Better Plan your            TYPO3 Projects with              Agile EstimatingVioleng Mamvioleng@web-essentials.asiaDominik...
Dominik Stankowski●   Software Engineer●   TYPO3 certified Integrator●   Online media expert, has worked    for the Swiss ...
Violeng Mam●   BA in Computer Sciences●   TYPO3 certified Integrator●   Project Manager and Team leader    Project Manager...
Agenda   Problems with Estimates   Agile Estimating       Relative Estimates       Velocity       Our Experience with...
Why Plan?●   Keep due dates and budget●   Manage resources●   Build trust with clients●   Reduce risks and last minute sur...
Problems with Estimations●   Its hard to know exactly how long a task will take●   People are not very good at giving accu...
Activity: Country Sizes                           South-East AsiaSource: wolframalpha.com
Activity: Country Sizes                           CambodiaSource: wolframalpha.com
Activity: Country Sizes                           Cambodia                           LaosSource: wolframalpha.com
Activity: Country Sizes                           Cambodia                           Laos                           Thaila...
Activity: Country Sizes                           Cambodia                           Laos                           Thaila...
Activity: Country Sizes                           Cambodia                           Laos                           Thaila...
Activity: Country Sizes                           Cambodia: 181,035 km2                           Laos: 236,800 km2       ...
Activity: Country Sizes                           Cambodia: 181,035 km2                           Laos: 236,800 km2       ...
Activity: Country Sizes                           Cambodia: 1 country pt.                           Laos: ?               ...
Activity: Country Sizes                           Cambodia: 1 country pt.                           Laos: 1 cpt.          ...
Activity: Country SizesIt is easier to compare in country points than in actual sizes.→ Relative Estimations
Relative EstimationsIt does not matter what unit we use to measure the size:●   Country Points●   Ideal days●   Bananas......
Relative Estimations
Relative Estimations
Relative EstimationsBuilding estimates on facts:If an activity takes longer the chances are high that a similaractivity ta...
Velocity●   Velocity is the number of country points or ideal days we    can do in a set time (e.g. a week)●   Things like...
Example ProjectImage Contest●   Users can upload images●   Users can view uploaded images and rate●   The Winners are disp...
Example Project                                                        Picture Detail      Concept,       Generate        ...
VelocitySimplified: All 9 tasks are the same sizeAssume: After 1 week, 3 tasks finished(simplified) Velocity = 3 tasks / 5...
VelocityWhen will we finish?●   Remaining: 6 tasksSo we can complete (simplified):6 tasks / 0.6 tasks/day = 9 days**if we ...
Example Project                                                          Picture Detail  Techn. Concept,      Generate    ...
VelocityTotal number of points: 12.5Assume:●   3.5 points finished●   3 days elapsed(simplified) Velocity = 3.5 points / 3...
VelocityWhen will we finish?●   Remaining: 9 pointsSo we can complete (simplified):9 points / 1.2 points/day = 7.5 days → ...
Increase accuracy●   Involve the whole team in estimating●   Use non-linear sequences for points such as e.g. Fibonacci:  ...
Our Experience                            Planned and actual completion and scope         180         160         140     ...
How to decrease time to finishMonitor effects on velocity regularly and make necessarychanges:●   Less interruptions and l...
SummaryEstimating is a continuous process as we understand moreabout how we perform→ agile = flexible, well coordinated, q...
SummaryAgile Estimating will make your planning more accuratebecause: ●   The whole team is involved ●   Estimates of size...
Further ReadingAgile Estimating and Planningby Mike Cohn
Thank You!dominik@web-essentials.asiavioleng@web-essentials.asia
Upcoming SlideShare
Loading in …5
×

Better Plan TYPO3 Projects with Agile Estimating

1,396 views

Published on

Absolute estimating of programming tasks proves to be challenging in (too) many cases. When development takes longer than foreseen, any or several of the following areas are impacted: quality, finances, resource planning and client satisfaction. Studies reveal that 2 out of 3 software development projects are unsuccessful because they are over budget, late, missing function or a combination – in short: estimating fails frequently enough.

