentives like group
of the month winning a fleece
each,” he adds.
Collaboration between client, contractor
and supply chain was crucial as the
construction project developed in scope,
writes Jackie Whitelaw.
MaNAGING THE TEAMS
COMMUNITY RELATIONS
As BBCJV project director, Mike
Casebourne has had to manage
640 professional staff, and 600
designers off site in the offices of
Scott Wilson and Tony Gee and
other designers.
He is aslo responsible for 2,500
operatives on site at peak and
up to 1,000 people engaged in
the offsite manufacture of all
the elements for the job all over
the UK. At peak, the project was
spending £30M every four weeks
or £1.5M a day.
The job was divided into four
construction sections under the
control of four BBCJV senior project
managers; northern civils under
Andy Swift; southern and central
civils under Paul Rasmussen; rail
systems under Elliott Young and
the depot under Howard Williams.
These were supported by design,
commercial and administrative
managers within their teams and
reporting also to their department
directors.
“We had to design,
construct, test,
commission and
deliver an operational
railway”
Mike Casebourne,
BBCJV
“The scope increased,
yet our design,
construction and
commissioning period
increased by only five
months”
Adam Stuart, BBCJV
Team work: The close
cooperation culture of the job
has been vital to successful
construction of complex projects
like Dalston Junction station
Community relations were a vital
part of successful delivery of the
East London Line with full time
community relations managers
working for London Overground
and BBCJV.
The usual issues of working
hours, noise and dust had to be
addressed but it was either end of
the project – at Dalston and New
Cross Gate where there were most
sensitivities.
“There was some resistance to the
idea of Dalston being gentrified,”
says head of communications for
London Rail Julie Dixon. “But we
always stress that the East London
Line is a regenerating railway with
the priority being to give people
access to jobs which has helped
allay concern.
“At New Cross Gate people were
unhappy at the idea of a 24 hour
train depot. The solution was to
get the residents involved, listen
to them and respond to their
concerns. For instance, the depot
will have low level lighting so as
not to create a nuisance.”
east london
line REBORN
MAJOR
PROJECT
REPORT
EAST LONDON LINE: DALSTON & NORTHERN STRUCTURES
Dalston Junction station is a massive,
complex structure that has been designed
to support multi-storey buildings and to
accommodate the potential Crossrail 2
line, as Margo Cole discovers. And Adrian
Greeman focuses on the array of civil
engineering work in the northern section
linking the Victorian Kingsland Viaduct to
the old East London Line at Whitechapel.
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 2928 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk
I
n theory, building a new
four-track four-platform
station at Dalston Junction
could have been fairly
straightforward.
Admittedly, space was very
tight, but the new line runs
through an existing cutting, so
surely it wouldn’t have been too
much of a challenge to build a
roof slab over a section of the
tracks and put a station building
on top – would it?
The reality is not quite so
simple. The area taken up
by the railway line as it runs
through the heart of Dalston is
prime development land and an
important area within Hackney’s
regeneration plans. As a result,
a slab had to be built over the
tracks not only to support the
station building but also the
loads from a series of apartment
blocks of up to 17 storeys that are
set to be constructed on top.
Within weeks of work starting,
what had once appeared to be a
generously-proportioned, open
cutting had become a highly
congested construction site, with
over 30 pieces of major plant
involved in excavation and pile
installation, as the London Over-
ground East London Line team
set about building a 250m long
by 40m wide podium slab and its
supports.
The loads from the proposed
apartment blocks will go into
downstand beams built into the
500mm thick podium slab, and
from there into a series of walls
and columns supported by deep
piled foundations. The new plat-
forms will sit under the podium
slab, just above pile cap level.
For the most part, the down-
stand beams are 1m deep, and
were cast in situ along with the
deck slab. Some of the beams
were very heavily reinforced,
as BBCJV section manager
for Dalston Kingsland Guy
Anstiss recalls. “In some places
there’s an awesome amount of
reinforcing steel. One section
of beam has over 100 H40 bars
at the top and bottom of the
downstand beam, and multiple
links,” he says.This gives a total
of 1,250kg of reinforcement per
linear metre in some locations.
However, in 19 beams, even
this heavily reinforced concrete
was unable to support the
anticipated point loads from the
apartment building which are
expected to be up to 7,000t. Here,
steel I-beams have been used as
part of the permanent reinforce-
ment, with pairs of I-beams
joined top and bottom with
diaphragm plates.
These pairs of beams weigh
up to 90t each, and span up
to 33m. They sit on specially
designed bearings supplied by
Freyssinet that weigh up to 3t
and are capable of handling the
uplift and the rotation that could
be caused by such heavy point
loads. Once the beams were in
place, the diaphragm plates were
welded insitu, the voids between
the plates were filled with grout
and then reinforcement cages
placed in and around the beams
to tie them into the podium slab
before the concrete was poured.
In all, there is 1,000t of structural
steelwork in the new station,
most of it in these massive
beams.
The downstand beams span
between walls and columns that
sit on pile caps up to 2m deep,
the largest of which takes up an
area of 3,600m2
. Beneath the pile
caps are heavily reinforced bored
concrete bearing piles, most of
which are 650mm or 750mm in
diameter, and sunk to a depth of
26m. However, at one end of the
site, provision has been made
for the possibility of the second
Crossrail line passing diagonally
beneath the East London Line.
In the original design, a raft
foundation would have
Whitechapel
Station
Shoreditch
High Street
Station
GE19
BRIDGE
Precast concrete
box enclosure
Air rights -
Precast concrete
box enclosure
protects the line
from future
development
works
Great
Eastern
main line
North
London
line
SHOREDITCH
HIGH STREET
BRIDGE
BISHOPSGATE
VIADUCT
Bishopsgate Goods Yard
Dalston
Junction
DLR
Hammersmith
City line
District line
Haggerston
Station
Hoxton
Station
of steel
SHOREDITCH HIGH
STREET BRIDGE
Bow arch bridge
HOLYWELL VIADUCT
links up with the refurbished
Kingsland viaduct
DALSTON STATION PODIUM
A massive and complex
structure designed to
support multi-storey
development and
accommodate Cross-
rail tunnels
SHOREDITCH HIGH
STREET STATION
SHOREDITCH
STATION BOX
ENCLOSURE
- DETAIL
BISHOPSGATE
VIADUCT
GE19 BRIDGE
Steel, Warren truss bridge
BISHOPSGATE
GOODS YARD
Prime develop-
ment area
300tabove ground
10m
foundation piles
1,366
viaduct length span
400m
platform length
100m 84m
Shadwell
Station
REGENTS CANAL
central sectionNorthern extension
HOLYWELL
VIADUCT
Kingsland Viaduct,
refurbished masonry
arches and addition
of underbridges
On embankment
1/4 mile
pile depth
30m
21 -23m
spans,
34m at
station
entrance
Pile cap
10m
Precast
panels
Precast
deck
Portal frame
sections
graphic: © www.paulweston.info
21 - 23m
spans
22m
6m
AIR RIGHTS DEVELOPMENT
Station
Crossrail
tunnels
Podium slab
HOXTON SQ N1HOXTON SQ N1HOXTON SQ N1
WHITECHAPEL RD E1WHITECHAPEL RD E1
MILE END ROAD E1MILE END ROAD E1
DALSTON LANE E8DALSTON LANE E8
KINGSLAND ROAD E2KINGSLAND ROAD E2
Skyway to
the north
DALSTON
JUNCTION
“One section of
beam has over 100
H40 bars at the top
and bottom of the
downstand beam and
multiple links”
Guy Anstiss,
BBCJV
Complete: A new train zips into Shoreditch High Street Station
east
london line
extension
MAJOR
PROJECT
REPORT
30 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk
EAST LONDON LINE: DALSTON & NORTHERN STRUCTURES
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 31
T
he northern section of
the London Overground
East London Line,
running mostly on once
abandoned Victorian viaduct,
has to make a swing eastwards
as it reaches the edge of the
City of London. This enables it
to link up with the old London
Underground East London
Line route to south London.
Two major bridges, substantial
new viaducts, reshaped cuttings
and a new, relocated station at
Shoreditch High Street, are just
some of the works needed to
make the link.
The new section takes the line
through and across Shoreditch
High Street, and on into the
historic Bishopsgate Goods
Yard area, once one of the
industrial wonders of Victorian
London. After three decades
of near dereliction, what was
once a huge, two-level railway
unloading depot with a half
kilometre length of vaulted brick
arches supporting its rail tracks
has become the largest potential
development zone in London
and is ripe for major office and
residential schemes.
Early work for the BBCJV
meant clearing thousands of
tonnes of brick rubble from the
northern half of the nearly 5ha
site. This was the residue of
pre-contract demolition works
which took away many of the old
arches. Some remain, including
the famous and now listed
Braithwaite brick arches, built
by Victorian civil engineer John
Braithwaite in the 1830s.
“We established a truck route
out of the yard using a tempo-
rary Bailey bridge,” says Andy
Swift, BBCJV project manager
for the northern section civils
works. The temporary bridge
took construction traffic over
famous Brick Lane, known for
its curry restaurants. The trucks
then passed over a still intact
Network Rail bridge, known as
GE19, whose later demolition
by Murphy and replacement by
BBCJV was one of the largest
jobs in this section. It crosses
a six track wide cutting for the
main lines between Liverpool
Street Station for the East Coast.
Just beyond this bridge the
line dips into cutting and then
underground at the Valence
Road portal. The brick rubble
the trucks carried was used
OTHER
STRUCTURES
spanned the line of the
tunnel, carrying the building
loads into the ground. But there
was concern about differential
settlement between this section
of foundation and the rest of
the site, which was piled, so an
alternative, piled, solution was
developed.
Two rows of bored piles have
been sunk on each side of the
tunnel line, topped with pile
caps that support walls carrying
the podium slab, the station
concourse and the multi-storey
development above.
“This acts as a ground level
bridge, one of the biggest on the
job, so they can put the Crossrail
tunnel in much later without too
much settlement,” says Anstiss.
It sounds straightforward, but
each of the 40 piles in these four
rows measures between 1.8m
and 2.1m in diameter, and has
been bored to a depth of 40m –
only just above the chalk layer
that underlies the London clay.
The reinforcement cages alone
weighed up to 13t, and required
two splices to enable them to be
lowered into the pile bore.
An inventive piling solution
was also needed as part of the
remedial work to the Forest
Road bridge, which spans the
rail cutting at the southern edge
of the podium slab.
In the original design, all of
this post-tensioned concrete
structure was due to be demol-
ished and replaced by a new
bridge with no parapet on one
side, to allow buses to come off
the Kingsland Road and into a
new bus station being built on
the podium slab. However, the
BBCJV felt that full demolition
would be a complex process, as
the structure is full of services
that would have had to be
diverted at great cost. It was
also very close to neighbouring
properties that would be affected
by noise and vibration during
the demolition.
Instead BBCJV proposed that
the structure be retained, and
turned into a “hybrid”, with the
post-tensioning remaining in
place on the eastern half, while
the parapet on the western side
was demolished to allow the
buses to turn off, with this half
of the bridge supported by one
of the walls designed to take the
podium slab loads. The new pier
wall is topped by an I-beam that
is tied into the existing bridge
reinforcement.
Beneath the wall is a large pile
cap and a total of 66 piles, each
300mm in diameter. “We wanted
750mm diameter piles, but when
we decided to keep the bridge,
the question was: ‘how do we get
the rigs in?’” says Anstiss.
Rigs large enough to sink
750mm diameter piles to the
depth required would not have
fitted under the bridge structure,
so the design was changed to
450mm diameter piles instead.
“That would have worked, but
we had a problem with ground
conditions,” says Anstiss. “It
looked OK from the boreholes,
but when we started piling, water
started boiling up from the base.
It meant that 450mm diameter
wouldn’t really work because
there wasn’t a rig available to
allow us to manage the boiling
sand.”
Instead, the design had to
be changed again for 300mm
diameter piles, with construction
carried out in a sequence that
saw a series of casings driven,
with the piles augered out inside
them. “We had to introduce
“We wanted 750mm
diameter piles, but
when we decided to
keep the bridge, the
question was ‘how do
we get the rigs in?’”
Guy Anstiss,
BBCJV
“We established a
truck route out of
the Bishopsgate
Goods Yard using a
Bailey bridge”
Andy Swift,
BBCJV
The new station at Hoxton is
built inside an existing set of
rail arches, with the concourse
constructed by punching through
the brick piers.
To create this space, ground
engineering specialist Bachy first
installed low headroom mini-piles
either side of each existing pier,
and a ground beam was cast
on top. Holes were then drilled
through the brickwork, and needle
beams threaded through the top of
the pier, and jacked off the ground
beam to support the arch roof
while the material below
was removed to form the
required space.
New columns and a lintel beam
were then grouted in place to form
a portal frame within the pier,
and the jacks removed to allow
the brickwork to sit back down
on top of the frame. The BBCJV’s
engineer Scott Wilson had to carry
out considerable finite element
analysis to ensure the new design
