SlideShare a Scribd company logo
1 of 1
Download to read offline
INSPECTION REPORT – 152 WEST 124TH
STREET - Manhattan
Date October 10, 2009
___________________________________________________________________________
On Wednesday, October 7, 2009, I inspected the building at 152 West 124
th
Street in Manhattan.
Reason for inspection: To ensure all rear apartments on all 5 floors are completely fireproofed at
demising walls to create 1 hr. rated partitioning from floor to floor.
Method of fireproofing. A double layer of sheetrock on 3-5/8” metal studs filled in with mineral
Wool was installed from floor to floor. At joists above ceiling, a layer of gypsum board was installed
below and between joists to create a gap free meeting joint, flush to the sub-floor above. The
meeting joints were then caulked continuously with fire-proof Hilti caulking along the gypsum
board edges, joist perimeter and subfloor surface.
I paid several visits to the site to inspect that all joints were continuously caulked, leaving
no gaps, thus creating 1hr fire rated demising walls between apartments.
Note:
1. upon my first visiting inspection, approx August 1, 2009 - Gypsum board was installed over
80 percent of the wall to floor meeting joints, but there was no caulking installed. I instructed
the contractor to install the balance of the gypsum board layers. Also, at the bathrooms on all
floors, the demising walls were not complete. I instructed the contractor to complete the
demising walls, so the final layer of gypsum. board and caulking could be installed.
2. Upon my second inspection on September 24, 2009. All gypsum board was installed and
80 percent of caulking. Caulking was not installed in areas where the contractor could not
access above the ceiling. I therefore instructed the contractor to cut away the gypsum board
ceiling along the entire perimeter wall, so he could access the locations not caulked, then to
caulk the entire perimeter of the ceiling.
3. Upon my third visit on October 7, 2009 99 percent of caulking was complete. The contractor
had cut - away the ceiling to complete the caulking and approx. 4 ft. of gypsum board was
installed to complete the bathroom demising walls and caulked. There were minor sporadic
locations not caulked, which were caulked during my inspection, for an entirety of approx. 4 ft.
for all 5 floors combined. I recognized that 98 percent of the fire-proofing was completed,
therefore, I instructed the contractor to touch up these areas, to complete the job. This was
performed and also inspected by the HPD inspector.
I now certify that the entire rear apartments are 100 percent 1hr fire rated at
the demising walls.
Gpguard
Inspector________________________________________ Date: 10/10/09
Gerald Guard

More Related Content

Viewers also liked

Fei pi classement (s) 16.10.16
Fei pi   classement (s) 16.10.16Fei pi   classement (s) 16.10.16
Fei pi classement (s) 16.10.16Laurent BUVRY
 
A Senior: Food Inventions
A Senior: Food InventionsA Senior: Food Inventions
A Senior: Food InventionsLingua Net
 
Aspects techniques, réglementaires - Quelles prescriptions ?
Aspects techniques, réglementaires - Quelles prescriptions ?Aspects techniques, réglementaires - Quelles prescriptions ?
Aspects techniques, réglementaires - Quelles prescriptions ?idealconnaissances
 
Comment plier un fichier dossiers [pour faire un "lapbook"]
Comment plier un fichier dossiers [pour faire un "lapbook"]Comment plier un fichier dossiers [pour faire un "lapbook"]
Comment plier un fichier dossiers [pour faire un "lapbook"]Lucy S.
 

Viewers also liked (9)

Interclubs 2014
Interclubs 2014Interclubs 2014
Interclubs 2014
 
Anugerah Pekerja Cemerlang 2013_opt
Anugerah Pekerja Cemerlang 2013_optAnugerah Pekerja Cemerlang 2013_opt
Anugerah Pekerja Cemerlang 2013_opt
 
Enmienda ordenanzas fiscales 2017 UPYD
Enmienda ordenanzas fiscales 2017 UPYD Enmienda ordenanzas fiscales 2017 UPYD
Enmienda ordenanzas fiscales 2017 UPYD
 
Njekwa - Practical Analysis of the Personal Saver Market
Njekwa - Practical Analysis of the Personal Saver MarketNjekwa - Practical Analysis of the Personal Saver Market
Njekwa - Practical Analysis of the Personal Saver Market
 
Fei pi classement (s) 16.10.16
Fei pi   classement (s) 16.10.16Fei pi   classement (s) 16.10.16
Fei pi classement (s) 16.10.16
 
A Senior: Food Inventions
A Senior: Food InventionsA Senior: Food Inventions
A Senior: Food Inventions
 
Aspects techniques, réglementaires - Quelles prescriptions ?
Aspects techniques, réglementaires - Quelles prescriptions ?Aspects techniques, réglementaires - Quelles prescriptions ?
Aspects techniques, réglementaires - Quelles prescriptions ?
 
Les jeux de la récré
Les jeux de la récré Les jeux de la récré
Les jeux de la récré
 
Comment plier un fichier dossiers [pour faire un "lapbook"]
Comment plier un fichier dossiers [pour faire un "lapbook"]Comment plier un fichier dossiers [pour faire un "lapbook"]
Comment plier un fichier dossiers [pour faire un "lapbook"]
 

152 West 124th Street Inspection Report

  • 1. INSPECTION REPORT – 152 WEST 124TH STREET - Manhattan Date October 10, 2009 ___________________________________________________________________________ On Wednesday, October 7, 2009, I inspected the building at 152 West 124 th Street in Manhattan. Reason for inspection: To ensure all rear apartments on all 5 floors are completely fireproofed at demising walls to create 1 hr. rated partitioning from floor to floor. Method of fireproofing. A double layer of sheetrock on 3-5/8” metal studs filled in with mineral Wool was installed from floor to floor. At joists above ceiling, a layer of gypsum board was installed below and between joists to create a gap free meeting joint, flush to the sub-floor above. The meeting joints were then caulked continuously with fire-proof Hilti caulking along the gypsum board edges, joist perimeter and subfloor surface. I paid several visits to the site to inspect that all joints were continuously caulked, leaving no gaps, thus creating 1hr fire rated demising walls between apartments. Note: 1. upon my first visiting inspection, approx August 1, 2009 - Gypsum board was installed over 80 percent of the wall to floor meeting joints, but there was no caulking installed. I instructed the contractor to install the balance of the gypsum board layers. Also, at the bathrooms on all floors, the demising walls were not complete. I instructed the contractor to complete the demising walls, so the final layer of gypsum. board and caulking could be installed. 2. Upon my second inspection on September 24, 2009. All gypsum board was installed and 80 percent of caulking. Caulking was not installed in areas where the contractor could not access above the ceiling. I therefore instructed the contractor to cut away the gypsum board ceiling along the entire perimeter wall, so he could access the locations not caulked, then to caulk the entire perimeter of the ceiling. 3. Upon my third visit on October 7, 2009 99 percent of caulking was complete. The contractor had cut - away the ceiling to complete the caulking and approx. 4 ft. of gypsum board was installed to complete the bathroom demising walls and caulked. There were minor sporadic locations not caulked, which were caulked during my inspection, for an entirety of approx. 4 ft. for all 5 floors combined. I recognized that 98 percent of the fire-proofing was completed, therefore, I instructed the contractor to touch up these areas, to complete the job. This was performed and also inspected by the HPD inspector. I now certify that the entire rear apartments are 100 percent 1hr fire rated at the demising walls. Gpguard Inspector________________________________________ Date: 10/10/09 Gerald Guard