 Introduction
 Over view at Haridwar Plant
 Layout of Block-3
 Details of Bay 1(Assembly, Machine shop and
OSBT)
 Details of Bay 2(Gas turbine section and rotor
assembly)
 Details of Bay 3(Governing and Broad
specifications of major machines)[CNC & Non
CNC]
 Bay 4( Blade and Heat treatment shop)
 BHEL is the largest engineering and
manufacturing enterprise in India in the
energy field today. It was established more
than 40 years ago and has been earning the
profits since 1971.
 It has very wide network over 150 project
sites, 8 service centers and 18 regional
offices and Headquarters in New Delhi. More
over it is one of the navratna of government
of India. 75% of electricity in India is
produced with the help of BHEL equipments.
3
 Vision :World class, innovative, competitive,
and profitable engineering enterprise
providing total business solutions.
 Mission :The leading engineering enterprise
providing quality product systems and
services in the field of energy,
transportation, infrastructure and other
potential areas.
 Manpower :Total strength is more than
10000 which includes around 3000 qualified
engineers and technicians, 5200 skilled
artisans and the rest in other categories.
4
Bay 1 Assembly, Heavy machine shop, OSBT
Bay 2 Gas turbine assembly, Rotor assembly
Bay 3 Governing section, Light machine shop
Bay 4 Blade shop, Heat treatment shop
5
6
 The final assembly of the turbine is done in
bay 1. Main assembly parts:
 1. High pressure steam turbine
 2. Intermediate pressure steam turbine
 3. Low pressure steam turbine
 4. Bearing pedestals
 5. Control valves
7
 This is the smallest of the three turbines. It
consists of two shells namely inner inner and
outer outer. Inner inner part is the part on
which guide blades are placed and outer
outer part mainly works as a casing of the
turbine. HP outer outer lower half is placed
on bed and leveling is done; now upper half
is assembled and alignment is done; now GBC
is aligned with respect to centre.
 Final alignment is checked and turbine is
dispatched in the assembled conditions.
8
9
 Capacity 210/250 MW
 Main components
 IP outer casing
 Inner casing
 GBC
 Shaft seals
 Rotor
 Descriptions In outer casing, lower half is placed on bed
and leveling is done. U/H is assembled and alignment is
done now inner casing is placed and it is aligned with help
of keys and pokers. Rotor is placed and alignment of rotor
is done, now axial and radial gap between inner casing and
rotor are checked (flow path). The studs are heat
tightened to achieve elongation. Turbine is dispatched in
assembled conditions.
10
 Capacity 210/250/500MW
 Main components:
 LP inner outer
 LP inner inner
 LP outer outer
 LP GBC
 Rotor
11
 LP I/O lower half is placed on bed and
leveling is done. Now upper half is assembled
and alignment is done. Now GBC is aligned
with respect to centre then GBC 2 and GBC 3
are aligned. Then inner core is aligned with
help of adjustment pokers.
 Now projection pipes are welded then
diffusers are aligned. Final alignment is
checked and turbine is dispatched in
disassembled condition
12
13
 Front HP/IP/LP, 210/250/500MW pipelines
are hydraulically tested. Then bearing is
aligned with help of phins, and pinning is
done. Assembly is completed and dispatched
in assembled conditions.
14 14
15
Valve seats are fitted in the casing by cooling in liquid oxygen. Pinning
of seats is done, welding of nipples and flanges is done and then
hydraulic testing with valves covers, now casing is sent for edge
preparation and the color of valve assembly and valve seat is checked.
Travel of valve is checked and locking is done. Then trial assembly of
s/m is done. Valve is dispatched in assembled condition.
 In this, there are very costly and big machines
which are used to carry operation on large parts
of a turbine such as rotor, diffuser, casing etc.
1) Machine number 1-120
Center lathe machine CNC
 Job: HP Rotor (on that time)
 Operation: slotting
 Specifications of the machine:-
 Main spindle bore: - 150mm
 Distance between centers: - 12000mm
 Turning dia. Over bed cover: - 1400mm
 Turning dia over carriage: - 1100mm
16
2) Machine number 1-28
Horizontal boring machine (Russian)
 Operation performed: - tapping,
threading,drilling, boring, facing, milling
etc,except knurling
 Specifications
 Capacity: - 600mm (bore dia)
 Weight capacity: - 40 tonne
 Dia of spindle: - 150 mm
17
Over speed balancing tunnel :
 This is the one of the most important section of the
turbine block. Here after the complete checking of
the rotor from the bay 1, rotor is bringing to get
check it in the working conditions. Here we rotate
our rotor in the vacuum condition on a very small
film of oil consisting of some microns; here the oil is
on very high pressure. Rotor is revolved on 3750 rpm,
while in the operating conditions rotor revolves at
3000rpm (500mw).
 The time being for which rotor is revolved is 3
minutes. The power required to rotate that much of
heavy rotor is very high which comes from the high
voltage line nearly of 11000 Volts, and the gear box
with the synchronize motor is used to get accurate
and desired speed
18
Oil plays a very important role in the rotor checking
the oil comes from the underground tanks having a
capacity up to 30000 liters this is pumped with the
help of large pumps and a large quantity of oil is
supplied continuously so that oil film doesn’t break.
Here we use a number of filters on many stages so
that oil is checked out against dust particles or any
foreign particles the attention is paid during this
checking so that everything going OK. The full
control of OSBT is done with help of control system
which is in control room, each and every care is
taken during the complete testing. The complete
checking of rotor costs nearly 8 crore Rs. Which is a
very high cost and after this testing if we find there
is any loosening in the blades or any blade is out of
its position then the department of OSBT sends the
rotor to the BAY1 along with checking report and
every effort is now put on the rotor so that it pass
the checking in the OSBT only then rotor is
assembled with the casing and dispatched. film
doesn’t break.
19
20
SYSTEM TO CREATE VACCUM FOR THE OSBT,AT BHEL HARDWAR
PART A: -Gas turbine section
The main thing that is done here is that the making of rotor for
the gas turbine, the rotor of gas turbine is very different from
that of the steam turbine, here the rotor is made in the form of
