TechKnowXpress

Online ERP
WHAT IS ERP?
• Enterprise resource planning (ERP) is a crossfunctional enterprise system driven by an integrated
suite of software modules that supports the basic
internal business processes of a company.
• ERP is an enterprise-wide information system
designed to coordinate all the
▫ resources
▫ information
▫ activities needed

• to complete business processes such as;
▫ order fulfillment
▫ billing.
TechKnowXpress

Online ERP
3

ERP APPLICATIONS
Core applications

• Online Transaction Processing (OLTP) are the
transaction processing systems.
• support the day-to-day operational activities of the
business.
• support mission-critical tasks through simple
queries of operational databases.
• include Sales and Distribution, Business Planning,
Production Planning, Shop Floor Control, and
Logistics modules.

TechKnowXpress

Online ERP
4

ERP APPLICATIONS

(continue…)

Business analysis applications
• Online Analytical Processing (OLAP).
• decision support tool for management-critical tasks through
analytical investigation of complex data associations.
• supplies management with ―real-time‖ information and permits
timely decisions to improve performance and achieve
competitive advantage .
• includes decision support, modeling, information retrieval, adhoc reporting/analysis, and what-if analysis.

TechKnowXpress

Online ERP
WHAT IS ONLINE ERP?
 ERP installed with a
server and a network
connection is called
Online ERP.
 It ensures complete
transparency
between developers
of application and
the clients.

TechKnowXpress

Online ERP
HISTORY
Companies before ERP Systems

Islands Of information

Material accounting

Customer Services

Material receipt

Payroll
TechKnowXpress

Online ERP
HISTORY (continue…)
• In 1990 Gartner Group first employed
the acronym ERP as an extension of material
requirement planning (MRP).
• ERP systems experienced rapid growth in the
1990s because the year 2000 problem and
introduction of the euro disrupted legacy
systems.

• Enterprise application suite is an alternate
name for such systems.
TechKnowXpress

Online ERP
MODULES OF ERP
1.
2.
3.
4.
5.
6.
7.
8.

Financial and Accounting
Materials Management
Production Planning
Order Entry
Purchasing
Financial Control
Distribution/Logistics
Asset Management

TechKnowXpress

Online ERP
ADVANCED MODULES
• SCM – Supply Chain Management.
• CRM – Customer Relationship Management.
• SRM – Supplier Relationship Management.
• Workflow – Process Sequence and Authorization

TechKnowXpress

Online ERP
SUB MODULES

ERP

TechKnowXpress

Online ERP
TECHNOLOGIES - DEVELOPMENT
• Front End : Java/J2EE, .NET
• Backend : MySQL, MSSQL, Oracle
• Application Server : Apache Tomcat, Glassfish

TechKnowXpress

Online ERP
12

DEPLOYMENT MODEL
Two-tier
• common server handles both application and database
transaction.
• used especially in LANs.

TechKnowXpress

Online ERP
13

DEPLOYMENT MODEL (continue…)
Three-tier
• Client links to the application server which then
initiates a second connection to the database
server.
• used especially in WANs.

TechKnowXpress

Online ERP
User
Presentatio
n Layer

First Tier

Second Tier

Third Tier

Applications

Database

Application
Server

Database
Server

Three-Tier Client
Server

Application
Layer

Database
Layer

Online ERP
User
Presentatio
n Layer

First Tier

Second Tier

Third Tier

OLTP
Applications

Operations
Database

OLTP
Server

OLAP
Server

OLAP
Applications

Operations
Database
Server

Data
Warehouse
Server

Data
Warehouse

Application
Layer

Databas
e Layer

ERP with OLTP and OLAP Client Server using Data Warehouse
Online ERP
DATA CENTRE
Additional Servers Required
• Antivirus Server
• Email Server
• FTP Server
• Proxy Server
• Domain Server
Additional Server Hosting Model
•On Site Data Centre (with in Premises of Company)
• Off Site Data Centre ( Data Centre Hosting at BSNL, IBM, MTNL etc)
• Virtual Data Centre (Cloud Environment)
• Software as a Service (SaaS)
• Platform as a Service (PaaS)
• Infrastructure as a Service (Iaas)
Online ERP
IMPLEMENTATION STEPS
Process preparation

Linking current processes to the organization's strategy.
Analyzing the effectiveness of each process
Understanding existing automated solutions.
Extensions
ERP systems can be extended with third–party software.
ERP vendors typically provide access to data and features
through published interfaces

Online ERP
IMPLEMENTATION STEPS

(continue…)

Configuration
ERP systems typically include many settings that modify
system operation. For example, an organization can select
the type of inventory accounting—FIFO or LIFO—to use;
whether to recognize revenue by geographical unit,
product line, or distribution channel; and whether to pay
for shipping costs on customer returns.

