PPT- JCRDLIS Project SE IC Jangaon - 02.08.2025.pptx
1.
J.Chokka Rao DevadulaLift
Irrigation Scheme
Irrigation & CAD Department
Government of Telangana
2.
J.Chokka Rao DevadulaLift Irrigation Scheme
Irrigation & CAD Department Approval Date of Project:08.01.2004
CCA Development Target
290737 ha(718426.77ac)
CCA Achieved
128410 ha(317308.02ac)
WUA (Achieved /Target)
0/498
Irrigation Potential
Contemplated
248786 ha (614763.59ac)
Irrigation Potential Created
128410 ha(317308.02ac)
Irrigation Potential
Utilized
85499 ha(211272.63ac)
Original Target Date
31.03.2009
Likely Date of Completion
31.12.2026
Revised Date of Completion:
31.07.2021
Estimated Cost
₹ 6016.00 cr (PL 2005-06) Revised Approved Cost
₹ 9427.73 cr (PL 2009-10)
Physical Progress
87.45 %
Financial Progress 102.81 %
(Rs. 12763.06 Cr/Rs.
12413.26cr)
Actual Revised Cost
₹ 13445.44 cr (PL 2016-17)
Central Assist. Provided/Eligible
Rs. 2182.121cr/Rs. 2283.731cr
Proposed Revised Cost
₹ 18,500.00 cr (PL 2024-25)
3.
J. Choka RaoDevadula Lift Irrigation Scheme (JCRDLIS)
4.
JCRDLIS Project
Components ofProject and their Progress
Location: Intake of project is on river Godavari, situated at Gangaram(V), Eturunagaram (M)
in Mulugu district of Telangana.
The Project is contemplated to irrigate an ayacut of 2.49 Lakh Ha. It envisages to
lift 38.16 Thousand Million Cubic feet (TMC) of water from +71 meter to a maximum of +540
meter in various stages through Pump Houses (20 Nos – completed), Pumps (44 Nos -
44installed), Pressurised pipelines (644 Kms - completed), tunnels (57 Kms - completed),
Reservoirs (19 nos -17 completed) and canal distribution system (2487Kms of which 1708
Kms completed). The project also provides water for stabilization of ayacut under en-route
existing reservoirs (10 Nos) along water conduit system besides formation of new reservoirs
(9 Nos). In addition, there is a provision of about 2 TMC for drinking and industrial needs.
The project is taken up in three phases i.e., Phase-I, II & III covers command area
of 2,48,786 Ha (6,14,750 Acres). The individual Ayacut of Phase-I: 50,088 Ha (1,23,768
Acres), Phase-II: 78,172 Ha (1,93,164 Acres), Phase-III: 97,042 Ha (2,39,790 Acres) with
Stabilization of about 23,484 Ha (58,028 Acres).
6.
• Phase-I :Consistsof 3 No. of Packages.
• Phase-I(Head works Package): Proposed to lift 5.18
TMC of water through laying of pipe lines and construction
of Pump houses are completed and water is being lifted.
• Distributory system under Phase-I Package-45 & 46
contemplated for an ayacut of 50088 Ha. The Distributory
system under Package-45 is completed and Package-46 is
in progress.
8.
• Phase-II Consistsof 5 No. of Packages
• Phase-II(Head works Package): Proposed to lift 7.25 TMC of water through
laying of pipe lines and construction of pump houses and formation of new
reservoir and improvements to existing tanks. All the head works are completed
and the water is being lifted.
Distributory system: contemplates to create ayacut of 78172Ha under
• 1) Right Flank Main Canal Distributory system of Ghanpur Reservoir
• 2) 4L-Distributory system under RFMC of R.S.Ghanpur Reservoir
• 3) Distributory system under Tapaspally Reservoir and
• 4) Distributory system under Ashwaropally and Chittakodur Reservoirs
• The distributor system under RFMC of R.S Ghanpur Reservoir is completed. The
works under other distributor system are in progress.
10.
Phase-III
• Proposed tolift 25.75 TMC of water through laying of pipe lines, excavation of Tunnels.
Main Components of works:-
• Construction of pump houses and formation of New reservoir and strengthening of
existing tanks and Distributory system covered to create an irrigation potential of
97042Ha and the works are taken up under 8 packages.
• Package-I and II are completed, Package-III completed out 3 motor , motor No.2 is
commission and water being lifted to Dharmasagr Tank and the commissioning of motor
1& 3 are in progress,
• Package-IV (Out 5 Pump House 4 No of pump houses are commissioned and water is
being lifted to the online reservoirs and commissioning of one pump house at
Rajawaram (R.S.Ghanpur Reservoir) is in progress .
• The works under distrubutory system of Package- V, VI,VII and VIII are in progress.
11.
