This webinar presents the probabilistic approach to reliability management developed by the ongoing collaborative project GARPUR (www.garpur-project.eu) involving the TSOs of 7 European countries.
The reliability management criteria and approach (RMAC) developed and tested by GARPUR aims at a better balance between reliability and cost, by taking into account the increasing uncertainty of generation due to intermittent renewable energy, but also the opportunities brought by demand side management and storage.
The webinar will present the methodology developed, its application to real time operation, and the overall benefits of such probabilistic approach. A 2nd webinar will be planned to present the test results of applying GARPUR methodology to asset management and system development.
2. GARPUR/ISGAN ACADEMY
Webinar 1
2
23 May 2017
Introduction:
Webinar outline,
GARPUR project and philosophy
Oddbjørn Gjerde
Coordinator
SINTEF Energi AS
1 2 3 54
3. 3
1. Introduction to GARPUR project &
philosophy
2. GARPUR methodology for Reliability
Management Approach & Criteria
(RMAC)
3. Application of RMAC to real time
operation: case study at Landsnet
4. Conclusions
5. Questions
Outline of the webinar
Oddbjørn Gjerde
SINTEF Energi AS
Louis Wehenkel
Université de Liège
Samuel Perkin
LANDSNET
Louis Wehenkel
Université de Liège
1 2 3 54
4. Introduction
4
Network Code on Operational Security:
(N-1)-Criterion means the rule according to which elements remaining in
operation [ ] after a Contingency [ ] must be capable of accommodating the new
operational situation without violating Operational Security Limits
Present practice: N-1
N-1 has been the cornerstone of TSO reliability
management
with N-1 there is no need to quantify the
consequences since they are not accepted
N-1 will stay one of the cornerstones of TSO
reliability management
But…
1 2 3 54
5. Introduction
5
N-1 limitations
Does not consider probability of outages
Does not distinguish situations that are
– Not N-1 secure (N-0, N-½ …) or,
– N-1 secure (but still many options)
Difficult/impossible to handle the comprehensive uncertainties in a
large interconnected system
Complexity of the pan-European system, increasing probability of
multiple outages
Volatility caused by RES increasingly necessitates probabilistic
approaches
Hard to handle new devices that enable fast corrective actions
1 2 3 54
6. Introduction
6
Purpose of GARPUR
Balancing reliability and costs:
Reducing socio economic costs and still maintaining reliability of supply.
Therefore GARPUR aims to:
Design, develop, and assess new probabilistic reliability criteria
Evaluate their practical use with more focus on social welfare effects
GARPUR covers the three time horizons:
1 2 3 54
Power system
operation
Asset
management
System
development
10. GARPUR/ISGAN ACADEMY
Webinar 1
10
23 May 2017
GARPUR Methodology
for probabilistic Reliability Management
Louis Wehenkel
GARPUR Scientific Advisor
University of Liège
1 2 3 54
11. 11
Weaknesses of the N-1 criterion
GARPUR proposal in a nutshell
Implementation in practice
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
Outline
12. 12
Weaknesses of the N-1 criterion
GARPUR proposal in a nutshell
Implementation in practice
Outline
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
13. 13
(e.g. in Real-Time operation)
Contingencies explicitly covered:
– all N-1 events (+ possibly some common mode N-k events)
Acceptable contingency response:
– simulated response within steady-state (and stability) limits, for
each and every contingency in the list.
Economic objective:
– Minimize operating costs: sum of TSOs preventive & corrective
control costs and congestion costs
The N-1 criterion
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
14. 14
Overall socio-economic impact: a cost function summing
up two terms (to be minimized):
The Total Risk (for end-users) = the expected socio-
economic costs of service interruptions, as implied by
all possible N-k contingencies and all possible failure
modes that could occur
The Operating Costs = all direct costs of TSO decisions
minus the induced electricity market surpluses
Socio-economic analysis of alternative reliability criteria
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
15. 15
Socio-economic impact of covering more or less
contingencies in real-time operation
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
N-0 N-2N-1N-1/2 …
€
CC
Operating
Cost
Total Risk
Overall socio-economic impact
CC = set of contingencies covered in real-time operation, by minimizing OC under the constraint of
acceptable response to each one of these contingencies
16. Facing a sudden drop in RES output:
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
N-1 clearly too pessimistic !
N-0 N-2N-1N-1/2 …
€
CC
Operating
Cost
Total Risk
Overall SEI
17. Facing harsh weather conditions:
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
N-0 N-2N-1N-1/2 …
€
CC
Operating
Cost
Total Risk
Overall SEI
N-1 too optimistic!
18. Summary
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
N-1 most often not optimal !!!
N-1.5?N-1?N-1/2?
