INTERNSHIP REPORT ON
BUDIHAL-PEERAPUR LIFT IRRIGATION SCHEME
SHREEHARI KULKARNI
USN:SG21SEC017
Semester: 4th
Date of Internship
From: JUNE To: JULY
Faculty Advisor
Asst Prof. RISHIKESH
Asst/Assoc/Professor, Department of Civil Engineering,
Sharnbasva University,
Kalaburagi, Karnataka.
2023
INTERNSHIP SCHEDULE
Week 1
Salient feature of the project Introduction
Plans and Drawing
Design and Detailing of drawing
Components of the project
Week 2
Brick laying
Plastering
Curing
Week 3
Painting
Msand
Week 4
Dewatering
Silt removal / Desiltering
Assemble the safety box
• Week 5
• Construction of roads – Compaction by roller
• RMC
• Construction of sidewall and removal form work
•
• Week 6
• Pipe laying
• Guniting
•
• Week 7
• Importance of cleaning
• Sealant - Crack repair
• Plastering
• Curing
• Build a high rise steel building
• Week 8
• Loading and unloading of steel
• Joining of HDPE pipe
KRISHNA BHAGYA JALA NIGAM LIMITED
• GOVT OF KARNATAKA
• Krishna Bhagya Jala Nigam Ltd (KBJNL) was incorporated on19th August 1994 under the Companies
Act, 1956 as a Company, wholly owned by the Government of Karnataka for implementation of the
Upper Krishna Project (UKP)in the State of Karnataka.
The Company is responsible for planning, investigation, estimation, execution, operation and
maintenance of all irrigation projects coming under the UKP. The Company is also responsible to
obtain Government of India's clearance and execute the UKP. The Company is also entrusted with
the responsibility of Rehabilitation and Resettlement of the people affected by the Project. The
Company is authorised to sell water and recover revenues from individuals, groups of farmers
including those in the Command Area Development Authority, towns, city municipalities and
industries.
Large parts of Karnataka are located in the drought-prone rain shadow of the Western Ghats
characterised by low and unreliable rainfall. UKP and other irrigation porjects are being executed in
the drought-prone northeastern part of Karnataka about 456 Kms from Bangalore in the districts of
Kalburgi, Yadgir, Raichur, Bagalkot and Vijayapura. It occupies a triangular area lying between the
Krishna and Bheema rivers. The population in this area subsists mainly on agriculture. The area,
though being subjected to vagaries of the monsoons, has highly fertile land. Making avaliable water
for irrigation, the economic picture of the area would be transformed contributing greatly to the
development of the region in particular and Karnataka State in general.
• AMRUTHA CONSTRUCTION PVT LIMITED
•
• Sri.P.Venkateshwar Rao popularly known as P.V.Rao hails from sindhanur town, Raichur district in
Karnataka. After his graduation from St. Josephs College, Bangalore, Mr.Rao founded a proprietary
firm known as P. Venkateshwar Rao & Co in 1988. Mr.Rao started with executing minor repair and
routine maintenance work for KPWD and Minor Irrigation Department of The Govt. of Karnataka.
The quality of work, timely completion and cost effectiveness of the firm did not go unnoticed and
it was only a matter of time before the firm started handling bigger projects for clients like The
KBJNL, KNNL, KIADB, KSCC and KPWD.
By the year 2006, the turnover of the firm had crossed 30 crores and Mr.Rao decided that to grow
further, professionals would have to be brought in and a proper corporate structure of reporting
and accountability created. To achieve the same, the proprietary firm P.Venkateshwar Rao & Co was
turned into a Private Limited firm and incorporated as Amrutha Constructions Pvt ltd. The
transformation and professional approach had the desired results and Amrutha Constructions
began achieving astounding growth of 50% YOY. Amrutha Constructions decided to be backward
integrate and foray into the cement and steel business by setting up plants to produce cement and
steel in collaboration with Bose Infra energy India Pvt Ltd, where Mr.Rao also holds equity.