Components of Projectand their Progress
Sl. No. Description Phase-I Phase-II Phase-III Total
1 Water to be lifted (TMC) 5.18 7.25 25.75 38.18
2 Discharge ( No of Pumps x Cumecs) 2 x 5 =10 2 x 7=14 6 x 8.27=49.60 73.60
3 No. of Lifts ( Nos) 4 7 10 21
4 Static Head (Mts) 268 470 510
5 Power requirement (MW) 56 124.60 315.50 495.55
6 No. of Pump Houses
1) Intake at Gangaram
2) Bheemghanpur
3) Nagaram
(Pulkurthy)
4) Dharmasagar
1) Intake at Gangaram
2) Bheemghanpur
3) Salivagu
4) Dharmasagar
5) R.S.Ghanpur
6) Gandiramaram
7) Bommakur
1) Intake at Gangaram
2) Bheemghanpur
3) Ramappa (Package-V)
4)Devannapet Tunnel PH
5) Dharmasagar
6) R.S.Ghanpur PH
7) RajavaramTunnel PH
8) Gandiramaram
9) Bommakur
20
7 Length of Pumping Main(Km) 139.00 197.00 308.00 642.00
8 Length of Tunnel (Km) - - 57.160 57.160
9 Formation /Improvements to the Tanks
1)R.C.C Tank at
Pulkurthy ( New)
2)Dharmasagar(Imp)
1) Narsingapur (Imp)
2) R.S.Ghanpur (Imp)
3) Ashwaraopally (Imp)
4) Chittakodur (New)
5) Gandiramaram (Imp)
6) Bommakur (New)
7) Veldanda(Imp)
8) Tapaspally (New)
1) Nashkal Tank(New)
2) Palakurthy Tank(Imp)
3) Chennur Tank(New)
4) Jaffergadh
Tank(Strengthening)
5) Nawabpet Tank(New)
6) Laddunur (New)
7) Kannaboinagudem (New)
8) Maa reddy Cheruvu(Imp)
9) Inapur Tank(Imp)
19
10 Proposed ayacut (Acres) 123768 193164 239790 556722
11 No of Packages 3 5 8 16
12 Cost of works (Rs. In Crores ) 1288.398 2360.965 6058.837 9708.199
12.
PHYSICAL PROGRESS:
Component TotalCompleted Balance % of
Progress
Earth Work Excavation
(in Kms)
2487 1708 799 67.67
Laying Pipeline
(in Kms)
644.00 644.00 0 100.00
Tunnel Excavation
(in Kms)
57.16 57.16 0 100.00
Structures
(in Nos)
18839 11692 7147 62.06
Lining (in Kms) 1011.84 639.81 372.02 63.15
Tanks (in Nos) 19 17 2 89.47
Pump House
(in Nos)
20 20 0 100.00
13.
ABSTRACT FOR LANDACQUISITION TO BE ACQUIRED IN J.CHOKKA RAO DEVADULA LIFT IRRIGATION SCHEME
S No Name of the work
LA to be
Acquired
(In Ac)
Present Stage of LA (A-G)
Detailed
Status
Action
Plan As
per
Cordinatio
n meeting
Peg
Marking
SDR
Stage
PN stage/
Enjoyment
PD
stage
Award
stage
To be
entered in
IFMIS
Payment
stage
1
Phase -II 4L Distributory
System
12.6625 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 12.6625
Requirement of
funds for paying
to beneficiaries
directly
Persuing
with Govt
for release
of Funds
2
Phase -II Ashwaraopally
Distributory System
81.5238 0.0000 0.0000 11.7563 5.2500 4.0000 47.8625 12.8050
3
Phase -II, Tapaspally
Distributory System
688.8825 0.0000 657.9700 0.0000 0.0000 30.9150 0.0000 0.0000
4 Phase-III-Package-II 9.0375 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 9.0375
5
Phase -III, Package-V
Distributory System
164.1165 17.5250 9.9250 0.6750 0.0000 0.0000 76.0165 59.9750
6
Phase -III, Package-VI
Distributory System
1143.425
3
105.975
0
182.4500 154.6063 109.5813 106.4628 0.0000 484.3500
7
Phase-III-Package-VII
Distributory System
63.5500 0.0000 0.0000 11.3875 0.0000 0.0000 27.5750 24.5875
8
Phase -III, Package-VIII
Distributory System
433.8938 54.4938 101.5500 0.0000 11.4500 0.0000 165.2000 101.2000
Total for JCRDLIS Project(in
Acres)
2597.0918 177.9938 951.8950 178.4250 126.2813 141.3778 316.6540 704.6175
Total for JCRDLIS Project(in Ha) 1051 72 385 73 51 57 128 285
14.