could carry loads from the tracks
above. For Haggerstone Station,
the old viaduct was demolished
and a new station built.
HOXTON AND HAGGERSTON STATIONs
bentonite before we hit the
sand, and then keep excavating
through the bentonite,” says
Anstiss. “Then we had to grout
under pressure to replace the
bentonite, and at the same time
install the 18m long reinforce-
ment cages.”
Now that Dalston Junction
station is complete, much of the
massive civil engineering work
will go unnoticed by passengers,
but during construction it was
one of the most complex parts of
the entire scheme.
At maximum there were 306
operatives working on this part
of the site, and the major plant
used to construct it included a
64m concrete pump – the biggest
available in the UK at the time.
With construction starting
on the apartments that will sit
on top of the podium slab and
passengers starting to use the
bright, airy, stainless steel lined
concourse, this ultra modern
station will soon be a centre
point of modern Dalston.
Crossrail crossing: Piling at Dalston included working around the Crossrail route
Tight spot: Hoxton station was snugly fitted under Kingsland viaduct
Catalyst: The station at Dalston Junction is expected to trigger regeneration
Transfer beam: Massive steel beams will carry
properry developments above Dalston Station
32 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk
EAST LONDON LINE: DALSTON & NORTHERN STRUCTURES
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 33
to infill part of that cutting,
reshaping the gradient and
approach to the new GE19
bridge. It also helped fill another
part of the cutting which
continued on the Bishopsgate
side, swinging around towards
Liverpool Street station.
This was where the original
Shoreditch Station was sited.
The new Shoreditch station
is set in the length of the old
goods yard, along much of a
new viaduct which carries the
track through the yard space
and out across Brick Lane. This
Bishopsgate viaduct carries the
line on 400m of a new concrete
elevated way, some 10m or so
above ground.
The viaduct comprises pairs
of mainly 6m high columns
which are mainly circular or
elliptical in cross section. They
carry a large 3.5m deep edge
beam on either side. “In fact
the depth varies at centre span
giving them a slightly arched
shape” says Swift.
The beams form the platforms
and are connected by a concrete
slab which forms the deep
trackwork trough between them.
Spans between are 21m to 23m
long apart from an extra long
34m span across the street at the
station entrance.
Concreting for these beams
was reasonably complicated
since they required a mass of
heavy T40 bar reinforcement, up
to five layers thick, which meant
care was needed in placing the
concrete. “We used limpet vibra-
tors on the formwork which gave
us issues of noise and vibration
to manage, since this is a busy
area with a lot of residential
property around,” says Swift.
Clusters of five bored piles
support each end of a series of
single pile caps as wide as the
viaduct on which sit each pair
of the columns that support
the viaduct above. One cluster
was bored very close to London
Underground Central Line
tunnels and monitoring equip-
ment was set up to give early
warning of possible distress.
Fortunately there was none.
Piles are as much as 30m deep
under the station section and
around 22m deep elsewhere.
They were driven into London
clay on which much of the site
rests.
“The clay rises from the
Brick Lane end somewhat as
you approach Shoreditch,” says
Swift. There is terraced gravel
beneath and for the longer
piles that meant using a “wet
pile” system to bore them, with
polymer support, into water
saturated gravel.
Piles were “substantial” says
Swift, between 1,200mm and
1,500mm diameter.
The larger diameter was used
to achieve a shorter pile in a few
places, allowing the pile end to
remain in clay and avoiding the
need for the polymer. Bachey
Soletanche was subcontractor
for the piling.
The longer piles carry the
heavier loads in the central part
of the viaduct where the 200m
length of the new Shoreditch
station is located. The entire
station at rail level is enclosed in
a precast concrete box, creating
a kind of “tunnel in the air”. The
box tube comes in two widths,
a central portion enclosing the
100m long platforms and two
smaller parts extending the
station enclosure at either end;
there is an option for future
expansion of the platform
lengths into these.
The point of the enclosure is
primarily to safeguard the line
from future construction and
development planned for the
entire Bishopsgate area, with
over-site “air rights” construc-
tion around the station, possibly
including a 40 storey high rise
office development. Work is
imminent, although delayed
temporarily by the economic
situation.
“The station enclosure is
really an expensive, perma-
nent crash deck to keep trains
running while work is done later
by the developer,” says Swift.
It is built from precast portal
frame sections attached to the
viaduct at 7.5m intervals. Three
2m high panels are bolted to
each side of these before an
insitu top deck is formed and
poured.
There were challenges on the
longer GE19 bridge to the east
of the station site. This was
fabricated and assembled by
Fairfield Mabey. The assembly
of the Warren truss bridge which
carries the new railway on a
85m span over the six Liverpool
Street main lines, went well. It
was fully assembled on tempo-
rary falsework on the track
alignment in the space which
became the approach ramp, and
push launched into place.
“It was powered over using a
multi-axle transporter provided
by Abnormal Load Equip-
ment” says Swift. A 30m long
nose section was added for the
launching at the front end and
the ALE transporter sat at the
rear end. “It was a balancing
exercise to keep the nose up”
says Swift “so we concreted the
back end deck and added more
weight, leaving the front deck
to be done later. The launching
was done with the strand jacks
between the permanent concrete
abutments being used as the
launch fulcrum, and the ALE
transporter at the rear end.”
West of Shoreditch Station,
the line crosses Shoreditch
High Street on a 35M span
bowstring arch bridge fabricated
by Fairfield Mabey partly within
the Bishopsgate Goodsyard
site. There, the firm welded the
curving steel beams to form the
bow and set the vertical hangers.
A critical part of the job
was a major crane lift for the
completed 330t bowstring arch
bridge, using the 1,200t Sarens
crane on a May weekend in 2008.
“The lift only took a couple of
hours but 12 months of prepara-
tion were needed beforehand”
says Swift, not least because the
busy crane is much sought after.
“We also had to coordinate
all the emergency services, local
authorities, and others for a road
closure,” Swift adds. The site
needed proper preparation for
the crane which arrived on some
forty trucks and took several
days to assemble. Ground had to
be properly cleared, and an area
piled to support the crane.
The viaduct continues west
of Shoreditch High Street with
the Holywell viaduct, curving
sharply to take the line back
across the street as it links north
to the existing Victorian brick
viaduct further on. Five 20m
spans were needed, built close
alongside a listed and untouch-
able building on Shoreditch
High Street, running within
330mm of it at one point.
This part of the work was
preceded by significant archaeo-
logical digging within the old
Holywell Yard. The Museum of
London was delighted by the
discovery of the remains of an
old monastery, including foot-
ings and columns, various burial
sites, plates and knives.
“The station
enclosure is really
a permanent crash
deck to keep trains
running while work
is done later by the
developer”
Andy Swift,
BBCJV
“The GE19 bridge
was powered over
using a multi-axle
transporter. It was a
balancing exercise to
keep the nose up”
Andy Swift,
BBCJV
Shoreditch High Street: A 35m span bow arch bridge is lifted into place
GE19: The bridge was launched over six mainline railway tracks
New link: The line runs on a mixture of new and
refurbished viaduct from Dalston to Shoreditch
34 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk
EAST LONDON LINE: SOUTHERN SECTION
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 35
River ThamesWAPPING
View along the Thames Tunnel, c. 1835
ROTHERHITHE
HIGH WATER
LOW WATER
Section
Masonry
construction
THAMES TUNNEL
Jubilee line
SLAB TRACK
Wapping
Station
RIVER
THAMES
SHADWELL
BASIN
CANADA
WATER
GREENLAND
DOCK
Rotherhithe
Station
Surrey Quays
Station
New Cross
Station
New Cross Gate
Station
Canada Water
Station
Central section Southern extension
Victorian road bridge
replacement
Victorian road bridge
replacement
Concrete
trough takes
slab track
Concrete sleeper
Mass concrete slab
Boot
(absorbent
membrane)
Rail mounted
on sleeper
Mass concrete slab
Rails mounted on
concrete block
sleepers
Track sections
- lengths to
suit project
Network Rail
main lines
Steel, Warren
truss bridge
Concrete ramp
Concrete
ramp
75m
32m
10m
Surrey Canal
Road bridge
NEW CROSS GATE
FLYOVER
THAMES TUNNEL
REFURBISHMENT
The East London line
has its roots in the
Brunel’s construction
beneath the Thames
(c. 1825 and 1843). The
tunnel was refurbished
for waterproofing and to
take slab track.
NEW CROSS GATE
FLYOVER
NEW CROSS GATE
DEPOT
To avoid the need for
points a much larger
grade crossing was
required over the
existing, near capacity,
Network Rail main lines.
A 1200t Warren truss
bridge with a 75m span
was employed
WAPPING
STATION
VENT
To create a second
means of escape
for the station,
shafts were sunk
either side of a
Victorian, brick
lined, smoke vent
span
75m
of steel
1200t
shaft depth
16m
To Croydon
Extension for
completion 2012
To Clapham
Junction
graphic: © www.paulweston.info
Cast iron
struts
Masonry Vent
Escape shafts
Made ground
Drift
London clay/
thin layer
Lambeth group
Thanet sandsMass concrete
New openingNew opening
Used on the new
viaducts and in
tunnel sections,
track slab
improves stability,
noise suppression
and maintenance
intervals
BOOTED SLEEPER - SECTION
For areas requiring the most noise
suppression sleepers are mounted in
an absorbent membrane
BRUNEL RD SE16BRUNEL RD SE16
WAPPING HIGH STREET E1WWAPPING HIGH STREET E1W
ROTHERHITHE NEW RD SE16ROTHERHITHE NEW RD SE16
NEW CROSS ROAD SE14NEW CROSS ROAD SE14
OLD KENT ROAD SE1OLD KENT ROAD SE1
LOWER RD SE16LOWER RD SE16
COPE ST SE16COPE ST SE16
T
he biggest civil engi-
neering challenges were
at Whitechapel and
Wapping as part of the
need to provide all the under-
ground stations with secondary
means of escape (SMEs)
Whitechapel
AtWhitechapel, a relatively
simple steel truss bridge sufficed
for the SME, with lattice towers
on the platforms and steel stair-
cases to link to an emergency
street level exit.
But on either side of
Whitechapel Station two large
excavations will be required for
the planned Crossrail station
which will sit above the Crossrail
tunnels but below the ELL.
The two subterranean Crossrail
concourses will be linked by a
pedestrian underpass beneath
the ELL tracks, and it made sense
to build the under rail structural
elements during the ELL works.
The ELL team also found itself
involved in some other advance
works for the Crossrail team.
Crossrail has almost no space
in the streets aboveWhitechapel
for work platforms from which
to construct its excavations. To
find space it has prepared for a
major bridging structure to be
built over a 70m length of the
Whitechapel cutting.
This “crash deck” work plat-
form will need to support major
equipment and heavy plant and
demands correspondingly hefty
foundations, explains BBCJV
engineering manager for central
and southern sections Andy
Bradshaw. During its work, the
ELL team installed for Crossrail
two rows of 600mm diameter
piles on each side of the ELL
tracks, with some careful design
required to give pile lengths
which stopped short of the
Crossrail track tunnels. “The
pile depths were limited to 10m,”
Bradshaw says.
In order for the Crossrail
crash deck piles to be installed
BBCJV had to remove the old
ELL service platforms at the base
of the 10m highVictorian brick
buttress-and-coffer retaining
walls that make up the ELL
Whitechapel cutting. This was a
tricky job because the toes of the
retaining walls had to be braced
off each other throughout the
works.
To prevent movement of the
walls, work had to be done in
two phases. In each phase, the
existing platform was broken
out in bays 4m to 9m long, new
precast struts were laid across the
trackbed and then a pilecap was
constructed at each side of the
cutting.
“We used hefty 406mm diam-
eter tubular steel struts as tempo-
rary support until the piles were
cast,” says Bradshaw. “The struts
were later reused for excava-
tion support elsewhere on the
project.” Circular voids had to
be left in the pilecaps for later
sinking of the piles needed to
support the Crossrail work plat-
form.
Two contiguous piled walls
some 3.5m apart across the tracks
were also cast to form the walls
of the future Crossrail station
connecting passage. A thick-
ened section of the track bed
makes a roof slab for this pedes-
trian tunnel which will be exca-
vated, when needed by Crossrail,
without disrupting the ELL.
The cost of “several millions”
has been met by the Crossrail
project.
Wapping
AtWapping station the main
entrance uses the Brunel tunnel
shaft to accommodate two lifts
and a spiral staircase but at the
other end there was no obvious
second escape route.
“There was a brick lined smoke
shaft however, about 11m across”
says Bradshaw. It dates from
the days when steam trains ran
underground which they did
until early in the 20th century.
Either side of this 16m deep vent,
it was decided to sink shafts in
which steel staircases could be
built, linked to the platforms by
cross passages at the base that
were created by breaking through
the thinner infills between the
retaining wall buttresses.
The original plan to form a
rectangular box shaft with big
1100mm secant piles did not
work within the overall construc-
tion programme. A value engi-
“We used big 530mm
diameter tubular
steel struts as
temporary support
during the casting”
Andy Bradshaw,
BBCJV
Negotiating exisiting tunnels, contracts
