Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

  1. 1. Route 1 Widening PARDON OUR DUST BRIEFING April 27th, 2016 – 6:30 PM Freedom High School Auditorium 15201 Neabsco Mills Road Woodbridge, VA 22191
  2. 2. Tonight's Objectives • Introduction of the Construction Team • Present Project Scope of Work – Widen U.S. 1 from four to six lanes between Mary's Way and Annapolis Way – Enhance access to the Woodbridge VRE kiss-and-ride facility – Construct new Route 1 bridge at Marumsco Creek – Improvements to Route 1 and Occoquan Road to improve traffic operations – Construct a ten-foot shared-use path and six-foot sidewalk – Underground utilities along Route 1 (duct bank work has been completed) • Construction Elements – Sequence of Construction – Detours • Answer your Questions 2
  3. 3. Project Team • Virginia Department of Transportation • Prince William County • Contractor: Fort Myer Construction Corporation 3
  4. 4. ROUTE 1 WIDENING Construction Team & Contact Information VDOT Construction Management contact information: • Chan B. Basnayake, P.E., PMP, CCM - Area Construction Engineer – (703) 259-2947 chan.basnayake@vdot.virginia.gov • Oscar D. Jamilla, DPE, PMP - Sr. Construction Manager – (703) 259- 2769 oj.jamilla@vdot.virginia.gov • Mike Hamp – Project Inspector – (571) 722-6919 michael.hamp@vdot.virginia.gov • Michelle Stubenbordt – Project Records Manager/Sr. Inspector – (571) 289-8003 michelle.stubenbordt@vdot.virginia.gov • Kathy Poole, P.E., CCM – Office Engineer – (571) 319-6509 kathy.poole@vdot.virginia.gov Contractor: Fort Myer Construction Corporation contact information: • Ardie Kalantar – Project Manager – (202) 497-5377 akalantar@fortmyer.com • Fabio Fernandes – Project Engineer – (202) 345-0695 ffernandes@fortmyer.com • Rick Fernandes – Vice President – (202) 437-4353 rfernandes@fortmyer.com Field office location (open during normal business hours): – 13408 Jefferson Davis Highway, Woodbridge, VA 22191 – Phone Number: TBD 4 Project updates will be posted on VDOT’s website at: http://www.virginiadot.org/projects/northernvirginia/route_1_widening.asp
  5. 5. Project Timeline • Contract Executed: March 25th, 2016 • Notice to Proceed Date: April 11th, 2016 • Start of Construction: April 12th, 2016 • Final Completion: November 29th, 2019 5 Contract Value = $43,246,647.92
  6. 6. 6 Project Location Project 0123-076-004, C501
  7. 7. 7 Project Information Phase 2 Future Route 123 Interchange Marumsco Creek Bridge Project Field Office
  8. 8. 8 Project Information Project Field Office VRE Station Marumsco Creek Belmont Bay I-95 Interchange CSXT RailroadKiss And Ride
  9. 9. 9 Project Information Project Field Office Ornamental Fence Retaining Walls
  10. 10. 10 Typical Section
  11. 11. 11 • Place Advance Warning Signs • Clearing and Grubbing • Building Demolitions • Remove Existing Raised Concrete Medians • Construct Temporary Sidewalks and Reroute Pedestrian Traffic to Southbound Side of Route 1 • Construct NB Proposed Pavement, Retaining Walls, Sidewalks and Drainage From Station 49+25 to Station 67+25 • Construct Temporary Pavement Wedge for Driveway Access Construction Stage 1: thru Aug 2016
  12. 12. 12 Construction Stage 2-1: Sept 2016 – Dec 2016 • Install Temporary Signals at Occoquan Road Intersection • Reroute Pedestrian Traffic to the Northbound Side of Route 1 • Shift NB and SB Traffic to the East Using Existing Pavement and Pavement Placed in Previous Stage • Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 49+50 to Station 64+00 and Easy Street Connector • Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 64+00 to Station 67+75 MarysWay