Agile Estimating is a methodology for project managers to better plan their projects in advance and to keep their planning up-to-date and accurate throughout the development process. Estimates of tasks are done on a relative basis using an independent unit instead of hours or days. As the team progresses on its tasks, indicators such as the actual business situation, the constitution of the team, the learning progress of the team members and the feedback of the client are tracked. These indicators are fed back into an updated planning allowing for more accurate forecasts and giving a better basis for decision making.

As the TYPO3 community is transitioning into greater possibilities and chances to establish itself increasingly in the enterprise CMS sector (keyword: TYPO3 Phoenix), new technical complexities will have to be faced and overcome. New business requirements and better interoperability with other systems is going to put high demands on project teams. Strong project management capabilities need to be acquired alongside the technological advancements within the community and with the different services providers to sustain the reputation of TYPO3 services as enterprise solutions.

Published in: Technology, Business
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
1,396
On SlideShare
0
From Embeds
0
Number of Embeds
7
Actions
Shares
0
Downloads
0
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide

Better Plan TYPO3 Projects with Agile Estimating

  1. 1. Better Plan your TYPO3 Projects with Agile EstimatingVioleng Mamvioleng@web-essentials.asiaDominik Stankowskidominik@web-essentials.asia
  2. 2. Dominik Stankowski● Software Engineer● TYPO3 certified Integrator● Online media expert, has worked for the Swiss news portal www.swissinfo.ch● Owner and CEO of Web Essentials● 4 years outsourcing experience in Cambodia
  3. 3. Violeng Mam● BA in Computer Sciences● TYPO3 certified Integrator● Project Manager and Team leader Project Managers Team● Senior Manager at Web Essentials● 3 years experience working with international clients
  4. 4. Agenda Problems with Estimates Agile Estimating  Relative Estimates  Velocity  Our Experience with AE Summary
  5. 5. Why Plan?● Keep due dates and budget● Manage resources● Build trust with clients● Reduce risks and last minute surprises● Create a basis for decision making→ Control the outcome/future of a project
  6. 6. Problems with Estimations● Its hard to know exactly how long a task will take● People are not very good at giving accurate estimates● Sometimes we get interrupted, it takes longer than thought● Sometimes we find unexpected problems● People get sick, take holidays...● Planning by hour or day gives wrong incentive● Activities are interdependent
  7. 7. Activity: Country Sizes South-East AsiaSource: wolframalpha.com
  8. 8. Activity: Country Sizes CambodiaSource: wolframalpha.com
  9. 9. Activity: Country Sizes Cambodia LaosSource: wolframalpha.com
  10. 10. Activity: Country Sizes Cambodia Laos ThailandSource: wolframalpha.com
  11. 11. Activity: Country Sizes Cambodia Laos Thailand VietnamSource: wolframalpha.com
  12. 12. Activity: Country Sizes Cambodia Laos Thailand Vietnam MyanmarSource: wolframalpha.com
  13. 13. Activity: Country Sizes Cambodia: 181,035 km2 Laos: 236,800 km2 Thailand: 513,120 km2 Vietnam: 329,560 km2 Myanmar: 676,578 km2Source: wolframalpha.com
  14. 14. Activity: Country Sizes Cambodia: 181,035 km2 Laos: 236,800 km2 Thailand: 513,120 km2 Vietnam: 329,560 km2 Myanmar: 676,578 km2 Germany: 357,022 km2 Switzerland: 41,277 km2Source: wolframalpha.com
  15. 15. Activity: Country Sizes Cambodia: 1 country pt. Laos: ? Thailand: ? Vietnam: ? Myanmar: ?Source: wolframalpha.com
  16. 16. Activity: Country Sizes Cambodia: 1 country pt. Laos: 1 cpt. Thailand: 3 cpts. Vietnam: 2 cpts. Myanmar: 4 cpts. Germany: 2 cpts. Switzerland: ¼ cpts.Source: wolframalpha.com
