Construction Project
Management
Assignment # 3
Submitted to:
Lec. Bilal Zafar
From:
Activity Duration ES EF LS LF TF FF
A 2 0 2 0 2 0 0
B 4 2 6 4 8 2 0
C 6 2 8 2 8 0 0
D 9 2 11 6 15 4 4
E 5 6 11 10 15 4 4
F...
Activity
A 3 3
B 2 2 2 2
C 4 4 4 4 4 4
D 3 3 3 3 3 3 3 3 3
E 4 4 4 4 4
F 2 2 2 2 2 2
G 4 4 4
Day 1 2 3 4 5 6 7 8 9 10 11 1...
Activity
A 3 3
B X X 2 2 2 2
C 4 4 4 4 4 4
D 3 3 3 3 3 3 3 3 3
E X X 4 4 4 4
F 2 2 2 2 2 2
G 4 4 4
Day 1 2 3 4 5 6 7 8 9 1...
Activity
A 3 3
B X X 2 2 2 2
C 4 4 4 4 4 4
D D D D D 3 3 3 3 3 3 3 3
E X X 4 4 4 4
F 2 2 2 2 2 2
G 4 4 4
Day 1 2 3 4 5 6 7...
Resource Levelling - PMBOK - Example
Upcoming SlideShare
Loading in …5
×

Resource Levelling - PMBOK - Example

2,400 views

Published on

An example describing resource levelling according to PMBOK

Published in: Education, Technology, Business

Resource Levelling - PMBOK - Example

  1. 1. Waleed Liaqat 122 SEC A Construction Project Management Assignment # 3 Submitted to: Lec. Bilal Zafar From:
  2. 2. Activity Duration ES EF LS LF TF FF A 2 0 2 0 2 0 0 B 4 2 6 4 8 2 0 C 6 2 8 2 8 0 0 D 9 2 11 6 15 4 4 E 5 6 11 10 15 4 4 F 7 8 15 8 15 0 0 G 3 15 18 15 18 0 nil 18 Total Duration of project (Days) B 4 D 9 C 6 F 7 E 5 G 3 A 2 PS Critical
  3. 3. Activity A 3 3 B 2 2 2 2 C 4 4 4 4 4 4 D 3 3 3 3 3 3 3 3 3 E 4 4 4 4 4 F 2 2 2 2 2 2 G 4 4 4 Day 1 2 3 4 5 6 7 8 9 10 11 13 14 15 16 17 18 Total Laborers 3 3 9 9 9 9 11 11 9 9 9 2 2 2 4 4 4 KEY OveruseFloat Non critical Activity Critical Activity 0 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 1 3 1 4 15 1 6 1 7 18 LABORERS DAYS BEFORE LEVELLING
  4. 4. Activity A 3 3 B X X 2 2 2 2 C 4 4 4 4 4 4 D 3 3 3 3 3 3 3 3 3 E X X 4 4 4 4 F 2 2 2 2 2 2 G 4 4 4 Day 1 2 3 4 5 6 7 8 9 10 11 13 14 15 16 17 18 Total Laborers 3 3 7 7 9 9 9 9 9 9 9 6 2 2 4 4 4 0 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 LABORERS DAYS INTERMEDIATE LEVELLING
  5. 5. Activity A 3 3 B X X 2 2 2 2 C 4 4 4 4 4 4 D D D D D 3 3 3 3 3 3 3 3 E X X 4 4 4 4 F 2 2 2 2 2 2 G 4 4 4 Day 1 2 3 4 5 6 7 8 9 10 11 13 14 15 16 17 18 Total Laborers 3 3 4 4 6 6 9 9 9 9 9 9 5 5 4 4 4 Float X ASSIGNMENT FIX D DISTRIBUTIO N FIX KEY Critical Activity Non critical Activity 0 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 LABORERS DAYS AFTER COMPLETE LEVELLING

×