discs and after that the complete rotor is made by joining the
discs.
On a simple disc firstly the grooves are cut on the broaching
machine , very similar to the gear cutting process. Now after
cutting one groove the indexing is done and the machine is ready
to cut the another groove. after cutting the all grooves on the
periphery of the disc now the process is done to make teethes on
both the surfaces with the help of the grinding so that each disc
should mesh all the teethes and proper joining and the alignment
can be done, and similar process is done to all the other discs,
now before assembling the all the discs an very important
operation is done to check the accuracy of all the discs in
meshing, and the operation is named as the Colour matching.
21
 Colour matching It is the process to check
the complete meshing of the two joining
parts here the part on which we have to join
is colored and the mating part is put on it so
that complete transfer of color on the other
part could be done if there is not the equal
distributions of the color on the second part
then the portions are identified to be
machined so that complete and accurate
matching could be done.
 Now after checking all the discs the blades
are inserted in the respective grooves and
now the shrink fitting of these discs is done
on the solid shaft which would be passing
from each disc thoroughly.
22
 Shrink It is the process of joining two parts, one
part Is called male part and the other is called as
female part, the party on which we have to
insert other part is called as male part and
another would be female part.
 In this process the male part is cooled say in the
liquid oxygen so that it contracts and the female
part is expanded by heating and now both the
parts are superimposed and are subjected to
room temperature conditions and after some
time both parts are tightly joined. Here in the
gas turbine rotor the shaft is the male part and
the discs are called female part.
 In this way the complete rotor of the gas turbine
is prepared and the testing of the rotor as in the
case of steam turbine is carried out in the OSBT.
fitting
23
In this section the rotor making is done for the steam turbine HP, LP, IP.
For the any steam turbine firstly the rotor is in the form of the shaft, the
procedure to make the complete rotor is explained here in the steps:-
 The rotor shaft is placed on the centre lathe machine and turning and
taper turning is done according to the provided drawings.
 Then grooves cutting is done for the blades fixing on all over the length
of the rotor accordingly as per in the drawing.
 Now with the help of the crane the rotor is placed on the other machine
on which rotor is just revolved to do the indexing.
 Talking about one groove a extra portion is cut so that blades can be
inserted in it easily.
 Then a locking blade is fixed to get lock all the blades of one stage. Here
unlike in gas turbine a single blade is fixed but in the GT each and every
blade was fixed individually.
 Sealing are placed on the portion in between two stages so that these
sailings match with the same sealing made on the casing so that leaking
of the fluid can be avoided from one stage to the other stage.
 After doing all this work the rotor is now send to the Bay 1 so that final
inspection and the checking in OSBT could be done and the finally rotor
with proper alignment is assembled in the casing.
24
Contents: - Governing section, light machine shop
Section 1:- Governing section
 Governing is the process of controlling the speed of
the rotor so that we can get constant frequency
under the fluctuating loads. This is done by
controlling the amount of fluid going inside the
turbine, means to say if the load is less that mean
speed of the rotor would tends to increase then we
make the less steam to enter inside so that rotor
speed come to desired value. Opposite thing Is done
in case of the heavy load when the speed of the
turbine is less more steam is made to enter inside the
turbine. To control this all, at the steam enterance
we use an electronic and mechanical system which
consists of oil pumps, servo motors pipes and many
indicators on the valve mouth.
25
Section 2:- Machine shop
A. CNC machines
 CNC LATHE
 CNC MILLING MACHINE
 CNC VERTICAL BORER
 CNC SURFACE BROACHING M/C
 CREEP FEED GRINDING M/C
 BROACH SHARPENING M/C
B. Non CNC machines
PRECISION HEAVY DUTY LATHE
26
Sections
 1. Turbine blade manufacturing.
 2. Heat treatment
Blades of turbine:-
 Blades are one of the most crucial parts of a
turbine. Blades are fitted in the grooves .The
shape of the blades is of aerofoil type
27
There are two types of blades (i) Guide blades (ii) Moving
blades
 1. Guide blades:-These blades are remained fixed during
the motion of the runner so these are also called as
fixed blades .These blades are fitted in the grooves in
the casing. The sealing action is also done before putting
the blades in the grooves so that during working
conditions the leakage of fluid can be stopped. Guide
blades are put in guide blade carriers.
 2. Moving blades:-As the name suggests these blades
remain in moving condition for the whole life cycle of a
turbine. They are arranged so that they become
opposite to the direction of the fixed blades. This
arrangement will help in striking of the fluid on more
area of the moving blades and hence helps in I
 Material for blades:-
 For steam turbines we mainly use the chrome steel, steel
with some % of V, W etc.
 For some special type of gas turbines we import blades
from other countries such as Germany, Russia etc.
ncreasing the efficiency of the turbine.
28
 Importance of wrang in blade shop:-
 Due to the aerofoil type of shape of the
blades it is not easy to handle the blades
when we are performing various operations
on them, so a material with low melting
point (100 deg. Cel.) is used for this purpose.
For this a die is taken, the blade is put
between the wrang and various machining
operations are performed. To take the blades
outside the die with blade, we put the die in
boiling water, wrang melts and thus blade is
taken outside.
29
 Working of blades:-
30
The fluid coming from the boiler is highly energetic the guide blades
which are also called as fixed blades Are arranged so that they are in
oppposite direction to moving blades,it helps the maximum fluid to
strike on the moving blades and increases the efficiency of turbine.
THANK YOU……….
31