AWARDS
•
• On November 28th,2009, Sri P.Venkateshwara Rao was
honored with "Indian Achievers Award for Construction &
Design" by All India Achievers Foundation,New Delhi. The
Honor was awarded by the governor,Dr.GVG krishnamurthy
(Former Election Commissioner of India), Justice O.P Verma
(Former Governor & Chief justice) and Major (Retd.) Ved
Prakash on the occasion of National Seminar on "National
economic Growth & World Peace"
• On July 4th 2011,Sri P Venkateshwara rao was honored
with "Bharatha Ratna Sir M.Visveshwaraya Global
Leadership" Award for excellency in environment,Social
work,education & health which was organized at the Town
Hall,Bangalore.
KEY PROJECTS
• Modernisation work of Bhadra Right Bank Main Canal for
KNNL Completed in a record time of 39 days, compared to
stipulated 60 days.
• Industrial layout Formation for KIADB at Tumkur District.
• Lift Irrigation scheme for KNNL at Tunga River, Shimoga on
Turnkey Basis
• .Lift Irrigation scheme for KNNL at Yettinahole package-I,
Sakaleshpura, Hassan on Turnkey Basis.It also includes
drinking water supply to chikkaballapur & Kolar District.
• Constructions of BESCOM integrated control centre-1 based
on parameters fixed by BESCOM on EPC at HSR Layout,
Bangalore. One of it’s kind & first BESCOM Distribution &
Automation system Building in India
• Improvements to Old Maddur, Shimoga & Kowdle branch canals for CNNL at
Mandya District.
• Construction of Malghan West Canal including Major Structures for KBJNL at
Yadgir.
• Lift irrigation scheme to fill up MI 10 tanks under KBJNL at Bijapur and Bagalkot
has been completed in record time of 6 months as against the original time of 18
months in the year of 2017.
• Lift irrigation scheme to fill up Devalapur tanks under water resource department
(MI) at Gangawati, Koppal Dist on turnkey basis has been completed in well
advanced time.
• Lift irrigation scheme for KBJNL at Muddebihal Taluk, Bijapur Dist, on the name of
work Budihal Peerapur LIS. It includes one of the major head (246M ) & 2350MM
of outer Dia. mild steel pipe.
• UDUGANI-TALAGUNDA-HOSURU TANK FILLING SCHEME-Lifting of water from
Tungabhadra river near Puradakere village to feed Tanks of Existing MI/ZP Tanks in
Udugani Talagunda Hosuru Hobli of Shikaripura Taluk of Shivamogga District.
Brief Description of the Project and its Importance to the
Region
• The proposed project is a lift irrigation
scheme. The scheme involves lifting of 2.22
TMC of water from Narayanapura reservoir
near Siddapur Village of Muddebihal Taluk,
Vijayapura District, by constructing an Intake
canal and jack well cum pump house, raising
main and Delivery Chambers. The proposed
take off point is from the Krishna River on the
foreshore of Narayanapura reservoir.
Salient feature of the project
COMPONENTS
Krishna river & Backwater Narayanpur dam
INTAKE STRUCTURE
JACKWELL CUM PUMPHOUSE
PIPE
• Basava Sagar Dam, previously known as Narayanpura Dam,
is a dam constructed across the Krishna River at Yadgir
District, Karnataka State, India.[1] The reservoir that it
impounds is known as Basava Sagar, and has a total storage
capacity of 37.965 tmcft (1.075 km³), with 30.5 tmcft
(0.85 km³) live storage.[2][3] The full reservoir level is 492.25 m
MSL and the minimum draw down level is 481.6 m MSL. It
was a single purpose project meant only for irrigation, but
downstream electrical generation and drinking water
considerations enter into its management. The dam is 29
meters high and over 10.637 kilometres (6.610 mi)
long,[2] and has 30 gates for water release. 22 Spillway Gates
are present in the Dam[3] It took Rs. 50.48 crore to
complete.[4]
•
• A dam is a large and solid barrier constructed across a river or
stream to impound water and create a reservoir. Dams serve
multiple purposes, including water storage for various uses
like irrigation, water supply, and hydroelectric power
generation. They also help regulate river flow, prevent
flooding downstream, and provide recreational opportunities.