€
CC
19. 19
Weaknesses of the N-1 criterion
GARPUR proposal in a nutshell
Implementation in practice
Outline
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
20. GARPUR proposal in a nutshell
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
In order to decide which subset of contingencies should be
covered, we dynamically adapt to information about
Socio-economic costs of service interruptions...
Corrective control failure modes…
Probabilities… of contingencies and failure modes
To formalize this, we formulate a stochastic
optimization problem called the GARPUR RMAC
21. The 4 ingredients of the GARPUR RMAC
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
A reliability target
A socio-economic objective function
A discarding principle
A relaxation principle
+ Probabilities of threats, and sets of candidate preventive and
corrective control actions used for reliability management
22. 22
Weaknesses of the N-1 criterion
GARPUR proposal in a nutshell
Implementation in practice
Outline
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
23. Implementation in practice
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
Grid development / Asset management / System operation
24. Declination from Real-Time to Long-Term
GARPUR methodology for Probabilistic Reliability Management1 2 3 54
We specify for each context
− The types of candidate decisions available
− The socio-economic objective function
− The reliability target
− The discarding/relaxation principles
We ensure coherency among different contexts
− Longer-term decisions are chosen to enable the
reachability of shorter-term reliability targets
25. GARPUR/ISGAN ACADEMY
Webinar 1
25
23 May 2017
Application of RMAC to real time operation:
case study at Landsnet
Samuel Perkin
Landsnet
1 2 3 54
26. 26
Outline
Moving from N-1 to Probabilistic Reliability Assessment
on the Icelandic system (10 minutes)
Pilot test overview (2 minutes)
Initial pilot test results (3 minutes)
Application of RMAC to real time operation1 2 3 54
29. 29
Pilot Test Grid Model
Buses: 85
Branches: 107
Generators: 71
The Icelandic System
Application of RMAC to real time operation1 2 3 54
30. 30
0 20 40 60 80 100 120 140 160
Contingency Number
LostLoad
MaxVm
MinVm
BranchLimsST
BranchLimsLT
Post-Contingency Operational Limit Compliance
Case: heavy system load &
common system topologyFrom N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
31. 31
0 20 40 60 80 100 120 140 160
Contingency Number
LostLoad
MaxVm
MinVm
BranchLimsST
BranchLimsLT
Post-Contingency Operational Limit Compliance
0 20 40 60 80 100 120 140 160
Contingency Number
LostLoad
MaxVm
MinVm
BranchLimsST
BranchLimsLT
Post-Control Operational Limit Compliance
Case: heavy system load &
common system topology
Apply Corrective Control Actions
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Corrective control resolves many short-term voltage issues...
32. Compare severity of contingencies based on relative lost load
=> 32 single component contingencies result in some loss of load
32
0 20 40 60 80 100 120 140 160
Contingency Number
0%
1%
2%
3%
4%
5%
6%
Lost Load per Contingency (% of system)
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Lost
Load
33. 33
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Lost
Load
ENSTo convert lost load to Energy Not Served (ENS) we need a System
Restoration Model that predicts the outage duration per contingency
34. To convert lost load to Energy Not Served (ENS) we need a System
Restoration Model that predicts the outage duration per contingency
34
Lack of data for large contingencies, so must use heuristic model
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Lost
Load
ENS
35. Can now compare contingencies based on ENS.
The heuristic model doesn‘t change the relative order of contingencies.
0 20 40 60 80 100 120 140 160
Contingency Number
0
20
40
60
80
100
120
ENS per Contingency (MWh)
35
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Lost
Load
ENS
36. 36
10 20 30 40 50 60 70
Demand Node
100%
80%
60%
40%
20%
0%
Demand nodes divided by consumer types
PublicServices
Commerce
Residential
OtherIndustry
AlSmelting
Agriculture
Other
AlFactory
FeSiSmelting
Utilities
Application of RMAC to real time operation1 2 3 54
From N-1 to GARPUR
Lost
Load
ENS
Int.
Cost
To convert ENS into interruption costs, need to know affected
consumer groups and their Value of Lost Load over time
37. To convert ENS into interruption costs, need to know affected
consumer groups and their Value of Lost Load over time
37
0 1 2 3 4 5 6 7 8
Outage Duration (hours)
0
2000
4000
6000
8000
10000
12000
14000
Value of Lost Load per Consumer Type (ISK/kWh)
PublicServices
Commerce
Residential
OtherIndustry
AlSmelting
Agriculture
Other
AlFactory
FeSiSmelting
Utilities
Application of RMAC to real time operation1 2 3 54
From N-1 to GARPUR
Lost
Load
ENS
Int.
Cost
38. To convert ENS into interruption costs, need to know affected
consumer groups and their Value of Lost Load over time
38
Application of RMAC to real time operation1 2 3 54
From N-1 to GARPUR
0 20 40 60 80 100 120 140 160
Contingency Number
0
10
20
30
40
Interruption Cost per Contingency (Million ISK)
Lost
Load
ENS
Int.
