CORRIDOR DU PONT CHAMPLAINBILAN DES TRAVAUX 2011POUR AUJOURD’HUI ET DEMAIN
PROGRAMMED’ENTRETIEN MAJEURPONT CHAMPLAIN212 M $ SUR 10 ANS
PROGRAMMED’ENTRETIEN MAJEURASSURER LA SÉCURITÉ
PROGRAMME EN 2011SUR LE PONT CHAMPLAIN10 CONTRATS33,3 M $ / 40 ENTREPRISES
CORRIDOR DU PONT CHAMPLAINCOORDINATION DES TRAVAUXUN GRAND DÉFI
INAUGURATION - 19625 500 USAGERS / JOUREMPRUNTENT LE PONT
INAUGURATION - 1962CIRCULATION SUR LE PONTPREMIÈRE JOURNÉE
AUJOURD’HUI - 2011160 000 USAGERS / JOUR14 400 CAMIONS / JOURTRAVERSENT LE PONT
DIRECTION MONTRÉAL - MATIN400 AUTOBUS SUR LE PONT CHAMPLAIN – 20 000 USAGERS       MÉTRO DE LONGUEUIL – 16 500 USAGERS
THÈMES ABORDÉS1.   TRAVAUX RÉALISÉS - 20112.   STRATÉGIES DÉPLOYÉES3.   PROJETS À VENIR - 20124.   DISCUSSION
1. TRAVAUX RÉALISÉS - 2011CORRIDOR DU PONT CHAMPLAIN2011
REVIEW OF WORK IN 2011PROGRESS & ACHIEVEMENTSFEDERAL SECTION OF THE HIGHWAY 15FEDERAL SECTION OF THE BONAVENTURE EXPRESSWA...
LACHINE          CANAL            BROSSARDATWATER
BONAVENTURE     EXPRESSWAYHIGHWAY 15             CHAMPLAIN             BRIDGE
BONAVENTURE EXPRESSWAYMAINTENANCE WORK – $ 7.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING
BONAVENTURE EXPRESSWAYMAINTENANCE WORK – $ 7.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING•   645 m² of deck repairs ...
BONAVENTURE EXPRESSWAYMAINTENANCE WORKREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING
HIGHWAY 15 (EAST OVERPASS & L’ÎLE-DES-SOEURS BRIDGE)MAINTENANCE WORK – $ 4.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARK...
HIGHWAY 15 (EAST OVERPASS & L’ÎLE-DES-SOEURS BRIDGE)MAINTENANCE WORK – $ 4.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARK...
HIGHWAY 15 (EAST OVERPASS & L’ÎLE-DES-SOEURS BRIDGE)MAINTENANCE WORK – $ 4.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARK...
CHAMPLAIN BRIDGEMAJOR MAINTENANCE PROGRAM – $ 33.3 MIMPORTANT WORK UNDER & ON THE BRIDGE
PROGRAMME D’ENTRETIENDU PONT CHAMPLAIN212 M$ SUR 10 ANS10 MOIS SUR 12 PAR ANNÉE75 À 125 OUVRIERS/SEMAINE40 À 50 INGÉNIEURS...
8 FINS DE SEMAINEFERMETURE D’UNE DIRECTIONTRAVAUX MAJEURS
8 FINS DE SEMAINEFERMETURE D’UNE DIRECTIONTRAVAUX MAJEURS                     X                     X                     X
8 FINS DE SEMAINEFERMETURE D’UNE DIRECTIONTRAVAUX MAJEURS                     X                     X                     X
2,75 KM REPAVÉS EN 2011 SUR LE PONT CHAMPLAIN
5 JOINTS DE DILATATION REMPLACÉS EN 2011