Online ERP
IMPLEMENTATION STEPS (continue…)
Customization

ERP customers have several options to reconcile feature
gaps. Technical solutions include rewriting part of the
delivered software, writing a homegrown module to work
within the ERP system, or interfacing to an external
system.
Data migration
Data migration is the process of moving, copying, and
restructuring data from an existing system to the ERP
system.

Online ERP
ERP IMPLEMENTATION PATTERN
Software

Market Share

SAP
Peoplesoft
Baan

3.0

CA

3.0

JDE

2.2

SSA

2.1

GEAC

2.0

IBM

1.8
1.7

Others

Oracle ; 4,8

4.8

JBA

Peoplesoft;
4,9

4.9

Oracle

SAP; 15,6

15.6

59.0

Baan; 3
Others ; 59

CA; 3
JDE; 2,2
SSA; 2,1
GEAC; 2
IBM; 1,8
JBA; 1,7

TechKnowXpress

Online ERP
OUTPUTS OF ERP SYSTEMS
DOCUMENTS
Printer

Proposal
Orders approval

Mail

Delivery plans
Shipping papers
Warehouse check list
Material document
Accounting document

Fax

Delivery/shipping document
Invoice
Dept & credit doc.

EDI
Online ERP
22

RISKS ASSOCIATED WITH ERP
IMPLEMENTATION
• Choosing the Wrong ERP
▫ Goodness of Fit: no ERP system is best for all
industries.
▫ Scalability: system’s ability to grow.

• Choosing the Wrong Consultant
▫ Common to use a third-party (the Big Five).
▫ Be thorough in interviewing potential consultants.
▫ Establish explicit expectations.

TechKnowXpress

Online ERP
23

RISKS ASSOCIATED WITH ERP
IMPLEMENTATION IMPLEMENTATION
STEPS (continue…)
• High Cost and Cost Overruns
▫ Common areas with high costs:
 Training
 Testing and Integration
 Database Conversion

• Disruptions to Operations
▫ ERP is reengineering--expect major changes in
how business is done.
TechKnowXpress

