  1. 1. 1yd/0609
  2. 2. 2yd/0609
  3. 3. 1) PIPE & PIPE 3) PIPE FITTING & FLANGE • Butt-weld • Elbow • Stub-in • Tee • Branch conn • Reducer2) PIPE & FLANGE 4) PIPE & FITTING • Slip-on • For 1-1/2” pipe & below • Welding Neck • Threaded • Threaded • Socket-weld • Socket-weld • Lap Joint 3 yd/0609
  4. 4. 4yd/0609
  5. 5. 5yd/0609
  6. 6. 6yd/0609
  7. 7. Branch teeunion branch coupling Straight stub-in Lateral stub-in 7 yd/0609
  8. 8. 8yd/0609
  9. 9. 9yd/0609
  10. 10. 10yd/0609
  11. 11. 11yd/0609
  12. 12. STRUCTURE • Primary • Secondary TYPE OF REINFORCEMENT• Water tight doubler • Non-tight doubler• Water tight pipe sleeve • Non-tight pipe sleeve• Insert Plate • Tubing - A0 / A60 / W.T.• Pipe Coupling • “CSD” Plug / “Rotex” Plug 12 yd/0609
  13. 13. 13yd/0609
  14. 14. 14yd/0609
  15. 15. 15yd/0609
  16. 16. 16yd/0609
  17. 17. 17yd/0609
  18. 18. 18yd/0609
  19. 19. 19yd/0609
  20. 20. GUIDE SUPPORT Steel with brass / VALVE HANDLE bronze bushing INDICATOR & PIPE SLEEVE AS GUARDSTEEL POLISHED ROD STUFFING BOX & W.T. GLANDVALVE ATTACHMENT :1) Rising Stem2) Non-rising Stem3) Fork Type JOINT :4) Butterfly Valve 1) Universal Cplg 2) Bevel Gear 20 yd/0609
  21. 21. 21yd/0609
  22. 22. Gate valve Attachment Guide support Extension rod Attachment Bevel gear Universal Butterfly Cplg Valve Guide support W.T. gland stuffing box Extension rodGuide support Butterfly valve position handleHandwheel 22 yd/0609
  23. 23. Handwheel W.T. gland Position stuffing box indicator 23yd/0609
  24. 24. • Firewater system• Sewage system• Dirty oil system• Bilge system 24 yd/0609
  25. 25. • The shore connection piece shall be kept near the filling station on either• The flange made of steel shall be side of the vessel. installed (welded) at the port & • It shall be kept together with bolts & starboard shore connections. washers 4sets-16mm (5/8”) x 50mm (2”) 4sets- (5/8” (2” LG, gasket 1pc-10.5kg/cm2(150 psi) 1pc- psi) 25 yd/0609
  26. 26. 26yd/0609
  27. 27. • The flange made of steel shall be installed (welded) at the port & starboard shore connections. • This deck facilities is adapted from the marine pollution regulation #19 • The flange is designed to accept pipes up to a max. internal dia. Of 125mm (5”) & dia. (5” shall be flat face • The flange shall complete with 6sets-M20 x 60mm LG 6sets- bolts & nuts with a gasket of oil proof material, suitable for service pressure of 0.6mPA (6 bar). Non asbestos gasket shall be full face, 1.5mm thickness & suitable for service pressure of 1.0mPA (10bar) 27yd/0609
  28. 28. • The flange made of steel shall be installed (welded) at the port & starboard shore connections together with blind flange. • This deck facility is adapted from the marine pollution regulation #11 • Both flange shall be flat face & provided with 4sets-M16 x 60mm LG 4sets- bolts & nuts together with a suitable gasket. • Flange & gasket shall be suitable for a service pressure of 0.6mPA (6 bar) 28yd/0609
  29. 29. 29yd/0609
  30. 30. • Top plug & coupling • Tank check valve• Extended pipe with (ball float) - cap single/double• Extended pipe with • Gooseneck self-closing valve• Bottom striking plate 30 yd/0609
  31. 31. • SW - SEA WTR • PW - POTABLE WTR • DW - DRILL WTR • BL - BILGE • FO - FUEL OIL • MC - MUD • VOID - VOID CONTAIMINATED • BO - BASE OIL • DO - DIRTY OIL 31yd/0609
  32. 32. NOTE: SELF CLOSING VALVE TO BE INSTALLED ONLY FOR OIL TANK SOUNDING PIPE TERMINATING BELOW SOUNDING WEATHER DECK 32 yd/0609
  33. 33. 33yd/0609
  34. 34. 34yd/0609
  35. 35. 35yd/0609
  36. 36. 36yd/0609
  37. 37. ITEM 7 INSECT SCREEN - SEWAGE FLAME SCREEN - OIL 37yd/0609
  38. 38. Coaming / drip pan (for oil tank) 38 yd/0609
  39. 39. • Butt-weld ends• Type 1 - Concentric reducer• Type 2 - Half pipe with cap 39 yd/0609
  40. 40. 40yd/0609
  41. 41. 41yd/0609
  42. 42. • RATIO OF CLEAR THROUGH STRAINER TO PIPE AREA IS 2.7:1 • ALL DRAINS IN AREAS WITH DECK COVERING TO BE ELEVATED TO DECK COVERING 42yd/0609
  43. 43. 43yd/0609
  44. 44. 44yd/0609
  45. 45. • U-BOLT • PIPE SHOE • PIPE CLAMP 45 yd/0609
  46. 46. • THIS TABLE IS APPLICABLE FOR MAX. SPACING BETWEEN PIPE SUPPORTS FOR HORIZONTAL STRAIGHT RUN OF STANDARD AND HEAVIER PIPE AT MAX. OPERATING TEMP. OF 750 ºF (300 º C) 46 yd/0609
  47. 47. 47yd/0609
  48. 48. 48yd/0609
  49. 49. 49yd/0609
  50. 50. 50yd/0609
  51. 51. 51yd/0609
  52. 52. 52yd/0609
  53. 53. • PIPE SUPPORT DIRECTLY WELDED TO SIDE SHELL IS NOT ALLOWED. DOUBLER IS TO BE USED. 53yd/0609
  54. 54. • ALL BOLTS AND NUTS TO BE CADMIUM PLATED SAE J429 Gr.8 AND SAE J995 Gr.8, HEAVY DUTY • ALL METAL COMPONENTS OF THE STAUFF CLAMPS TO BE ZINC PLATED. 54yd/0609
  55. 55. 55yd/0609
  56. 56. 56yd/0609
  57. 57. 57yd/0609
  58. 58. 58yd/0609

×