and Victorian structures was all in a
day’s work for the East London Line team
as it worked to construct and renovate
the railway. This section of the project
also involved work to ensure the new
structures did not interfere with planned
works for the Crossrail line which crosses
the route. Adrian Greeman reports.
TUNNELS
& TRACKS
HEading
South
Wapping: Here, the line runs south into Brunel’s twin bore Thames Tunnel
east london
line REBORN
MAJOR
PROJECT
REPORT
36 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk
EAST LONDON LINE: SOUTHERN SECTION
www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 37
O
nce the ELL emerges
from its tunnels just
past Surrey Quays
onto conventional bal-
lasted track, it might be thought
there was less to do.
But renewing bridges,
providing for new connections
to the mainline and future
London Overground extensions
and installing big flyover at New
Cross were all significant chal-
lenges.
And there was the building of
a brand new carriage servicing
depot to add into the mix.
Cope Street Bridge
Two significant bridges carry
busy South London road
connections across the line
just after Surrey Quays station,
where it is still in cutting, rising
out of the river tunnel section to
surface running. Both of these
were old Victorian bridges, 10m
wide, comprising parallel cast
iron I-beams and masonry jack
arch infills. Both carried a single
carriageway road and pedestrian
pavement and were supported
in the middle by a central pier.
Originally rail tracks ran either
side of the pier but now they
only run on the western side.
The cast iron piers did not
meet modern derailment resist-
ance standards and had to go. At
the Cope Street bridge, an initial
scheme for a single unsupported
span was dropped because the
deck beams would have been too
deep. Instead new concrete piers
were installed but set back from
the live track, creating one long
and one short span.
Simple replacement of the
deck above was complicated
by the high concentration of
services carried within the decks,
most critically a fibre optic cable.
Diverting it to a temporary
bridge during the work would
have been very expensive –
around £250,000. “And diverting
it back afterwards would have
doubled that,” says Andy
Bradshaw, BBCJV construction
engineering manager for the
section.
Costs were contained after a
value engineering study devised
a scheme that left the narrow
strip of bridge deck with the
fibre optic cable intact while the
rest was rebuilt with new precast
concrete beams. “And then we
only had to move the cable once
onto the new part and finish the
construction,” says Bradshaw.
Rotherhithe New Road Bridge
At the second bridge, Rother-
hithe New Road Bridge, an even
more expensive utility diversion
was needed to handle several
high voltage cables which served
most of South London. These
were embedded in a concrete
block which had replaced one of
the original jack arches between
two I-beams.
Rather than a double move for
the cables at an overall cost of
£1.4M, and some risk of blacking
out a big part of the conurbation,
BBCJV devised a system to leave
the block intact and rebuild the
rest of the bridge around it.
The bridge was tackled in
two halves in order to leave a
carriageway open for busy traffic.
Most of one side was demol-
ished first, leaving the power
line slab in place supported on
its portion of the pier. Once the
new steel beams were installed,
two transverse I-beams were
then attached underneath the
new deck, to support the power
line slab, on either side of its
support pier.
With the power cable slab load
transferred to these temporary
hanging beams, the pier could be
demolished. A third steel I-beam
was then installed between the
temporary ones, to be a perma-
nent support, while the outer
two were removed.
The new Rotherhithe bridge
has one single span. It is longer
than before but does not run the
full length of the old bridge’s
two spans. Instead the far abut-
ment was built outwards on
the disused side of the cutting.
Rebuilding the bridge in this
way produced a net saving to
the client of around £1M, says
Bradshaw.
Further south in the Silwood
depot, there is to be an eventual
connection to the South London
Line. Points suffice to make
the transition on the up-line
into London, but the down-line
trains will have to dip under the
up line to travel west to Clapham
Junction.
Secant piled walls were used
to form a new cutting taking
the connecting track down
and around, with a slab placed
across the top of this cutting to
carry the up-line. The new grade
separated junction has been
built to avoid service disruption
in the future when the project to
connect the East London Line
to Clapham Junction gets under
way.
Further south, a third road
bridge was replaced, this time
with the straightforward demoli-
tion and lifting in of a new deck
with a 1,000t crane. Apart from
finding space between buried
services to put crane outriggers,
the main problem was to avoid
traffic closures on weekends
when Millwall Football Club had
home games, says Bradshaw.
New Cross Gate Flyover
A much bigger grade separated
crossing was needed near the
end of the renewed East London
Line section where it merges
with and uses the existing
Network Rail slow lines at New
Cross Gate on the route south
to Croydon and Crystal Palace
at New Cross Gate. New Cross
Gate flyover avoids the need for
a four-track ladder of switches
and crossings to carry the ELL
trains across four near-capacity
main line tracks onto its own
line which runs past the new
service depot.
The connection takes north-
bound trains heading for the
ELL off the main slow line and
then up an inclined concrete
ramp to a 75m steel bridge which
spans the four tracks. A short
32m steel span continues the
10m wide bridge from a concrete
pier onto another inclined
concrete ramp that carried the
trains through the new depot
and onto the ELL’s dedicated
line.
The new ELL depot sits on old
sidings which for some years
had become a local authority
site for impounded cars
says Mark Walker of BBCJV
who supervised the depot
construction.
The depot is domnated by the
four-track, four-crane, four train
rolling stock maintenance facility
and its three storeys of offices all
housed in a huge 90m by 40m
by 12m high rectangular steel-
framed, steel-clad building. Inside
the depot are three raised tracks
enabling clear access below
the trains. The fourth track is
equipped with synchronized jacks
capable of lifting a whole train
in one minute for the purpose of
bogie changing.
Another 90m building, split
longitudinally into two, has one
track dedicated to a twin-headed
wheel lathe and a second in the
other half committed to heavy
cleaning and painting. It also
has a blast and fire proofed top
floor dedicated to an operational
control and signaling centre
which allows signallers 10
minutes to safey shut down all
rail systems in the event of a fire.
NEW CROSS GATE DEPOT
neering rethink suggested
sinking jacked caissons with
mucking out by long reach exca-
vator “which paid a health and
safety dividend because you
don’t need anyone in the shaft
until you have reached forma-
tion level and pumped out,” says
Bradshaw.
This went well until the time
came to make the first cross
passage, excavating through
what it had been thought would
be firm London clay. Instead old
rotten timbers, possibly some
temporary works left in place by
builders of the wall, were encoun-
tered. These timbers posed a
problem because, once disturbed,
it was realised that they were
providing a water flow route from
the terrace gravels above. “And
since the Thames is just next
door the water was not going to
stop,” says Bradshaw
Initial grouting was just
washed out and a programme of
minipiling between buttresses
and shafts was devised to form
a grout curtain to cut off the
flow while the cross passage was
completed. On the other shaft,
forewarned, the grout curtain
was created before any trapped
ground water was disturbed.
Meanwhile inside the smoke
vent a series ofVictorian cast iron
struts needed upgrading. Two
levels of three rather elegantly
shaped struts, with flared ends,
had to be replaced. Architec-
tural heritage considerations
dictated that the replacement
struts should resemble the origi-
nals as far as possible. The upper
struts were removed completely
and new steel struts installed in
their place, but the lower struts
were more difficult because it
was hard to see exactly how they
connected at the wall.
Rather than risk displacing
anything the lower struts were
cut away in the centre and new
steel sections were inserted.
Around the remaining cast iron
lengths a sleeve was devised in
South of
the thames
new steel to take the loads. Apart
from the complexity of this work
the job was a major exercise in
logistics, with a crane at the top
of the shaft juggling old and new
pieces of steel around both the
permanent struts and three sets
of 250kN temporary props.
Marc and Isambard Brunel
had accessed their Thames
Tunnel works via a shaft on the
south bank of the Thames.
To make a lasting contribu-
tion to London’s engineering
heritage, BBCJV cast a whole
new floor in, sealing it off
from the tunnel and trains, so
leaving it available to the Brunel
Museum to develop as additional
exhibition space, including a
chance for visitors to see the orig-
inal shaft structure.
Other station work was also
complex.
“After contract award the client
decided to completely refur-
bish the station buildings and
platforms bringing them up to
modern standards; this devel-
oped into interior demolition
back to bare walls and even some
of those were reconstructed,” says
BBCJV stations project manager
PhilWharton.
Renewing bridges,
providing for
connections to the
mainline and future
London Overground
connections and a
flyover at New Cross
were big challenges
Excavation through
what had been
thought to be London
Clay instead turned
out to be rotten
timbers, possibly
from some long-
forgotten wharf
Depot: The South London site is a huge 90m by 40m steel framed structure
Whitechapel: Vital interchange
Hot stuff: Thermal welders at work Junction: The depot is just to the east of the massive New Cross Gate flyover
Wapping station: Orange temporary struts
brace the original 16m high buttress-and-coffer
brick retaining walls while the original struts are
replaced with new, stronger white lookalikes
38 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk
EAST LONDON LINE: SOUTHERN SECTION
The most complex part of
the operation to build the four
track crossing was placing the
main 1,200t Warren truss for
the 75m span. “Fortunately there
was some unused Network Rail
land alongside the mainline
tracks where our subcontractor
Fairfield Mabey could assemble
the bridge,” says Bradshaw.
To get it into position needed
a 56 hour possession, booked
long in advance.
“We used multi-axle self-
powered transporter units for
the move. The truss was jacked
at finished height onto trestles
on the back of the transporter
units and then moved south-
wards some 60m. Then one end
of the truss was slewed across in
a 60m long arc while the south
end took a shorter 20m long
path” says Bradshaw.
The construction yard
embankment area was previ-
ously surfaced with a 300mm
thick layer of recycled demoli-
tion aggregate to improve its
load bearing capacity for the
move.
To prepare the four mainline
tracks for the heavy loadings of
the bridge and its transporter
units, various bespoke level
crossing options were consid-
ered. But they would have been
expensive, not only because
a lot would have been needed
but they would have had to be
tailored to fit irregular track and
sleeper spacings.
Instead, a simpler solution
was found. By removing the
third rails that provide traction
power for trains in Network
Rail’s Southern Region and
protecting the running rails
with steel channel sections, it
was possible to build up a load
bearing platform using conven-
tional ballast. This meant it
was unnecessary to keep the
temporary fill and the existing
line ballast separate. Any surplus
would simply form part of the
railway afterwards.
“To get the flyover
into position needed
a 56 hour possession.
We used multi-
axle self powered
transporter units for
the move”
Andy Bradshaw, BBCJV
On the new viaducts and in the
tunnel, the East London Line
sees the first application of the
Sonneville boot system of slab
track.
For new viaducts and tunnels,
slab track was installed, using
the Sonneville system of concrete
blocks to support either end of
the sleeper, all embedded in a
concrete slab. Each independent
block sits on a neoprene pad inside
a rubber “boot” which dampens
vibrations; and the blocks can be
extracted and the boot renewed
easily when necessary. Noise
suppression was the key factor on
viaducts particulary as they run
through crowded areas of the city,
but reduced maintenance was the
prime reason for the choice in the
tunnels, where only night-time
access is possible.
“We had two variants of slab,
the basic one and in some places
the mass spring system,” says
BBCJV’s Steve Bradley who was
track construction manager for
three years of the project. The
difference lies in the concrete
surround for the blocks. Mostly this
is just mass concrete poured around
the booted blocks that are carefully
positioned by hanging them from
the precisely positioned rails that
have been placed inside a basic
concrete trough. But for additional
noise suppression on viaducts, the
trough is lined with an additional
absorbent membrane and the
concrete track slab poured around
it has to be reinforced to handle the
additional movement created by
the addition of the membrane.
The boot system is complex to
install, since each sleeper end is
independent and must be accurate
for rail inclination, gradient, gauge,
alignment and more, before fixing
in concrete. It is the first application
in the UK. Drivers have already
informally declared the line the
smoothest they have experienced.
TRACK
Big move: Four multi-axle transporters move the 1,200t Warren truss for the New Cross Gate flyover into position
Covering up: Temporary fill cover the track during the flyover move
Sound solution: Rubber “boots” under the track damp down vibration
Truss: Last minute adjustments