More Related Content

What's hot

Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1
khemraj298
 
BHEL Final Report
BHEL Final ReportBHEL Final Report
BHEL Final Report
Bharti Airtel Ltd.
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
Devendra Kumar
 
Bhel ppt
Bhel pptBhel ppt
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
Sumit Singh
 
BHEL Trainning Report
BHEL Trainning ReportBHEL Trainning Report
BHEL Trainning Report
Pradip Goswami
 
Industrial Training BHEL
Industrial Training BHELIndustrial Training BHEL
Industrial Training BHEL
Lalit Kumar
 
B.H.E.L., Haridwar Summer Training Report
B.H.E.L., Haridwar Summer Training ReportB.H.E.L., Haridwar Summer Training Report
B.H.E.L., Haridwar Summer Training Report
Abhishek Kumar
 
BHEL steam turbine manufacturing
BHEL steam turbine manufacturingBHEL steam turbine manufacturing
BHEL steam turbine manufacturing
Sakshyam Rai
 
BHEL PROJECT REPORT ( TRAINING REPORT )
 BHEL PROJECT REPORT ( TRAINING REPORT ) BHEL PROJECT REPORT ( TRAINING REPORT )
BHEL PROJECT REPORT ( TRAINING REPORT )
jaideep kishanpuri
 
general awareness in steam turbine manufacturing
general awareness in steam turbine manufacturinggeneral awareness in steam turbine manufacturing
general awareness in steam turbine manufacturing
Gaurav Sharma
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
Rajan Kumar Choudhary
 
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
Abhishek Chaudhary
 
bhel report file on turbine shop & blade
 bhel report file on turbine shop & blade bhel report file on turbine shop & blade
bhel report file on turbine shop & blade
ABHISHEK SINGH
 
training report on steam turbine manufacturing
 training report on steam turbine manufacturing training report on steam turbine manufacturing
training report on steam turbine manufacturing
aryannigam
 
PPT on summer training BHEL BHOPAL by Chetan Sahu
PPT on summer training BHEL BHOPAL by Chetan SahuPPT on summer training BHEL BHOPAL by Chetan Sahu
PPT on summer training BHEL BHOPAL by Chetan Sahu
Chetan Sahu
 
Bhel vocational training report_1301
Bhel vocational training report_1301Bhel vocational training report_1301
Bhel vocational training report_1301
Shubham Yadav
 
Vocational training report (SIRTE, BHOPAL)
Vocational training  report (SIRTE, BHOPAL)Vocational training  report (SIRTE, BHOPAL)
Vocational training report (SIRTE, BHOPAL)
Akshay Suryawanshi
 
Bhel summer training (industrial training) report
Bhel summer training (industrial training) reportBhel summer training (industrial training) report
Bhel summer training (industrial training) report
Ratnesh Ahirwar
 
Bhel steam turbine manufacturing
Bhel steam turbine manufacturingBhel steam turbine manufacturing
Bhel steam turbine manufacturing
Home
 

What's hot (20)

Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1Bhel haridwar vocational training report block 1
Bhel haridwar vocational training report block 1
 
BHEL Final Report
BHEL Final ReportBHEL Final Report
BHEL Final Report
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
 
Bhel ppt
Bhel pptBhel ppt
Bhel ppt
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
 
BHEL Trainning Report
BHEL Trainning ReportBHEL Trainning Report
BHEL Trainning Report
 
Industrial Training BHEL
Industrial Training BHELIndustrial Training BHEL
Industrial Training BHEL
 