Dams can be made of various materials such as concrete,
rock, earth, or a combination of these, depending on the
site's geological and engineering considerations.
INTAKE CANAL
INTAKE STRUCTURE
An intake structure refers to facility or
arrangement built to collect or take in
a water from its source for various
purposes such as water supply
irrigation.
It is an essential component of water-
related infrastructure projects and
serves as the entry point for the fluid
into the system.
• JACKWELL CUM PUMPHOUSE
• It is designed to to draw water from the
river or reservoir into the pumphouse using
pumps. The water is then lifted
• to a higher higher elevation or transported
through pipelines to the desired locations
for distribution or storage.
•
• PUMPING STATION
•
• A pumping station is a critical infrastructure
facility used to transport liquids, typically
water or ge, from one location to another. It
serves the purpose of moving liquids from a
lower elevation to a higher elevation or
from one location with low pressure to
another with higher pressure.
•
The choice of pipe type and size depends on factors such as
the water source's pressure, the distance of water transport,
the type of crops being irrigated, and the specific
requirements of the irrigation system. Proper installation,
maintenance, and management of irrigation pipes are
crucial for ensuring efficient water distribution, conserving
water resources, and maximizing crop yield in agricultural
fields.
Here is an overview of how water is supplied to an irrigation
field using a pipe system:
1. Water Source: The water source can be a river, lake,
reservoir, well, or any other water body from which water is
extracted for irrigation. In some cases, the water may also
come from treated wastewater or recycled water.
2. Pumping Station: If the water source is at a lower
elevation than the fields, a pumping station may be required
to lift the water and provide the necessary pressure to move
it through the pipe system. The pumping station houses
pumps and other equipment needed to lift and move the
water.
3. Main Supply Pipe: A large-diameter pipe, known as the
main supply pipe, is laid from the water source or pumping
station to the irrigation fields. This pipe is responsible for
transporting a significant volume of water over relatively
long distances.
• 4. Branch Lines and Sub-Mains: The main supply pipe is connected to smaller pipes called branch
lines and sub-mains. These pipes distribute the water to different sections of the irrigation field.
The diameter of these pipes depends on the required flow rate and the distance they need to cover.
•
• 5. Lateral Lines: Lateral lines are the smallest pipes in the system and are used to distribute water
directly to the individual plants or crops. They are placed along the rows of crops and can be either
buried underground or placed on the soil surface.
•
• 6
• 7. Control Valves and Automation: Control valves are strategically placed in the pipe system to
regulate the flow of water and control which areas of the field receive irrigation at any given time.
Automation systems can be integrated to schedule irrigation cycles and optimize water usage based
on factors such as soil moisture levels and weather conditions.
•
• By using a pipe system to supply water to the irrigation field, farmers can efficiently deliver water to
their crops, reduce water wastage, and ensure a more uniform distribution of water, which
ultimately leads to better crop yields and resource conservation.
SWITCH YARD
•
• A switchyard for a pump house is a vital component of the electrical infrastructure that facilitates
the distribution and control of electricity to power the pumps and other electrical equipment in the
pump house. The switchyard acts as an intermediate link between the power source (usually the
electrical grid or a power generator) and the pump house's electrical systems. Here are the key
features and considerations for a switchyard in a pump house:
•
• **1. Power Distribution:** The primary function of the switchyard is to distribute electrical power
efficiently and safely to the various pumps, motors, and electrical equipment within the pump
house. It typically consists of switchgear, circuit breakers, and transformers for controlling voltage
levels and managing power flow.
• Designing and implementing a reliable and efficient switchyard for a pump house is essential to
ensure smooth and safe electrical operations. It is recommended to involve experienced electrical
engineers and professionals to plan, design, and commission the switchyard to meet the specific
requirements of the pump house and comply with industry standards.
