VIP 3-Valve Flushing Bypass Manifold Unit
See our full range online at: www.vip-ltd.co.uk
VIP Product Code 00/0189
• Fixed Orifice Double Regulating Valve
• Variable Orifice Double Regulating
Valve
• Various PICVs
• On/Off Balancing Valve
• Dynamic Balancing Valve
• Drain Points
• Strainers
• Strainers c/w Drains
• Metering Stations
• Hoses
• Extension Spindles for chilled water
applications
Each unit can be sized according to your
flow rates and pressure.
Every unit is pressure tested and tagged
according to your schedule.
VIP is launching a new and complete 3 valve manifold
specifically designed to be installed on to Fan Coils and
other terminal units. Our solution is flexible in its
configuration and regulating characteristics.
It simplifies unit maintenance, permitting its
disassembly without having to empty the entire
system. The unit provides lower leak potential due to
there being fewer joints, with the 3 isolating valves
being integral.
The unit provides a significant reduction in site labour
and installation costs.
Example Unit with
Actuated PICV and
Y-Strainer c/w Drain.
The Belimo PICV can be
remotely adjusted.
Drain for
line vent
Various Bespoke Assembled Units Available Including:
Features:
• 20mm Full Bore for optimum flow
• Can be adapted to ½”, ¾” and 1”, 15mm and 22mm end
connections
Material Specification:
Body - DZR Brass - CW602N
Ball - Chrome Plated DZR
Seat & Seals - PTFE
O Ring & Gasket - EPDM
Union End Connections Available Including:
BSP Female, BSP Male, Compression, Press Fit.
Max Pressure - 16 Bar
Max Temperature - 120°C
www.hurlstonesnorthern.com
STANDARD OPERATION
UNIT MAINTENANCE
By closing the Flow and Return valves and by
opening the bypass, the exchanger is isolated from
the system. It is now possible to drain and disconnect
it for maintenance.
Flow
Return
Female
BSP
Female
BSP
Y Strainer
With Drain
PICV
= Open Valve
= Closed Valve
FLUSHING
By closing the bypass and the Return valve it is
possible to perform a “Forward Flushing” of the
strainer.
By closing the bypass and Flow valve (and with clean
fluid in the system) it is also possible to perform a
“Back Flushing” of the system, by forcing the flow of
the fluid back into the heat exchanger before it is
drained through the strainer.
Or
FLUSHING WITH DRAIN TEST POINTS
By using drain test points on both sides it is possible
to clean the unit independently from the line’s
regular working conditions.
Registered Office:
Alexander House
197 Market Street
Tottington
Bury
Lancashire
BL8 3HF
Company Registered No: 6655167 VAT Registration No: 937 4588 76

3-Valve Flushing Bypass Manifold Unit (Hurslstones Header and Footer)

  • 1.
    VIP 3-Valve FlushingBypass Manifold Unit See our full range online at: www.vip-ltd.co.uk VIP Product Code 00/0189 • Fixed Orifice Double Regulating Valve • Variable Orifice Double Regulating Valve • Various PICVs • On/Off Balancing Valve • Dynamic Balancing Valve • Drain Points • Strainers • Strainers c/w Drains • Metering Stations • Hoses • Extension Spindles for chilled water applications Each unit can be sized according to your flow rates and pressure. Every unit is pressure tested and tagged according to your schedule. VIP is launching a new and complete 3 valve manifold specifically designed to be installed on to Fan Coils and other terminal units. Our solution is flexible in its configuration and regulating characteristics. It simplifies unit maintenance, permitting its disassembly without having to empty the entire system. The unit provides lower leak potential due to there being fewer joints, with the 3 isolating valves being integral. The unit provides a significant reduction in site labour and installation costs. Example Unit with Actuated PICV and Y-Strainer c/w Drain. The Belimo PICV can be remotely adjusted. Drain for line vent Various Bespoke Assembled Units Available Including: Features: • 20mm Full Bore for optimum flow • Can be adapted to ½”, ¾” and 1”, 15mm and 22mm end connections Material Specification: Body - DZR Brass - CW602N Ball - Chrome Plated DZR Seat & Seals - PTFE O Ring & Gasket - EPDM Union End Connections Available Including: BSP Female, BSP Male, Compression, Press Fit. Max Pressure - 16 Bar Max Temperature - 120°C www.hurlstonesnorthern.com
  • 2.
    STANDARD OPERATION UNIT MAINTENANCE Byclosing the Flow and Return valves and by opening the bypass, the exchanger is isolated from the system. It is now possible to drain and disconnect it for maintenance. Flow Return Female BSP Female BSP Y Strainer With Drain PICV = Open Valve = Closed Valve FLUSHING By closing the bypass and the Return valve it is possible to perform a “Forward Flushing” of the strainer. By closing the bypass and Flow valve (and with clean fluid in the system) it is also possible to perform a “Back Flushing” of the system, by forcing the flow of the fluid back into the heat exchanger before it is drained through the strainer. Or FLUSHING WITH DRAIN TEST POINTS By using drain test points on both sides it is possible to clean the unit independently from the line’s regular working conditions. Registered Office: Alexander House 197 Market Street Tottington Bury Lancashire BL8 3HF Company Registered No: 6655167 VAT Registration No: 937 4588 76