B.H.E.L., Haridwar Summer Training Report
B.H.E.L., Haridwar Summer Training ReportB.H.E.L., Haridwar Summer Training Report
B.H.E.L., Haridwar Summer Training Report
 
BHEL steam turbine manufacturing
BHEL steam turbine manufacturingBHEL steam turbine manufacturing
BHEL steam turbine manufacturing
 
BHEL PROJECT REPORT ( TRAINING REPORT )
 BHEL PROJECT REPORT ( TRAINING REPORT ) BHEL PROJECT REPORT ( TRAINING REPORT )
BHEL PROJECT REPORT ( TRAINING REPORT )
 
general awareness in steam turbine manufacturing
general awareness in steam turbine manufacturinggeneral awareness in steam turbine manufacturing
general awareness in steam turbine manufacturing
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
BHEL MECHANICAL ( 4TH YEAR ) INTERNSHIP -BLOCK-3(TURBINE SHOP)
 
bhel report file on turbine shop & blade
 bhel report file on turbine shop & blade bhel report file on turbine shop & blade
bhel report file on turbine shop & blade
 
training report on steam turbine manufacturing
 training report on steam turbine manufacturing training report on steam turbine manufacturing
training report on steam turbine manufacturing
 
PPT on summer training BHEL BHOPAL by Chetan Sahu
PPT on summer training BHEL BHOPAL by Chetan SahuPPT on summer training BHEL BHOPAL by Chetan Sahu
PPT on summer training BHEL BHOPAL by Chetan Sahu
 
Bhel vocational training report_1301
Bhel vocational training report_1301Bhel vocational training report_1301
Bhel vocational training report_1301
 
Vocational training report (SIRTE, BHOPAL)
Vocational training  report (SIRTE, BHOPAL)Vocational training  report (SIRTE, BHOPAL)
Vocational training report (SIRTE, BHOPAL)
 
Bhel summer training (industrial training) report
Bhel summer training (industrial training) reportBhel summer training (industrial training) report
Bhel summer training (industrial training) report
 
Bhel steam turbine manufacturing
Bhel steam turbine manufacturingBhel steam turbine manufacturing
Bhel steam turbine manufacturing
 

Viewers also liked

Grant nov99
Grant nov99Grant nov99
Grant nov99
Clifford Stone
 
PPT ON INDUSTRIAL TRAINING IN BHEL HARIDWAR
PPT ON INDUSTRIAL TRAINING IN BHEL HARIDWARPPT ON INDUSTRIAL TRAINING IN BHEL HARIDWAR
PPT ON INDUSTRIAL TRAINING IN BHEL HARIDWAR
Anil Gupta
 
STEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGSSTEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGS
Akhil Krishnan G
 
turbine governing oil system
turbine governing oil systemturbine governing oil system
turbine governing oil system
pradeep chotia
 
Governing of hydraulic turbines.
Governing of hydraulic turbines.Governing of hydraulic turbines.
Governors
GovernorsGovernors
Governors
ASAD ABID
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
Salil Vaidya
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
Gaurav Kaushik
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection system
Sachin Pyasi
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.
Anish Anand
 
Construction and manufacturing of steam turbine
Construction and manufacturing of steam turbineConstruction and manufacturing of steam turbine
Construction and manufacturing of steam turbine
Home
 
Governor Woodward 505 calibration
Governor Woodward 505 calibrationGovernor Woodward 505 calibration
Governor Woodward 505 calibration
Lalit_943240
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
SAI SHARATH GAMPA
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
Nagesh H
 
Best ppt on thermal power station working
Best ppt on thermal power station workingBest ppt on thermal power station working
Best ppt on thermal power station working
Ronak Thakare
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Shikhar Sodhani
 

Viewers also liked (16)

Grant nov99
Grant nov99Grant nov99
Grant nov99
 
PPT ON INDUSTRIAL TRAINING IN BHEL HARIDWAR
PPT ON INDUSTRIAL TRAINING IN BHEL HARIDWARPPT ON INDUSTRIAL TRAINING IN BHEL HARIDWAR
PPT ON INDUSTRIAL TRAINING IN BHEL HARIDWAR
 
STEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGSSTEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGS
 
turbine governing oil system
turbine governing oil systemturbine governing oil system
turbine governing oil system
 
Governing of hydraulic turbines.
Governing of hydraulic turbines.Governing of hydraulic turbines.
Governing of hydraulic turbines.
 
Governors
GovernorsGovernors
Governors
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
 
Governing and protection system
Governing and protection systemGoverning and protection system
Governing and protection system
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.
 
