Pcc green comm_jan_10_13

166 views

Published on

  • Be the first to comment

  • Be the first to like this

Pcc green comm_jan_10_13

  1. 1. Pinehurst Country ClubGreen Committee Meeting January 10, 2013
  2. 2. Agenda Chairperson Report – Erich Tiepel  Approval of minutes General Manager’s Report – Loren Pippin Grounds Report – Steve Sarro  Driving Range Status  Report on Safety Nets  Discussion on Integrated Plan  Course Preview  Tree Care  Winter Care for Trees  Update on DuPont Imprelis  Tee boxes  Winter/Spring Schedule  Sand replacement in bunkers  Winter/Spring Schedule  Water Update  Harriman Construction  Water Supply Acquisition Status – Paul Motzkus  Outlook on 2013  Water  Spring/Summer schedule for turf maintenance  Update on Native Area Plans  New Business
  3. 3. Tanner Consulting Hired to create ball trajectory study and recommend options for improving the safety and overall health of the driving range. Improvements take into account variables such as elevation, club speed, temperature, etc. Developed four options for improvements. Combinations of options can be implemented as well.
  4. 4. Tree Care Pruning will begin in January Seeking arborist hazardous opinion on cottonwood fate on #7 green. Removing dead trees on 2, 14, 15 Imprelis Update
  5. 5. Tee Boxes Fall of 2012: forward tees on Pfluger #2 & #6. Increased tee space, due to open in spring of 2013.
  6. 6. Maxwell 5 middle tee
  7. 7. Maxwell 8 middle tee
  8. 8. Maxwell 15 back tee
  9. 9. Maxwell 17 middle and forward tee
  10. 10. 18 Fairway Bunker Management Goal: Perform the model bunker for Pinehurst CC and future bunker renovations. Removed contaminated sand Replace drain lines Re-sod edges Install irrigation Apply liner to prevent future contamination Install sand
  11. 11. HarrimanConstructionCompleted outletstructure was pouredincorrectly the first timeand is the reason fordelays.The dam inspector waspleased with the damoverall this week.Denver Water hopes tobegin filling byFebruary.
  12. 12. HarrimanConstructionThese gauges manageflow for the JohnsonLateral and eventuallythe Ft. Logan Ditch.
  13. 13. HarrimanConstructionBear Creek is currentlyrunning near 10 cfs.Since November1st, Bowles Reservoirand Soda Lakes havebeen filling.Once Harriman isready to fill, it has firstpriority to fill.
  14. 14. 2013 TurfMaintenance1. Identify more areas ofthe course that cansustain lowermaintenance inputs2. Aesthetically pleasingareas out of play3. Lesswater, mowing, fertilizer4. Over seed withnative or droughttolerant turfgrassspecies
  15. 15. Pfluger
  16. 16. Maxwell
  17. 17. Other Spring Projects 3 Dam Repairs and paving Johnson Lateral Cleaning Irrigation upgrades Flower Beds aroundbio bathrooms Increase gardens
  18. 18. Future Dates  Green Committee Dates: Thursday, February 14th 2013 at 4pm Thursday, March 14th 2013 at 4pm*

×