More Related Content

What's hot

2005 - Public Private Partnership_Two Year Review
2005 - Public Private Partnership_Two Year Review2005 - Public Private Partnership_Two Year Review
2005 - Public Private Partnership_Two Year ReviewDanny Myers
 
TFL Presentation
TFL Presentation TFL Presentation
TFL Presentation Sandra Idio
 
15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris
15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris
15.12.31 Project Glossary of Commissions Completed at Arcadis_EC HarrisPat Walsh MCIOB
 
ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)Mark Shanholtzer
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen PowerpointHayley Sharp
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen PowerpointMay Begum
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli SealinkDesignTeja
 
2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-enTeresa Elliott
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea linkAnkita Pal
 
Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case studyAKSHAY CHATURVEDI
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...Rajesh Prasad
 
Bandra worli sea link jay
Bandra worli sea link jayBandra worli sea link jay
Bandra worli sea link jayDhruv Seth
 
AEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 FinalistsAEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 FinalistsAutodesk AEC
 
Kkk final
Kkk finalKkk final
Kkk finalAh Jun
 
CB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesCB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesRebecca Abel
 

What's hot (20)

2005 - Public Private Partnership_Two Year Review
2005 - Public Private Partnership_Two Year Review2005 - Public Private Partnership_Two Year Review
2005 - Public Private Partnership_Two Year Review
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
TFL Presentation
TFL Presentation TFL Presentation
TFL Presentation
 
15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris
15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris
15.12.31 Project Glossary of Commissions Completed at Arcadis_EC Harris
 
ACT December 2015 - OM (2)
ACT December 2015 - OM (2)ACT December 2015 - OM (2)
ACT December 2015 - OM (2)
 
AGC Presentation_Final_12.6.11(2)
AGC Presentation_Final_12.6.11(2)AGC Presentation_Final_12.6.11(2)
AGC Presentation_Final_12.6.11(2)
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bus
BusBus
Bus
 
2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en
 
Bridge apr 2014
Bridge apr 2014Bridge apr 2014
Bridge apr 2014
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea link
 
Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case study
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
 
Bandra worli sea link jay
Bandra worli sea link jayBandra worli sea link jay
Bandra worli sea link jay
 
AEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 FinalistsAEC Excellence Awards 2016 Finalists
AEC Excellence Awards 2016 Finalists
 
Kkk final
Kkk finalKkk final
Kkk final
 
CB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesCB_SeptOct_2015_bridges
CB_SeptOct_2015_bridges
 

Viewers also liked

ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...
ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...
ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...Engineers Australia
 
ElanaFrydmanCapstoneFinalPresentation
ElanaFrydmanCapstoneFinalPresentationElanaFrydmanCapstoneFinalPresentation
ElanaFrydmanCapstoneFinalPresentationElana Frydman
 
Godrej loud 2015 (kritika)
Godrej loud 2015 (kritika)Godrej loud 2015 (kritika)
Godrej loud 2015 (kritika)Kritika Agarwal
 
La Cascada de Piragua.
La Cascada de Piragua.La Cascada de Piragua.
La Cascada de Piragua.Danielaliseth
 
Rev. John Grueal and Exodus 1947: Aspirations of Concentration Camp Survivors
Rev. John Grueal and Exodus 1947: Aspirations of Concentration Camp SurvivorsRev. John Grueal and Exodus 1947: Aspirations of Concentration Camp Survivors
Rev. John Grueal and Exodus 1947: Aspirations of Concentration Camp SurvivorsArthur L. Finkle
 
Hollywood, Gaming and Immersive Storytelling
Hollywood, Gaming and Immersive Storytelling Hollywood, Gaming and Immersive Storytelling
Hollywood, Gaming and Immersive Storytelling Kim Voynar
 
Floorbrite Brochure 2015
Floorbrite Brochure 2015Floorbrite Brochure 2015
Floorbrite Brochure 2015Trudie Williams
 
ده روش براي آرام كردن كودكان
ده روش براي آرام كردن كودكانده روش براي آرام كردن كودكان
ده روش براي آرام كردن كودكانdigidanesh
 
Standardization of Poly Herbal Siddha Medicine Eladhi Chooranam
Standardization of Poly Herbal Siddha Medicine Eladhi ChooranamStandardization of Poly Herbal Siddha Medicine Eladhi Chooranam
Standardization of Poly Herbal Siddha Medicine Eladhi Chooranaminventionjournals
 
Digital finance - visualizing a new era of finance
Digital finance - visualizing a new era of financeDigital finance - visualizing a new era of finance
Digital finance - visualizing a new era of financeCrowdValley
 
20150721-mosh
20150721-mosh20150721-mosh
20150721-moshhicksca
 

Viewers also liked (18)

ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...
ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...
ICWES15 - The Promotion of Women Engineers in Management Positions, Problems ...
 
ElanaFrydmanCapstoneFinalPresentation
ElanaFrydmanCapstoneFinalPresentationElanaFrydmanCapstoneFinalPresentation
ElanaFrydmanCapstoneFinalPresentation
 
Godrej loud 2015 (kritika)
Godrej loud 2015 (kritika)Godrej loud 2015 (kritika)
Godrej loud 2015 (kritika)
 
Adolf Resume
Adolf ResumeAdolf Resume
Adolf Resume
 
La Cascada de Piragua.
La Cascada de Piragua.La Cascada de Piragua.
La Cascada de Piragua.
 
Rev. John Grueal and Exodus 1947: Aspirations of Concentration Camp Survivors
Rev. John Grueal and Exodus 1947: Aspirations of Concentration Camp SurvivorsRev. John Grueal and Exodus 1947: Aspirations of Concentration Camp Survivors
Rev. John Grueal and Exodus 1947: Aspirations of Concentration Camp Survivors
 
Hollywood, Gaming and Immersive Storytelling
Hollywood, Gaming and Immersive Storytelling Hollywood, Gaming and Immersive Storytelling
Hollywood, Gaming and Immersive Storytelling
 
KevinMaxwellCV2
KevinMaxwellCV2KevinMaxwellCV2
KevinMaxwellCV2
 
Cartazva ve
Cartazva veCartazva ve
Cartazva ve
 
Floorbrite Brochure 2015
Floorbrite Brochure 2015Floorbrite Brochure 2015
Floorbrite Brochure 2015
 
ده روش براي آرام كردن كودكان
ده روش براي آرام كردن كودكانده روش براي آرام كردن كودكان
ده روش براي آرام كردن كودكان
 
Standardization of Poly Herbal Siddha Medicine Eladhi Chooranam
Standardization of Poly Herbal Siddha Medicine Eladhi ChooranamStandardization of Poly Herbal Siddha Medicine Eladhi Chooranam
Standardization of Poly Herbal Siddha Medicine Eladhi Chooranam
 
Ecobynamnung
EcobynamnungEcobynamnung
Ecobynamnung
 
Seven seas
Seven seasSeven seas
Seven seas
 
Digital finance - visualizing a new era of finance
Digital finance - visualizing a new era of financeDigital finance - visualizing a new era of finance
Digital finance - visualizing a new era of finance
 
20150721-mosh
20150721-mosh20150721-mosh
20150721-mosh
 
gavahan susan pro
gavahan susan progavahan susan pro
gavahan susan pro
 
conor new CV
conor new CVconor new CV
conor new CV
 

Similar to east_london_line_reborn (2)

Oldham metrolink
Oldham metrolinkOldham metrolink
Oldham metrolinktaylaadams
 
068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homes068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homesAdrian Cole
 
068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homes068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homesAdrian Cole
 
Atkins' tunnelling projects
Atkins' tunnelling projectsAtkins' tunnelling projects
Atkins' tunnelling projectsAtkins
 
Crossrail Presentation: Moving London Forward
Crossrail Presentation: Moving London ForwardCrossrail Presentation: Moving London Forward
Crossrail Presentation: Moving London Forwardinmidtown
 
23 Nov Major Transport Projects
23 Nov Major Transport Projects23 Nov Major Transport Projects
23 Nov Major Transport Projectsfutureoflondon
 
Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Atkins
 
Community Forum presentation - 31st January 2017
Community Forum presentation - 31st January 2017Community Forum presentation - 31st January 2017
Community Forum presentation - 31st January 2017Alexandra Dobson
 
Fit For The Future - TfL Plan For Modernising London Underground, London Over...
Fit For The Future - TfL Plan For Modernising London Underground, London Over...Fit For The Future - TfL Plan For Modernising London Underground, London Over...
Fit For The Future - TfL Plan For Modernising London Underground, London Over...Thorne & Derrick International
 
Mass transit railway (mtr) hongkong
Mass transit railway (mtr) hongkongMass transit railway (mtr) hongkong
Mass transit railway (mtr) hongkongShahrukh Niaz
 
South East Route - Sussex Area Route Study FINAL
South East Route - Sussex Area Route Study FINALSouth East Route - Sussex Area Route Study FINAL
South East Route - Sussex Area Route Study FINALSteve Knight
 
Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Auckland Transport
 
Integrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureIntegrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureAuckland Transport
 
RV 2014: Mobile Workshop #15- Integrating Transit into Large Institutions
RV 2014: Mobile Workshop #15- Integrating Transit into Large InstitutionsRV 2014: Mobile Workshop #15- Integrating Transit into Large Institutions
RV 2014: Mobile Workshop #15- Integrating Transit into Large InstitutionsRail~Volution
 
sydney harbour bridge;Report submission
sydney harbour bridge;Report submissionsydney harbour bridge;Report submission
sydney harbour bridge;Report submissionAAMIR CHAUDHARY
 

Similar to east_london_line_reborn (2) (20)

Crossrail 2 - Planning for the Future
Crossrail 2 - Planning for the FutureCrossrail 2 - Planning for the Future
Crossrail 2 - Planning for the Future
 
Oldham metrolink
Oldham metrolinkOldham metrolink
Oldham metrolink
 
068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homes068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homes
 
068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homes068-069_MR_Nov 2016_new homes
068-069_MR_Nov 2016_new homes
 
Atkins' tunnelling projects
Atkins' tunnelling projectsAtkins' tunnelling projects
Atkins' tunnelling projects
 
Transport in london
 Transport in london  Transport in london
Transport in london
 
Crossrail Presentation: Moving London Forward
Crossrail Presentation: Moving London ForwardCrossrail Presentation: Moving London Forward
Crossrail Presentation: Moving London Forward
 
23 Nov Major Transport Projects
23 Nov Major Transport Projects23 Nov Major Transport Projects
23 Nov Major Transport Projects
 
Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...
 
