Installing In Slab Heat Piping
- 1. INSTALLING THE “IN SLAB” HEAT
AT WORLD WIDE AUTOMOTIVE
Installed on:
April 22, 2009
EarthDay!
- 3. The first step in the installation in laying
the insulation blanket in place
- 6. Next comes the rebar “chairs” that will
hold the rebar sheets above the blanket
- 7. Then the sheets of reinforcement wire
(rebar) are placed on top of the chairs
- 8. The “chairs” position the rebar sheets
so they end up in the middle of the
concrete slab once in is poured
- 10. The pipe is fed out across the sheets of
rebar in giant loops
- 11. Areas where the shop’s lifts will bolt
down are marked as “no pipe” zones
- 12. To keep the pipe in place during the
pouring of the concrete…
- 13. The great crew from Simanton wired
the pipe to the rebar every few feet
- 15. The ends of the pipe had to be
channeled to a central location…