• A power station for a pump house is an essential component of a water distribution system. The
power station provides the necessary electrical power to operate the pumps and other electrical
equipment within the pump house. It ensures a reliable and continuous supply of electricity to
maintain the water supply or manage wastewater effectively. Here are the key aspects of a power
station for a pump house:
Structures
GANTRY GIRDER
• Usually, most of the industrial buildings have built-in overhead cranes for
handling heavy equipment or goods. With the help of the overhead
cranes, heavy equipment or goods can be lifted and moved from one point
of work place to another. The cranes may be hand operated (generally
they have a capacity of up to 5 tonnes) and electrically operated (EOT).
•
• Overhead travelling cranes are used in factories and workshops to lift
heavy materials, equipments, etc and to carry them from one place to the
other. These cranes are either hand operated or electrically operated. The
crane consists of a bridge spanning the bay of the shop. A trolley or a crab
is mounted on the bridge. The trolley moves along the bridge. The bridge
as a whole moves longitudinally on rails provided at the ends. The rails on
either side of the bridge rest on crane gantry girders. The gantry girders
are the girders which support the loads transmitted through the travelling
(moving) wheels of the cranes as shown in figure
FLOOR SLAB OR ROOF SLAB
• Design of floor or roof slab
•
• floor slab and a roof slab are both structural elements used in building construction, but they serve
different purposes.
• Floor Slab: A floor slab is a horizontal structural element that forms the bottom surface of a
building's floor. It provides a solid and level platform for occupants to walk on and supports the
weight of people, furniture, and other loads. Floor slabs are typically made of reinforced concrete
or sometimes steel. The thickness and design of the floor slab depend on factors such as the
expected load, span, and specific building requirements.
•
•
•
• Roof Slab: A roof slab, on the other hand, is a horizontal structural element that forms the upper
surface of a building's roof. It provides a protective covering over the building, shielding it from
weather elements such as rain, snow, and sunlight. The roof slab is designed to support its own
weight, as well as any additional loads such as equipment, maintenance personnel, or the weight of
accumulated snow. Roof slabs are commonly made of reinforced concrete, steel, or other roofing
materials such as tiles, shingles, or metal sheets.
• In summary, a floor slab is located at the ground level and provides a stable walking surface, while a
roof slab is located at the top of the building and forms the protective covering over the structure.
Both slabs are essential components of a building's structure and contribute to its overall strength,
stability, and functionality.
•
• Because of severe loading, the slab is prone to potential or sagging
bonding movement on the bottom surface at the centre of the span and
negative or hogging bending moment at top near supports. To counter
these moments main reinforcement is arranged at bottom surface along
the direction of span to get rid of positive bending moment.
• Based on the span, an RCC slab should be designed as either one way
reinforced slab or two way reinforced slab. In one way slab, beams provide
support to the slabs on the two opposite sides. When the ratio among the
length and width of the room over which the slab will be arranged remains
in excess of 2, one way slab is suitable. One way slab comprises of main
reinforcement distancing among the supports with dispersion of
reinforcement at right angles to it. Two way slab stretches in two
directions, when the length to breadth ratio remains under 2. Under such
situation, main reinforcement is arranged in both directions in the form of
a mesh.
• The complete thickness of slab normally remains 10 cm though the minimum
thickness increases up to 7.5 cm. The minimum area of reinforcement per unit
width of a slab shall not remain under 0.15% concerning the gross cross sectional
area of concrete. But because of other constraints, it is essential to arrange greater
percentage of steel in the slab.
•
• Spacing of bars of main reinforcement should not go beyond 3 times the effective
depth of slab and spacing for the distribution bars should not remain in excess of
five times the effective depth. Spacing in excess of 20 cm diameter for main bars
and not in excess of 40 cm for distribution bars should be arranged.