Construction and manufacturing of steam turbine
Construction and manufacturing of steam turbineConstruction and manufacturing of steam turbine
Construction and manufacturing of steam turbine
 
Governor Woodward 505 calibration
Governor Woodward 505 calibrationGovernor Woodward 505 calibration
Governor Woodward 505 calibration
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Best ppt on thermal power station working
Best ppt on thermal power station workingBest ppt on thermal power station working
Best ppt on thermal power station working
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 

Similar to Bhel presentation

Dlw training session
Dlw training sessionDlw training session
Dlw training session
Shubham Khendkar
 
Report steffones
Report steffonesReport steffones
Report steffones
Steffones K
 
The general tyre and rubber company
The general tyre and rubber companyThe general tyre and rubber company
The general tyre and rubber company
Raza Jahangir
 
IRJET- Review Paper on Stirrup Making Machine
IRJET-  	  Review Paper on Stirrup Making MachineIRJET-  	  Review Paper on Stirrup Making Machine
IRJET- Review Paper on Stirrup Making Machine
IRJET Journal
 
Internship at Pakistan Railways
Internship at Pakistan RailwaysInternship at Pakistan Railways
Internship at Pakistan Railways
Muhammad Usman
 
Training at BHEL Haridwar
Training at BHEL Haridwar Training at BHEL Haridwar
Training at BHEL Haridwar
Harshit Bhandari
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
haxxo24
 
Lmw turbine oprn. manual
Lmw turbine oprn. manualLmw turbine oprn. manual
Lmw turbine oprn. manual
Kattukolu Kishorereddy
 
Project Motorized Scotch Yoke Mechanism
Project Motorized Scotch Yoke MechanismProject Motorized Scotch Yoke Mechanism
Project Motorized Scotch Yoke Mechanism
NAUMAN NAEEM
 
turbocharger
 turbocharger turbocharger
turbocharger
Pawan Singh
 
HMt training p pt
HMt training p ptHMt training p pt
HMt training p pt
Harpreet Singh
 
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdfVolvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
fapanhe306271
 
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdfVolvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
f8ioseoodkmmd
 
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdfVolvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
lunrizan628
 
Zero Turn Radius Presentation - Team Panache
Zero Turn Radius Presentation - Team PanacheZero Turn Radius Presentation - Team Panache
Zero Turn Radius Presentation - Team Panache
Siddhesh Ozarkar
 
frame manufacture overview
frame manufacture overviewframe manufacture overview
frame manufacture overview
beingsayan
 
Best Seminar report on Torque converter
Best Seminar report on Torque converter Best Seminar report on Torque converter
Best Seminar report on Torque converter
nilesh choubey
 
Ongc ppt (1) (maintenance workshop)
Ongc ppt (1) (maintenance workshop) Ongc ppt (1) (maintenance workshop)
Ongc ppt (1) (maintenance workshop)
Sudhanshu Purohit
 
Volvo ec220 d n ec220dn excavator service repair manual
Volvo ec220 d n ec220dn excavator service repair manualVolvo ec220 d n ec220dn excavator service repair manual
Volvo ec220 d n ec220dn excavator service repair manual
jfjkskefksmem
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressureparts
Vijay Raj
 

Similar to Bhel presentation (20)

Dlw training session
Dlw training sessionDlw training session
Dlw training session
 
Report steffones
Report steffonesReport steffones
Report steffones
 
The general tyre and rubber company
The general tyre and rubber companyThe general tyre and rubber company
The general tyre and rubber company
 
IRJET- Review Paper on Stirrup Making Machine
IRJET-  	  Review Paper on Stirrup Making MachineIRJET-  	  Review Paper on Stirrup Making Machine
IRJET- Review Paper on Stirrup Making Machine
 
Internship at Pakistan Railways
Internship at Pakistan RailwaysInternship at Pakistan Railways
Internship at Pakistan Railways
 
Training at BHEL Haridwar
Training at BHEL Haridwar Training at BHEL Haridwar
Training at BHEL Haridwar
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
 
Lmw turbine oprn. manual
Lmw turbine oprn. manualLmw turbine oprn. manual
Lmw turbine oprn. manual
 
Project Motorized Scotch Yoke Mechanism
Project Motorized Scotch Yoke MechanismProject Motorized Scotch Yoke Mechanism
Project Motorized Scotch Yoke Mechanism
 
turbocharger
 turbocharger turbocharger
turbocharger
 
HMt training p pt
HMt training p ptHMt training p pt
HMt training p pt
 
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdfVolvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
 
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdfVolvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
 
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdfVolvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
Volvo L50D Wheel Loader Service Repair Manual Instant Download.pdf
 
Zero Turn Radius Presentation - Team Panache
Zero Turn Radius Presentation - Team PanacheZero Turn Radius Presentation - Team Panache
Zero Turn Radius Presentation - Team Panache
 
frame manufacture overview
frame manufacture overviewframe manufacture overview
frame manufacture overview
 
Best Seminar report on Torque converter
Best Seminar report on Torque converter Best Seminar report on Torque converter
Best Seminar report on Torque converter
 
Ongc ppt (1) (maintenance workshop)
Ongc ppt (1) (maintenance workshop) Ongc ppt (1) (maintenance workshop)
Ongc ppt (1) (maintenance workshop)
 
Volvo ec220 d n ec220dn excavator service repair manual
Volvo ec220 d n ec220dn excavator service repair manualVolvo ec220 d n ec220dn excavator service repair manual
Volvo ec220 d n ec220dn excavator service repair manual
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressureparts
 

More from Ishant Gautam.

Advanced speed breaker
Advanced speed breakerAdvanced speed breaker
Advanced speed breaker
Ishant Gautam.
 
