עידו אלישיב, סמנכ"ל פרוייקטים, טלמניע "מקרה מבחן - הקמת תחנת כוח המונעת בגז טבעי בגבון"

1,070 views

Published on

Published in: Business, Technology
  • Login to see the comments

  • Be the first to like this

עידו אלישיב, סמנכ"ל פרוייקטים, טלמניע "מקרה מבחן - הקמת תחנת כוח המונעת בגז טבעי בגבון"

  1. 1. *
  2. 2. * A global provider of power generation solutions & an Independent Power Producer (IPP) since 1956. Excellent track record in 55 countries, on 4 continents. Over 1,800 MW of installed capacity. Strong financial standing and project financing capabilities. Telemenia’s expertise includes the development of power projects based on natural gas, hydropower, HFO, Diesel, biomass, and biofuels ranging from 1MW to 450MW. Full EPC capabilities, including: o Power station design, engineering, construction & commissioning. o Overall project management. o Electrical & electro-mechanical control panel production & testing. o O&M services (long term agreements).
  3. 3. *Telemenia offers flexible business models to its clients and associates: EPC EPC Package Full EPC contracting for full EPC contracting and power projects ranging from project financing for clients 1 to 450MW seeking project financing to develop power projects IPP BOT, BOO Currently, the company has Capability to develop and new IPP interests in Europe operate power projects & Africa and is starting worldwide for transfer to project development in owner or for delivery of various countries in South power to selected customers America.
  4. 4. * F.K. Generators & Equipment Ltd. 100% 100% 48% 100% 73.42% 100% 100% Hazerem INBAR Moked Amgazit Telemenia F.K Ituran F.K. Energy Solar Energy F.K. Ltd Renewable Location & Services Ltd. Ltd. Energy Ltd.4 Energy Ltd. Control Ltd. Ltd. 1 49% Engen Participacoes 50% 50% 51% 100% 85% 55% 51% 25% Telemenia Telemenia Rus-TMEnergo Telemenia Telemenia Telemenia Telemenia BR3 G2Telemenia Impact Ltd.6 Renewable Gabon Renewable ALB Energy Energy B.V.5 S.A. Energies Ltd.2 sh.a (Romania)Notes:1 Ituran is publicly traded2 15% is owned by Climatrade3 49% is owned by GenRent do Brasil4 52% is owned by Ituran5 51% voting6 50% is owned by Solar Impact Ltd.
  5. 5. * Project financing in Strong cooperation international with leading presence. financial entities. Proven power plant O&M development capabilities as track record in part of the EPC the contract. international market. On-time, on- Flexible budget, project business execution structures to record that meet specific enhances project projects’ requirements. economics. Close co- Successfully operation with strives to leading shorten equipment installation and suppliers, commissioning guaranteeing times to a seamless minimum to integration and enhance optimal profits/savings solutions for to owner. every project.
  6. 6. * Specializing in power plants that run on: • Natural Gas The company oversees the • Diesel design and execution of all • HFO company projects through its • Hydropower engineering teams. • Diesel-Gas generating sets • Biomass, Biofuels, & Landfill-Gas. Telemenias goal is to design power plants that are: Specializes in unique and • Simple to build, maintain, & customized projects that are operate. tailored to meet clients • Equipped with the latest specifications and requirements. technologies and improved controls, resulting in a maximum efficiency power plant.
  7. 7. * A CASE HISTORY: Alenakiri, Libreville, Gabon, West Africa 2 x 35 MW Operated on Natural Gas or Diesel
  8. 8. * 2 x 35MW power plant in Alenakiri, near Libreville, Gabon. 4 x 17.5 MW MAN dual fuel engines. 90kV substation Gas or Diesel operated. Telemenia won the international tenders competing against major international EPC contractors Project included access road, full power plant construction and substation. Telemenia committed itself to extensive social involvement - schools, housing and medical care for the local community. Following on the success of Alenakiri, Telemenia won a new international tender and is currently building a 105MW plant in Port Gentile, Gabon.
  9. 9. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Site Mobilization & Soil Investigation Tests Feb 2010
  10. 10. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 * Via Dolorosa Face Lift: Part 1: Soon to May 2010 Apr 2010 Mar 2010 Feb 2010 support transport of 4 huge engines
  11. 11. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Confirming Drill Coordinates
  12. 12. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Site Management Team Review Design Feb 2010
  13. 13. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 * Commencement of works for access Apr 2010 Mar 2010 Feb 2010 road to site
  14. 14. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 * The First Containers & Work Vehicles May 2010 Apr 2010 Mar 2010 Feb 2010 Arrive on Site
  15. 15. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Access road – work in progress Mar 2010 Feb 2010
  16. 16. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * First Concrete Pour for Power House
  17. 17. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Concrete works into the night
  18. 18. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Concrete cast for the power house
  19. 19. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Concrete works: walls, tank bases, channel Feb 2010
  20. 20. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Drill team on site – Pills for the building foundations Feb 2010
  21. 21. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * One of 190 containers sent to Gabon
  22. 22. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 One of the main diesel fuel tanks Feb 2010 installation works
  23. 23. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Access road – the work continues
  24. 24. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Positioning one of the tanks
  25. 25. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Concrete trench and caisson drilling
  26. 26. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Power house concrete works in full swing
  27. 27. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Power house concrete works in full swing
  28. 28. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Capping monster tanks
  29. 29. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Pouring concrete for cable channels
