Site 27 Update

Restoration Advisory Board Meeting
Former Naval Air Station Moffett Field
July 12, 2007


Presented by:
Sc...
Overview


•   Site Background
•   Recently Completed Actions
•   Upcoming Action
•   Remedial Action Completion Report
• ...
Site 27 Aerial Photo




                       3
Recently Completed Actions


• Property Survey

• Moffett Field Road Restoration




                                   4
Moffett Field Road Restoration




                                 5
Moffett Field Road Restoration




                                 6
Upcoming Actions


• Re-hydroseed areas of the Northern Channel
  slope with limited growth

  – Mixture of salt tolerant ...
Upcoming Action




                  8
Upcoming Action




                  9
Remedial Action Completion Report



• Describe activities of Remedial Action
  – Pre-construction, construction, demobili...
Schedule

• Draft Remedial Action Completion Report –
  September 2007

• Respond to Comments – November 2007

• Draft Fin...
Questions?




             12
Upcoming SlideShare
Loading in …5
×

Moffett Site 27 Presentation to RAB July 12, 2007

639 views

Published on

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
639
On SlideShare
0
From Embeds
0
Number of Embeds
34
Actions
Shares
0
Downloads
10
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Moffett Site 27 Presentation to RAB July 12, 2007

  1. 1. Site 27 Update Restoration Advisory Board Meeting Former Naval Air Station Moffett Field July 12, 2007 Presented by: Scott Gromko Navy Remedial Project Manager
  2. 2. Overview • Site Background • Recently Completed Actions • Upcoming Action • Remedial Action Completion Report • Schedule • Questions 2
  3. 3. Site 27 Aerial Photo 3
  4. 4. Recently Completed Actions • Property Survey • Moffett Field Road Restoration 4
  5. 5. Moffett Field Road Restoration 5
  6. 6. Moffett Field Road Restoration 6
  7. 7. Upcoming Actions • Re-hydroseed areas of the Northern Channel slope with limited growth – Mixture of salt tolerant grasses (salt grass, alkali sacaton) – California native species – Water application into the rainy season (October) 7
  8. 8. Upcoming Action 8
  9. 9. Upcoming Action 9
  10. 10. Remedial Action Completion Report • Describe activities of Remedial Action – Pre-construction, construction, demobilization activities – Biological Mitigation – Waste management – Site Restoration – As Builts • Appendices – Lots of Data 10
  11. 11. Schedule • Draft Remedial Action Completion Report – September 2007 • Respond to Comments – November 2007 • Draft Final RACR – December 2007 • Final RACR and Site Close Out – January 2008 11
  12. 12. Questions? 12

×