Online ERP
IMPLEMENTATION OUTCOME

TechKnowXpress

Online ERP
TechKnowXpress

Online ERP

Online erp

  • 1.
  • 2.
    WHAT IS ERP? •Enterprise resource planning (ERP) is a crossfunctional enterprise system driven by an integrated suite of software modules that supports the basic internal business processes of a company. • ERP is an enterprise-wide information system designed to coordinate all the ▫ resources ▫ information ▫ activities needed • to complete business processes such as; ▫ order fulfillment ▫ billing. TechKnowXpress Online ERP
  • 3.
    3 ERP APPLICATIONS Core applications •Online Transaction Processing (OLTP) are the transaction processing systems. • support the day-to-day operational activities of the business. • support mission-critical tasks through simple queries of operational databases. • include Sales and Distribution, Business Planning, Production Planning, Shop Floor Control, and Logistics modules. TechKnowXpress Online ERP
  • 4.
    4 ERP APPLICATIONS (continue…) Business analysisapplications • Online Analytical Processing (OLAP). • decision support tool for management-critical tasks through analytical investigation of complex data associations. • supplies management with ―real-time‖ information and permits timely decisions to improve performance and achieve competitive advantage . • includes decision support, modeling, information retrieval, adhoc reporting/analysis, and what-if analysis. TechKnowXpress Online ERP
  • 5.
    WHAT IS ONLINEERP?  ERP installed with a server and a network connection is called Online ERP.  It ensures complete transparency between developers of application and the clients. TechKnowXpress Online ERP
  • 6.
    HISTORY Companies before ERPSystems Islands Of information Material accounting Customer Services Material receipt Payroll TechKnowXpress Online ERP
  • 7.
    HISTORY (continue…) • In1990 Gartner Group first employed the acronym ERP as an extension of material requirement planning (MRP). • ERP systems experienced rapid growth in the 1990s because the year 2000 problem and introduction of the euro disrupted legacy systems. • Enterprise application suite is an alternate name for such systems. TechKnowXpress Online ERP
  • 8.
    MODULES OF ERP 1. 2. 3. 4. 5. 6. 7. 8. Financialand Accounting Materials Management Production Planning Order Entry Purchasing Financial Control Distribution/Logistics Asset Management TechKnowXpress Online ERP
  • 9.
    ADVANCED MODULES • SCM– Supply Chain Management. • CRM – Customer Relationship Management. • SRM – Supplier Relationship Management. • Workflow – Process Sequence and Authorization TechKnowXpress Online ERP
  • 10.
  • 11.
    TECHNOLOGIES - DEVELOPMENT •Front End : Java/J2EE, .NET • Backend : MySQL, MSSQL, Oracle • Application Server : Apache Tomcat, Glassfish TechKnowXpress Online ERP
  • 12.
    12 DEPLOYMENT MODEL Two-tier • commonserver handles both application and database transaction. • used especially in LANs. TechKnowXpress Online ERP
  • 13.
    13 DEPLOYMENT MODEL (continue…) Three-tier •Client links to the application server which then initiates a second connection to the database server. • used especially in WANs. TechKnowXpress Online ERP
  • 14.
    User Presentatio n Layer First Tier SecondTier Third Tier Applications Database Application Server Database Server Three-Tier Client Server Application Layer Database Layer Online ERP
  • 15.
    User Presentatio n Layer First Tier SecondTier Third Tier OLTP Applications Operations Database OLTP Server OLAP Server OLAP Applications Operations Database Server Data Warehouse Server Data Warehouse Application Layer Databas e Layer ERP with OLTP and OLAP Client Server using Data Warehouse Online ERP
  • 16.
    DATA CENTRE Additional ServersRequired • Antivirus Server • Email Server • FTP Server • Proxy Server • Domain Server Additional Server Hosting Model •On Site Data Centre (with in Premises of Company) • Off Site Data Centre ( Data Centre Hosting at BSNL, IBM, MTNL etc) • Virtual Data Centre (Cloud Environment) • Software as a Service (SaaS) • Platform as a Service (PaaS) • Infrastructure as a Service (Iaas) Online ERP
  • 17.
    IMPLEMENTATION STEPS Process preparation Linkingcurrent processes to the organization's strategy. Analyzing the effectiveness of each process Understanding existing automated solutions. Extensions ERP systems can be extended with third–party software. ERP vendors typically provide access to data and features through published interfaces Online ERP
  • 18.
    IMPLEMENTATION STEPS (continue…) Configuration ERP systemstypically include many settings that modify system operation. For example, an organization can select the type of inventory accounting—FIFO or LIFO—to use; whether to recognize revenue by geographical unit, product line, or distribution channel; and whether to pay for shipping costs on customer returns. Online ERP
  • 19.
    IMPLEMENTATION STEPS (continue…) Customization ERPcustomers have several options to reconcile feature gaps. Technical solutions include rewriting part of the delivered software, writing a homegrown module to work within the ERP system, or interfacing to an external system. Data migration Data migration is the process of moving, copying, and restructuring data from an existing system to the ERP system. Online ERP
  • 20.
    ERP IMPLEMENTATION PATTERN Software MarketShare SAP Peoplesoft Baan 3.0 CA 3.0 JDE 2.2 SSA 2.1 GEAC 2.0 IBM 1.8 1.7 Others Oracle ; 4,8 4.8 JBA Peoplesoft; 4,9 4.9 Oracle SAP; 15,6 15.6 59.0 Baan; 3 Others ; 59 CA; 3 JDE; 2,2 SSA; 2,1 GEAC; 2 IBM; 1,8 JBA; 1,7 TechKnowXpress Online ERP
  • 21.
    OUTPUTS OF ERPSYSTEMS DOCUMENTS Printer Proposal Orders approval Mail Delivery plans Shipping papers Warehouse check list Material document Accounting document Fax Delivery/shipping document Invoice Dept & credit doc. EDI Online ERP
  • 22.
    22 RISKS ASSOCIATED WITHERP IMPLEMENTATION • Choosing the Wrong ERP ▫ Goodness of Fit: no ERP system is best for all industries. ▫ Scalability: system’s ability to grow. • Choosing the Wrong Consultant ▫ Common to use a third-party (the Big Five). ▫ Be thorough in interviewing potential consultants. ▫ Establish explicit expectations. TechKnowXpress Online ERP
  • 23.
    23 RISKS ASSOCIATED WITHERP IMPLEMENTATION IMPLEMENTATION STEPS (continue…) • High Cost and Cost Overruns ▫ Common areas with high costs:  Training  Testing and Integration  Database Conversion • Disruptions to Operations ▫ ERP is reengineering--expect major changes in how business is done. TechKnowXpress Online ERP
  • 24.
  • 25.