ADVANCED SPEED BREAKER
ADVANCED SPEED BREAKERADVANCED SPEED BREAKER
ADVANCED SPEED BREAKER
Ishant Gautam.
 
ADVANCED SPEED BREAKER
ADVANCED SPEED BREAKERADVANCED SPEED BREAKER
ADVANCED SPEED BREAKER
Ishant Gautam.
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
Ishant Gautam.
 
Hal lucknow
Hal lucknowHal lucknow
Hal lucknow
Ishant Gautam.
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Ishant Gautam.
 
Auto cad tutorial 002
Auto cad tutorial 002Auto cad tutorial 002
Auto cad tutorial 002
Ishant Gautam.
 
Dlw varanasi
Dlw varanasiDlw varanasi
Dlw varanasi
Ishant Gautam.
 
Bhel hrd nts_ishant_me_titm
Bhel hrd nts_ishant_me_titmBhel hrd nts_ishant_me_titm
Bhel hrd nts_ishant_me_titm
Ishant Gautam.
 
Bhel hrd seminar (ishant gautam)
Bhel hrd seminar (ishant gautam)Bhel hrd seminar (ishant gautam)
Bhel hrd seminar (ishant gautam)
Ishant Gautam.
 
Suspension system
Suspension systemSuspension system
Suspension system
Ishant Gautam.
 
DLW training report
DLW  training reportDLW  training report
DLW training report
Ishant Gautam.
 
TYPES OF WELDING
TYPES OF WELDINGTYPES OF WELDING
TYPES OF WELDING
Ishant Gautam.
 
BHEL Vocational training report Haridwar
BHEL Vocational training report HaridwarBHEL Vocational training report Haridwar
BHEL Vocational training report Haridwar
Ishant Gautam.
 
Classification of Hydraulic Turbines
Classification of Hydraulic TurbinesClassification of Hydraulic Turbines
Classification of Hydraulic Turbines
Ishant Gautam.
 

More from Ishant Gautam. (15)

Advanced speed breaker
Advanced speed breakerAdvanced speed breaker
Advanced speed breaker
 
ADVANCED SPEED BREAKER
ADVANCED SPEED BREAKERADVANCED SPEED BREAKER
ADVANCED SPEED BREAKER
 
ADVANCED SPEED BREAKER
ADVANCED SPEED BREAKERADVANCED SPEED BREAKER
ADVANCED SPEED BREAKER
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Hal lucknow
Hal lucknowHal lucknow
Hal lucknow
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Auto cad tutorial 002
Auto cad tutorial 002Auto cad tutorial 002
Auto cad tutorial 002
 
Dlw varanasi
Dlw varanasiDlw varanasi
Dlw varanasi
 
Bhel hrd nts_ishant_me_titm
Bhel hrd nts_ishant_me_titmBhel hrd nts_ishant_me_titm
Bhel hrd nts_ishant_me_titm
 
Bhel hrd seminar (ishant gautam)
Bhel hrd seminar (ishant gautam)Bhel hrd seminar (ishant gautam)
Bhel hrd seminar (ishant gautam)
 
Suspension system
Suspension systemSuspension system
Suspension system
 
DLW training report
DLW  training reportDLW  training report
DLW training report
 
TYPES OF WELDING
TYPES OF WELDINGTYPES OF WELDING
TYPES OF WELDING
 
BHEL Vocational training report Haridwar
BHEL Vocational training report HaridwarBHEL Vocational training report Haridwar
BHEL Vocational training report Haridwar
 
Classification of Hydraulic Turbines
Classification of Hydraulic TurbinesClassification of Hydraulic Turbines
Classification of Hydraulic Turbines
 

Recently uploaded

DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 

Recently uploaded (20)

DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 

Bhel presentation

  • 1. Submitted to: Submitted by: Er. Rajesh Chaubey Ishant Gautam 1
  • 2. 2  Introduction  Over view at Haridwar Plant  Layout of Block-3  Details of Bay 1(Assembly, Machine shop and OSBT)  Details of Bay 2(Gas turbine section and rotor assembly)  Details of Bay 3(Governing and Broad specifications of major machines)[CNC & Non CNC]  Bay 4( Blade and Heat treatment shop)
  • 3.  BHEL is the largest engineering and manufacturing enterprise in India in the energy field today. It was established more than 40 years ago and has been earning the profits since 1971.  It has very wide network over 150 project sites, 8 service centers and 18 regional offices and Headquarters in New Delhi. More over it is one of the navratna of government of India. 75% of electricity in India is produced with the help of BHEL equipments. 3
  • 4.  Vision :World class, innovative, competitive, and profitable engineering enterprise providing total business solutions.  Mission :The leading engineering enterprise providing quality product systems and services in the field of energy, transportation, infrastructure and other potential areas.  Manpower :Total strength is more than 10000 which includes around 3000 qualified engineers and technicians, 5200 skilled artisans and the rest in other categories. 4
  • 5. Bay 1 Assembly, Heavy machine shop, OSBT Bay 2 Gas turbine assembly, Rotor assembly Bay 3 Governing section, Light machine shop Bay 4 Blade shop, Heat treatment shop 5
  • 6. 6
  • 7.  The final assembly of the turbine is done in bay 1. Main assembly parts:  1. High pressure steam turbine  2. Intermediate pressure steam turbine  3. Low pressure steam turbine  4. Bearing pedestals  5. Control valves 7
  • 8.  This is the smallest of the three turbines. It consists of two shells namely inner inner and outer outer. Inner inner part is the part on which guide blades are placed and outer outer part mainly works as a casing of the turbine. HP outer outer lower half is placed on bed and leveling is done; now upper half is assembled and alignment is done; now GBC is aligned with respect to centre.  Final alignment is checked and turbine is dispatched in the assembled conditions. 8
  • 9. 9
  • 10.  Capacity 210/250 MW  Main components  IP outer casing  Inner casing  GBC  Shaft seals  Rotor  Descriptions In outer casing, lower half is placed on bed and leveling is done. U/H is assembled and alignment is done now inner casing is placed and it is aligned with help of keys and pokers. Rotor is placed and alignment of rotor is done, now axial and radial gap between inner casing and rotor are checked (flow path). The studs are heat tightened to achieve elongation. Turbine is dispatched in assembled conditions. 10
  • 11.  Capacity 210/250/500MW  Main components:  LP inner outer  LP inner inner  LP outer outer  LP GBC  Rotor 11
  • 12.  LP I/O lower half is placed on bed and leveling is done. Now upper half is assembled and alignment is done. Now GBC is aligned with respect to centre then GBC 2 and GBC 3 are aligned. Then inner core is aligned with help of adjustment pokers.  Now projection pipes are welded then diffusers are aligned. Final alignment is checked and turbine is dispatched in disassembled condition 12
  • 13. 13
  • 14.  Front HP/IP/LP, 210/250/500MW pipelines are hydraulically tested. Then bearing is aligned with help of phins, and pinning is done. Assembly is completed and dispatched in assembled conditions. 14 14
  • 15. 15 Valve seats are fitted in the casing by cooling in liquid oxygen. Pinning of seats is done, welding of nipples and flanges is done and then hydraulic testing with valves covers, now casing is sent for edge preparation and the color of valve assembly and valve seat is checked. Travel of valve is checked and locking is done. Then trial assembly of s/m is done. Valve is dispatched in assembled condition.
  • 16.  In this, there are very costly and big machines which are used to carry operation on large parts of a turbine such as rotor, diffuser, casing etc. 1) Machine number 1-120 Center lathe machine CNC  Job: HP Rotor (on that time)  Operation: slotting  Specifications of the machine:-  Main spindle bore: - 150mm  Distance between centers: - 12000mm  Turning dia. Over bed cover: - 1400mm  Turning dia over carriage: - 1100mm 16
  • 17. 2) Machine number 1-28 Horizontal boring machine (Russian)  Operation performed: - tapping, threading,drilling, boring, facing, milling etc,except knurling  Specifications  Capacity: - 600mm (bore dia)  Weight capacity: - 40 tonne  Dia of spindle: - 150 mm 17
  • 18. Over speed balancing tunnel :  This is the one of the most important section of the turbine block. Here after the complete checking of the rotor from the bay 1, rotor is bringing to get check it in the working conditions. Here we rotate our rotor in the vacuum condition on a very small film of oil consisting of some microns; here the oil is on very high pressure. Rotor is revolved on 3750 rpm, while in the operating conditions rotor revolves at 3000rpm (500mw).  The time being for which rotor is revolved is 3 minutes. The power required to rotate that much of heavy rotor is very high which comes from the high voltage line nearly of 11000 Volts, and the gear box with the synchronize motor is used to get accurate and desired speed 18
  • 19. Oil plays a very important role in the rotor checking the oil comes from the underground tanks having a capacity up to 30000 liters this is pumped with the help of large pumps and a large quantity of oil is supplied continuously so that oil film doesn’t break. Here we use a number of filters on many stages so that oil is checked out against dust particles or any foreign particles the attention is paid during this checking so that everything going OK. The full control of OSBT is done with help of control system which is in control room, each and every care is taken during the complete testing. The complete checking of rotor costs nearly 8 crore Rs. Which is a very high cost and after this testing if we find there is any loosening in the blades or any blade is out of its position then the department of OSBT sends the rotor to the BAY1 along with checking report and every effort is now put on the rotor so that it pass the checking in the OSBT only then rotor is assembled with the casing and dispatched. film doesn’t break. 19
  • 20. 20 SYSTEM TO CREATE VACCUM FOR THE OSBT,AT BHEL HARDWAR