Community Forum presentation - 31st January 2017
Community Forum presentation - 31st January 2017Community Forum presentation - 31st January 2017
Community Forum presentation - 31st January 2017
 
Firas Abbawy CV - Atkins
Firas Abbawy CV - AtkinsFiras Abbawy CV - Atkins
Firas Abbawy CV - Atkins
 
Fit For The Future - TfL Plan For Modernising London Underground, London Over...
Fit For The Future - TfL Plan For Modernising London Underground, London Over...Fit For The Future - TfL Plan For Modernising London Underground, London Over...
Fit For The Future - TfL Plan For Modernising London Underground, London Over...
 
Mass transit railway (mtr) hongkong
Mass transit railway (mtr) hongkongMass transit railway (mtr) hongkong
Mass transit railway (mtr) hongkong
 
WesternVision
WesternVisionWesternVision
WesternVision
 
South East Route - Sussex Area Route Study FINAL
South East Route - Sussex Area Route Study FINALSouth East Route - Sussex Area Route Study FINAL
South East Route - Sussex Area Route Study FINAL
 
Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015Community liason-group-presentation-10-02-2015
Community liason-group-presentation-10-02-2015
 
Integrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's futureIntegrated transport - investing in Auckland's future
Integrated transport - investing in Auckland's future
 
RV 2014: Mobile Workshop #15- Integrating Transit into Large Institutions
RV 2014: Mobile Workshop #15- Integrating Transit into Large InstitutionsRV 2014: Mobile Workshop #15- Integrating Transit into Large Institutions
RV 2014: Mobile Workshop #15- Integrating Transit into Large Institutions
 
Dhaka metro rail
Dhaka metro railDhaka metro rail
Dhaka metro rail
 
sydney harbour bridge;Report submission
sydney harbour bridge;Report submissionsydney harbour bridge;Report submission
sydney harbour bridge;Report submission
 

east_london_line_reborn (2)

