Skip to main content
RWS&S, Division : Rayagada
Name of the Project : Execution of Rural Piped Water Supply Projects
pertaining to Bissamcuttack block of Rayagada District
including five years Operation & Maintenance”
Agreement Cost : 84.22Cr
Executing Agency : Zuberi Engineering Construction Pvt. Ltd., Jaipur
Date of Commencement : 17-12-2019
Scheduled date of completion : 31-12-2021
2nd Extended Date : 31-12-2023
Salient Feature of Scheme -1 Kosagumada Block
SALIENT FEATURE (ZECPL) (JJM) Dt. 15.11.2023
1 Name of the work Execution of Rural Piped Water Supply Projects pertaining to Bissamcuttack block of Rayagada District
Details of Scheme PWS to 18 GPs of Bissamcuttack Block.
2 Agreement No EIC/RWSS/58/2018-19
3 Agreement Value Rs 84.22 Crores ( Execution – 80.46 Cr + O&M 3.76 Cr )
4 Date of signing of contract 17/12/2029
Extetendet Date of Completion 31/12/2023
5
6 Executive Agency Zuberi Engineering Construction Pvt. Ltd. Jaipur.
7 GP covered Bissamcuttack 18GPs.
Villages- 263
No's
Habitation-
263No's
79588
(Population) FHTC - 22825No's
Target Achivement % Progress Expected Completion
date
Remarks
8 Intake Well
Well size - 8mtr dia
100% 70% 97% 28.02.2024 In all respect
V T Pump- (2W+1S) – 280Cum/Hr, H-121M
Motor - 125KW - 167 HP
Transformer -(33/0.435KV) 1250KVA - 1No.
DG - (62.50 KV) - 1No.
9 Water Tretment Plant
Capacity – 10.6MLD
100% 78% 80% 30.05.2023 In all respect
HSC Pump- (4W+2S) – 104.69 & 179.31 Cum/Hr,
H-163 &227 M.
Transformer -(33/0.4KV) 1600KVA - 1No.
DG - (62.50 KV) - 1No.
10 ESR/GSR 18Nos 18 3 77% 30.01.2023
11 Pipe line Target in Km
Achivement
in Km
% Age
A Raw water - DI Pipe line 10.807
10.445
97% 30.11.2023
B Rising Main - DI Pipe line
89
83 94% 30.12.2023 PWD Clearance required 3 KM
C Distribution line - HDPE Pipe Line 506 468 92% 30.01.2024 Permission required for FHTC in Some villages.
12 FHTC 22825 17773 78% 30.01.2024
13 Transmission line work
Poles
11 Km 1 Km 9% 31.05.2024
Conductor
14 Overall Progress Physical 85%
Financial 73%
15 Expected Date of Completion 30-05-2024
Progress Photographs : (Scheme : I)
Intake well
Location : , Kutraguda village, Bissmcuttack Block.
River Source : Vanshdhara River
Capacity : 10.6 MLD
Intake well
Sl No. Component Completed as on date
17.10.2023
Completed as on date
18.11.2023
Completion Date
1 Intake well & Pump House Structure completed
upto Pump Floor Beam
Bottom Level.
Structure completed up
to Pump Floor Slab.
20-12-2023
2 Pier Pier completed upto
Pier cap bottom
Structure completed up
to Pump Floor Slab.
20-12-2023
3 Pannel Room Not Started. 30.12.2023
4 Mechanical work Not Started. 28.02.2024
5 Electrical work Electrical work under
progress
28.02.2024
10.6MLD WTP
Sl No. Component Completed as on date
17.10.2023
Completed as on date
18.11.2023
Completion Date
1 CASCADE AERATOR Structural work
Completed
Completed
2
FLASH MIXER 1 & 2
Structural work
Completed
Completed
3 CLARIFLOCCULATOR 1 Completed Completed
4 CLARIFLOCCULATOR 2 Completed Completed
5 Wash water recovery Tank Completed Completed
6 Clarifier sludge sump Not Started Not Started 20-12-2023
7 CWR Completed up to FRB
Bottom
Top Dome Work Under
Progress
15-12-2023
8 Pump House Completed up to Raft. Completed up to 1st
lift RCC
Wall.
31-01-2024
9 Raw water Channel & Bypass
Channel
Raw channel Completed. Bypass channel completed.
to Channel slab
30.11.2023
10 Filter house & Annex Building Comp. up to filter inlet
channel
Slab work under progress 31.12.2023
11 Sludge thickener sump &
Centrifuge Building
Thickener completed &
Centrifuge Building comp. up to
3rd lift
Centrifuge Building completed upto
Lintel Beam
31.12.2023
13 Back wash over head tank Full staging complete Bottom Dome work under
progress.
31-01-2024
Progress Photographs : (Scheme : I)
WTP : Aerial View
Location : Purnapani Village Bissamcuttack Block.
Capacity : 10.6 MLD
DAILY WATER SUPPLY ESR WISE: TOTAL NO OF ESR 25
Sl. No. Block Name of GP Name of ESR Staging
Height (M)
Capacity
In KL
Completed as on date 18.11.2023 Completi
on Date
FHTC Scope & Supply Data
Target/Achievement/Supply
1
Hatmuniguda Hatamuniguda 15 550
Completed
2
Hazaridonga Hazaridonga 15 250
Completed
3
Kankubadi Kankubadi 15 250 Completed
4
Chatikona Chatikona 25 450
Top Dome work is under progress 10.12.2023
5
Bhatpur Bhatpur 25 150
Up to full staging 31.01.2024
6
Durgi Durgi 18 450
Top Dome work is under progress 10.12.2023
7
Dumernelli Dumernelli 18 250
Top Dome work is under progress 15.12.2023
8
Sahada Sahada 10 350
Bottom dome Under Progress 15.01.2024
9 Bissamcuttack
Dukum Dukum 25 300
Up to full staging 15.03.2024
10
Thuapadi Thuapadi 25 150
Up to full staging 31.03.2024
11
Paidakulguda Paidakulguda 20 250
Up to full staging 31.03.2024
12
Chanchraguda Chancharaguda 22 200
Up to full staging 30.03.2024
13
Kumardhamuni Kumardhamuni 15 300
Bottom dome Under Progress 15.02.2024
14
Bethiapada Bethiapada 15 300
Bottom dome Under Progress 15.02.2024
15
Konabai Konabai 07 250
Raft Work. 15.02.2024
16
Kutraguda Kutraguda 22 300
Excavation Under Progress 30.05.2024
17
Jhigdi Urlajodi 22
350 30.03.2024
BISSAMCUTTACK.pptx zindagi ka number hai kya hain ye
BISSAMCUTTACK.pptx zindagi ka number hai kya hain ye
BISSAMCUTTACK.pptx zindagi ka number hai kya hain ye