  • 21. PART A: -Gas turbine section The main thing that is done here is that the making of rotor for the gas turbine, the rotor of gas turbine is very different from that of the steam turbine, here the rotor is made in the form of discs and after that the complete rotor is made by joining the discs. On a simple disc firstly the grooves are cut on the broaching machine , very similar to the gear cutting process. Now after cutting one groove the indexing is done and the machine is ready to cut the another groove. after cutting the all grooves on the periphery of the disc now the process is done to make teethes on both the surfaces with the help of the grinding so that each disc should mesh all the teethes and proper joining and the alignment can be done, and similar process is done to all the other discs, now before assembling the all the discs an very important operation is done to check the accuracy of all the discs in meshing, and the operation is named as the Colour matching. 21
  • 22.  Colour matching It is the process to check the complete meshing of the two joining parts here the part on which we have to join is colored and the mating part is put on it so that complete transfer of color on the other part could be done if there is not the equal distributions of the color on the second part then the portions are identified to be machined so that complete and accurate matching could be done.  Now after checking all the discs the blades are inserted in the respective grooves and now the shrink fitting of these discs is done on the solid shaft which would be passing from each disc thoroughly. 22
  • 23.  Shrink It is the process of joining two parts, one part Is called male part and the other is called as female part, the party on which we have to insert other part is called as male part and another would be female part.  In this process the male part is cooled say in the liquid oxygen so that it contracts and the female part is expanded by heating and now both the parts are superimposed and are subjected to room temperature conditions and after some time both parts are tightly joined. Here in the gas turbine rotor the shaft is the male part and the discs are called female part.  In this way the complete rotor of the gas turbine is prepared and the testing of the rotor as in the case of steam turbine is carried out in the OSBT. fitting 23
  • 24. In this section the rotor making is done for the steam turbine HP, LP, IP. For the any steam turbine firstly the rotor is in the form of the shaft, the procedure to make the complete rotor is explained here in the steps:-  The rotor shaft is placed on the centre lathe machine and turning and taper turning is done according to the provided drawings.  Then grooves cutting is done for the blades fixing on all over the length of the rotor accordingly as per in the drawing.  Now with the help of the crane the rotor is placed on the other machine on which rotor is just revolved to do the indexing.  Talking about one groove a extra portion is cut so that blades can be inserted in it easily.  Then a locking blade is fixed to get lock all the blades of one stage. Here unlike in gas turbine a single blade is fixed but in the GT each and every blade was fixed individually.  Sealing are placed on the portion in between two stages so that these sailings match with the same sealing made on the casing so that leaking of the fluid can be avoided from one stage to the other stage.  After doing all this work the rotor is now send to the Bay 1 so that final inspection and the checking in OSBT could be done and the finally rotor with proper alignment is assembled in the casing. 24
  • 25. Contents: - Governing section, light machine shop Section 1:- Governing section  Governing is the process of controlling the speed of the rotor so that we can get constant frequency under the fluctuating loads. This is done by controlling the amount of fluid going inside the turbine, means to say if the load is less that mean speed of the rotor would tends to increase then we make the less steam to enter inside so that rotor speed come to desired value. Opposite thing Is done in case of the heavy load when the speed of the turbine is less more steam is made to enter inside the turbine. To control this all, at the steam enterance we use an electronic and mechanical system which consists of oil pumps, servo motors pipes and many indicators on the valve mouth. 25
  • 26. Section 2:- Machine shop A. CNC machines  CNC LATHE  CNC MILLING MACHINE  CNC VERTICAL BORER  CNC SURFACE BROACHING M/C  CREEP FEED GRINDING M/C  BROACH SHARPENING M/C B. Non CNC machines PRECISION HEAVY DUTY LATHE 26
  • 27. Sections  1. Turbine blade manufacturing.  2. Heat treatment Blades of turbine:-  Blades are one of the most crucial parts of a turbine. Blades are fitted in the grooves .The shape of the blades is of aerofoil type 27
  • 28. There are two types of blades (i) Guide blades (ii) Moving blades  1. Guide blades:-These blades are remained fixed during the motion of the runner so these are also called as fixed blades .These blades are fitted in the grooves in the casing. The sealing action is also done before putting the blades in the grooves so that during working conditions the leakage of fluid can be stopped. Guide blades are put in guide blade carriers.  2. Moving blades:-As the name suggests these blades remain in moving condition for the whole life cycle of a turbine. They are arranged so that they become opposite to the direction of the fixed blades. This arrangement will help in striking of the fluid on more area of the moving blades and hence helps in I  Material for blades:-  For steam turbines we mainly use the chrome steel, steel with some % of V, W etc.  For some special type of gas turbines we import blades from other countries such as Germany, Russia etc. ncreasing the efficiency of the turbine. 28
  • 29.  Importance of wrang in blade shop:-  Due to the aerofoil type of shape of the blades it is not easy to handle the blades when we are performing various operations on them, so a material with low melting point (100 deg. Cel.) is used for this purpose. For this a die is taken, the blade is put between the wrang and various machining operations are performed. To take the blades outside the die with blade, we put the die in boiling water, wrang melts and thus blade is taken outside. 29
  • 30.  Working of blades:- 30 The fluid coming from the boiler is highly energetic the guide blades which are also called as fixed blades Are arranged so that they are in oppposite direction to moving blades,it helps the maximum fluid to strike on the moving blades and increases the efficiency of turbine.