  13. 13. 13 Construction Stage 2-2 and 2-3: Jan 2017 – June 2017MarysWay • Close Easy Street South and Detour Traffic to Easy Street Connector and Construct Easy Street South Entrance • Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 39+50 to Station 49+50 • Construct First Stage of the Bridge over Marumsco Creek (Stage 2-3)
  14. 14. 14 Construction Stage 3-1: July 2017 – Oct 2017 • Shift SB Traffic to Pavement and Partial Bridge Constructed in Stage 2 • Construct SB Proposed Pavement from Station 42+50 to Station 51+25 • Construct Second Stage of the Bridge over Marumsco Creek • Install Temporary Signals at Annapolis Way and Occoquan Road • Reroute Route 123 Pedestrian Traffic to Horner Road and Occoquan Road • Relocate Waterlines and Sanitary Sewers MarysWay
  15. 15. 15 Construction Stage 3-2, 3-3, 3-4: Nov 2017 – June 2018 • Construct SB Proposed Pavement, Trail and Drainage from Station 70+00 to Station 82+75 and from Station 84+00 to Station 97+50 and from Station 98+00 to Station 101+00 • Construct WB Lanes of Annapolis Way • Construct Occoquan Road Proposed Pavement, Drainage and Sidewalks in Three Phases (3- 3A WB Lanes, 3-3B Center Lanes and 3-3C EB Lanes) • Sanitary Sewer Relocations Concurrent with this Stage South of Occoquan Rd • Construct Route 123 Detour and Install Temporary Signal (Stage 3-4A) • Reroute Route 123 Traffic to Detour (Stage 3-4B) • Construct Route 123 Proposed Pavement, Sidewalks and Drainage (Stage 3-4B) Route 123 Detour
  16. 16. 16 Construction Stage 4-1, 4-2, 4-3, 4-4: July 2018 – Dec 2018 • Install Temporary Signals at Annapolis Way and Route 123 Intersections • Shift Route 123 Traffic to Newly Constructed Route 123 Pavement • Detour Annapolis Way Traffic and Construct Remaining Annapolis Way • Construct NB Proposed Pavement from Station 93+00 to Station 99+75 (Stage 4-3) • Install Temporary Signal at Occoquan Road and Shift NB and SB Traffic to the West to Bridge and Pavement Placed in Previous Stages • Construct SB Proposed Pavement from Station 101+00 to Station 104+00 and NB Proposed Pavement from Station 99+75 to Station 104+00 (Stage 4-4) US Route 1
  17. 17. 17 Construction Stage 4-5: Jan 2019 – Apr 2019 • Construct NB Proposed Pavement, Drainage, Retaining Walls and Sidewalk from Station 42+50 to Station 67+25 and from Station 69+25 to Station 82+00 • Construct Third Stage of the Bridge over Marumsco Creek
  18. 18. 18 Construction Stages 5 and 6: May 2019 – Nov 2019 STAGE 5 • Construct NB Proposed Pavement from Station 38+25 to Station 42+50 • Install Temporary Signal at Dawson Beach Road • Construct Dawson Beach Road Intersection • Construct Remaining Sections of SB Route 1 from Station 39+00 to Station 43+00 • Shift NB Traffic to Newly Constructed NB Lanes • Construct Raised Median STAGE 6 • Place Final Pavement Surface and Pavement Markings
  19. 19. Lane Closure Restrictions 19 Lane Closures will only be permitted: Day Hours Monday - Thursday 9:30 AM – 3:00 PM 10:00 PM – 5:00 AM Friday 9:30 AM – 12:00 PM 10:00 PM – 9:00 AM Saturday - Sunday 10:00 PM – 8:00 AM Sunday - Monday 10:00 PM – 5:00 AM Two-way Traffic Will Be Maintained At All Times!
  20. 20. Night Work 20 • Installation of Traffic Control Devices • Traffic Shifts • Pavement Milling and Overlays • Pavement Striping • Utility Relocations • Lane Closures
  21. 21. 21 Annapolis Way Detour – Stage 4
  22. 22. Pedestrian Detours & Bus Stop Coordination 22 • There Will be Several Pedestrian Detours • Pedestrian Detour Signs Will be Provided • All Bus Stops Will be Maintained During All Phases of Construction • Bus Stops May be Temporarily Relocated But Will Remain ADA Compliant
  23. 23. Kiss and Ride 23 • Facilities Will Remain Open During Construction and After Construction
  24. 24. Question & Answer Session 24

×