1. RPA Project- Status As of Week Ending
September 21, 2022
Overall Project
Actual Progress
Sign-Off the PDD document for GOSI process
Sign-Off the SDD document for GOSI process
Sign-Off the PDD document for Scheduling Batches Processing
Sign-Off the PDD document for Trigger Batches Processing
Finalize walkthrough for Customer Update Process PDD with business owner and it’s
under his review.
Deliver Mission Payment Process PDD and it’s under review.
Gathering Requirements Sessions for SCM Processes (PR Analysis Form Process,
Monitoring Issue Plan Process, Converting PR to RFQ process and Supplier Registration
Process)
Communicate with Finance Dept. to prepare RPA Demo session for CFO and his
department
Completed Activities for week of 21-Sep-22
Follow up with the business owners to sign-off PDD (PR Analysis Form Process, Mission
Payment Process and Customer Update Process)
Follow up with SCM to arrange for gathering remaining processes.
Follow up with Finance Department for awareness session meeting about RPA
Follow up with information Security for gathering session.
Internal testing with GOSI process.
Internal testing with Mission Payment Process.
Internal testing with Scheduling Batches Processing.
Planned Activities for week of 29-Sep-22
Task
#
Tasks Business Owner PDD SDD Dev.
1
GOSI Process Hussam A. Alsabr –
HC
%100 %100 %85
2 Scheduling Batches Processing
Nasser S. Alharbi –
DC
%100 %100 %85
3 Trigger Batches Processing
Nasser S. Alharbi –
DC
%100 %80 %50
4 WebLogic Monitoring
Abdulaziz Almuhana
– CCB IT
%100 %0 %0
5 Customer Update Process
Khloud Shaker –
Customer Exp.
%100 %100 %50
6 Mission Payment Process Jacob – Payroll %100 %50 %50
7
Inventory Utilization - PR Analysis
Form Process
Wayne Steel – SCM %50 %0 %0
8
Inventory Utilization -Monitoring
Issue Plan Process
Wayne Steel – SCM %15 %0 %0
9
Validation & extraction of
registration
Wayne Steel – SCM %5 %0 %0
10
Automation of bank guarantees &
RFP bidding fees
Wayne Steel - SCM %5 %0 %0
15%
Deliverables Status
Overall Project
Planned Progress
15%
Editor's Notes
- Tool Integration UCMDB + PSM + Jira + SSO 25%
Tool data load 70 strategy + validation
Tool implementation 80 reporting
Framework missing the view point
Charter missing processes