• Besides, the bars arranged at the bottom along the main direction, bars along the
longer extent are also provided on top of the main bars and at right angles to
them. These are known as ‘ distribution’ bars or ‘temperature reinforcement’ or ‘
transverse bars’. The purpose of the distribution bars is to control cracks caused by
deviation of temperature and shrinkage stresses. They also help in dispersing
loads. The area of such reinforcement normally remains 20 % of that of main
reinforcement. Plain M.S. bars with 6 mm diameter are normally utilized for this
purpose.
•
• Besides, the bars arranged at the bottom along the main direction, bars along the longer extent are
also provided on top of the main bars and at right angles to them. These are known as ‘
distribution’ bars or ‘temperature reinforcement’ or ‘ transverse bars’. The purpose of the
distribution bars is to control cracks caused by deviation of temperature and shrinkage stresses.
They also help in dispersing loads. The area of such reinforcement normally remains 20 % of that of
main reinforcement. Plain M.S. bars with 6 mm diameter are normally utilized for this purpose.
•
•
• In all buildings, slabs cover the full width of the wall over which walls are uplifted. It produces
partially fixed conditions for the slab. Under such condition, every alternate bar should be bent up.
This arrangement is inexpensive in respect of arranging extra bars at the top. The main bottom bar
is cranked at one-fifth of the span at either end and taken up.
•
•
• Main and distribution bars are attached together through black mild steel wire containing 16 guage
by affording a cross and twisting the ends. If wire with lower diameter is applied, double strands of
wire should be arranged rather than single strand. To bind 1 tonne of reinforcing bars, around 5 kg.
of binding wire is necessary.
RAFT FOUNDATION
• A raft or mat foundation is a sizable concrete slab or slab-and-beam
system whichsupports all the loads of superstructure through walls
or columns in two or more rows and rests on soil layer or rock. A
raft foundation may be rectangular or circular. When mat
foundation is supported by columns rather than theunderlying
materials, it is termed as Piled raft foundation.
•
• Mat or raft foundation is classified as a shallow foundation since its
depth is considerably smaller than deep foundation, but its depth is
greater than other typesof shallow foundation. It is useful in
controlling the differential settlement andtransferring the loads not
exceeding the bearing capacity of the soil due to integralaction of
the raft foundation.
• Mat foundations are an ideal type of foundation in several
conditions for instance low bearing capacity soil, spread footing
cover about 70% of the structure, highstructure loads, soft pockets
or cavities of in the soil to unknown extent raft, and highly
compressible soil and extents to a great depth.
•
•
•
• There are certain requirements that need to be considered during
the of raftfoundation in order to produce adequate design such as
minimum depth of 50cm,required excavation depth of
approximately 2.5m, and rebar cover of 50mm.
•
•
• Applicability of Raft (Mat) Foundations
• Low bearing capacity soil
• Spread footing cover about 70% of the structure
• High structure loads
• For heavy structures like chimneys, silos, tanks, large machines
• Structures and equipment sensitive to differential settlement
• Soft pockets or cavities of in the Soil to unknown extent raft
• Watertight construction under basements below groundwater
table
• Highly compressible soil and extends to a great depth
RETAINING WALL
• Retaining walls are relatively rigid walls used for supporting soil laterally so that it can be retained
at differentlevels on the two sides. Retaining walls are structures designed to restrain soil to a slope
that it would not naturally keep to (typically a steep, near-vertical or vertical slope). They are used
to bound soils between two different elevations often in areas of terrain possessing undesirable
slopes or in areas where the landscape needs to be shaped severely and engineered for more
specific purposes like hillside farming or roadway overpasses. A retaining wall that retains soil on
the backside and water on the front side is called a seawall or a bulkhead.
•
•
•
• The most important consideration in proper design and installation of retaining walls is to
recognize and counteract the tendency of the retained material to move downslope due to gravity.
This creates lateral earth pressure behind the wall which depends on the angle of internal
friction(phi) and the cohesive strength (c) of the retained material, as well as the direction and
magnitude of movement the retaining structure undergoes.
