No. Description Durat
ion(D
ays)
Start Date Finish
Date
2017 2018
JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN
2 9 1
6
2
3
6 1
3
2
0
2
7
3 1
0
1
7
2
4
8 1
5
2
2
2
9
5 1
2
1
9
2
6
3 1
0
1
7
2
4
7 1
4
2
1
2
8
4 1
1
1
8
2
5
4 1
1
1
8
2
5
1 8 1
5
2
2
6 1
3
2
0
2
7
3 1
0
1
7
2
4
1 Premilaries 19 02/07/17 21/07/17
1.1 Mobilization&site survey 7 02/07/17 09/07/17
1.2 Site Cleaning 12 10/07/17 21/07/17
2 Substructure Works 70 10/07/17 16/09/17
2.1 Soil Investigation 21 22/07/17 12/08/17
2.2 Excavation 14 12/08/17 26/08/17
2.3 Piling 14 26/08/17 09/09/17
2.4 Foundation 21 26/08/17 16/09/17
3 Structural Works 84 18/09/17 11/12/17
3.1 RC Ground Floor Slab
&Structure
21 18/09/17 09/10/17
3.2 RC First Floor Slab &Structure 14 09/10/17 23/10/17
3.3 RC Third Floor Slab &Structure 14 23/10/17 06/11/17
3.4 RC Roof Slab 21 06/11/17 27/11/17
3.5 Steel staircases &elevator 14 27/11/17 11/12/17
4 Wall 72
4.1 Ground floor concrete wall &
opening
18
4.2 First floor concrete wall &
opening
18
4.3 Second floor concrete wall &
opening
18
4.4 Third floor concrete wall &
opening
18
5 Roof 31
5.1 Metal Beam & Frame 14
5.2 Metal decking 17
6 Architecture Finishes 90
6.1 External/Internal wall curtain(all
floors)
24
6.2 External/Internal timber
tiling(all floors)
14
6.3 Tiling works 7
6.4 Ceiling finishes 7
6.5 Door & Window installation 3
6.6 Sanitary Fitting 10
7 Mechanical & Electrical finishes 48
7.1 Electrical & Light fittings 10
7.2 Plumbing & Sanitary (rainwater
harvest)
14
7.3 Fire fighting system 14
7.4 Air-conditioning units 10
8 External facade 14
8.1 Installation of façade
layer&framing
14
9 External infrastructure 21
9.1 Ramps 7
9.2 Road & Pavements 7
9.3 Sewerage & Water reticulation 3
9.4 Landscaping 4
10 Phase out 14
10.
1
Clearing & Site cleaning 14
11 Testing/Commissioning 14
11.
1
Sub Task 14
12 Inspection 14
12.
1
Inspection & Handover 10

Pm final gann chart

  • 1.
    No. Description Durat ion(D ays) StartDate Finish Date 2017 2018 JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN 2 9 1 6 2 3 6 1 3 2 0 2 7 3 1 0 1 7 2 4 8 1 5 2 2 2 9 5 1 2 1 9 2 6 3 1 0 1 7 2 4 7 1 4 2 1 2 8 4 1 1 1 8 2 5 4 1 1 1 8 2 5 1 8 1 5 2 2 6 1 3 2 0 2 7 3 1 0 1 7 2 4 1 Premilaries 19 02/07/17 21/07/17 1.1 Mobilization&site survey 7 02/07/17 09/07/17 1.2 Site Cleaning 12 10/07/17 21/07/17 2 Substructure Works 70 10/07/17 16/09/17 2.1 Soil Investigation 21 22/07/17 12/08/17 2.2 Excavation 14 12/08/17 26/08/17 2.3 Piling 14 26/08/17 09/09/17 2.4 Foundation 21 26/08/17 16/09/17 3 Structural Works 84 18/09/17 11/12/17 3.1 RC Ground Floor Slab &Structure 21 18/09/17 09/10/17 3.2 RC First Floor Slab &Structure 14 09/10/17 23/10/17 3.3 RC Third Floor Slab &Structure 14 23/10/17 06/11/17 3.4 RC Roof Slab 21 06/11/17 27/11/17 3.5 Steel staircases &elevator 14 27/11/17 11/12/17 4 Wall 72 4.1 Ground floor concrete wall & opening 18 4.2 First floor concrete wall & opening 18 4.3 Second floor concrete wall & opening 18 4.4 Third floor concrete wall & opening 18 5 Roof 31 5.1 Metal Beam & Frame 14 5.2 Metal decking 17 6 Architecture Finishes 90 6.1 External/Internal wall curtain(all floors) 24 6.2 External/Internal timber tiling(all floors) 14 6.3 Tiling works 7
  • 2.
    6.4 Ceiling finishes7 6.5 Door & Window installation 3 6.6 Sanitary Fitting 10 7 Mechanical & Electrical finishes 48 7.1 Electrical & Light fittings 10 7.2 Plumbing & Sanitary (rainwater harvest) 14 7.3 Fire fighting system 14 7.4 Air-conditioning units 10 8 External facade 14 8.1 Installation of façade layer&framing 14 9 External infrastructure 21 9.1 Ramps 7 9.2 Road & Pavements 7 9.3 Sewerage & Water reticulation 3 9.4 Landscaping 4 10 Phase out 14 10. 1 Clearing & Site cleaning 14 11 Testing/Commissioning 14 11. 1 Sub Task 14 12 Inspection 14 12. 1 Inspection & Handover 10