Status of proposalfor central assistance
District Total project
beneficiary
No. of SC
beneficiaries
No. of ST
beneficiaries
No. of Women
beneficiaries
Hanumakonda 17726 3756 2924 7090
Warangal 23322 3323 3560 11008
Mahabubabad 675 20 82 269
Jangaon 75337 5792 15474 36915
Siddipet 23474 1987 3617 11504
Yadadri 14669 5870 2933 6601
Suryapet 4106 1292 822 1888
Mulugu 2130 852 426 1044
Jayashankar Bhupalpally 480 83 63 202
Karimnagar 311 47 0 124
Total 162230 23022 29901 76645
Beneficiary Details
• Balance CA: Rs. 101.67 Cr
• Last CA release: 2022,March (Rs. 43.95 Cr)
• CA Proposal status: Under Submission for FY 2024-25
• Whether legacy data entries made in the PFMS?
• Status of interest deposition:
15.
JCRDLIS – JANGAONDISTRICT
• Under the jurisdiction of Superintending Engineer, Irrigation Circle, Jangaon the
contemplated Ayacut is 3,59,144 acres out of which Irrigated ayacut is 1,67,368
acres. The contemplated Ayacut under Jangaon District is 2,56,551 acres out of
which irrigated ayacut is 1,50,780 acres. The project works are in progress to create
and serve the balance ayacut.
The works taken up under various packages are as detailed below:
• Phase-III Package – VIII: Sanctioned amount of Rs. 446.03 crores, to irrigate an
ayacut of 76000 acres. 80% of work is completed balance work is in progress.
• Phase-II Ashwaraopally & Chitakodur Distributory System: Sanctioned amount
of Rs. 266.88 crores, to irrigate an ayacut of 56100 acres. Ayacut under Jangaon
District is 22,109 acres. 82% of work is completed balance work is in progress.
• Phase-III Package – VII: Sanctioned amount of Rs. 408.76 crores, to irrigate an
ayacut of 53400 acres. 90% of work is completed balance work is in progress.
16.
• Phase-II RSGhanpur Distributory System: Sanctioned amount of Rs. 145.90
crores, to irrigate an ayacut of 28806 acres. 98% of work is completed balance
work is in progress.
• Phase-II - 4L Distributory: Sanctioned amount of Rs. 87.67 crores, to irrigate an
ayacut of 24016 acres. 87% of work is completed balance work is in progress.
• Phase-III – Package-IV: Sanctioned amount of Rs. 946.65 crores. Work is
completed.
• Phase-III – Package-VI: Sanctioned amount of Rs. 408.96 crores, to irrigate an
ayacut of 77890 acres for Palakurthy Reservoir and to irrigate an ayacut of 25165
acres for Chennur Reservoir. Works are in progress.
• Tapaspally Distributory System: Sanctioned amount of Rs. 252.47 crores, to
irrigate an ayacut of 82542 acres. Ayacut under Jangaon District is 19,000 acres.
88% of work is completed balance work is in progress.
• Gandiramaram Reservoir Right Main Canal: Sanctioned amount of Rs. 29.00
crores, to irrigate an ayacut of 5600 acres. Works are under progress.
17.
JCRDLIS - RESERVOIRSUNDER JANGAON DISTRICT
Sl
N
o
Name of the
Reservoir
Location District
Present Level in
Mtrs
Present Capacity in
MCFT
1 Gandiramaram
Gandiramaram(V),
Narmetta(M)
Jangaon 419.660 316.000
2 Bommakur
Bommakur(V),
Narmetta(M)
Jangaon 473.200 149.220
3 Cheetakodur
Cheetakodur(V),
Jangaon(M)
Jangaon 387.200 178.200
4 Nawabpet
Nawabpet(V),
Lingalaghanpur (M)
Jangaon 322.400 78.500
5 R.S. Ghanpur Station Ghanpur (V) & (M) Jangaon 336.050 873.000
6 Ashwaraopally
Ashwaraopally(V),
Raghunathpally(M)
Jangaon 396.400 379.000
9 Tapaspally Tapaspally Siddipet 536.550 135.324
18.
JCRDLIS – PUMPHOUSES UNDER IRRIGATIOIN CIRCLE, JANGAON
Division Name of Pump Houses No of Pumps
Discharge in
Cusecs
Irrigation
Division No.4,
Jangaon
Gandiramaram Pump House- Phase-II. 2 295
Gandiramaram Pump House
(Phase - III, Package-IV - (EM-3 PH) 2 372
Bommakur Pump House
Phase - III, Package-IV - (EM-4 PH) 2 360
Bommakur Pump House - Phase -II. 2 176
Irrigation
Division No.7
R.S Ghanpur
Jangaon
R.S. Ghanpur Pump House - Phase - II 2 212
R.S. Ghanpur Pump house
Phase -III, Package IV). Rajavaram(V) EM-1 2 240
R.S. Ghanpur Pump house
Phase -III, Package IV) EM-5 2 77
Total 14