•
•
•
•
•
•
PIER AND BREAST WALL
• PIER AND BREAST WALL
• A pier and breast wall is a type of combined structure used in hydraulic structures
construction to provide support and stability to the structures deck and withstand
the forces exerted by the hydraulic structure loads and the surrounding
environment. It is commonly employed in situations where the bridge spans a
water body or a significant gap.
• A pier is a vertical structural element that serves as a support for the bridge deck.
It is typically constructed with reinforced concrete or steel and extends from the
foundation or footing to the height necessary to support the bridge
superstructure. Piers are strategically placed at intervals along the bridge to
provide the required support and resist vertical and horizontal forces.
• A breast wall, also known as an abutment wall or wing wall, is a horizontal or
sloping structural element that connects the bridge pier to the adjacent land or
embankment. It is built perpendicular to the bridge axis and helps distribute the
loads from the bridge deck to the ground. Breast walls are designed to provide
lateral support and prevent the embankment from spreading or eroding under the
loads and forces exerted by the bridge.
• The combination of the pier and breast wall creates a stable and integrated system
that ensures the structural integrity of the bridge. The breast wall transfers the
lateral forces from the bridge deck to the pier, which in turn transfers the loads to
the foundation and ground. By providing support and stability, the pier and breast
wall system allows the bridge to safely carry the traffic loads and resist external
forces such as wind, water flow, and seismic activity.
• The design and construction of pier and breast wall structures vary depending on
factors such as the bridge type, span length, soil conditions, water conditions, and
site-specific requirements. Detailed engineering analysis and calculations are
performed to ensure that the structure can withstand the anticipated loads and
forces over its design lifespan.
• It's worth noting that the specific terminology and usage of pier and breast wall
can vary in different regions or contexts. Consulting with a qualified engineer or
bridge design professional is recommended for accurate and specific information
regarding the design and construction of pier and breast wall structures in a
particular project.
•
THRUST BLOCK
• A thrust block is a reinforced concrete structure or block that is used to resist the
thrust or horizontal forces generated by a pipeline or conduit system. It is typically
installed at changes in direction, such as bends or elbows, or at the endpoints
where the pipeline changes direction abruptly.
• When fluid flows through a pipeline or conduit system, it exerts a force on the
walls of the pipe. Changes in direction, particularly sharp bends, can result in
significant horizontal forces, known as thrust, acting on the pipe. These forces have
the potential to push or displace the pipeline, causing damage to the system or
surrounding infrastructure.
• Thrust blocks are designed and constructed to counteract these horizontal forces
and provide resistance to the movement of the pipeline. They are typically
constructed as solid concrete blocks adjacent to the pipeline. The size, shape, and
reinforcement of the thrust block are determined based on factors such as the
pipe size, fluid pressure, angle of the bend, and soil conditions.
• By anchoring the pipeline and preventing movement, thrust blocks help maintain
the structural integrity and stability of the pipeline system. They ensure that the
pipe remains in its intended position and minimizes the risk of damage or failure.
Typical thrust block installations
STAIRS
•
• Stairs are a series of steps or flights that
provide vertical access between different
levels of a building or structure. They are an
essential architectural and structural element
•
COLUMN
• There are various types of RCC Column based on its shape, length and
forces. Function and construction methods are discussed here for these
types of column. Column is a vertical member which takes complete load
of the beam, slabs and the entire structure and the floor and other area of
the building is adjusted as per the requirement of the client or owner. The
size of the columns, quantity of cement sand and aggregate to be mixed,
the number of steel bars to be placed, spacing between the stirrups is all
mentioned in the structural drawing which is designed by structural
designer as per the actual load on the column and considering the factor
of safety. A column is a vertical member which effectively takes load by
compression. Basically column is a compression member as load acts
along its longitudinal axis. Bending moment may occur due to wind
earthquake or accidental loads. Column transfers the load of the structure
of slabs beams above to below, and finally load is transferred to the soil.
Position of the columns should be so that there are no tensile stresses
developed at the cross section of the columns. Columns location should
be such that it hides in the walls partially or fully.