BRIS DE JOINTS DE DILATATION DEPUIS 2000         voie 6        voie 5        voie 4        voie 3       voie 2       voie ...
13 POUTRESDE RIVE ONTREÇU DE LAPOST-TENSION
RÉFECTIONDE 5 FÛTS
RÉFECTION DE4 CHEVÊTRES
POST-TENSIONDE 7 CHEVÊTRES
PROCÉDÉSINNOVATEURS
4 ARBALÈTESINSTALLÉES
PROGRAMME D’ENTRETIEN MAJEURBILAN DES TRAVAUX EN 2011Ajout de post-tensionextérieureaux poutresde rive         Réfection  ...
75%DU PONTREPAVÉDEPUIS 20092011•   40 000 m² de superficie de dalle pavée•   6 800 m² de membrane détanchéité•   4 500 ton...
+BRETELLESD’ACCÈS ET DESORTIE DU CÔTÉDE LA RIVE-SUD
2. STRATÉGIES DÉPLOYÉESCORRIDOR DU PONT CHAMPLAINASSURER LA SÉCURITÉGuy Mailhot, ing., M. Eng.Directeur principal, Ingénie...
GESTION EFFICACE DU PONT ET DE SON ENTRETIENMESURES MISES EN PLACE           1. INSPECTION DE L’OUVRAGE               ET S...
GESTION EFFICACE DU PONT ET DE SON ENTRETIENSAVOIR CIBLER LES PRIORITÉS
GESTION EFFICACE DU PONT ET DE SON ENTRETIENINNOVER ET PROPOSER DES MESURES IN HOUSE
GESTION EFFICACE DU PONT ET DE SON ENTRETIENINNOVER ET PROPOSER DES MESURES IN HOUSE Diaphragme                           ...
GESTION EFFICACE DU PONT ET DE SON ENTRETIENINNOVER ET PROPOSER DES MESURES IN HOUSESYSTÈME DE RENFORT AU MOYEN D’ARBALÈTES
GESTION EFFICACE DE L’ENTRETIEN DU PONTSUIVRE LE COMPORTEMENT DU PONT EN CONTINUECAPTEURS DE SUIVI - 66
INTERVENTION EN DÉVELOPPEMENT : INTER-DALLESECTION DE LA DALLE ENTRE DEUX POUTRES
CONFORTEMENT EN PLACE ACTUELLEMENTINSTALLATION DE SUPPORT AUX ZONES ENDOMMAGÉES
INTERVENTION EN DÉVELOPPEMENT : INTER-DALLEPOST-TENSION ET SUPPORT DE LA DALLE
3. PROJETS À VENIR - 2012CORRIDOR DU PONT CHAMPLAINPOURSUIVRE DANS LA MÊME VOIEGlen P. Carlin, ing.Directeur général
POURSUITEDU PROGRAMMED’ENTRETIENMAJEUR – 34 M $
JOINTS DE DILATATION
CHAUSSÉE ET PAVAGE
PIERS REPAIRS
EDGE BEAMS
ENVIRONNEMENTMISE EN MARCHEPROJET SECTEUR OUEST
MESURES MISE EN PLACE SECTEUR OUESTPROJET EN MARCHE – FINANCEMENT PASCF – 24 M $
MESURES MISE EN PLACE SECTEUR OUESTPROJET EN MARCHE – FINANCEMENT PASCF – 24 M $   JMUR DE CONFINEMENT    ET USINE DE TRAI...
TRAVAUX RÉALISÉS ET PLANIFIÉSCORRIDOR DU PONT CHAMPLAINÉVALUATION BUDGÉTAIRE                        2011         2012Pont ...
SUIVIDES TRAVAUXFOLLOW-UPON THE WORKS2012- BRIEFING TECHNIQUE : PRÉSENTATION DE LA PLANIFICATION 2012- TWITTER : @PONTCHAM...
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Présentation   bilan des travaux 2011 - 15 décembre - pjcci - slideshare
Upcoming SlideShare
Loading in …5
×