  • 1. east london line REBORN MAJOR PROJECT REPORT 27|05|10 London’s new Railway PLanning, design and construction of a new 10km rail route for London Overground
  • 2. 24 NEW CIVIL ENGINEER 27.05.1O | www.nce.co.uk EAST LONDON LINE: INTRODUCTION www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 25 upgrade the East London Un- derground Line that ran from Shoreditch to New Cross Gate since 1997. London Underground had the idea to take a railway into Hackney on a disused viaduct that had once carried the North London Overground Line from Broad Street Station, which had disappeared under the Broadgate development in 1986. It got Transport & Works Act (TWA) powers for the scheme, which was then expanded again when it was realised the railway could interconnect with the North London Line. Another Transport & Works Act was ac- quired, and as the project by that stage had effectively become part of Overground rather than Underground rail, it was passed to the newly formed Strategic Rail Authority (SRA) to manage. ELL plans languished there without a champion. But over at Transport for London it did have its backers – Smith and his managing director Ian Brown at TfL’s developing London Rail division in particular. And when the SRA wound up and the route was bequeathed to TfL in 2004 they fought for, and won the funding. “There was pressure to make a decision as the TWA powers were about to run out, and then the Olympics came along, which finally tipped the balance and we could get on with building the project,” Smith says. Peter Richards was brought in from the SRA to run the job as infrastructure director for the now dubbed London Over- ground, along with Mike Stubbs as engineering director, and they got stuck into design. There had been a brief flirta- tion with funding the route through private finance. “But the ELL is a grey asset,” Smith says. “There is a lot of old in- frastructure it would have been difficult to box up for PFI, and a PFI takes time to put together.” With the 2012 Olympics fast ap- proaching, it was decided to go for a design and build option. It was a good decision. The scheme, built by a Balfour Beatty Carillion joint venture (BBCJV), opened early on 23 May. BBCJV won the contract in October 2006, started design immedi- ately, and then started the major structures in 2007. It got onto the tunnel and south sections of the site when the old East London Underground was closed in December 2007 and handed over in late January 2008. “From the start, we stressed to everyone that this job is about delivering an operational railway – infrastructure, rolling stock and operations,” says Richards. “We have managed the integra- tion between these aspects and given the responsibility for man- aging the interface between the existing infrastructure and main works structures and rail sys- tems to Balfour Beatty Carillion as our main works contractor. “That is why we went for a single NEC3 design and build main works contract. “It has meant that BBCJV has managed the interfaces, and all the responsibility has rested with one party to get on and do the whole thing.” When Richards set up the job he wanted to create momentum, so he formed an integrated client team to manage the job and drive its progress. This included himself, Parsons Brincker- hoff’s Ashok Kothari as head of programme management and designers from Mott MacDonald as technical adviser to the project. Refurbishment work along the route on some of the older structures like the Kingsland Viaduct was let as enabling works contracts to Murphy and Taylor Woodrow (now Vinci Construction). “Refurbishment is risky and it was prudent to do some of that first before we let the bigger contract,” Richards says. “And then, as a client team, we worked very hard towards letting the main works contract to programme. “We didn’t let ourselves slip. By doing that we created float for the rest of the project and that has helped us come in early. We are delighted to have opened on 23 May, ahead of a pro- gramme set back in 2004.” O ne day after the opening of the core route of the London Overground East London Line last month, pas- sengers were wandering around wide-eyed, taking in the wonder of the capital’s newest rail route. Londoners who know the detail of the Underground better than their bank pin numbers were cooing contentedly to themselves while looking at a map of the route which revealed a whole new circuit board of travel possibilities. As the first section of ELL opened they could go from Dalston in Hack- ney in the north, south to the Docklands at Canada Water and then on to New Cross. From this week, since the full line opened on 23 May, the route will take them as far into the south Lon- don suburbs as West Croydon and Crystal Palace. By early next year when phase 1a of the East London Line opens, Croydon will have a direct connection to Highbury and Islington, and at Dalston travel- lers will be able to switch onto a newly upgraded North London Line to go east to Stratford and the Olympics or west to Willes- den Junction and Richmond. And by 2012, construction of a link from the East London Line at Surrey Quays to railway at Old Kent Road will allow a western trip to Clapham Junction via Peckham Rye and Wandsworth Road and link to the Overground Clapham Junction to Willesden Junction Line. The capital will have an outer orbital metro railway under the banner of London Overground, interconnecting along the way with its Underground lines and serving 20 of its 33 boroughs; and commuters will have oppor- tunities aplenty to avoid central bottlenecks when they are trying to cross the city. The key to creating this will have been a £1bn Transport for London investment in infra- structure and new rolling stock. This has reinvigorated and expanded the old East London Line Tube line, reusing Victorian infrastructure and introducing some new modern landmarks along the way. There are going to be huge benefits in terms of regeneration and new jobs for some of the less developed parts of the City, rail-deprived Hackney will at last have a metro, and east and southeast London will acquire some life changing infrastruc- ture. Around 33M passengers are expected to be using the route every year by 2011, rising to a projected 39M by 2016. “The really good part of this job,” says London Rail chief executive Howard Smith, under who’s remit the East London Line falls, “is that we are chang- ing the face of London and the way we think of and use London in a permanent way. It is really dramatic.” There has been a plan to east end efficiencyThis week the London Overground East London Line opened a full service from West Croydon in south London to Dalston in the north. In a remarkable achievement, the project has been delivered early. Jackie Whitelaw reports. “As a client team, we worked very hard towards letting the main works contract to programme” Peter Richards, infrastructure director London Overground “We are changing the face of London and the way we think of and use London in a permanent way. It is really dramatic” Howard Smith, London Rail Client London Overground for Transport for London Other parties London Underground, Network Rail Contractor Balfour Beatty Carillion joint venture (BBCJV) Contractor’s designers Scott Wilson, Tony Gee & Partners Programme manager Parsons Brinckerhoff Client’s technical adviser Mott MacDonald Rolling stock Bombardier Operator LOROL Signalling,communications and power systems, 3.5km of new or refurbished viaduct from Whitechapel to Dalston Junction; 3.2km of track in tunnel south of Whitechapel to Surrey Quay New stations at Dalston Junction, Haggerston, Hoxton and Shoreditch High Street; refurbishments at Whitechapel, Shadwell, Wapping, Rotherhithe and Surrey Quays; an operational control centre; depot; and 44 four car Electrostar 378 trains – 20 for the East London Line and 24 for the North London Line. WHO’S WHO EAST LONDON LINE IN BRIEF Stratford Dalston Junction Haggerston Hoxton Shoreditch High Street Highbury & Islington Blackhorse Road Whitechapel Gospel Oak Shadwell Canada Water Surrey Quays Queens Road Peckham Denmark Hill West Brompton Kensington (Olympia) Shepherd’s Bush EustonKensal Green Queen’s Park CENTRAL LONDON Willesden Junction West Hampstead Harlesden Stonebridge Park Clapham High Street Kew Gardens Gunnersbury Clapham Junction New Cross Brockley Honor Oak Park Forest Hill Sydenham Penge West Anerley Norwood Junction Crystal Palace West Croydon New Cross Gate Peckham Rye North West to Watford Junction East to Barking To Richmond KEY Phase 1 opened 23 May 2010 Phase 1a completed by 2011 Phase 2 completed by 2012 OVERGROUND East London Line is vital for creating an outer orbital railway around the capital. Phase 1 opened on 23 May. City slicker: The East London Line is a vital new link to London’s financial heart east london line REBORN MAJOR PROJECT REPORT LONDON OVERGROUND: THE FUTURE
  • 3. venture finally got onto the line three months early at the end of January 2008. That is when the scope of the job began to develop. There was the depot to add in. And two bulk supply points for power. “Those two 132kV bulk supply points came on top of three 33kV traction substations already in the contract, and those three had to change from pre-assembly to larger built insitu on site versions,” says Balfour Beatty Carillion construction director Adam Stuart. An enabling works contract had beefed up the Victorian Kingsland brick arch viaduct between Shoreditch High Street and Dalston. “But that still left BBCJV a lot of work in further assessment and strengthening,” says Stuart. The six “tunnel” stations between Whitechapel and Surrey Quays also needed much more work than originally thought and London Over- ground decided to properly refurbish them, he adds. “A grade separated junction was also introduced to make the link with phase 2 to Clapham Junction so as not to disrupt East London Line running when that project goes ahead. “One of the things I am most proud of here is that the scope has increased very significantly yet our design, construction and commissioning period increased by only five months,” says Stuart. BBCJV drove itself along, and for added momentum it had a set of about one hundred non-contractual milestones to hit, worked out with Parsons Brinckerhoff. “In December 2008 we said that we’d have all the structures, track, and operational systems complete to start test train running 10 months later on 5 October 09, and we did,” says Stuart. “And from that date we ran up to six of the new trains every day for four months during which we finished the new station buildings behind the platforms; our track gives a very smooth ride and the Invensys signalling system proved fault- less.” “Also in December 2008 we gave a date of 17 January 2010 to hand over to trial operations and on that very date we started the week long process of handover to Transport for London for trial operations,” adds Casebourne. “In parallel the refurbishment of the tunnel stations was completed and the customer information systems were finished. Now customers are on board and everything is working reliably.” www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 2726 NEW CIVIL ENGINEER 27.05.1O | www.nce.co.uk EAST LONDON LINE: Management W hat is remark- able about the management of the London Overground East London Line construction work is that the job has so successfully beaten its deadlines; particularly when the scope of the scheme was some- what fluid when the job was tendered. Balfour Beatty Carillion Joint Venture (BBCJV) bid for and won the basic project against strong competition and with the addition of many changes. The final job is coming in at £700M or thereabouts after new elements were added in and the amount of work required became clearer as the construction teams got stuck in on site. “We knew there would be additional work in the central section but we couldn’t find out how much until we took posses- sion of the railway from London Underground (LUL),” says London Overground Infrastruc- ture director Peter Richards. “We also knew the depot, for instance, had to be added in but the contractor could not price that in the original tender because the designs from [rolling stock supplier] Bombar- dier were still being developed. “That is why we went for a target cost design and build contract rather than fixed price.” But Richards points out that there was always a total budget and as the work grew, “we adjusted the scope to suit the budget.” “Is it safety critical?” was the mantra. If it was, then the money was found, if not, then as much cash was saved on each opera- tion as possible so there was some to spare when needed. That approach required close collaboration between the client team, BBCJV and its supply chain throughout the works. “The closely cooperative culture of the job has been vital,” says Balfour Beatty Carillion project director Mike Case- bourne. “It is one of complete openness; no secrets, shared decisions and facing and solving problems together.” Richards agrees: “We have some very dedicated people on this project. There is a collabora- tive, positive culture which has all helped towards getting the job out the door on time and on budget.” Actually the railway is two months ahead of schedule. The original opening date set at the start of the job in 2004 was 30 June 2010. The full line opened on 23 May to coincide with the seasonal timetable change; and passengers were using the central section of the route from 27 April. Not bad for a complex, modern railway squeezed into a packed capital city. “We are particularly pleased about getting the route into service early as it will have a huge benefit to the travelling public,” Richards says. “Right from the start, when we signed the contract on 20 October 2006 we had to remember that we had committed to design, construct, test, commission and deliver an operational railway, not just its separate structures and rail systems,” says Casebourne. “It was a requirement driven contract – for example to design for three minute headways between trains.” “There were 6,000 require- ments and about two thirds of them were changed or modified as we all got on with the job,” says Balfour Beatty Carillion engineering director Andy Nettleton. “Without strong management of a resilient, responsive design organisation we would never have achieved so much in such a short time.” The key to pinning down the scope was gaining access to the old Underground section of the route between Shoreditch and New Cross Gate. “We pushed to get London Underground to agree to get the route closed as early as possible,” says Parsons Brinckerhoff head of programme management Ashok Kothari . LU agreed to shut down the line in December 2007 although it had originally wanted to keep it open until the following April. There was a slight delay while Underground upgrade contractor Metronet stripped out all of its assets but the joint Working Together as a team SAFETY The London Overground East London Line scheme has had an excellent safety record over the duration of the project. The site has twice recorded 1M accident free hours under the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations (Riddor) 1995. This was achieved in December 2008 and again in November 2009. The job hit over 1.5M continuous Riddor-free hours, and the current accident frequency ratio of reportable accidents to 100,000 man hours worked is an excellent 0.12, a performance which recently landed a coveted Rospa Gold Award. “We have had a really big push on the safety culture on this project,” says health and safety manager Mike Davies. “We have focused on the supervisors and gangers and put in some fun incentives like group of the month winning a fleece each,” he adds. Collaboration between client, contractor and supply chain was crucial as the construction project developed in scope, writes Jackie Whitelaw. MaNAGING THE TEAMS COMMUNITY RELATIONS As BBCJV project director, Mike Casebourne has had to manage 640 professional staff, and 600 designers off site in the offices of Scott Wilson and Tony Gee and other designers. He is aslo responsible for 2,500 operatives on site at peak and up to 1,000 people engaged in the offsite manufacture of all the elements for the job all over the UK. At peak, the project was spending £30M every four weeks or £1.5M a day. The job was divided into four construction sections under the control of four BBCJV senior project managers; northern civils under Andy Swift; southern and central civils under Paul Rasmussen; rail systems under Elliott Young and the depot under Howard Williams. These were supported by design, commercial and administrative managers within their teams and reporting also to their department directors. “We had to design, construct, test, commission and deliver an operational railway” Mike Casebourne, BBCJV “The scope increased, yet our design, construction and commissioning period increased by only five months” Adam Stuart, BBCJV Team work: The close cooperation culture of the job has been vital to successful construction of complex projects like Dalston Junction station Community relations were a vital part of successful delivery of the East London Line with full time community relations managers working for London Overground and BBCJV. The usual issues of working hours, noise and dust had to be addressed but it was either end of the project – at Dalston and New Cross Gate where there were most sensitivities. “There was some resistance to the idea of Dalston being gentrified,” says head of communications for London Rail Julie Dixon. “But we always stress that the East London Line is a regenerating railway with the priority being to give people access to jobs which has helped allay concern. “At New Cross Gate people were unhappy at the idea of a 24 hour train depot. The solution was to get the residents involved, listen to them and respond to their concerns. For instance, the depot will have low level lighting so as not to create a nuisance.” east london line REBORN MAJOR PROJECT REPORT