Details of isolated footing
reinforcement
• It is just as crucial to do a thorough site investigation prior
to placing a footing as it is during the structural design
phase. The importance of ensuring the footing’s structural
integrity is shown in its meticulous attention to detail.
Detailing such as the minimum reinforcement needed, bar
diameters, and allowable footing dimensions, as well as a
cover-to-reinforcement ratio dictated by environmental
factors, are all examples of proper reinforcement.
• A footing’s primary reinforcement must be at least 50
millimetres thick if it will be in touch with the ground.
However, for surfaces that will be open to the environment,
such as surface levelling PCC, the primary reinforcement
should be at least 40 millimetres thick.
Designing isolated footings for
specific loads
• When designing an isolated footing, there are a few things to keep in
mind, including:
• Determine the space required for the footings by utilising the calculated
loads.
• Take into account an appropriate thickness for the footing.
• Compute the flexure critical section as well as the shear critical section.
• Perform the calculations necessary to determine the bending moment as
well as the shear stresses in the tangential direction.
• Investigate the extent of the predicted layer’s thickness.
• Investigate the specifics of the reinforcement, and check that there are no
bearing stresses in the structure.
• Check to see how long the process of development will take.
• The weights on the footings, the soil’s safe bearing capacity (SBC), the
concrete quality, and the steel strength are all taken into account
throughout this process.
BEAM
• The design of a reinforced concrete beam is achieved through a trial and error method. However, design codes,
certain thumb rules, and past experiences can significantly reduce the lengthy design process.
• Initially, certain aspects of design, like geometry and self-weight, should be estimated and then checked during
the design process. The applicable codes such as ACI 318-19 provide specifications to help the designer, but some
estimations and assumptions are still required to be made.
• An experienced designer can come up with very accurate assumptions. In contrast, new designers, who have little
or no experience, have to rely on trial calculations or arbitrary rules modified to suit a particular situation.
• Design assumptions for reinforced concrete beams may be required for the self-weight of a beam and its
geometrical dimensions. Design codes provide specifications regarding bar size selection, spacing, concrete cover,
and bar placement.
• Assumptions and Specifications for Design of Reinforced Concrete Beam
• 1. Beam Dimension
• The size of a beam is governed by negative moments or shear forces at supports. ACI moment coefficient can be
used to calculate moments of a particular span. Alternatively, designers can estimate the depth of a beam at 60
mm to 65 mm per meter of the beam's span.
• Requirements related to the width-depth ratio of reinforced concrete beams are not provided by codes. However,
as a rule of thumb, it is better to use a depth which is two and a half to three times the beam's width. For long-
span beams, it is economical to use deep and narrow sections.
• However, architectural considerations may prevent the use of deep concrete beams, and the designer would be
obliged to select wide beams. The lesser the number of different beam sizes in a structure, the better it is from an
economic standpoint.
• Beam width (b)
• The ratio of beam depth to its width is
recommended to be between 1.5 to 2 with upper
bound 2 being the most common used. The
reinforcement arrangement is one of major
factors that specify beam width. So, minimum bar
spacing shall be considered while beam width is
estimated. The width of the beam shall be equal
or less than the dimension of the column
• Reinforcing bar sizes
• Generally, it is advised to avoid the use of large
bar sizes for beams. This is because such bars
cause flexural cracking and required greater
length to develop their strength. However, large
bar size placement cost is smaller than the
installation cost of large number of small bar
sizes. Moreover, common bar sizes for beams
range from NO.10 to NO.36 (SI unit) and the two
larger diameter bars NO.43 (NO.14) and NO.57
(NO.18) are used for columns.
• Furthermore, it is possible to mix different bar
diameter to meet steel area requirements
more closely. Finally, the maximum number of
bars which can be installed in a beam of given
width is controlled by the bar diameter,
minimum spacing, maximum aggregate size,
stirrup diameter, and concrete cover
requirements.