Présentation bilan des travaux 2011 - 15 décembre - pjcci - slideshare

5,851 views

Published on

  • Be the first to comment

Présentation bilan des travaux 2011 - 15 décembre - pjcci - slideshare

  1. 1. CORRIDOR DU PONT CHAMPLAINBILAN DES TRAVAUX 2011POUR AUJOURD’HUI ET DEMAIN
  2. 2. PROGRAMMED’ENTRETIEN MAJEURPONT CHAMPLAIN212 M $ SUR 10 ANS
  3. 3. PROGRAMMED’ENTRETIEN MAJEURASSURER LA SÉCURITÉ
  4. 4. PROGRAMME EN 2011SUR LE PONT CHAMPLAIN10 CONTRATS33,3 M $ / 40 ENTREPRISES
  5. 5. CORRIDOR DU PONT CHAMPLAINCOORDINATION DES TRAVAUXUN GRAND DÉFI
  6. 6. INAUGURATION - 19625 500 USAGERS / JOUREMPRUNTENT LE PONT
  7. 7. INAUGURATION - 1962CIRCULATION SUR LE PONTPREMIÈRE JOURNÉE
  8. 8. AUJOURD’HUI - 2011160 000 USAGERS / JOUR14 400 CAMIONS / JOURTRAVERSENT LE PONT
  9. 9. DIRECTION MONTRÉAL - MATIN400 AUTOBUS SUR LE PONT CHAMPLAIN – 20 000 USAGERS MÉTRO DE LONGUEUIL – 16 500 USAGERS
  10. 10. THÈMES ABORDÉS1. TRAVAUX RÉALISÉS - 20112. STRATÉGIES DÉPLOYÉES3. PROJETS À VENIR - 20124. DISCUSSION
  11. 11. 1. TRAVAUX RÉALISÉS - 2011CORRIDOR DU PONT CHAMPLAIN2011
  12. 12. REVIEW OF WORK IN 2011PROGRESS & ACHIEVEMENTSFEDERAL SECTION OF THE HIGHWAY 15FEDERAL SECTION OF THE BONAVENTURE EXPRESSWAYCHAMPLAIN BRIDGE
  13. 13. LACHINE CANAL BROSSARDATWATER
  14. 14. BONAVENTURE EXPRESSWAYHIGHWAY 15 CHAMPLAIN BRIDGE
  15. 15. BONAVENTURE EXPRESSWAYMAINTENANCE WORK – $ 7.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING
  16. 16. BONAVENTURE EXPRESSWAYMAINTENANCE WORK – $ 7.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING• 645 m² of deck repairs • 710 tonnes of pavement• 219 bearing replacements • 1 165 m² of concrete repairs• 5 245 m² of waterproofing membrane • 3 expansion joints replacements
  17. 17. BONAVENTURE EXPRESSWAYMAINTENANCE WORKREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING
  18. 18. HIGHWAY 15 (EAST OVERPASS & L’ÎLE-DES-SOEURS BRIDGE)MAINTENANCE WORK – $ 4.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKING
  19. 19. HIGHWAY 15 (EAST OVERPASS & L’ÎLE-DES-SOEURS BRIDGE)MAINTENANCE WORK – $ 4.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKINGEast Overpass (Highway 15)• New waterproofing membrane • Deck repairs• Repairs to beams soffits • Repairs to the abutments• Replacement of 4 expansion joints • Pavement
  20. 20. HIGHWAY 15 (EAST OVERPASS & L’ÎLE-DES-SOEURS BRIDGE)MAINTENANCE WORK – $ 4.2 MREPAIRS / EXPANSION JOINTS / PAVEMENT / MARKINGL’Île-des-Sœurs Bridge• 105 m² of deck repairs
  21. 21. CHAMPLAIN BRIDGEMAJOR MAINTENANCE PROGRAM – $ 33.3 MIMPORTANT WORK UNDER & ON THE BRIDGE
  22. 22. PROGRAMME D’ENTRETIENDU PONT CHAMPLAIN212 M$ SUR 10 ANS10 MOIS SUR 12 PAR ANNÉE75 À 125 OUVRIERS/SEMAINE40 À 50 INGÉNIEURS DIFFÉRENTS
  23. 23. 8 FINS DE SEMAINEFERMETURE D’UNE DIRECTIONTRAVAUX MAJEURS
  24. 24. 8 FINS DE SEMAINEFERMETURE D’UNE DIRECTIONTRAVAUX MAJEURS X X X
  25. 25. 8 FINS DE SEMAINEFERMETURE D’UNE DIRECTIONTRAVAUX MAJEURS X X X
  26. 26. 2,75 KM REPAVÉS EN 2011 SUR LE PONT CHAMPLAIN
  27. 27. 5 JOINTS DE DILATATION REMPLACÉS EN 2011
  28. 28. BRIS DE JOINTS DE DILATATION DEPUIS 2000 voie 6 voie 5 voie 4 voie 3 voie 2 voie 1 TOTAL 2000 0 0 0 0 0 0 0 2001 0 0 0 0 0 0 0 2002 0 1 0 0 0 0 1 2003 1 0 0 0 0 0 1 2004 0 1 2 0 0 19 22 2005 0 2 1 0 0 1 4 2006 2 2 2 2 0 2 10 2007 0 0 1 1 1 1 4 2008 0 1 2 1 0 1 5 2009 1 2 5 5 2 2 17 2010 1 4 9 1 1 0 16 75 17 15 7 6 65 185
  29. 29. 13 POUTRESDE RIVE ONTREÇU DE LAPOST-TENSION