Cost
39. 39
𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹 = 𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪 × 𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷 𝑷𝑷
Application of RMAC to real time operation1 2 3 54
From N-1 to GARPUR
Lost
Load
ENS
Int.
Cost
Risk
Conversion from Interruption Costs to Risk requires the following
fundamental equation:
40. 40
Conversion from Interruption Costs to Risk requires the following
fundamental equation:
𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹 = 𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪𝑪 × 𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷 𝑷𝑷
Application of RMAC to real time operation1 2 3 54
From N-1 to GARPUR
0 20 40 60 80 100 120 140 160
Contingency Number
0%
0.01%
0.02%
0.03%
0.04%
Hourly contingency probability (% per hour)
Lost
Load
ENS
Int.
Cost
Risk
41. Comparing contingencies by Risk results in different priorities than if
sorting by Interruption Costs or ENS/Lost Load
41
0 20 40 60 80 100 120 140 160
Contingency Number
0
500
1000
1500
2000
Risk per Contingency (expected ISK/hour)
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Lost
Load
ENS
Int.
Cost
Risk
42. 42
The three main aggregate indicators in the GARPUR method are:
Assessed Risk
Residual Risk
Probability of an acceptable system state
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Lost
Load
ENS
Int.
Cost
Risk
Rel.
Indic.
43. 43
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
Assessed Risk is simply the sum of each assessed contingency‘s risk
𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨 𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹 = 9422 𝐼𝐼𝐼𝐼 𝐼𝐼
The three main aggregate indicators in the GARPUR method are:
Assessed Risk
Residual Risk
Probability of an acceptable system state
Lost
Load
ENS
Int.
Cost
Risk
Rel.
Indic.
44. 44
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 = 9422 𝐼𝐼𝐼𝐼 𝐼𝐼
𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹 = 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 × 𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐
The three main aggregate indicators in the GARPUR method are:
Assessed Risk
Residual Risk
Probability of an acceptable system state
Lost
Load
ENS
Int.
Cost
Risk
Rel.
Indic.
Discarded probability is the probability of an unassessed event
occurring (i.e. N-2 or worse)
Residual Risk is the product of discarded probability and the worst
case consequences (equivalent to the total loss of the system)
45. 45
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 = 9422 𝐼𝐼𝐼𝐼 𝐼𝐼
𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹𝑹𝑹𝑹𝑹 𝑹𝑹 = 0.0013% × 5223 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝐼𝐼𝐼𝐼 𝐼𝐼 = 68 000 𝐼𝐼𝐼𝐼 𝐼𝐼
The three main aggregate indicators in the GARPUR method are:
Assessed Risk
Residual Risk
Probability of an acceptable system state
Lost
Load
ENS
Int.
Cost
Risk
Rel.
Indic.
Residual Risk is the product of discarded probability and the worst
case consequences (equivalent to the total loss of the system)
Discarded probability is the probability of an unassessed event
occurring (i.e. N-2 or worse)
46. 0 20 40 60 80 100 120 140 160
Contingency Number
LostLoad
MaxVm
MinVm
BranchLimsST
BranchLimsLT
Post-Control Operational Limit Compliance
46
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 = 9422 𝐼𝐼𝐼𝐼 𝐼𝐼
The three main aggregate indicators in the GARPUR method are:
Assessed Risk
Residual Risk
Probability of an acceptable system state
𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 = 68 000 𝐼𝐼𝐼𝐼 𝐼𝐼
First we define an acceptable system state as one that complies with
operational limits (referred to in GARPUR as acceptability constraints)
Lost
Load
ENS
Int.
Cost
Risk
Rel.
Indic.
47. Lost
Load
ENS
Int.
Cost
Risk
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
P(Acceptable state) = P(No Fault) + P(Acceptable Contingencies)
0 20 40 60 80 100 120 140 160
Contingency Number
LostLoad
MaxVm
MinVm
BranchLimsST
BranchLimsLT
Post-Control Operational Limit Compliance
Rel.
Indic.
𝑷𝑷 𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨 𝑺𝑺𝑺𝑺𝑺𝑺𝑺𝑺𝑺𝑺 = 99.48% + 0.075%
𝑷𝑷 𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨𝑨 𝑺𝑺𝑺𝑺𝑺𝑺𝑺𝑺𝑺𝑺 = 99.555%
The three main aggregate indicators in the GARPUR method are:
Assessed Risk
Residual Risk
Probability of an acceptable system state
𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 = 9422 𝐼𝐼𝐼𝐼 𝐼𝐼
𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 = 68 000 𝐼𝐼𝐼𝐼 𝐼𝐼
48. 48
From N-1 to GARPUR
Application of RMAC to real time operation1 2 3 54
1) Variable failure rates (dependent on weather and other threats)
2) Variable contingency lists (dependent upon the above)
3) Use real-time system state data
4) Assessment across multiple scenarios (of load and generation)
5) Assessment using full socio-economic impact assessment (SEIA)
6) Finding actions that optimise SEIA while maintaining some probability
of an acceptable system state.