  30. 30. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Commencement of metal works
  31. 31. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Raising the power house steel structure
  32. 32. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Outfitting the cable trench with trays
  33. 33. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Casting walls for power plant office block
  34. 34. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Power house erection works
  35. 35. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Office building construction in full swing
  36. 36. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Fastening the ventilation louvres
  37. 37. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Concrete bases for the substation yard
  38. 38. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Tying down the roof beams
  39. 39. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * The FAT in St. Nazaire, France
  40. 40. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Main power house ready for stacks installation Feb 2010
  41. 41. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Engines & transformers ready for shipme
  42. 42. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Overland transport from LBV port to Site
  43. 43. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Driving through the village
  44. 44. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Clearing overhead electrical lines
  45. 45. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Village attraction: the engine low-loader mounts the nearly-completed access road Feb 2010
  46. 46. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Transformer arrive to Site
  47. 47. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * The first engine enters the building
  48. 48. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 2nd engine ready to enter the power house
  49. 49. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Both MAN engines in the Power House!
  50. 50. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Maneuvering the exhaust stacks into place
  51. 51. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 45 MVA Transformer fully installed
  52. 52. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Radiator Placement
  53. 53. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Stage One Radiator Array
  54. 54. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Finishing works underway in office block
  55. 55. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Control room floating floor & drop ceiling
  56. 56. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Minister of Energy & his CEO visit site
  57. 57. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Engine gantries & stacks connected
  58. 58. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Fire-fighting piping & platforms
  59. 59. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Kilometers of piping
  60. 60. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Progress in the control room
  61. 61. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Control Room: programming & cabling
  62. 62. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Control Room: End of Stage 1 is at hand!
  63. 63. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Power house main entrance
  64. 64. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Alternator connection
  65. 65. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Stage 1, 35 MW, is complete!
  66. 66. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Presidential visit to Site
  67. 67. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Stage 2 commencement
  68. 68. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Expanding the power house for Stage 2
  69. 69. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Four exhaust stacks in place
  70. 70. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Prepping for Stage 2 engines’ arrival
  71. 71. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 MV & LV room
  72. 72. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * More equipment to expedite pace of work Feb 2010
  73. 73. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 Piping & electrical work at advanced stages
  74. 74. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * Non-stop welding works
  75. 75. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 Feb 2010 * 45 MVA Trafos for Stage 2 Arrive
  76. 76. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Aerial view of the nearly-complete Libreville 2 x 35 MW Power Plant Feb 2010
  77. 77. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * The engines experts from MAN at site Mar 2010 Feb 2010
  78. 78. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Connecting intake air duct to the Engines Mar 2010 Feb 2010
  79. 79. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * A little touch of Africa Mar 2010 Feb 2010
  80. 80. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Eng. Aaron Gal at FAT in St. Nazaire, France Mar 2010 Feb 2010
  81. 81. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 * Lowering one of two 305 ton engines onto Apr 2010 Mar 2010 Feb 2010 the special shipping vessel
  82. 82. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 * Engines below decks, remaining equipment Apr 2010 Mar 2010 being placed for voyage to Gabon Feb 2010
  83. 83. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Testing the fire fighting systems Mar 2010 Feb 2010
  84. 84. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Lowering units into Stage 2’s radiator array Mar 2010 Feb 2010
  85. 85. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Power House: Inserting Stage 2’s Engines Mar 2010 Feb 2010
  86. 86. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 Mar 2010 * Power House: alternator positioning work Feb 2010
  87. 87. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * All 4 Engines in the House! Mar 2010 Feb 2010
  88. 88. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Finishing Works Mar 2010 Feb 2010
  89. 89. Apr 2012 Mar 2012 Feb 2012 Jan 2012S t a g e Tw o Dec 2011 Nov 2011 Oct 2011 Sep 2011 Aug 2011 Jul 2011 Jun 2011 May 2011 Apr 2011 Mar 2011 Feb 2011 Jan 2011 Dec 2010 Nov 2010Stage One Oct 2010 Sep 2010 Aug 2010 Jul 2010 Jun 2010 May 2010 Apr 2010 * Kitting out the Control Room Mar 2010 Feb 2010
  90. 90. *

×