  30. 30. RÉFECTIONDE 5 FÛTS
  31. 31. RÉFECTION DE4 CHEVÊTRES
  32. 32. POST-TENSIONDE 7 CHEVÊTRES
  33. 33. PROCÉDÉSINNOVATEURS
  34. 34. 4 ARBALÈTESINSTALLÉES
  35. 35. PROGRAMME D’ENTRETIEN MAJEURBILAN DES TRAVAUX EN 2011Ajout de post-tensionextérieureaux poutresde rive Réfection des chevêtres 94% Renforcement 92 % des chevêtres par l’ajout de post-tension 73 % Remplacement de la médiane 47 % Remplacement Renforcement des joints de des poutres par Réfection dilatation l’installation des fûts d’arbalètes 17 % 11 % 14 %
  36. 36. 75%DU PONTREPAVÉDEPUIS 20092011• 40 000 m² de superficie de dalle pavée• 6 800 m² de membrane détanchéité• 4 500 tonnes de pavage• 655,80 m² de réparation de béton
  37. 37. +BRETELLESD’ACCÈS ET DESORTIE DU CÔTÉDE LA RIVE-SUD
  38. 38. 2. STRATÉGIES DÉPLOYÉESCORRIDOR DU PONT CHAMPLAINASSURER LA SÉCURITÉGuy Mailhot, ing., M. Eng.Directeur principal, Ingénierie
  39. 39. GESTION EFFICACE DU PONT ET DE SON ENTRETIENMESURES MISES EN PLACE 1. INSPECTION DE L’OUVRAGE ET SES COMPOSANTES (GÉNÉRALE, DÉTAILLÉE ET SPÉCIALE) 2. PRIORISATION / COORDINATION IMPORTANTE EXPERTISE À DES INTERVENTIONS L’INTERNE (9 INGÉNIEURS IMPLIQUÉS DE PRÈS, DONT 3 DÉDIÉS PRATIQUEMENT À 3. RÉALISATION TEMPS PLEIN AU PONT) DES TRAVAUX 4. SUIVI DU COMPORTEMENT DE L’OUVRAGE EN TEMPS RÉEL VIA DES CAPTEURS
  40. 40. GESTION EFFICACE DU PONT ET DE SON ENTRETIENSAVOIR CIBLER LES PRIORITÉS
  41. 41. GESTION EFFICACE DU PONT ET DE SON ENTRETIENINNOVER ET PROPOSER DES MESURES IN HOUSE
  42. 42. GESTION EFFICACE DU PONT ET DE SON ENTRETIENINNOVER ET PROPOSER DES MESURES IN HOUSE Diaphragme Console d’attache existant en béton Post-tension Appareil d’appui Longitudinal externe Poinçon Bloc d’ancrage pour tirant diagonal Tirant diagonal – 4 barres en acier Tirant longitudinal – 4 barres en haute résistance acier haute résistance
  43. 43. GESTION EFFICACE DU PONT ET DE SON ENTRETIENINNOVER ET PROPOSER DES MESURES IN HOUSESYSTÈME DE RENFORT AU MOYEN D’ARBALÈTES
  44. 44. GESTION EFFICACE DE L’ENTRETIEN DU PONTSUIVRE LE COMPORTEMENT DU PONT EN CONTINUECAPTEURS DE SUIVI - 66
  45. 45. INTERVENTION EN DÉVELOPPEMENT : INTER-DALLESECTION DE LA DALLE ENTRE DEUX POUTRES
  46. 46. CONFORTEMENT EN PLACE ACTUELLEMENTINSTALLATION DE SUPPORT AUX ZONES ENDOMMAGÉES
  47. 47. INTERVENTION EN DÉVELOPPEMENT : INTER-DALLEPOST-TENSION ET SUPPORT DE LA DALLE
  48. 48. 3. PROJETS À VENIR - 2012CORRIDOR DU PONT CHAMPLAINPOURSUIVRE DANS LA MÊME VOIEGlen P. Carlin, ing.Directeur général
  49. 49. POURSUITEDU PROGRAMMED’ENTRETIENMAJEUR – 34 M $
  50. 50. JOINTS DE DILATATION
  51. 51. CHAUSSÉE ET PAVAGE
  52. 52. PIERS REPAIRS
  53. 53. EDGE BEAMS
  54. 54. ENVIRONNEMENTMISE EN MARCHEPROJET SECTEUR OUEST
  55. 55. MESURES MISE EN PLACE SECTEUR OUESTPROJET EN MARCHE – FINANCEMENT PASCF – 24 M $
  56. 56. MESURES MISE EN PLACE SECTEUR OUESTPROJET EN MARCHE – FINANCEMENT PASCF – 24 M $ JMUR DE CONFINEMENT ET USINE DE TRAITEMENT CONCEPTION – 2012 CONSTRUCTION – 2013-2014
  57. 57. TRAVAUX RÉALISÉS ET PLANIFIÉSCORRIDOR DU PONT CHAMPLAINÉVALUATION BUDGÉTAIRE 2011 2012Pont Champlain 33 300 k $ 34 000 k $Autoroute 15 4 208 k $ 19 000 k $Autoroute Bonaventure 7 239 k $ 11 000 k $TOTAL 44 747 k $ 64 000 k $
  58. 58. SUIVIDES TRAVAUXFOLLOW-UPON THE WORKS2012- BRIEFING TECHNIQUE : PRÉSENTATION DE LA PLANIFICATION 2012- TWITTER : @PONTCHAMPBRIDGE- BLOGUE : PONTCHAMPLAIN.CA- SITE INTERNET : PJCCI.CA

×