So far we have achieved a probabilistic N-1 reliability assessment.
What is missing in order to acheive the GARPUR approach?
49. 49
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
1) Variable failure rates (dependent on weather and other threats)
2) Variable contingency lists (dependent upon the above)
3) Use real-time system state data
4) Assessment across multiple scenarios (of load and generation)
5) Assessment using full socio-economic impact assessment (SEIA)
6) Finding actions that optimise SEIA while maintaining some probability
of an acceptable system state.
At present we have achieved the green items and are yet to implement
those in red
So far we have achieved a probabilistic N-1 reliability assessment.
What is missing in order to acheive the GARPUR approach?
50. 50
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Basic inputs:
System state updates every
minute
Weather data updates every
20 minutes
Residual risk target equal to
68 000 ISK (N-1 equivalent)
Contingency list limited to
5000 or fewer to keep
runtime below 2 minutes
52. 52
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Live outputs
Risk and acceptability are clearly sensitive to weather
Step in risk between 20:00 and 06:00 caused by variation in economic model
53. 53
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Live outputs
Contingency set is most often smaller than the N-1 set, but increases
considerably during periods of bad weather
54. 54
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Live outputs
0: Anomaly
1: Noteworthy
Disturbance
2: Extensive
Incidents
3: Widespread or
Major Incident
For reference: ENTSOe (2012) Incidents Classification Scale Guidelines
Class Definitions:
55. 55
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Live outputs
Displaying live weather data (used by the model) on dashboard to improve
understanding of the pilot test outputs
56. 56
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Live outputs
Initial attempts to ‚dig‘ into the outputs provided only minor insights, and
were difficult to read at a glance
57. 57
LANDSNET PILOT TEST
Application of RMAC to real time operation1 2 3 54
Risk Map:
Same information as on
previous slide
Captures temporal aspect
(paths showing prior changes)
Simple to compare
contingencies
Consistent & unique colours
allows for quick interpretation
58. 58
Closing remarks
Application of RMAC to real time operation1 2 3 54
Showed the path from N-1 to probabilistic risk assessment
Landsnet pilot test shows that the approach is feasible with
presently available data
Future work required to upgrade the models to capture
dynamic stability, system restoration, and to move from
assessment to control.
59. GARPUR/ISGAN ACADEMY
Webinar 1
59
23 May 2017
Conclusion:
Benefits of the GARPUR Methodology
for probabilistic Reliability Management
Louis Wehenkel
GARPUR Scientific Advisor
University of Liège
1 2 3 54
60. 60
Dynamic contingency selection
Coherent decision making among timeframes
New approaches for reliability assessment and
control
Conclusion: benefits of GARPUR methodology1 2 3 54
Main benefits
61. 61
A theoretically founded principle for choosing the
subset of N-k contingencies that have to the covered by
preventive and corrective control actions
Its implementation will support operators to adjust
their perception of the risk and determine a strategy to
manage reliability
Overall, the principle will help to optimize the socio-
economic impact of the reliability management
decisions taken by TSOs
Conclusion: benefits of GARPUR methodology1 2 3 54
Dynamic contingency selection
62. 62
We show how to take into account the short-term
reliability management approach when carrying out
longer-term studies
Conclusion: benefits of GARPUR methodology1 2 3 54
Coherent decision-making from planning to operation
63. 63
Reliability assessment, from long-term to real-time
Reliability control for real-time and mid-term
A simulation framework to study off-line the impact of
moving from N-1 to the probabilistic RMAC
Conclusion: benefits of GARPUR methodology1 2 3 54
New tools and methods
64. 64
Simulates the operation of the power system submitted to
a given set of external event, by allowing one to plug in the
RMAC the operator would use
Allows to compare the outcome of operating the system
while using different RMACs
Is used to compare the N-1 RMAC with the GARPUR RMAC
Comparison is based on socio-economic impact, and its
decomposition in several ‘cost’ terms
Conclusion: benefits of GARPUR methodology1 2 3 54
Teaser 1 for next Webinar, Fall 2017
GARPUR Quanification Platform
65. 65
Testing the use of the GQP in realistic conditions
Studying the outcomes of the probabilistic
RMAC when used in long-term grid development
studies
Conclusion: benefits of GARPUR methodology1 2 3 54
Teaser 2 for next Webinar, Fall 2017
The other pilots tests
66. 66
Q & A session1 2 3 54
http://www.garpur-project.eu/