• Spacing between bars
• This minimum spacing shall be maintained to
guarantee proper placement of concrete around
steel bars. Additionally, to prevent air pockets
below reinforcements, and ensure good contact
between concrete and bars so as to achieve
satisfactory bond. If two layer of steel bars are
placed in a beam, then the distance between
them shall not be less than 25 mm.
• Concrete protection for reinforcement
• the designer must maintain minimum thickness or
concrete cover outside of the outermost steel to
provide the steel with adequate concrete protection
against fire and corrosion. According to ACI Code 7.7,
concrete cover of 40 mm for cast in place beams, not
exposed directly to the ground or weather. At least
50mm cover, if the concrete surface is to be exposed to
the weather or in contact. To simplify construction and
thereby to reduce costs, the overall dimensions of
beams, b and h are almost rounded up to nearest 25
mm.
BASE PLATE
• A base plate, also known as a base or sole plate, is a flat, horizontal structural component that
serves as the foundation or anchor for other structural elements. It is typically made of steel or
reinforced concrete and is used to distribute the loads from columns, posts, or equipment to the
supporting surface, such as the foundation or floor.
• Here are some key aspects of base plates:
• Load Distribution: The primary function of a base plate is to distribute the vertical loads from the
supported element, such as a column or post, to the underlying foundation or structure. The base
plate spreads the load over a larger area to prevent excessive stress on the supporting surface.
• Stability: Base plates also provide stability and resistance against horizontal forces or moments. By
securely anchoring the supported element to the foundation or floor, the base plate helps to
prevent overturning or lateral movement.
• Connection: Base plates are typically attached or connected to the supported element, such as a
column or post, through bolts, welds, or other means. This connection ensures that the load is
transferred efficiently from the supported element to the base plate.
• Size and Shape: The size and shape of a base plate depend on factors such as the load magnitude,
the type of supported element, and the soil or foundation conditions. Base plates are designed with
adequate dimensions and thickness to handle the expected loads and prevent excessive deflection
or deformation.
• Anchorage: Base plates often incorporate anchor bolts or dowels to provide a secure connection
between the base plate and the underlying foundation. These anchor bolts are embedded or
attached to the foundation to prevent uplift or movement of the base plate.
• Base plates are commonly used in a variety of structures, including buildings,
bridges, industrial equipment, and machinery. They play a crucial role in providing
stability, load transfer, and support for the supported elements.
• The design and specification of base plates should be done in accordance with
engineering principles, applicable codes, and project-specific requirements.
Consulting with a structural engineer or design professional is recommended to
ensure proper design, sizing, and installation of base plates for your specific
project.
•
•
• The base plate acts as an interface between the superstructure and the
foundation; thus, completing the load path into the foundation. Base plates help
provide a uniform distribution of superstructure loads to the foundation, and
therefore conform to the shape of the foundation, typically a square or a
rectangle.
•
Plans and drawing
ACTIVITIES AND RESPONSIBILTIES
PLASTERING
• Plaster is a thin layer of mortar applied over the
masonry surface and it acts as a damp-proof coat
over the brick masonry work. Plastering also
provides a finished surface over the masonry that
is firm and smooth hence it enhances the
appearance of the building. The primary
objectives of plastering are to protect the surface
from atmospheric influences, to cover the
defective workmanship in masonry, to conceal
porous materials, and to provide a suitable
surface for painting.
• Plaster is a thin layer of mortar applied over the masonry surface and it
acts as a damp-proof coat over the brick masonry work. Plastering also
provides a finished surface over the masonry that is firm and smooth
hence it enhances the appearance of the building. The primary objectives
of plastering are to protect the surface from atmospheric influences, to
cover the defective workmanship in masonry, to conceal porous materials,
and to provide a suitable surface for painting.
•
• Procedure of Plastering Work
• 1. Preparation of Surface for Plastering
• Wash the mortar joints and entire wall to be plastered, and keep it wet for
at least 6 hours before applying cement plaster.
• 2. Groundwork for Plaster
• 3. Applying Under Coat or Base Coat
• 4. Applying Finishing Coat
• 5. Curing of Plastering works