  1. 1. Supplemental Drawings p r e s e n t a t i o n April 18, 2007 eu:a eppstein uhen architects 1
  2. 2. Presentation Outline  Supplemental Drawings  ADT Process  Revit Demonstration  Construction Bulletins April 18, 2007 eu:a eppstein uhen architects 2
  3. 3. Supplemental Drawings Supplemental Drawings:  The graphic deliverable to identify revisions.  Included with front-end documentation which describes the revision. Revisions:  Modifications, clarifications, or interpretations made to the Construction Documents  Bidding Phase:  Addendum  Construction Administration:  Construction Bulletin (CB) April 18, 2007 eu:a eppstein uhen architects 3
  4. 4. Revision Work Flow Incorporated in GC & Contract Change Order Subs Const Docs Bidding Construction DESIGN ADDENDUM CB TEAM CONTRACT April 18, 2007 eu:a eppstein uhen architects 4
  5. 5. Supplemental Drawings Sheet Formats 8.5” x 11”  TB - CA 8.5 x 11 (Landscape)  TB - CA 8.5 x 11 (Portrait) 11” x 17”  TB - CA 11 x 17 (Landscape)  TB - CA 11 x 17 (Portrait) April 18, 2007 eu:a eppstein uhen architects 5
  6. 6. Sheet Formats April 18, 2007 eu:a eppstein uhen architects 6
  7. 7. Supplemental Sheet Info Construction Set or Bid Set #1 MM/DD/YY e.g. 04/18/07 Per Vision April 18, 2007 eu:a eppstein uhen architects 7
  8. 8. Supplemental Sheet Info Acme Warehouse 1234 Main Street Anywhere, WI 54321 April 18, 2007 eu:a eppstein uhen architects 8
  9. 9. Supplemental Sheet Info Abbreviation + Number Construction Bulletin CB #000 Addendum ADD #00 Request for Information RFI #000 April 18, 2007 eu:a eppstein uhen architects 9
  10. 10. Supplemental Sheet Info Date of Revision Different from “ISSUANCE DATE” Date of CB or Addendum or RFI April 18, 2007 eu:a eppstein uhen architects 10
  11. 11. Supplemental Sheet Info Axxx : Sheet Number •A105 5th Flr Plan •A200 Exterior Elevations X01 : Consecutive Revision •X01 1st Revision •X15 15th Revision April 18, 2007 eu:a eppstein uhen architects 11
  12. 12. Nomenclature: Supplemental Dwgs CD sheet + Dash + X suffix + (2) Sequential Numbers A0000-X00 A1001-X01 A00-X00 A201-X13 A0-X00 A5-X02 Naming convention: Modifications : a. Construction Bulletin CB #000 b. Construction Change Directive CCD #000 c. Proposal Request PR #000 Clarifications a. Addendum ADD #00 b. Architectural Supplemental Information ASI #000 c. Field Directives FD #000 Interpretations a. Request for Information RFI #000 April 18, 2007 eu:a eppstein uhen architects 12
  13. 13. Supplemental Dwgs Architectural Examples  G103-X11 11th revision to sheet G103 - First Floor Life Safety Plan  A101-X01 1st revision to sheet A101 - First Floor Plan  A1021-X03 3rd revision to sheet A1021 - Twenty-First Floor Plan  A501-X29 29th revision to sheet A501 - Exterior Plan Details Consultant Examples  Would follow this same naming convention:  S103-X06 6th revision to sheet S103 - Third Floor Framing Plan  E101-X01 1st revision to sheet E101 - First Floor Electrical Plan  H1021-X03 3rd revision to sheet A1021 - Twenty-First Floor HVAC Plan  P105-X11 11th revision to sheet P105 - Fifth Floor Plumbing Plan April 18, 2007 eu:a eppstein uhen architects 13
  14. 14. ADT Process  Cloud the revision in the MS (model space) of the source drawing (plan, elevation, section, etc) on layer A-Anno-Revs  Open the sheet affected (GXXX.dwg, AXXX.dwg, etc)  Copy view from the “Main” Sheet tab into a Supplemental Sheets’ tab.  Resize the view to fit the page.  Print Supplemental Sheet to PDF (AXXX-00.pdf)  Save to 00000-00DocumentsCAConstruction Bulletins  Once CB’s itemized proposal has been received & accepted: Bluebeam Staple all associated PDF’s into a single PDF (CB-000) Copy Supplemental Drawing PDF’s (only!) into: Record DocumentsContract DrawingsSupplemental Dwgs April 18, 2007 eu:a eppstein uhen architects 14
  15. 15. Revit Demonstration April 18, 2007 eu:a eppstein uhen architects 15
  16. 16. Conclusion Questions??? Comments??? Concerns??? Suggestions??? April 18, 2007 eu:a eppstein uhen architects 16

×