  • 4. EAST LONDON LINE: DALSTON & NORTHERN STRUCTURES Dalston Junction station is a massive, complex structure that has been designed to support multi-storey buildings and to accommodate the potential Crossrail 2 line, as Margo Cole discovers. And Adrian Greeman focuses on the array of civil engineering work in the northern section linking the Victorian Kingsland Viaduct to the old East London Line at Whitechapel. www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 2928 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk I n theory, building a new four-track four-platform station at Dalston Junction could have been fairly straightforward. Admittedly, space was very tight, but the new line runs through an existing cutting, so surely it wouldn’t have been too much of a challenge to build a roof slab over a section of the tracks and put a station building on top – would it? The reality is not quite so simple. The area taken up by the railway line as it runs through the heart of Dalston is prime development land and an important area within Hackney’s regeneration plans. As a result, a slab had to be built over the tracks not only to support the station building but also the loads from a series of apartment blocks of up to 17 storeys that are set to be constructed on top. Within weeks of work starting, what had once appeared to be a generously-proportioned, open cutting had become a highly congested construction site, with over 30 pieces of major plant involved in excavation and pile installation, as the London Over- ground East London Line team set about building a 250m long by 40m wide podium slab and its supports. The loads from the proposed apartment blocks will go into downstand beams built into the 500mm thick podium slab, and from there into a series of walls and columns supported by deep piled foundations. The new plat- forms will sit under the podium slab, just above pile cap level. For the most part, the down- stand beams are 1m deep, and were cast in situ along with the deck slab. Some of the beams were very heavily reinforced, as BBCJV section manager for Dalston Kingsland Guy Anstiss recalls. “In some places there’s an awesome amount of reinforcing steel. One section of beam has over 100 H40 bars at the top and bottom of the downstand beam, and multiple links,” he says.This gives a total of 1,250kg of reinforcement per linear metre in some locations. However, in 19 beams, even this heavily reinforced concrete was unable to support the anticipated point loads from the apartment building which are expected to be up to 7,000t. Here, steel I-beams have been used as part of the permanent reinforce- ment, with pairs of I-beams joined top and bottom with diaphragm plates. These pairs of beams weigh up to 90t each, and span up to 33m. They sit on specially designed bearings supplied by Freyssinet that weigh up to 3t and are capable of handling the uplift and the rotation that could be caused by such heavy point loads. Once the beams were in place, the diaphragm plates were welded insitu, the voids between the plates were filled with grout and then reinforcement cages placed in and around the beams to tie them into the podium slab before the concrete was poured. In all, there is 1,000t of structural steelwork in the new station, most of it in these massive beams. The downstand beams span between walls and columns that sit on pile caps up to 2m deep, the largest of which takes up an area of 3,600m2 . Beneath the pile caps are heavily reinforced bored concrete bearing piles, most of which are 650mm or 750mm in diameter, and sunk to a depth of 26m. However, at one end of the site, provision has been made for the possibility of the second Crossrail line passing diagonally beneath the East London Line. In the original design, a raft foundation would have Whitechapel Station Shoreditch High Street Station GE19 BRIDGE Precast concrete box enclosure Air rights - Precast concrete box enclosure protects the line from future development works Great Eastern main line North London line SHOREDITCH HIGH STREET BRIDGE BISHOPSGATE VIADUCT Bishopsgate Goods Yard Dalston Junction DLR Hammersmith City line District line Haggerston Station Hoxton Station of steel SHOREDITCH HIGH STREET BRIDGE Bow arch bridge HOLYWELL VIADUCT links up with the refurbished Kingsland viaduct DALSTON STATION PODIUM A massive and complex structure designed to support multi-storey development and accommodate Cross- rail tunnels SHOREDITCH HIGH STREET STATION SHOREDITCH STATION BOX ENCLOSURE - DETAIL BISHOPSGATE VIADUCT GE19 BRIDGE Steel, Warren truss bridge BISHOPSGATE GOODS YARD Prime develop- ment area 300tabove ground 10m foundation piles 1,366 viaduct length span 400m platform length 100m 84m Shadwell Station REGENTS CANAL central sectionNorthern extension HOLYWELL VIADUCT Kingsland Viaduct, refurbished masonry arches and addition of underbridges On embankment 1/4 mile pile depth 30m 21 -23m spans, 34m at station entrance Pile cap 10m Precast panels Precast deck Portal frame sections graphic: © www.paulweston.info 21 - 23m spans 22m 6m AIR RIGHTS DEVELOPMENT Station Crossrail tunnels Podium slab HOXTON SQ N1HOXTON SQ N1HOXTON SQ N1 WHITECHAPEL RD E1WHITECHAPEL RD E1 MILE END ROAD E1MILE END ROAD E1 DALSTON LANE E8DALSTON LANE E8 KINGSLAND ROAD E2KINGSLAND ROAD E2 Skyway to the north DALSTON JUNCTION “One section of beam has over 100 H40 bars at the top and bottom of the downstand beam and multiple links” Guy Anstiss, BBCJV Complete: A new train zips into Shoreditch High Street Station east london line extension MAJOR PROJECT REPORT
  • 5. 30 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk EAST LONDON LINE: DALSTON & NORTHERN STRUCTURES www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 31 T he northern section of the London Overground East London Line, running mostly on once abandoned Victorian viaduct, has to make a swing eastwards as it reaches the edge of the City of London. This enables it to link up with the old London Underground East London Line route to south London. Two major bridges, substantial new viaducts, reshaped cuttings and a new, relocated station at Shoreditch High Street, are just some of the works needed to make the link. The new section takes the line through and across Shoreditch High Street, and on into the historic Bishopsgate Goods Yard area, once one of the industrial wonders of Victorian London. After three decades of near dereliction, what was once a huge, two-level railway unloading depot with a half kilometre length of vaulted brick arches supporting its rail tracks has become the largest potential development zone in London and is ripe for major office and residential schemes. Early work for the BBCJV meant clearing thousands of tonnes of brick rubble from the northern half of the nearly 5ha site. This was the residue of pre-contract demolition works which took away many of the old arches. Some remain, including the famous and now listed Braithwaite brick arches, built by Victorian civil engineer John Braithwaite in the 1830s. “We established a truck route out of the yard using a tempo- rary Bailey bridge,” says Andy Swift, BBCJV project manager for the northern section civils works. The temporary bridge took construction traffic over famous Brick Lane, known for its curry restaurants. The trucks then passed over a still intact Network Rail bridge, known as GE19, whose later demolition by Murphy and replacement by BBCJV was one of the largest jobs in this section. It crosses a six track wide cutting for the main lines between Liverpool Street Station for the East Coast. Just beyond this bridge the line dips into cutting and then underground at the Valence Road portal. The brick rubble the trucks carried was used OTHER STRUCTURES spanned the line of the tunnel, carrying the building loads into the ground. But there was concern about differential settlement between this section of foundation and the rest of the site, which was piled, so an alternative, piled, solution was developed. Two rows of bored piles have been sunk on each side of the tunnel line, topped with pile caps that support walls carrying the podium slab, the station concourse and the multi-storey development above. “This acts as a ground level bridge, one of the biggest on the job, so they can put the Crossrail tunnel in much later without too much settlement,” says Anstiss. It sounds straightforward, but each of the 40 piles in these four rows measures between 1.8m and 2.1m in diameter, and has been bored to a depth of 40m – only just above the chalk layer that underlies the London clay. The reinforcement cages alone weighed up to 13t, and required two splices to enable them to be lowered into the pile bore. An inventive piling solution was also needed as part of the remedial work to the Forest Road bridge, which spans the rail cutting at the southern edge of the podium slab. In the original design, all of this post-tensioned concrete structure was due to be demol- ished and replaced by a new bridge with no parapet on one side, to allow buses to come off the Kingsland Road and into a new bus station being built on the podium slab. However, the BBCJV felt that full demolition would be a complex process, as the structure is full of services that would have had to be diverted at great cost. It was also very close to neighbouring properties that would be affected by noise and vibration during the demolition. Instead BBCJV proposed that the structure be retained, and turned into a “hybrid”, with the post-tensioning remaining in place on the eastern half, while the parapet on the western side was demolished to allow the buses to turn off, with this half of the bridge supported by one of the walls designed to take the podium slab loads. The new pier wall is topped by an I-beam that is tied into the existing bridge reinforcement. Beneath the wall is a large pile cap and a total of 66 piles, each 300mm in diameter. “We wanted 750mm diameter piles, but when we decided to keep the bridge, the question was: ‘how do we get the rigs in?’” says Anstiss. Rigs large enough to sink 750mm diameter piles to the depth required would not have fitted under the bridge structure, so the design was changed to 450mm diameter piles instead. “That would have worked, but we had a problem with ground conditions,” says Anstiss. “It looked OK from the boreholes, but when we started piling, water started boiling up from the base. It meant that 450mm diameter wouldn’t really work because there wasn’t a rig available to allow us to manage the boiling sand.” Instead, the design had to be changed again for 300mm diameter piles, with construction carried out in a sequence that saw a series of casings driven, with the piles augered out inside them. “We had to introduce “We wanted 750mm diameter piles, but when we decided to keep the bridge, the question was ‘how do we get the rigs in?’” Guy Anstiss, BBCJV “We established a truck route out of the Bishopsgate Goods Yard using a Bailey bridge” Andy Swift, BBCJV The new station at Hoxton is built inside an existing set of rail arches, with the concourse constructed by punching through the brick piers. To create this space, ground engineering specialist Bachy first installed low headroom mini-piles either side of each existing pier, and a ground beam was cast on top. Holes were then drilled through the brickwork, and needle beams threaded through the top of the pier, and jacked off the ground beam to support the arch roof while the material below was removed to form the required space. New columns and a lintel beam were then grouted in place to form a portal frame within the pier, and the jacks removed to allow the brickwork to sit back down on top of the frame. The BBCJV’s engineer Scott Wilson had to carry out considerable finite element analysis to ensure the new design could carry loads from the tracks above. For Haggerstone Station, the old viaduct was demolished and a new station built. HOXTON AND HAGGERSTON STATIONs bentonite before we hit the sand, and then keep excavating through the bentonite,” says Anstiss. “Then we had to grout under pressure to replace the bentonite, and at the same time install the 18m long reinforce- ment cages.” Now that Dalston Junction station is complete, much of the massive civil engineering work will go unnoticed by passengers, but during construction it was one of the most complex parts of the entire scheme. At maximum there were 306 operatives working on this part of the site, and the major plant used to construct it included a 64m concrete pump – the biggest available in the UK at the time. With construction starting on the apartments that will sit on top of the podium slab and passengers starting to use the bright, airy, stainless steel lined concourse, this ultra modern station will soon be a centre point of modern Dalston. Crossrail crossing: Piling at Dalston included working around the Crossrail route Tight spot: Hoxton station was snugly fitted under Kingsland viaduct Catalyst: The station at Dalston Junction is expected to trigger regeneration Transfer beam: Massive steel beams will carry properry developments above Dalston Station
  • 6. 32 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk EAST LONDON LINE: DALSTON & NORTHERN STRUCTURES www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 33 to infill part of that cutting, reshaping the gradient and approach to the new GE19 bridge. It also helped fill another part of the cutting which continued on the Bishopsgate side, swinging around towards Liverpool Street station. This was where the original Shoreditch Station was sited. The new Shoreditch station is set in the length of the old goods yard, along much of a new viaduct which carries the track through the yard space and out across Brick Lane. This Bishopsgate viaduct carries the line on 400m of a new concrete elevated way, some 10m or so above ground. The viaduct comprises pairs of mainly 6m high columns which are mainly circular or elliptical in cross section. They carry a large 3.5m deep edge beam on either side. “In fact the depth varies at centre span giving them a slightly arched shape” says Swift. The beams form the platforms and are connected by a concrete slab which forms the deep trackwork trough between them. Spans between are 21m to 23m long apart from an extra long 34m span across the street at the station entrance. Concreting for these beams was reasonably complicated since they required a mass of heavy T40 bar reinforcement, up to five layers thick, which meant care was needed in placing the concrete. “We used limpet vibra- tors on the formwork which gave us issues of noise and vibration to manage, since this is a busy area with a lot of residential property around,” says Swift. Clusters of five bored piles support each end of a series of single pile caps as wide as the viaduct on which sit each pair of the columns that support the viaduct above. One cluster was bored very close to London Underground Central Line tunnels and monitoring equip- ment was set up to give early warning of possible distress. Fortunately there was none. Piles are as much as 30m deep under the station section and around 22m deep elsewhere. They were driven into London clay on which much of the site rests. “The clay rises from the Brick Lane end somewhat as you approach Shoreditch,” says Swift. There is terraced gravel beneath and for the longer piles that meant using a “wet pile” system to bore them, with polymer support, into water saturated gravel. Piles were “substantial” says Swift, between 1,200mm and 1,500mm diameter. The larger diameter was used to achieve a shorter pile in a few places, allowing the pile end to remain in clay and avoiding the need for the polymer. Bachey Soletanche was subcontractor for the piling. The longer piles carry the heavier loads in the central part of the viaduct where the 200m length of the new Shoreditch station is located. The entire station at rail level is enclosed in a precast concrete box, creating a kind of “tunnel in the air”. The box tube comes in two widths, a central portion enclosing the 100m long platforms and two smaller parts extending the station enclosure at either end; there is an option for future expansion of the platform lengths into these. The point of the enclosure is primarily to safeguard the line from future construction and development planned for the entire Bishopsgate area, with over-site “air rights” construc- tion around the station, possibly including a 40 storey high rise office development. Work is imminent, although delayed temporarily by the economic situation. “The station enclosure is really an expensive, perma- nent crash deck to keep trains running while work is done later by the developer,” says Swift. It is built from precast portal frame sections attached to the viaduct at 7.5m intervals. Three 2m high panels are bolted to each side of these before an insitu top deck is formed and poured. There were challenges on the longer GE19 bridge to the east of the station site. This was fabricated and assembled by Fairfield Mabey. The assembly of the Warren truss bridge which carries the new railway on a 85m span over the six Liverpool Street main lines, went well. It was fully assembled on tempo- rary falsework on the track alignment in the space which became the approach ramp, and push launched into place. “It was powered over using a multi-axle transporter provided by Abnormal Load Equip- ment” says Swift. A 30m long nose section was added for the launching at the front end and the ALE transporter sat at the rear end. “It was a balancing exercise to keep the nose up” says Swift “so we concreted the back end deck and added more weight, leaving the front deck to be done later. The launching was done with the strand jacks between the permanent concrete abutments being used as the launch fulcrum, and the ALE transporter at the rear end.” West of Shoreditch Station, the line crosses Shoreditch High Street on a 35M span bowstring arch bridge fabricated by Fairfield Mabey partly within the Bishopsgate Goodsyard site. There, the firm welded the curving steel beams to form the bow and set the vertical hangers. A critical part of the job was a major crane lift for the completed 330t bowstring arch bridge, using the 1,200t Sarens crane on a May weekend in 2008. “The lift only took a couple of hours but 12 months of prepara- tion were needed beforehand” says Swift, not least because the busy crane is much sought after. “We also had to coordinate all the emergency services, local authorities, and others for a road closure,” Swift adds. The site needed proper preparation for the crane which arrived on some forty trucks and took several days to assemble. Ground had to be properly cleared, and an area piled to support the crane. The viaduct continues west of Shoreditch High Street with the Holywell viaduct, curving sharply to take the line back across the street as it links north to the existing Victorian brick viaduct further on. Five 20m spans were needed, built close alongside a listed and untouch- able building on Shoreditch High Street, running within 330mm of it at one point. This part of the work was preceded by significant archaeo- logical digging within the old Holywell Yard. The Museum of London was delighted by the discovery of the remains of an old monastery, including foot- ings and columns, various burial sites, plates and knives. “The station enclosure is really a permanent crash deck to keep trains running while work is done later by the developer” Andy Swift, BBCJV “The GE19 bridge was powered over using a multi-axle transporter. It was a balancing exercise to keep the nose up” Andy Swift, BBCJV Shoreditch High Street: A 35m span bow arch bridge is lifted into place GE19: The bridge was launched over six mainline railway tracks New link: The line runs on a mixture of new and refurbished viaduct from Dalston to Shoreditch
