The document provides a budget and itemized list of costs for a project totaling RM4,167. It includes the purchase of a computer, printer, paper, camera/phone, colored pens, and software like Microsoft Office, PowerPoint, and Audacity. A timetable is also included showing the planned 10 steps of the project from forming a group to the final presentation, spanning from March 19th to May 8th over 30 days.
1. 5
5.0 KOS PEMBANGUNAN PROJEK
No Item Kuantiti Harga seunit
(RM)
Harga
(RM)
1 1 set computer 1 2000 2000
2 Printer 1 250 250
3 Kertas 40 Keping 0.20 8
4 Kertas Warna 20 0.20 4
5 Kamera/Handphone 1 600 600
6 Pen Warna 5 1 5
7 Software(Microsoft Office Word) 1 600 600
8 Software(Microsoft Power Point) 1 700 700
9 Software(Window Movie Maker) 1 0 0
10 Software(Audacity) 1 0 0
Jumlah 4167
2. 6
6.0 TIMETABLE
Bil Test Name Duration Start Finish Predecessor Reserve
Names
19Mar 21Mar-31 Apr 8May
S M T W T F S S M T W T F S S M T W T F S
1 Looking for group
members
1 day Thu
19/3
Thu
19/3
2 Discuss title project 1 day Fri
20/3
Fri
20/2
3 Project Planning 1 day Sa
21/3
Sa
21/3
4 Preparation of
paper workds
2 days Sun
22/3
Mon
23/3
5 Discuss storyboard 2 days Tue
24/3
Wed
25/3
6 Presentation
storyboard
1 day Thu
26/3
Thu
26/3
7 Discuss about
proposal
3 days Fri
27/3
Sun
29/3
8 Improving
storyboard
3 days Mon
30/3
Tue
1/4
9 Launch a project 30days Thu
2/4
Thu
8/5
10 Presentation final
project
1days Thu
8/5
Thu
8/5