  17. 17. Activity: Country SizesIt is easier to compare in country points than in actual sizes.→ Relative Estimations
  18. 18. Relative EstimationsIt does not matter what unit we use to measure the size:● Country Points● Ideal days● Bananas...It is important that the estimates are consistent:Same sizes get same number of points
  19. 19. Relative Estimations
  20. 20. Relative Estimations
  21. 21. Relative EstimationsBuilding estimates on facts:If an activity takes longer the chances are high that a similaractivity takes longer, too.→ Velocity will define the time needed
  22. 22. Velocity● Velocity is the number of country points or ideal days we can do in a set time (e.g. a week)● Things like interruptions, meetings, infrastructure failures will lower our velocity● As long as our estimate of a task is consistent with our estimate for the other tasks, we can use velocity to tell us when we will be finished
  23. 23. Example ProjectImage Contest● Users can upload images● Users can view uploaded images and rate● The Winners are displayed and notified
  24. 24. Example Project Picture Detail Concept, Generate (Lightbox) Data Model Extension & TCA Picture Gallery Load more when scrolling downVote & Comment Functionality Highscore Send Email Image Functionality Upload
  25. 25. VelocitySimplified: All 9 tasks are the same sizeAssume: After 1 week, 3 tasks finished(simplified) Velocity = 3 tasks / 5 days = 0.6 tasks / day
  26. 26. VelocityWhen will we finish?● Remaining: 6 tasksSo we can complete (simplified):6 tasks / 0.6 tasks/day = 9 days**if we continue with the same velocity, but:Velocity will get more reliable if tracked over longer period
  27. 27. Example Project Picture Detail Techn. Concept, Generate (Lightbox) Data Model Extension & TCA Picture Gallery 1 ½ View 1 2 Load more when scrolling downVote & Comment Functionality Highscore Send Email 1 Image 2 Upload 1 Functionality 2 2
  28. 28. VelocityTotal number of points: 12.5Assume:● 3.5 points finished● 3 days elapsed(simplified) Velocity = 3.5 points / 3 days = 1.2 points / day
  29. 29. VelocityWhen will we finish?● Remaining: 9 pointsSo we can complete (simplified):9 points / 1.2 points/day = 7.5 days → 8 daysProposition: It is better to track the points we cancomplete/week than the remaining days.
  30. 30. Increase accuracy● Involve the whole team in estimating● Use non-linear sequences for points such as e.g. Fibonacci: 0, (½), 1, 1, 2, 3, 5, 8, 13, 21, …● Man-days instead of elapsed time for velocity calculation● Clearly define what means a task is complete● Verify velocity on a regular basis● Re-estimate stories if needed (but only if the relative size is wrong – absolute errors will be corrected by velocity)
  31. 31. Our Experience Planned and actual completion and scope 180 160 140 120 100 Total Planned Capacity Total ScopePoints 80 Total Dev Complete 60 40 20 0 0 1 2 3 4 5 5 5 6 7 8 9 10 11 12 13 14 15 16 16 17 Iteration
  32. 32. How to decrease time to finishMonitor effects on velocity regularly and make necessarychanges:● Less interruptions and less multi-tasking (velocity +)● Give team members more time on project (man days +)● Add skilled developer to the team (velocity +, man days +)● Reduce scope of features or project (points -)
  33. 33. SummaryEstimating is a continuous process as we understand moreabout how we perform→ agile = flexible, well coordinated, quick to move
  34. 34. SummaryAgile Estimating will make your planning more accuratebecause: ● The whole team is involved ● Estimates of size and duration are separated ● Estimates and plans are based on facts ● Learning and adjusting is fostered→ Accurate estimates allow for better decision making
  35. 35. Further ReadingAgile Estimating and Planningby Mike Cohn
  36. 36. Thank You!dominik@web-essentials.asiavioleng@web-essentials.asia

×