  • 7. 34 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk EAST LONDON LINE: SOUTHERN SECTION www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 35 River ThamesWAPPING View along the Thames Tunnel, c. 1835 ROTHERHITHE HIGH WATER LOW WATER Section Masonry construction THAMES TUNNEL Jubilee line SLAB TRACK Wapping Station RIVER THAMES SHADWELL BASIN CANADA WATER GREENLAND DOCK Rotherhithe Station Surrey Quays Station New Cross Station New Cross Gate Station Canada Water Station Central section Southern extension Victorian road bridge replacement Victorian road bridge replacement Concrete trough takes slab track Concrete sleeper Mass concrete slab Boot (absorbent membrane) Rail mounted on sleeper Mass concrete slab Rails mounted on concrete block sleepers Track sections - lengths to suit project Network Rail main lines Steel, Warren truss bridge Concrete ramp Concrete ramp 75m 32m 10m Surrey Canal Road bridge NEW CROSS GATE FLYOVER THAMES TUNNEL REFURBISHMENT The East London line has its roots in the Brunel’s construction beneath the Thames (c. 1825 and 1843). The tunnel was refurbished for waterproofing and to take slab track. NEW CROSS GATE FLYOVER NEW CROSS GATE DEPOT To avoid the need for points a much larger grade crossing was required over the existing, near capacity, Network Rail main lines. A 1200t Warren truss bridge with a 75m span was employed WAPPING STATION VENT To create a second means of escape for the station, shafts were sunk either side of a Victorian, brick lined, smoke vent span 75m of steel 1200t shaft depth 16m To Croydon Extension for completion 2012 To Clapham Junction graphic: © www.paulweston.info Cast iron struts Masonry Vent Escape shafts Made ground Drift London clay/ thin layer Lambeth group Thanet sandsMass concrete New openingNew opening Used on the new viaducts and in tunnel sections, track slab improves stability, noise suppression and maintenance intervals BOOTED SLEEPER - SECTION For areas requiring the most noise suppression sleepers are mounted in an absorbent membrane BRUNEL RD SE16BRUNEL RD SE16 WAPPING HIGH STREET E1WWAPPING HIGH STREET E1W ROTHERHITHE NEW RD SE16ROTHERHITHE NEW RD SE16 NEW CROSS ROAD SE14NEW CROSS ROAD SE14 OLD KENT ROAD SE1OLD KENT ROAD SE1 LOWER RD SE16LOWER RD SE16 COPE ST SE16COPE ST SE16 T he biggest civil engi- neering challenges were at Whitechapel and Wapping as part of the need to provide all the under- ground stations with secondary means of escape (SMEs) Whitechapel AtWhitechapel, a relatively simple steel truss bridge sufficed for the SME, with lattice towers on the platforms and steel stair- cases to link to an emergency street level exit. But on either side of Whitechapel Station two large excavations will be required for the planned Crossrail station which will sit above the Crossrail tunnels but below the ELL. The two subterranean Crossrail concourses will be linked by a pedestrian underpass beneath the ELL tracks, and it made sense to build the under rail structural elements during the ELL works. The ELL team also found itself involved in some other advance works for the Crossrail team. Crossrail has almost no space in the streets aboveWhitechapel for work platforms from which to construct its excavations. To find space it has prepared for a major bridging structure to be built over a 70m length of the Whitechapel cutting. This “crash deck” work plat- form will need to support major equipment and heavy plant and demands correspondingly hefty foundations, explains BBCJV engineering manager for central and southern sections Andy Bradshaw. During its work, the ELL team installed for Crossrail two rows of 600mm diameter piles on each side of the ELL tracks, with some careful design required to give pile lengths which stopped short of the Crossrail track tunnels. “The pile depths were limited to 10m,” Bradshaw says. In order for the Crossrail crash deck piles to be installed BBCJV had to remove the old ELL service platforms at the base of the 10m highVictorian brick buttress-and-coffer retaining walls that make up the ELL Whitechapel cutting. This was a tricky job because the toes of the retaining walls had to be braced off each other throughout the works. To prevent movement of the walls, work had to be done in two phases. In each phase, the existing platform was broken out in bays 4m to 9m long, new precast struts were laid across the trackbed and then a pilecap was constructed at each side of the cutting. “We used hefty 406mm diam- eter tubular steel struts as tempo- rary support until the piles were cast,” says Bradshaw. “The struts were later reused for excava- tion support elsewhere on the project.” Circular voids had to be left in the pilecaps for later sinking of the piles needed to support the Crossrail work plat- form. Two contiguous piled walls some 3.5m apart across the tracks were also cast to form the walls of the future Crossrail station connecting passage. A thick- ened section of the track bed makes a roof slab for this pedes- trian tunnel which will be exca- vated, when needed by Crossrail, without disrupting the ELL. The cost of “several millions” has been met by the Crossrail project. Wapping AtWapping station the main entrance uses the Brunel tunnel shaft to accommodate two lifts and a spiral staircase but at the other end there was no obvious second escape route. “There was a brick lined smoke shaft however, about 11m across” says Bradshaw. It dates from the days when steam trains ran underground which they did until early in the 20th century. Either side of this 16m deep vent, it was decided to sink shafts in which steel staircases could be built, linked to the platforms by cross passages at the base that were created by breaking through the thinner infills between the retaining wall buttresses. The original plan to form a rectangular box shaft with big 1100mm secant piles did not work within the overall construc- tion programme. A value engi- “We used big 530mm diameter tubular steel struts as temporary support during the casting” Andy Bradshaw, BBCJV Negotiating exisiting tunnels, contracts and Victorian structures was all in a day’s work for the East London Line team as it worked to construct and renovate the railway. This section of the project also involved work to ensure the new structures did not interfere with planned works for the Crossrail line which crosses the route. Adrian Greeman reports. TUNNELS & TRACKS HEading South Wapping: Here, the line runs south into Brunel’s twin bore Thames Tunnel east london line REBORN MAJOR PROJECT REPORT
  • 8. 36 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk EAST LONDON LINE: SOUTHERN SECTION www.nce.co.uk | 27.05.10 NEW CIVIL ENGINEER 37 O nce the ELL emerges from its tunnels just past Surrey Quays onto conventional bal- lasted track, it might be thought there was less to do. But renewing bridges, providing for new connections to the mainline and future London Overground extensions and installing big flyover at New Cross were all significant chal- lenges. And there was the building of a brand new carriage servicing depot to add into the mix. Cope Street Bridge Two significant bridges carry busy South London road connections across the line just after Surrey Quays station, where it is still in cutting, rising out of the river tunnel section to surface running. Both of these were old Victorian bridges, 10m wide, comprising parallel cast iron I-beams and masonry jack arch infills. Both carried a single carriageway road and pedestrian pavement and were supported in the middle by a central pier. Originally rail tracks ran either side of the pier but now they only run on the western side. The cast iron piers did not meet modern derailment resist- ance standards and had to go. At the Cope Street bridge, an initial scheme for a single unsupported span was dropped because the deck beams would have been too deep. Instead new concrete piers were installed but set back from the live track, creating one long and one short span. Simple replacement of the deck above was complicated by the high concentration of services carried within the decks, most critically a fibre optic cable. Diverting it to a temporary bridge during the work would have been very expensive – around £250,000. “And diverting it back afterwards would have doubled that,” says Andy Bradshaw, BBCJV construction engineering manager for the section. Costs were contained after a value engineering study devised a scheme that left the narrow strip of bridge deck with the fibre optic cable intact while the rest was rebuilt with new precast concrete beams. “And then we only had to move the cable once onto the new part and finish the construction,” says Bradshaw. Rotherhithe New Road Bridge At the second bridge, Rother- hithe New Road Bridge, an even more expensive utility diversion was needed to handle several high voltage cables which served most of South London. These were embedded in a concrete block which had replaced one of the original jack arches between two I-beams. Rather than a double move for the cables at an overall cost of £1.4M, and some risk of blacking out a big part of the conurbation, BBCJV devised a system to leave the block intact and rebuild the rest of the bridge around it. The bridge was tackled in two halves in order to leave a carriageway open for busy traffic. Most of one side was demol- ished first, leaving the power line slab in place supported on its portion of the pier. Once the new steel beams were installed, two transverse I-beams were then attached underneath the new deck, to support the power line slab, on either side of its support pier. With the power cable slab load transferred to these temporary hanging beams, the pier could be demolished. A third steel I-beam was then installed between the temporary ones, to be a perma- nent support, while the outer two were removed. The new Rotherhithe bridge has one single span. It is longer than before but does not run the full length of the old bridge’s two spans. Instead the far abut- ment was built outwards on the disused side of the cutting. Rebuilding the bridge in this way produced a net saving to the client of around £1M, says Bradshaw. Further south in the Silwood depot, there is to be an eventual connection to the South London Line. Points suffice to make the transition on the up-line into London, but the down-line trains will have to dip under the up line to travel west to Clapham Junction. Secant piled walls were used to form a new cutting taking the connecting track down and around, with a slab placed across the top of this cutting to carry the up-line. The new grade separated junction has been built to avoid service disruption in the future when the project to connect the East London Line to Clapham Junction gets under way. Further south, a third road bridge was replaced, this time with the straightforward demoli- tion and lifting in of a new deck with a 1,000t crane. Apart from finding space between buried services to put crane outriggers, the main problem was to avoid traffic closures on weekends when Millwall Football Club had home games, says Bradshaw. New Cross Gate Flyover A much bigger grade separated crossing was needed near the end of the renewed East London Line section where it merges with and uses the existing Network Rail slow lines at New Cross Gate on the route south to Croydon and Crystal Palace at New Cross Gate. New Cross Gate flyover avoids the need for a four-track ladder of switches and crossings to carry the ELL trains across four near-capacity main line tracks onto its own line which runs past the new service depot. The connection takes north- bound trains heading for the ELL off the main slow line and then up an inclined concrete ramp to a 75m steel bridge which spans the four tracks. A short 32m steel span continues the 10m wide bridge from a concrete pier onto another inclined concrete ramp that carried the trains through the new depot and onto the ELL’s dedicated line. The new ELL depot sits on old sidings which for some years had become a local authority site for impounded cars says Mark Walker of BBCJV who supervised the depot construction. The depot is domnated by the four-track, four-crane, four train rolling stock maintenance facility and its three storeys of offices all housed in a huge 90m by 40m by 12m high rectangular steel- framed, steel-clad building. Inside the depot are three raised tracks enabling clear access below the trains. The fourth track is equipped with synchronized jacks capable of lifting a whole train in one minute for the purpose of bogie changing. Another 90m building, split longitudinally into two, has one track dedicated to a twin-headed wheel lathe and a second in the other half committed to heavy cleaning and painting. It also has a blast and fire proofed top floor dedicated to an operational control and signaling centre which allows signallers 10 minutes to safey shut down all rail systems in the event of a fire. NEW CROSS GATE DEPOT neering rethink suggested sinking jacked caissons with mucking out by long reach exca- vator “which paid a health and safety dividend because you don’t need anyone in the shaft until you have reached forma- tion level and pumped out,” says Bradshaw. This went well until the time came to make the first cross passage, excavating through what it had been thought would be firm London clay. Instead old rotten timbers, possibly some temporary works left in place by builders of the wall, were encoun- tered. These timbers posed a problem because, once disturbed, it was realised that they were providing a water flow route from the terrace gravels above. “And since the Thames is just next door the water was not going to stop,” says Bradshaw Initial grouting was just washed out and a programme of minipiling between buttresses and shafts was devised to form a grout curtain to cut off the flow while the cross passage was completed. On the other shaft, forewarned, the grout curtain was created before any trapped ground water was disturbed. Meanwhile inside the smoke vent a series ofVictorian cast iron struts needed upgrading. Two levels of three rather elegantly shaped struts, with flared ends, had to be replaced. Architec- tural heritage considerations dictated that the replacement struts should resemble the origi- nals as far as possible. The upper struts were removed completely and new steel struts installed in their place, but the lower struts were more difficult because it was hard to see exactly how they connected at the wall. Rather than risk displacing anything the lower struts were cut away in the centre and new steel sections were inserted. Around the remaining cast iron lengths a sleeve was devised in South of the thames new steel to take the loads. Apart from the complexity of this work the job was a major exercise in logistics, with a crane at the top of the shaft juggling old and new pieces of steel around both the permanent struts and three sets of 250kN temporary props. Marc and Isambard Brunel had accessed their Thames Tunnel works via a shaft on the south bank of the Thames. To make a lasting contribu- tion to London’s engineering heritage, BBCJV cast a whole new floor in, sealing it off from the tunnel and trains, so leaving it available to the Brunel Museum to develop as additional exhibition space, including a chance for visitors to see the orig- inal shaft structure. Other station work was also complex. “After contract award the client decided to completely refur- bish the station buildings and platforms bringing them up to modern standards; this devel- oped into interior demolition back to bare walls and even some of those were reconstructed,” says BBCJV stations project manager PhilWharton. Renewing bridges, providing for connections to the mainline and future London Overground connections and a flyover at New Cross were big challenges Excavation through what had been thought to be London Clay instead turned out to be rotten timbers, possibly from some long- forgotten wharf Depot: The South London site is a huge 90m by 40m steel framed structure Whitechapel: Vital interchange Hot stuff: Thermal welders at work Junction: The depot is just to the east of the massive New Cross Gate flyover Wapping station: Orange temporary struts brace the original 16m high buttress-and-coffer brick retaining walls while the original struts are replaced with new, stronger white lookalikes
  • 9. 38 NEW CIVIL ENGINEER 27.05.10 | www.nce.co.uk EAST LONDON LINE: SOUTHERN SECTION The most complex part of the operation to build the four track crossing was placing the main 1,200t Warren truss for the 75m span. “Fortunately there was some unused Network Rail land alongside the mainline tracks where our subcontractor Fairfield Mabey could assemble the bridge,” says Bradshaw. To get it into position needed a 56 hour possession, booked long in advance. “We used multi-axle self- powered transporter units for the move. The truss was jacked at finished height onto trestles on the back of the transporter units and then moved south- wards some 60m. Then one end of the truss was slewed across in a 60m long arc while the south end took a shorter 20m long path” says Bradshaw. The construction yard embankment area was previ- ously surfaced with a 300mm thick layer of recycled demoli- tion aggregate to improve its load bearing capacity for the move. To prepare the four mainline tracks for the heavy loadings of the bridge and its transporter units, various bespoke level crossing options were consid- ered. But they would have been expensive, not only because a lot would have been needed but they would have had to be tailored to fit irregular track and sleeper spacings. Instead, a simpler solution was found. By removing the third rails that provide traction power for trains in Network Rail’s Southern Region and protecting the running rails with steel channel sections, it was possible to build up a load bearing platform using conven- tional ballast. This meant it was unnecessary to keep the temporary fill and the existing line ballast separate. Any surplus would simply form part of the railway afterwards. “To get the flyover into position needed a 56 hour possession. We used multi- axle self powered transporter units for the move” Andy Bradshaw, BBCJV On the new viaducts and in the tunnel, the East London Line sees the first application of the Sonneville boot system of slab track. For new viaducts and tunnels, slab track was installed, using the Sonneville system of concrete blocks to support either end of the sleeper, all embedded in a concrete slab. Each independent block sits on a neoprene pad inside a rubber “boot” which dampens vibrations; and the blocks can be extracted and the boot renewed easily when necessary. Noise suppression was the key factor on viaducts particulary as they run through crowded areas of the city, but reduced maintenance was the prime reason for the choice in the tunnels, where only night-time access is possible. “We had two variants of slab, the basic one and in some places the mass spring system,” says BBCJV’s Steve Bradley who was track construction manager for three years of the project. The difference lies in the concrete surround for the blocks. Mostly this is just mass concrete poured around the booted blocks that are carefully positioned by hanging them from the precisely positioned rails that have been placed inside a basic concrete trough. But for additional noise suppression on viaducts, the trough is lined with an additional absorbent membrane and the concrete track slab poured around it has to be reinforced to handle the additional movement created by the addition of the membrane. The boot system is complex to install, since each sleeper end is independent and must be accurate for rail inclination, gradient, gauge, alignment and more, before fixing in concrete. It is the first application in the UK. Drivers have already informally declared the line the smoothest they have experienced. TRACK Big move: Four multi-axle transporters move the 1,200t Warren truss for the New Cross Gate flyover into position Covering up: Temporary fill cover the track during the flyover move Sound solution: Rubber “boots” under the track damp down vibration Truss: Last minute adjustments